Opinion

Speed Way Transp., L.L.C. v. Gahanna

  • 2024 Ohio 5890
Court
Ohio Court of Appeals
Filed
Dec 17, 2024
Status
Published
On the bench
Luper Schuster
Cited by
0 cases
Authority
More cited than 33.3%

The opinion

[Cite as Speed Way Transp., L.L.C. v. Gahanna, 2024-Ohio-5890.]

IN THE COURT OF APPEALS OF OHIO

TENTH APPELLATE DISTRICT

Speed Way Transportation, LLC, :

dba Speed Way Towing,

: No. 24AP-141

Plaintiff-Appellant, (C.P.C. No. 18CV-10373)

:

v. (REGULAR CALENDAR)

:

City of Gahanna,

:

Defendant-Appellee.

:

D E C I S I O N

Rendered on December 17, 2024

On brief: Michael A. Partlow, for appellant. Argued:

Michael A. Partlow.

On brief: Frost Brown Todd LLP, Frank J. Reed, Jr., and

Jesse J. Shamp, for appellee. Argued: Frank J. Reed, Jr.

APPEAL from the Franklin County Court of Common Pleas

LUPER SCHUSTER, J.

{¶ 1} Plaintiff-appellant, Speed Way Transportation, LLC, doing business as Speed

Way Towing (“Speed Way”), appeals from a decision and entry of the Franklin County

Court of Common Pleas granting the motion for summary judgment of defendant-appellee,

City of Gahanna. For the following reasons, we affirm.

I. Facts and Procedural History

{¶ 2} This case relates to Gahanna’s rejection of Speed Way’s proposal application

to operate a vehicle towing business as an agent of the city. In 2017, Gahanna published a

request for proposals of bids from towing companies to act as an agent of the city related to

Gahanna’s police towing needs. Gahanna does not own or maintain its own tow trucks for

use in police towing and hauling functions. The request for proposals included various

No. 24AP-141 2

specifications required of any bidder that wished to be considered for a towing contract. In

the request for proposals, Gahanna expressly stated it “shall have the sole responsibility of

making final judgment as to acceptability of the equipment and the facilities preferred by

the bidder and shall have full option to reject all bids.” (June 2, 2022 Mot. for Summ. Jgmt,

Ex. 1 at 6.)

{¶ 3} Speed Way operated a towing company located within Gahanna. Ahmed

Shehata, an agent of Speed Way, averred he first located the property he wished to use to

operate his towing company in 2016 and immediately contacted Gahanna to inquire

whether he could operate a towing business on the property. Speed Way undertook various

improvements of the property in order to obtain conditional use approval from Gahanna

for Speed Way’s business operations, including installing a wood fence, placing a large

water tank and trailer on the property with restroom facilities, and installing an accessibility

ramp. The city approved Speed Way’s conditional use application on May 26, 2017.

{¶ 4} While Speed Way was in the process of improving the property, Shehata met

with representatives of the city at various times. Shehata said these representatives

informed him of the changing improvements needed for approval of his conditional use

application. During a February 2017 meeting with Gahanna’s mayor and other

representatives, Shehata “was told Speed Way could get a contract to tow motor vehicles

for Gahanna.” (Shehata Aff. at ¶ 25.) In another meeting, in May 2017, Shehata averred

the mayor stated that “Speed Way should be able to get a towing contract with Gahanna as

Gahanna had only two such contracts at the time and wanted to add two more.” (Shehata

Aff. at ¶ 29.)

{¶ 5} After it had obtained its conditional use permit for the premises, Speed Way

submitted a towing proposal application on July 19, 2017 in response to the city’s request

for proposals. Gahanna did not accept Speed Way’s bid. In an August 14, 2017 letter to

Speed Way, the city stated it rejected Speed Way’s bid for the towing contract because: (1)

Speed Way’s vehicle storage area lacked a hard surface with proper drainage, (2) Speed

Way’s property did not have a storage area enclosed by a chain link fence, and (3) Speed

Way’s vehicle storage area did not comply with applicable city ordinances. The city notified

Speed Way it intended to reopen the request-for-proposal period again in 2020.

