Opinion

Widewaters Stillwater Co. v. City of Bangor

Court
Superior Court of Maine
Filed
Mar 26, 2003
Status
Unpublished
On the bench
Jeffrey L. Hjelm
Cited by
0 cases
Authority
More cited than 34.1%

The opinion

STATE OF MAINE SUPERIOR COURT

PENOBSCOT, SS. Docket No. AP-02-12 ,

\ fp - Or Ale 2). far 2

ULE RE, J 260/800,

:

Widewaters Stillwater Co., LLC,

Appellant

V.

ORDER ON APPEAL

City of Bangor,

Appellee

and / DONLD Sapa

BACORD,

Intervenor

Widewaters Stillwater Co., LLC, (Widewaters) appeals from a decision of the

Bangor Planning Board denying its application for a site plan development permit under

the City’s Land Development Code. The parties and the intervenor have filed written

argument, which the court has considered in conjunction with the record on appeal.

Much of the procedural backdrop of this case is discussed in the court’s order

issued in May 2001. That order is incorporated into this decision. For present purposes,

a limited review of the proceedings in this matter may be helpful. Widewaters filed the

application for a site development permit and two conditional use permits in early 2001.

These permit applications are associated with Widewaters’ plans to develop a parcel of

land located on Stillwater Avenue in Bangor and construct a Wal-Mart superstore. A

public hearing on the applications was held in March and April 2001. Following

deliberations, the Board members voted 3-2 to deny Widewaters’ site development

application. The Board unanimously approved the application for the conditional use

permits. Widewaters appealed the denial of the site development application. See

Widewaters Stillwater Co., LLC v. City of Bangor, AP-01-16 (Superior Court, Penobscot

County). This court construed the administrative record to reveal that the Board’s

decision was based on CITY OF BANGOR, MAINE LAND DEVELOPMENT CODE § 165-

114(1), which obligates the Board to consider the “[e]ffect [of the land development

project] on the scenic or natural beauty of the area or on historic sites of rare and

irreplaceable natural areas... .” For the reasons set out in the order dated May 30, 2001,

the court concluded that section 165-114(1) violated the constitutional principles

developed in Kosalka v. Town of Georgetown, 2000 ME 106, 752 A.2d 183. On that

basis, the court vacated the Board’s decision to deny the permit application.

That decision was then appealed to the Supreme Judicial Court. Holding that the

administrative record did not adequately reveal the Board’s findings and the specific

legislative basis for its decision denying Widewaters’ application, the Court remanded the

case to the Planning Board for further proceedings, namely, the issuance of findings of

fact. Widewaters Stillwater Co., LLC v. Bangor Area Citizens Organized for Responsible

Development, 2002 ME 27, J 12, 790 A.2d 597, 601.’ Pursuant to that mandate on

remand, the Planning Board considered Widewaters’ application at two meetings in May

2002. The evidentiary record was not reopened. Rather, in light of the limited purpose

of the remand, the Board’s action was limited to formulating a set of specific factual

findings corresponding to the 11 separate factors that, under section 165-114, the Board

is required to consider.

When the Board voted in 2001 to deny Widewaters’ site development permit

application, the majority consisted of Frederick Costlow, Robert Lingley and Robert

Kreitzer. Richard Fournier (the Board’s chair) and George Burgoyne voted to approve

the permit application. Robert Guerette was a member who was present at the 2001

meetings but was designated as a non-voting member, possibiy because only five

members would be called to vote in any proceeding.” Even though Guerette did not vote

on the application in 2001, he was permitted to express his views on the merits of the

issues, presumably in an advisory capacity. See R. H-2 at 10-11. In 2002, when the

1 The intervenor, BACORD, rather than the City of Bangor, was named as the responding

party in caption of the Law Court opinion because the City did not participate in that

appeal.

* The procedural rules or protocol governing Planning Board meetings do not appear to

be included in the record on this appeal.

