Opinion

City of Brewer v. Conners

Court
Superior Court of Maine
Filed
May 28, 2004
Status
Unpublished
On the bench
Jeffrey L. Hjelm
Cited by
0 cases
Authority
More cited than 34.1%

in estoppel claim, any reliance must be reasonable

How later courts described this case

  • in estoppel claim, any reliance must be reasonable

Written by the judges who cited it.

The opinion

STATE OF MAINE SUPERIOR COURT

PENOBSCOT, SS. CIVIL ACTION

Docket Ane. CVvp 35 2 Ei Eo [ERED a ENTERED] =A

City of Brewer, “|S May 28 |

Plaintiff | auth |

PENOBSCOT CoyNTy

V. Decision and Judgment

PAL TY T

Michael W. Conners, bon

Defendant

‘JUN 4 2004

Hearing on the City of Brewer’s complaint was held on December 4, 2003, and

January 8, 2004. On both hearing dates, a representative of the City, the defendant

Michael W. Conners and both attorneys of record were present. Following the jury-

waived trial, the parties filed written argument, which the court has considered. In this

action, the City seeks recovery from Conners for the expense it incurred when it caused

the demolition of two buildings that were owned by Conners and that the City had

condemned. See 17 M.R.S.A. § 2851 et seg. The City also seeks an award of its costs

and attorneys fees.

The two buildings at issue were located at 14 DeRusha Lane and 8 Rooney Street

in Brewer. In 1994 and 1995 respectively, Conners purchased them as investment

properties, intending to lease them as residences. Presently, he is the sole owner of the

two properties.’ Due to the poor condition of the buildings, the City’s code enforcement

officer, David Russell, condemned the Rooney Street building in July 1996 and the

DeRusha Lane property in J anuary 1997, concluding at those respective times that neither

was fit for human habitation but after giving Conners an Opportunity to remediate the

problems. With the exception of some cosmetic work (such as mowing the lawn),

Conners took virtually no action to repair or correct the problems with either house, even

’ Conners purchased them jointly with his then-wife. When they were divorced in 2000,

the two parcels were set aside to him.

after the CEO condemned them. They remained placarded and unoccupied through the

matters were considering the commencement of legal or condemnation proceedings for

both buildings. In June, Russell wrote Conners advising that he (Russell) would turn the

issue Over to the City’s attorney in anticipation of a July 16 city counsel meeting if

Conners did not start the demolition work himself by July 15. At trial, Conners testified

that Russell told him, expressly or impliedly, that although Conners needed to correct the

substantial defects in the buildings, there was no urgency because the legal proceedings

would take time. The court does not find this testimony to be credible because it runs

contrary to the City’s more aggressive efforts to address the serious health and safety

problems posed by the buildings.

By letter dated July 10, the city clerk sent a letter to Conners notifying him that on

July 16, the city counsel would decide whether to hold public hearing on the condition

and fate of the two buildings. The counsel in fact addressed that issue at the J uly 16

meeting. Conners was not present. The counsel voted to hold a public hearing on the

two buildings. The hearing would be held on August 13. A formal notice of the city

counsel’s decision for each of the two properties was served on Conners on J uly 25. The

notice for the Rooney Street property contained the correct date for the public hearing.

However, the notice for the DeRusha Lane building provided that the hearing would be

held on August 20, rather than August 13. (When the proposed orders were prepared in

advance of the July 16 Meeting, the drafter expected that the hearing, if ordered by the

counsel, would be held on August 20. The counsel decided to schedule the public

hearing for August 13. The proposed order for the DeRusha Lane building was not

Cnanged or corrected ¢ flect > i ict i

hanged or corrected fo reriect the counsel’s scheduling decision.) 0wever, in late July,

vv

the city clerk sent letters to Conners regarding the upcoming public hearing, and those

the correct hearing date (August 13). Additionally, the City published a notice of the

August 13 hearing dates (with the correct date) in the Bangor Daily News.