No. 24AP-141 3

{¶ 6} On December 13, 2018, Speed Way filed a complaint against Gahanna,

asserting claims for declaratory judgment, promissory estoppel, and recovery of the costs

of its bid preparation. Gahanna moved for judgment on the pleadings, and the trial court

subsequently granted the motion in a March 25, 2020 decision and entry. Speed Way

timely appealed, and this court reversed the trial court’s decision with respect to the claims

for promissory estoppel and declaratory judgment. Speed Way Transp., L.L.C. v.

Gahanna, 10th Dist. No. 20AP-239, 2021-Ohio-4455 (“Speed Way I”). In Speed Way I, we

determined the trial court erred in granting judgment on the pleadings as to the promissory

estoppel claim because Gahanna failed to show, from the pleadings, that no factual issues

exist on the question of whether it was engaged in a governmental function. Speed Way I

at ¶ 24. Additionally, we determined the trial court erred in granting judgment on the

pleadings as to the declaratory judgment claim because Gahanna failed to show, from the

pleadings, that no factual question remained as to whether it abused its discretion in its

public contract decision-making. Id. at ¶ 32-33. Thus, we remanded the matter for further

proceedings related to the promissory estoppel and declaratory judgment claims. Id. at

¶ 39-40.

{¶ 7} On remand, the parties engaged in additional discovery. Gahanna then

moved for summary judgment on June 2, 2022, arguing there remained no genuine issue

of material fact that it was engaged in a governmental function and that the city did not

abuse its discretion in rejecting Speed Way’s bid for the towing contract. Speed Way filed

a memorandum in opposition on July 20, 2022 and a corrected memorandum in

opposition on August 3, 2022.

{¶ 8} Subsequently, in a February 2, 2024 decision and entry, the trial court

granted the city’s motion for summary judgment. The trial court determined Speed Way

could not maintain its promissory estoppel claim because the city was engaged in a

governmental function. Further, the trial court determined Speed Way could not show the

city abused its discretion in rejecting its towing contract bid. As a result, the trial court

determined the city was entitled to judgment on both the promissory estoppel claim and

the declaratory judgment claim. Speed Way timely appeals.

II. Assignments of Error

{¶ 9} Speed Way assigns the following two assignments of error for our review:

No. 24AP-141 4

I. The trial court erred as a matter of law by granting summary

judgment to defendant on plaintiff’s claim for promissory

estoppel.

II. The trial court erred as a matter of law by granting summary

judgment as to plaintiff’s claim for declaratory judgment.

III. Standard of Review and Applicable Law

{¶ 10} An appellate court reviews summary judgment under a de novo standard.

Estate of Sample v. Xenos Christian Fellowship, Inc., 10th Dist. No. 20AP-563, 2021-Ohio-

3898, ¶ 9. Summary judgment is appropriate only when the moving party demonstrates:

(1) no genuine issue of material fact exists, (2) the moving party is entitled to judgment as

a matter of law, and (3) reasonable minds could come to but one conclusion and that

conclusion is adverse to the party against whom the motion for summary judgment is made,

that party being entitled to have the evidence most strongly construed in its favor. Civ.R.

56(C); State ex rel. Grady v. State Emp. Relations Bd., 78 Ohio St.3d 181, 183 (1997).

{¶ 11} Pursuant to Civ.R. 56(C), the moving party bears the initial burden of

informing the trial court of the basis for the motion and identifying those portions of the

record demonstrating the absence of a material fact. Dresher v. Burt, 75 Ohio St.3d 280,

293 (1996). However, the moving party cannot discharge its initial burden under this rule

with a conclusory assertion that the nonmoving party has no evidence to prove its case; the

moving party must specifically point to evidence of the type listed in Civ.R. 56(C)

affirmatively demonstrating that the nonmoving party has no evidence to support the

nonmoving party’s claims. Id.; Vahila v. Hall, 77 Ohio St.3d 421, 429 (1997). Once the

moving party discharges its initial burden, summary judgment is appropriate if the

nonmoving party does not respond, by affidavit or as otherwise provided in Civ.R. 56, with

specific facts showing that a genuine issue exists for trial. Dresher at 293; Vahila at 430;

Civ.R. 56(E).