Board was instructed to issue findings following remand from the Law Court, neither

Kreitzer nor Burgoyne was a Board member. Costlow, Lingley, Fournier and Guerette,

however, were still members. In anticipation of the first of the two May 2002 meetings,

Costlow or a member of the Board’s staff contacted Kreitzer and reviewed at least one

draft of proposed findings that were responsive to the Law Court’s mandate. See R. I-7 at

p. 4, 1-8 at p. 3.° At the May 7 meeting, after some preliminary discussion of the matter,

the Board voted to postpone consideration of the proposed findings, which were

presented in several alternative drafts, to allow more time for the Board members to study

that material. Two weeks later, when the Board held another meeting, the Board

unanimously approved several changes to one of the draft sets of findings they had

considered. With that, the four members of the Board who also were members of the

Board in 2001 and were present at the two 2001 hearings application in 2001 and who

were also Board members in 2002 (namely, Fournier, Costlow, Lingley and Guerette)

unanimously approved a set of findings of fact setting out the basis for the Board’s action

in 2001.*

As revealed in those findings, the Board’s 2001 decision denying Widewaters’

site development permit application was based on three of the eleven considerations set

out in section 165-114, namely, sections 165-114(D), (I) and (J). With respect to the last

? The minutes of the May 7 meeting reflect that Costlow contacted Kreitzer. However,

the transcript of that meeting indicates that a member of the Board’s staff did so.

“ Thus, even the remaining Board member (Fournier) who voted in favor of the permit

application in 2001 voted to approve the findings as a reflection of the basis for the

majority vote denying that application. The fourth member who voted to accept the

findings was Guerette, who was present as a non-voting member during the 2001

hearings. The vote to approve the findings in 2002 thus reflected the judgment of the

2001 voting members that the findings reflected the majority view and on a collateral

determination that the findings also represented the views of the 2001 member who no

longer served as a Board member in 2002. .

It should also be noted that Harold Wheeler and David Clark were members of the

Board as it was constituted in 2002 but were not members of the 2001 Board when it

originally considered Widewaters’ applications. They abstained from the 2002 vote of

whether to approve the proposed findings of fact.

5 Section 165-114(1) is the factor that this court found unconstitutional in the order that

subsequently was vacated by the Law Court.

of these three provisions, section 165-114 requires the Board to “consider the following

features and impacts before granting approval: . . . (J) Whenever situated, in whole or in

part, within 250 feet of any pond, lake, river, stream or tidal waters, whether any project

will not adversely affect the shoreline of such body or water.” On this issue, the Board

issued the following findings:

Member Lingley and Kreitzer found that the outflow of the detention pond would

have a negative impact on the stream at the project site. Additionally, a majority

concludes that the shoreline would be affected as stated in paragraph I, above. To

the extent that the shoreline provides nesting areas, it too would be affected as

stated in paragraph I, above. Members Costlow and Lingley also find that the

proposed detention pond is insufficient to address temperature, volume, and water

quality issues which would affect the shoreline downstream. (See testimony of

Dr. Andren.)

R. 1-6 at p.7. As a result, the Board issued its findings dated May 7, 2002,° again denying

Widewaters’ application for site plan approval and approving its application for two

conditional use permits. Widewaters has filed this appeal from that decision.

On this appeal, Widewaters argues that the Board’s 2002 findings and decision

are tainted by an ex parte communication, that the City and BACORD have waived their

right to be heard in support of the Board’s decision as it is presently framed, that the

Board’s findings are not supported by the evidence, and that the three sections on which

the Board denied the application are unconstitutional. The court has considered the

parties’ written arguments on these issues.