On August 13, the public hearing on the two Conners parcels was held. Conners

himself did not attend the meeting, either himself or through a representative. The

Situation where, for example, he chose not to attend the August 13 hearing and was

simply awaiting an August 20 meeting because he was more interested in the DeRusha

Lane house (which was subject of the purported August 20 hearing) than the Rooney

Street house. In fact, he did not show up at the place and time indicated in the erroneous

order. Thus, the error in the one city counsel order was immaterial and had no effect on

Conner’s rights, because he intended not to attend any public hearing on his properties,

regardless of when any such hearing was to be held,

At the August 13 public Meeting, the city counsel heard evidence presented by the

CEO. On the basis of the information developed during that proceeding, the city counsel

made specific findings regarding the condition of the 8 Rooney Street and 12 DeRusha

Lane properties. On the basis of those findings, the counsel concluded that both

properties posed health and safety hazards and were dangerous to life and property. On

this basis, the counsel ordered that Conners have the Opportunity to abate the condition

within 31 days of the effective date of its order (August 18), and, if Conners failed to do

So, the city manager was instructed to remove the nuisance. In the latter instance, the

matter would be referred for collection of the resulting expenses from Conners. Conners

vas served in hand with the two notices, which the City also recorded in the Penobscot

County Registry of Deeds. Conners did not take any steps to remediate or remove either

building. Further, he did not appeal the decision affecting either of the properties,

Consequently, in October, the City entered into a contract with a local contractor for the

demolition and removal of the buildings on the two parcels. Pursuant to that contract, the

buildings in fact were demolished, and the material was removed from the sites. The

City made demand on Conners for the costs of that work, which were $6,800 for the

Rooney Street house and $16,500 for the building on DeRusha Lane. Conners did not

satisfy that demand, and the City then brought this action.

In his written summation, Conners argues that he did not receive sufficient notice

of the July 16 city counsel meeting and that the defective notice associated with the

August 13 public hearing vitiates the City’s claim. He also contends that the City has

waived its right to recover because Russel] led him to believe that he did not need to

comply with any demand to repair or remove the buildings. Conners has not argued

expressly that the two buildings were dangerous within the meaning of 17 M.R.S.A. §

2851. N onetheless, it was an issue caised at trial, and the court addresses it here.

A. Dangerous buildings

The City contends that Conners is bound by the counsel’s determination that the

two buildings were dangerous, because he elected not to appeal those orders despite his

night to do so under section 2852. Conners argues that, because of insufficient notice and

because of notions of waiver and estoppel, the counsel’s determination was void, and so

he is not barred from litigating the issue now. This, however, is a collateral attack on the

effect of the counsel’s August 13 adjudication. For the reasons set out below, the court

concludes that those contentions are unavailing. Consequently, the counsel’s

determination that the conditions of the building were dangerous within the meaning of

section 2851 is a final adjudication on the matter and one that bars relitigation here.

Even if that were not so, however, the independent evidence regarding the

condition of the two buildings amply demonstrates that they were structurally unsafe; that

they were unstable; that they were unsanitary; that they posed a fire hazard: that they

were unsuitable for occupancy; that they were a hazard to health and safety because of

inadequate maintenance and dilapidation; and that they were dangerous to life and

eretore, the City has established here that it was statutorily entitled to pursue

and accomplish the demolition of the buildings.

B. Defective notice

Conners argues that the City gave him legally insufficient notice of the July 16

and August 13 city counsel meetings, thus undermining the City’ right to obtain relief

from him here.