1. Ex parte communications

In reviewing the administrative record, the Law Court concluded that the Board’s

findings were insufficient to the point where judicial review was “severeiy hamperjedj

....The majority of the Board should have stated the basis of the denial of the permit and

should have made factual findings underlying the decision.” 2002 ME 27, { 11, 790 A.2d

at 600. To cure that problem, in its mandate the Court remanded the matter back to this

® The May 7 date is in error. The record makes clear that the findings were adopted as a

result of the May 21 meeting. This discrepancy in dates would probably have

significance only to the timeliness of Widewaters’ appeal from that decision. That appeal

was filed on June 20, which would be within 30 days of the date the findings in fact were

issued. The appeal is therefore timely under rule 80B(b), which governs this case by

virtue of section 165-11(F) of the City’s ordinance.

court “with instructions [for this court] to remand to the Bangor Planning Board to issue

findings of fact.” Kreitzer was one of the members of the three-member majority of the

Board as it was constituted in 2001. However, he was no longer a member of the Board

when it received the case on remand. Accordingly, as a means to secure the basis for

Kreitzer’s vote on the application, he was contacted by a current Board member or by a

member of the Board’s staff. His conclusions, as expressed to that contact person, were

then integrated into the findings of fact issued by the Board on remand. Kreitzer did not

attend either of the May 2002 Board meetings where the nature of the Board’s factual

findings was addressed. Here, Widewaters argues that the contact with Kreitzer was

improper. An allegation of an improper ex parte communication may be pursued as part

on arule 80B appeal either on the basis of the administrative record or through a trial of

the facts. Baker’s Table, Inc. v. City of Portland, 2000 ME 7, { 9, 743 A.2d 237, 240-41.

In support of its argument, Widewaters relies on Mutton Hill Estates v. Town of

Oakland, 468 A.2d 989 (Me. 1983). There, the Law Court found a conclusive violation

of a permit applicant’s rights to procedural due process when a municipal body prepared

findings of fact with the participation of “admittedly biased opponents of the application”

and where the applicant had not received notice of that process and was not afforded an

opportunity to be heard. Id. at 992. This result would obtain if either the applicant’s

opponent presented evidence to the municipality in that ex parte process or, even without

the presentation of such evidence, the opponents “unduly influenced members of the

Board in making findings of fact unfavorable to the applicant’s proposal.” Id.

The circumstances of the Board’s contact with Kreitzer here are fundamentally

the Board to articulate the factual basis for its 2001 decision denying Widewaters’ site

development application permit. One of those decision-makers was no longer on the

Board. Although there may have been other methods to obtain that former member’s

participation in the process that resulted in the findings of fact, one such approach was

simply to seek his views through the informal process used here. That was accomplished

by a Board member or by a member of the Board’s staff. This is not considerably

different than the process that was used with the other Board members, who, at a time

other than during a Board meeting, reviewed the several draft sets of findings and

ultimately approved one of them. The record on this appeal, which is the manner in

which Widewaters has elected to present this issue, does not suggest any improprieties in

the contact with Kreitzer.

More importantly, the contact between the Board representative and Kreitzer does

not implicate the substantive problems created by ex parte contact condemned in Mutton

Hill. There, partisans met ex parte with the decision-makers. Here, Kreitzer met either

with a staff member or with Costlow. This court previously rejected Widewaters’ claim

that Costlow was not impartial, and Widewaters does not advance any additional

argument that Costlow was biased. Further, it has made no argument at all that the

Board’s staff was biased. Therefore, the contact between Kreitzer and the Board

representative carries none of the taint that undermined the process in Mutton Hill.

Accordingly, the court concludes that the portion of the findings attributed to Kreitzer are

not the product of improper contact and that Widewaters’ right to due process were not

compromised by the manner of his participation.

2. Waiver of argument

Widewaters next contends that the City and BACORD are barred in this action

from defending the Board’s findings that its application did not satisfy the criteria set out

in sections 165-114(D) and (J). This argument is premised on the nature of those parties’

arguments in the appeal from the Board’s 2001 decision denying Widewaters’ site

development permit application. Widewaters reasons that, during the first appeal in this

matter, the arguments of the City and BACORD were limited to an analysis of section

165-114(1) and that in this proceedings those parties therefore have waived any argument

defending the Board’s reliance on subsections (D) and (J).