First, Conners urges that he was deprived of due process because he was not

given adequate notice of the July 16 city counsel meeting, where the counsel considered

the CEO’s request to pursue demolition of the buildings. On July 10, the city clerk

mailed a letter advising Conners that the agenda for the July 16 meeting would include

this issue. The clerk wrote Conners that he was “welcome to attend this meeting and

comment on this item.” Conners did not attend. He argues, however, that the amount of

notice was too short. During his trial testimony, Conners confirmed that he received this

letter. Although there is no evidence on this specific point, the court is willing to infer

that Conners received the letter prior to the meeting itself. Despite this, Conners did not

appear at the counsel meeting to object to the short notice, to request that the issue be

rescheduled to a later date or to seek any other form of relief. See Sawyer v. Board of

Licensure in Medicine, 2000 ME 125, J 15, 754 A.2d 996, 999-1000 (respondent in

agency action was not denied an Opportunity to be heard when he failed to appear at the

hearing). Further, here, Conners does not identify any specific form of prejudice flowing

from the notice he did receive: he makes no specific argument, for example, that he was

unable to marshal particular information due to the limited about of time between the date

he received notice and the counsel meeting itself.

Conners acknowledges that there is no law defining the amount of time a

municipality is required to provide a landowner regarding a municipal body’s impending

consideration of the issue at hand. However, the pivotal point is that the city counsel’s

* As Conners points out in his summation, section 2851(1) provides, “The notice [of the

municipal hearing] shall be served on the owner. . in the same way service of process is

made in accordance with the Maine Rules of Civil Procedure.” Here, Conners does no

argue that the City failed to Satisfy the requirements of service under M.R.Civ.P. 4. This,

however, does not address the issue at hand, which relates to the timing of that service in

relation to the hearing date.

consideration of the fate of the properties on July 16 was preliminary in nature. The

counsel simply considered the question of whether a public hearing should be held at

some later time, to allow the presentation. of evidence that the counsel would then assess

and use as a basis for its decision of whether to seek relief under section 2851. The

limited nature of the July 16 meeting distinguishes this case from Kirkpatrick v. City of

Bangor, 1999 ME 73, { 15, 728 A.2d 1268, 1272, where the Law Court examined the

adequacy of notice that preceded the hearing where the demolition decision was actually

made. This raises a true question about the extent of any due process interest Conners

may have had in the July 16 proceeding. See generally Seider v. Board of Examiners of

Psychologists, 2000 ME 118, {! 19, 754 A.2d 986, 991 (“Due process is a flexible concept

calling for such procedural protections as the particular situation demands.” (Citation

and internal punctuation omitted.)). If Conners had a constitutionally protected, due

process interest in the July 16 hearing, then it was of a limited magnitude, thereby

reducing the amount of notice that the City was required to provide him. Under all of

these circumstances, the court cannot conclude that the notice provided to him prior to

the July city counsel meeting improperly compromised his rights.

Conners also contends that the incorrect date on the notice of public hearing

relating to the DeRusha Lane property vitiates the City’s rights against him here. As is

noted above, however, that error did not create any prejudice to Conners, because he had

no interest or intention to attend any public hearing, regardless of the date of such a

hearing. Further, Conners received a copy of the city counsel’s August 13 decision

affecting the two properties, and he was given that notice well prior to the deadlines for

filing an appeal to the Superior Court. His election not to pursue such an appeal, where

he could have challenged the legality of the City’s decision regarding DeRusha Lane due

to the incorrect notice, bars him from raising such an argument here. Therefore, because

Conners has waived his right to challenge the City’s action on the ground of the defective

notice, and because any such defect was harmless under the circumstances present here,

the court concludes that the City’s pursuit of its statutory remedies does not violate

Conners’ rights to due process.’

* For purposes of this issue, the court assumes without deciding that the notice relating to

the DeRusha Lane property in fact was flawed. The court does not address the City’s

C. Waiver/estoppel

Finally, Conners contends that the City has waived its right to seek recovery from

him because the City’s CEO led him to believe that he did not need to take prompt action

to repair the two buildings or to remove them on his own. Conners asserted waiver as an

affirmative defense in his responsive pleading. Although he did not also raise a defense

of estoppel, the court finds that the articulation of the waiver defense, which in this case

has the same factual basis as an estoppel argument, was sufficient to place the City on

notice of the issue.