This argument, however, overlooks the essence of the Law Court’s decision in

the first appeal. In that first appeal, Widewaters, the City and BACORD all certainly

proceeded on the premise that the Board’s decision rested entirely on section 165-114().

Indeed, the parties’ arguments regarding the basis for the Board’s decision did not go

beyond that one provision. Further, this court construed the Board’s findings in the same

way, and the basis for the resulting opinion rested entirely on an examination of that

isolated provision. However, the Law Court examined the same record and concluded

that the record did not adequately reveal the basis for the Board’s decision to deny

Widewaters’ application. Widewaters Stillwater Co., 2002 ME 27, {11, 790 A.2d at

600.’ The Law Court specifically pointed out that the record did not clearly disclose

whether (as the parties and this court had believed) the Board’s decision was based on

section 165-114(1). Id., 790 A.2d at 600-01. If the Board’s decision clearly rested on

that one provision, then it would be appropriate to consider the constitutionality of that

ordinance. Id., 790 A.2d at 601. However, because the record did not foreclose the

possibility that the Board denied Widewaters’ application on the basis of some other

provision of section 165-114, the Board would be required to provide that clarification.

Id. Then, the court could engage in a more meaningful analysis of the decision.

It follows that the post-remand clarification required of the Board would not only

give the courts a foundation for meaningful appellate review, but it would also allow the

parties and the intervenor to know the reasons for the Board’s ruling and, from that, the

nature of the appellate issues that should be pursued. Thus, none of the parties —

including Widewaters itself — can properly be deemed to have waived any argument that

is generated by the Board’s proper findings. As it turned out from the Law Court’s

- decision and the findings subsequently issued by the Board, the parties and this court did

not comprehensively categorize the Board’s findings in the first appeal. Because the

basis for the Board’s 2001 decision was seen too narrowly during the first appeal, the

arguments of the parties and the intervenor were also too narrow in scope in that first

action. The basis for the Board’s 2001 decision was not brought into plain view until the

Board issued its findings in May 2002. Now with the benefit of the Board’s

comprehensive findings, the parties and the intervenor all are now in a position to engage

in a full appellate analysis of the resusting decision, and they cannot be limited to

something less than that.

3. Sufficiency of the evidence

As is noted above, a majority of the Board concluded in its 2002 findings that

Widewaters’ permit application failed to satisfy three of the eleven considerations found

in section 165-114. Widewaters urges here that the evidence was insufficient to support

7 This element of the Law Court’s holding disposes of Widewaters’ argument that the

record clearly shows that the Board must have rested its decision to deny the application

on the basis of section 165-114(1). If that were apparent from the record, there would be

no need for the remand ordered by the Court.

that finding. Because Widewaters was the applicant, it now must demonstrate that the

Board was compelled to reach a contrary result. Veilleux v. City of Augusta, 684 A.2d

413, 415 (Me. 1996). On this issue, the court examines the record and reviews the

Board's findings “for an abuse of discretion, error of law, or findings unsupported by

substantial evidence in the record.” Cumberland Farms, Inc. v. Town of Scarborough,

1997 ME 11, 7 3, 688 A.2d 914, 915. "Substantial evidence is evidence that a reasonable

mind would accept as sufficient to support a conclusion. . . .The possibility of drawing

two inconsistent conclusions from the evidence does not make the evidence

insubstantial." Sproul v. Town of Boothbay Harbor, 2000 ME 30, { 8, 746 A.2d 368, 372

(citation omitted).

As articulated by the Board in its 2002 findings, one of the three factors

underlying the decision to deny Widewaters’ application is found in section 165-1144),

which requires the Board to “consider the following features and impacts before granting

approval: .. . (J) Whenever situated, in whole or in part, within 250 feet of any pond,

lake, river, stream or tidal waters, whether any project will not adversely affect the

shoreline of such body or water.” A majority of the Board concluded that Widewaters’

plan did not satisfy this requirement.

Widewaters’ development plan included the creation of a 5 feet deep detention

pond. See R. H-1 at 6. The purpose of the detention pond is to catch water and other

substances (both solid and liquid) that run off the impervious surfaces of the

development, such as buildings, paved parking areas, roads and walkways. Jd. An

engineer involved in the development plans testified that the pond was intended to collect

that runoff from the impervious area and then allow only water to be discharged into the

stream. Id. at 7. The written plan submitted by Widewaters noted that the total

impervious area covers more than 18 acres, or two-thirds, of the 28 acre parcel. See R.

G-4. The location and configuration of the proposed detention pond is shown in several

of the plans that make up exhibit G-9 of the record on this appeal. It was designed in a

way “to fit into the topography” and to locate it as close as possible to the proposed

buildings. See R. H-1 at 6. Although the buildings, parking areas and other aspects of

the “development” would be located more than 250 feet from the stream, the architect for

the proposal advised the Board that “a good portion” of the detention pond is within 250

feet of the stream. See R. H-2 at 3.

One of the opponents who presented testimony at the Board’s March 20, 2001,

hearing was Richard Andren, who was a retired professor of biology and environmental

studies. See R. H-1 at 23. He explained to the Board that he had reviewed Widewaters’

submissions regarding runoff from the impervious areas. Jd. Andren said that the

Penjajawoc Stream has the capacity to tolerate runoff caused by existing development.

The detention pond is designed to allow water that is collected in it to enter the stream

slowly. Id. He projected, however, that with a rainstorm or snowmelt, because the runoff

from the proposed development will be directed entirely into the detention pond and then

eventually into the stream, “the character of the stream from that point on will be altered”

because a greater volume of water will be directed into the stream, and that water would

enter the stream more quickly than it does naturally (that is, without the creation of a

large impervious surface). Id. at 24. This causes the soil in the stream to become

unstable, thereby causing silt that “literally suffocates the stream’s inhabitants.” Id.

That has a consequential effect on other animals in the food chain. Id. Additionally,

because of the large impervious area associated with the proposed development, the

water table in the area would be lowered. Jd. During dry periods, there would be a

reduction of water in the stream compared to its present state, and then during rainstorms,

there would be a surge of water that would create erosion and change the course of the

stream. Id.

Andren also stated that debris ultimately would be washed into the stream. Id. at

24. Other contaminants, such as oil or gas from the parking areas and nutrients from the

garden center of the proposed store, would also enter the stream. Id. at 24, 25.

Another witness at the public hearing held by the Board was Chandler Morse, a

University of Maine graduate student in ecology and environmental science who had

conducted a study on the effects of urban development on streams in Maine. Morse

found that major stream components, such as water quality, the physical integrity of the

stream and waterlife, degrade when 6 percent of the watershed is rendered impervious.

See H-1 at 27. Without the proposed development, 7 percent of the Penjajawoc

watershed already was impervious. Jd. at 28. From that, Morse stated that “any further

development inside that watershed is going to have significant issues with both the

physical water quality and the benthic community [plants and animal living in or near

water].” Id. Morse also explained that the detention pond is designed to accommodate a

25 year rainstorm. Id. However, that is an average assessment and is not an assurance

that such significant storms would not occur more frequently. Jd.

The majority of the Board expressly accepted and relied the testimony of Andren,

Morse and several other witnesses. See R. I-6 at 6-7. Based largely on that evidence, a

majority of the Board concluded that the development project would adversely affect the

shoreline of the Penjajawoc Stream and that the application therefore did not satisfy the

criterion set out in section 165-114(J) of the City’s ordinance. More specifically, the

majority concluded that, among other things, the development would result in an erosion

of the streambed, in increased pollution in the stream water and a destruction of habitat.