For three reasons, Conners has not demonstrated that the City was waived its

claim against him or that it is estopped from securing recovery here. First, the record

establishes that Russell, in his capacity as the City’s CEO, had no authority to counter the

city counsel’s decision to demolish the two buildings (either by directing Conners to

remove them or, if he failed to do so, by making its own arrangement for the demolition).

“[T]he unauthorized act of a municipal officer cannot be grounds for estopping the

municipality.” Shackford & Gooch, Inc. v. Town of Kennebunk, 486 A.2d 102, 106 (Me.

1984). Thus, even if Russell had made statements to Conners that would rise to the level

of a representation that the City would not follow through with any plans to secure the

buildings’ demolition, those statements do not estop the City from obtaining relief here.

Second, the court is satisfied that Russell did not make statements or engage in

any other conduct that, as Conners contends, the City was not serious about seeking the

demolition of the two buildings. According to Conners’ testimony, Russell told him

during a telephone call that the City was not in a rush to address the problems created by

the two buildings, and Russell acceded to Conner’s intention to take care of the problem

in the near future. Although the City had tolerated the decrepit condition of the houses

for several years, the best evidence reveals that the City had quickened its pace by 2002

and was determined to address the issue more vigorously. This is demonstrated by

Russell’s letter to Conners in November 2001, their meeting in May 2002 when Russell

told Conners that the city counsel planned to take action, and Russell’s letter to Conners

argument that this error was rectified by the correct date in a letter accompanying the

copy of the city counsel’s order and sent to Conners by the city clerk, and by publication

of the announcement for the August 13 hearing in three editions of the Bangor Daily

News, as arranged by the City.

in June 2002. The 2002 communications, which were roughly contemporaneous with the

statements that Conners attributes to Russell, credibly belie the notion that Russell was

content to let the matter progress slowly. Thus, the court cannot credit Conners’

testimony that Russell engaged in conduct that would estop the City from pursuing its

claim at bar.

Finally, even if Russell had misled Conners into thinking that he (Conners) still

had the opportunity to remediate the problems himself at a pace of his choice, any

reliance on Russell’s statements was not reasonable. The City put Conners on notice that

it was serious about the problem. Russell advised Conners in writing, as part of the June

19, 2002, letter, that he was pressing the matter by referring it to the City’s attorney and

that the city counsel would consider the issue at it July 16 meeting. Then, the City

notified Conners that the city counsel would hold a public hearing in August to determine

whether the building should be demolished. (Irrespective of any problem with the date of

the hearing, the notice was clearly sufficient to advise Conners that the City was moving

forward.) Finally, following the August 13 hearing, the City notified Conners of the city

counsel’s directive requiring Conners to abate the nuisance. In light of ail of this

information (which was actually known to Conners) about the City’s enforcement efforts,

it was plainly unreasonable for Conners to hope, based on Conners’ account of an

ambiguous comment made by Russell, that it would not press the issue. For any reliance

to be reasonable, Conners would need to have disregarded the strong and express signals

that the City intended to take prompt action against his property and then against him in

this proceeding. Therefore, the City is not estopped from asserting its claim here. See

HE. Sargent, Inc. v. Town of Wells, 676 A.2d 920, 925 (Me 1996) (in estoppel claim, any

reliance must be reasonable).

D. Relief

The cost to demolish the two buildings was $23,300. The City is entitled to

recover that amount, in addition to expenses associated with the condemnation process.

See 17 M.R.S.A. § 2853. This amounts to a total of $29,003.20. Additionally, the City is

entitled to an award of its reasonable attorney’s fees. Here, for legal work performed

through January 6, 2004, those fees and expenses are $5,568.40 ($$2,874.87 + $2,829.53

- $136 (time spent on possible summary judgment motion that the City elected not to file;

the City is not seeking reimbursement for those fees)). Within 14 days of the date of this

order, the City’s counsel may submit a supplemental affidavit setting out fees for legal

services performed subsequent to January 6, 2004. Within 10 days of that filing,

Conners’ attorney may file any response to that submission.

The entry shall be:

For the foregoing reasons, judgment is entered for the plaintiff in the amount of

$29,003.20, plus pre-judgment interest at the annual rate of 8%, plus post-judgment

interest at the annual rate of 7.41%. See l4M.RS.A. §§ 1602-B, 1602-C. The plaintiff

shall be awarded its reasonable attorney’s fees, which shall be determined following

further submissions by the parties.

Dated: May 27, 2004 (Hike

a Pt ——_

Justice,"Maine Superior Court

Jeffrey L. Hjelm

BREWER CITY OF - PLAINTIFF SUPERIOR COURT

80 NORTH MAIN STREET PENOBSCOT, ss.

BREWER. ME 04412 : ' Docket No BANSC-CV-2003-00002

Attorney for: BREWER CITY OF

JOEL DEARBORN

LAW OFFICE OF JOEL DEARBORN SR PA DOCKET RECORD

120 NORTH MAIN STREET ,

BREWER ME 04412

Vs

MICHAEL W CONNERS - DEFENDANT

3 WESTWOOD ROAD

BANGOR ME 04401

Attorney for: MICHAEL w CONNERS

STEVEN LYMAN

LAW OFFICE OF STEVEN J. LYMAN

96 HARLOW STREET

BANGOR ME 04401-4920

Filing Document: NOTICE oF REMOVAL Minor Case Type: CONSTITUTIONAL / CIVIL RIGHTS

Filing Date: 01/03/2003

Docket Events:

01/06/2003

01/06/2003

01/06/2003

01/06/2003

01/07/2003

01/09/2003

01/09/2003

03/11/2003

FILING DOCUMENT - NOTICE oF REMOVAL FILED ON 01/03/2003

REMOVAL FROM DISTRICT COURT, DISTRICT THREE, DIVISION OF SOUTHERN PENOBSCOT, BANGOR,

MAINE. (BANDC-CV-2002-598) (EXHIBIT A ATTACHED) DISTRICT COURT DOCKET ENTRIES WERE

CHECKAGAINST PLEADINGS RECEIVED. ALL PLEADINGS EXCEPT THE SUMMONS SHOWING SERVICE WERE

RECEIVED. CALL IN TO DISTRICT COURT TO RETREIVE IT.

Party(s): BREWER CITY oF

ATTORNEY - RETAINED ENTERED ON 01/03/2003

Plaintiff's Attorney: JOEL DEARBORN

Party(s): MICHAEL W CONNERS

ATTORNEY - RETAINED ENTERED ON 01/03/2003

Defendant's Attorney: STEVEN LYMAN

CERTIFY/NOTIFICATION - RULE 13(J) NOTICE OF REMOVAL SENT ON 01/06/2003

MARGARET GARDNER , CLERK II

TO ALL ATTORNEYS OF RECORD.

NOTE - OTHER CASE NOTE ENTERED ON 01/07/2003

COPY OF SUMMONS RECEIVED FROM DISTRICT COURT TODAY.

ASSIGNMENT - SINGLE JUDGE/JUSTICE ASSIGNED TO JUSTICE ON 01/09/2003

JEFFREY L HJELM , JUSTICE

ORDER - SCHEDULING ORDER ENTERED ON 01/09/2003

JEFFREY L HJELM , JUSTICE

THE ENTRY WILL BE: SCHEDULING ORDER FILED. DISCOVERY DEADLINE IS OCTOBER 1, 2003.

PARTIES TO SELECT ADR PROCESS AND NEUTRAL. COPY FORWARDED TO ALL ATTORNEYS OF RECORD.

Party(s): BREWER CITY OF

MOTION - MOTION FOR ENLARGEMENT OF TIME FILED WITH AFFIDAVIT ON 03/10/2003

Page 1 of 7 Printed on: 05/28/2004

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.