Id. Further, two members of the majority (Lingley and Kreitzer)“‘found that the outflow

of the detention pond would have a negative impact on the stream at the project site.” Id.

at 7. Lingley and Costlow found that the water volume and quality would be affected

downstream. Jd. Consequently, each of the three majority members of the Board

concluded that the proposed development would adversely affect the shoreline of the

Penjajawoc Stream. Those three Board members agreed on least one of the bases for this

finding. The record provides evidentiary support for this finding, as well as for the two

plurality findings in which all three of the majority members participated.

Widewaters contends here that the findings made orally by some of these Board

members at the conclusion of the April 3, 2001, hearing undermine the written findings

issued in May 2002 and therefore demonstrate that there is insufficient evidence to

support the latter. A full and fair review of those oral comments, however, reveals that

the Board members who voted to deny Widewaters’ permit application in 2001 expressed

fundamental concern about the adequacy of the detention pond to protect the stream.

Kreitzer made reference to Morse’s testimony as well as “other evidence which speaks to

the nature of the run-off and what happens with impervious services.” See R. H-2 at 9.

Lingley said, “clearly this buffer zone is very important to the ecology of the area and Pll

tell the applicant that if the [detention] pond were outside of this 250 foot zone, I could

support the application, but as it has been presented to us tonight, I couldn’t and

10

therefore, I would have to vote against it on that single basis.” Id. at 10. It is clear from

Lingley’s explanation that the basis for his vote was the proximity of the detention pond

to the stream and the consequential impact on the stream’s ecology. This concern falls

squarely within the scope of section 165-114(J). Finally, Costlow agreed with Lingley’s

assessment that the location of the detention pond within 250 feet of the stream was an

influential factor in his analysis. Id. at 12. Each of these remarks directly implicates the

shoreline issues that were developed in the evidence presented to the Board. Therefore,

even if the findings made by the Board at the conclusion of the 2001 administrative

process may be used to impeach the written findings issued later, then those oral findings

do not have that effect.

Finally, Widewaters argues that the Board’s decision is undermined because it

was based in part on consideration of the effects of the detention pond on the shoreline

more than 250 feet away from the project site. “The interpretation of the provisions of a

zoning ordinance is a question of law... .” Kurlanski v. Portland Yacht Club, 2001 ME

147, 9 9, 782 A.2d 783, 786. Language used in a municipal ordinance must be construed

in a way that is reasonable, that takes into account its specific purpose and general

structure, and that does not lead to “absurd, illogical or inconsistent results.” Id. (internal

punctuation omitted).

The plain terms of section 165-114(J) require the Board to consider the effects of

a proposed development, “[w]henever situated, in whole or in part,” on a shoreline if that

project would be located within 250 of any stream or other body of water. The ordinance

does not limit the Board and prevent it from considering the project’s effect on that

watercourse beyond the 250 foot perimeter. Such a restriction wouid be ijiogicai and

inconsistent with the stated purposes of the ordinance, which, among other things, is “to

prevent and control water pollution; to protect fish spawning grounds, aquatic life and

bird and other wildlife habitat; to protect buildings and lands from flooding and

accelerated erosion;. . . to protect freshwater and coastal wetland; to conserve shore

cover. . .; and to anticipate and respond to the impacts of development in shoreland

areas.” CITY OF BANGOR, MAINE LAND DEVELOPMENT CODE § 165-1(H). As Widewaters

construes section 165-114(J), the Board would be authorized to consider the adverse

shoreline impact caused by a development project up to 250 feet from the project site but

11

then turn a blind eye toward any effects that occur 251 away and beyond that

geographical boundary. Here, however, the evidence on which the Board based its

findings demonstrates that the riparian effects of development can be more far-reaching.

As long as there exists a stream within 250 feet of the project site, section 165-114(J)

requires the Board to examine any adverse consequence — even those that may occur to

that part of the stream that is not within 250 feet of the site.

For these reasons, the administrative record supports the Board’s finding that .

Widewaters’ site development application did not satisfy the condition set out in section

165-114(J). This finding, taken alone, was a sufficient basis on which to deny the permit

application. As is discussed below in the context of Widewaters’ constitutional challenge

to section 165-114, the court construes subsection (J) as creating a necessary (but not

sufficient) condition to the issuance of a site development permit. The introductory

paragraph to section 165-114 requires the Board to “consider the following features and

impacts before granting approval... .” One of those “impacts” is identified in subsection

(J). Subsection (J) obligates the Board to determine “whether any project will not

adversely affect the shoreline” of a body of water located within 250 feet of the project

(emphasis added). The formulation of subsection (J) is different than that of most of the

other factors, which simply describe the subject that the Board must address. For

example, the Board is also required to consider parking and loading areas (section 165-

114(B)), storm water drainage (section 165-114(D)), outdoor lighting (section 165-

114(E)) and other aspects of the proposed development. In contrast, when the Board

examines the factor specified in section 165-114(J), it must find that the project “will not

Such a result is not an impossibility, as revealed by this record. Indeed,

Widewaters presented evidence to the Board that the detention pond would allow “water

and only water” to discharge. See R. H-1 at 7. Therefore, this construction of section

165-114(J) coheres with the conventional principles of construction of municipal

ordinances and, in fact, flows from the evidentiary analysis offered by Widewaters.

Therefore, because the Board was entitled to conclude that Widewaters had not

satisfied section 165-114(J) and because that failure of proof was fatal to the site

development permit application, the court need not and therefore does not address the

12

parties’ remaining contentions regarding the other two provisions (sections 165-114(D)

and (I)) at issue here.

4, Constitutional challenge

Finally, Widewaters argues that the three provisions of the ordinance on which

the Board based its decision are unconstitutional because they embody an illegally

excessive delegation of authority to the Board. For the reasons noted above, the court

addresses only this argument as it implicates section 165-114(J).

In its May 31, 2001, order, this court discussed the legal principles underlying the

different roles between a legislative body, such as a city council, that enacts zoning

ordinances and an administrative body, such as a planning board, that is charged with

implementing those ordinances by applying them to specific permit applications. The

court incorporates the May 2001 order and does not reiterate that discussion here. For

purposes of this order, it is sufficient to note that in the end, a planning board may be

given only the authority “to hear and decide whether the applicant has met those factual

conditions” necessary to obtain a permit. Wakelin v. Town of Yarmouth, 523 A.2d 575,

577 (Me. 1987). Stated conversely, the administrative body cannot properly be given

“discretion. . .as to whether or not to grant the permit if the conditions stated in the

ordinance exist.” Stuckiv. Plavin, 291 A.2d 508, 511 (Me. 1972).

For the reasons noted above, the court construes section 165-114(J) to require an

applicant to satisfy the Board, as a factual matter, that the proposed development project

“will not adversely affect the shoreline of” a stream that is located within 250 of any part

of the project. This construction is warranted not only for the reasons noted above, but,

watt ee nd AL p11. 7

ULLON al CHALICUES,

fal 2

id

cm ee L. L wlll 4s nan ~

tis CONnSsiut 107 t t

in the face © or the additional reason that this construction,

which is warranted by the language and purpose of the ordinance, also avoids even the

argument that Widewaters advances here. See Irish v. Gimbel, 1997 ME 50, { 6, 691

A.2d 664, 669. This comports with the principle that legislation should be construed in a

way that does not render it unconstitutional.

Seen in this way, section 165-114(J) leaves no room for discretion. The Board is

not entitled to exercise any judgment regarding policy, because the policy is established

in that provision: development is not permitted if it would adversely affect such a

shoreline. Further, the tight formulation of that provision forecloses the “selectivity” that

13

is one of the evils of an unconstitutional delegation, see Town of Windham v. LaPointe,

308 A.2d 286, 293 (Me. 1973). Finally, it provides the applicant with very specific

notice of a requirement that it must satisfy in order to obtain a permit. Wakelin, 532 A.2d

at 577. Because of the qualitatively different structures between subsections (I) and (J),

the Board’s obligation to “consider” both of them has very different consequences. Even

if Widewaters is correct in its conclusion that the Board has discretion of legislative

magnitude because it is merely required to “consider” some of the factors, that flexibility

and discretion vanishes when the Board concludes under section 165-114(J) that a

proposed development would have an adverse affect on the shoreline of a stream located

within 250 feet of the development. Therefore, if the Board’s obligation to “consider”

other particular features and impacts is an impermissible delegation of policy-making

authority, that flaw — if it is one, see Order dated May 31, 2001, at

13-14 --, does not affect section 165-114(J).

Therefore, the court concludes that section 165-114(J) does not unconstitutionally

defer the policy prerogatives of a legislative body to the Planning Board. The court need

not and does not address the remaining constitutional challenges raised here by

Widewaters.

The entry shall be:

For the foregoing reasons, the decision of the Bangor Planning Board to deny

Widewaters’ application for a site development permit is affirmed.

Z if a

Dated: March 25, 2003 SE Vina

Justice, Maine Superior Court

14

6/20/02 Penobscot

Docket No.

Date Filed

County

Action Rule 80B Appeal

AP-2002-12

ASSIGNED TO JUSTICE JEFFREY L. HJELM

WIDEWATERS STILLWATER CO. LLC

BACORD (9/8/02)

vs. CITY OF BANGOR

Plaintiff's Attorney

Stephen Langsdorf, Esq.

Virginia Davis, Esq.

Defendant’s Attorney

JOHN HAMER, ESQ

73 HARLOW STREET

Preti-Flahérty Beliveau Pachios & Haley BANGOR, ME. 04401

P O Box 1058 GROSS, MINSKY & MOGUL, P.A.

Anonuetra ME 04229— 1NS58 ™~ A mA ALD

Augusta Ma Uses or eee F O BOX Si7

BANGOR ME 04402-0917

BY: EDWARD W. GOULD, ESQ.

FOR: BACORD

Date of

Entry

6/20/02 Complaint (Rule 80B) filed.

6/20/02 Notice and Briefing Schedule ‘Rule 80B Appeal of Governmental Actions

forwarded to attorney for the Appellant.

6/25/02 Entry of Appearance filed by John Hamer, Esq. for Defendant City of Bangor.

6/25/02 Notice and Briefing Schedule Rule 80B Appeal of Governmental Actions

forwarded to attorney of the Defendant. .

6/25/02 BACORD's Motion to Intervene filed by Gross, Minsky & Mogul, P.A.

6/25/02 Answer of Intervenor BACORD filed by Gross, Minsky & Mogul, P.A.

7/9/02 Defendant's Response to Bacord's Motion to Intervene filed.

7/15/02 | Plaintiff's Objection to BACORD's Motion to Intervene filed.

7/26/02 File presented to Justice Hjelm for review.

7/26/02 Motion to Extend Time for Filing Brief and Record filed by Plaintiffs.

7/29/02 This matter is now before the Superior Court on the plaintiff's appeal

from the City of Bangor Planning Board, following remand to the Board from

the Law Court. Under the provisions of the Single Justice Assignment

Program, this case has been re-assigned to me. Within 14 days of this

order, counsel for the parties and the prospective intervenor shall advise

the clerk in writing of whether any such party seéks recusal, does not seek

or wishes to be heard further prior to formulating either position. If the

clerk is advised of a position, that advice shall constitute a

representation that counsel has fully conferred with the party or

prospective intervenor regarding this order. Until this issue is resolved,

I will take no further action in this matter. The entry shall be: Order

issued on potential recusal issue. (Hjelm, J.) Copy forwarded to all

attorneys of record.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.