IV. First Assignment of Error – Promissory Estoppel

{¶ 12} In its first assignment of error, Speed Way argues the trial court erred in

granting the city’s motion for summary judgment on the promissory estoppel claim.

{¶ 13} As we explained in Speed Way I, the doctrine of promissory estoppel provides

“ ‘[a] promise which the promisor should reasonably expect to induce action or forbearance

on the part of the promisee or a third person and which does induce such action or

No. 24AP-141 5

forbearance is binding if injustice can be avoided only by enforcement of the promise.’ ”

(Further quotations and citations omitted.) Speed Way I at ¶ 18, quoting Hortman v.

Miamisburg, 110 Ohio St.3d 194, 2006-Ohio-4251, ¶ 24. A plaintiff proves a claim for

promissory estoppel by demonstrating: (1) a clear and unambiguous promise, (2) reliance

by the party to whom the promise is made, (3) the reliance is reasonable and foreseeable,

and (4) injury as a result of the reliance on the promise. Id., citing Mocznianski v. Ohio

Dept. of Medicaid, 10th Dist. No. 18AP-894, 2020-Ohio-165, ¶ 24. See also Fluellen v.

Miller, 10th Dist. No. 23AP-472, 2024-Ohio-265, ¶ 21, citing Malempati v. Indep. Inpatient

Physicians, Inc., 10th Dist. No. 12AP-565, 2013-Ohio-3543, ¶ 25.

{¶ 14} Speed Way asserted a claim for promissory estoppel based on alleged

promises representatives of the city made to it related to its ability to secure a contract with

Gahanna to operate its towing business for the city’s police department. Generally, “a

political subdivision is not liable in damages in a civil action for injury, death, or loss to

person or property allegedly caused by any act or omission of the political subdivision or an

employee of the political subdivision in connection with a governmental or proprietary

function” unless an exception applies. R.C. 2744.02(A)(1). However, without exception,

“the doctrine of promissory estoppel is ‘inapplicable against a political subdivision when

the political subdivision is engaged in a governmental function.’ ” Speed Way I at ¶ 18,

quoting Hortman at ¶ 25. The issue, therefore, is whether Gahanna demonstrated in its

motion for summary judgment it was engaged in a governmental function when it sought

bids for towing services.

{¶ 15} R.C. 2744.01(C) defines “governmental function.” As relevant here, the

statute provides:

(1) “Governmental function” means a function of a political

subdivision that is specified in division (C)(2) of this section or

that satisfies any of the following:

(a) A function that is imposed upon the state as an obligation

of sovereignty and that is performed by a political subdivision

voluntarily or pursuant to legislative requirement;

(b) A function that is for the common good of all citizens of the

state;

No. 24AP-141 6

(c) A function that promotes or preserves the public peace,

health, safety, or welfare; that involves activities that are not

engaged in or not customarily engaged in by nongovernmental

persons; and that is not specified in division (G)(2) of this

section as a proprietary function.

(2) A “governmental function” includes, but is not limited to,

the following:

(a) The provision or nonprovision of police, fire, emergency

medical, ambulance, and rescue services or protection;

***

(e) The regulation of the use of, and the maintenance and repair

of, roads, highways, streets, avenues, alleys, sidewalks, bridges,

aqueducts, viaducts, and public grounds[.]

R.C. 2744.01(C)(1) through (2)(a) and (e).

{¶ 16} In Speed Way I, we determined the trial court erred in granting judgment on

the pleadings on the promissory estoppel claim because Gahanna failed to allege facts in its

answer demonstrating it was engaged in a governmental function when it requested

proposals for contracts for towing services. Speed Way I at ¶ 22. On remand, in support

of its motion for summary judgment, Gahanna relied on the affidavit of Jeffrey Spence, the

Chief of Police for Gahanna, who averred Gahanna does not own and/or maintain the

equipment capable of performing towing and hauling services for vehicles left on the city’s

roadways and streets. Chief Spence averred that securing a towing contract bid would allow

the city to utilize a private company to remove abandoned and damaged vehicles from the

city streets, alleviating safety hazards to the public. Gahanna argues this activity satisfies

the definition of governmental function contained in R.C. 2744.01(C)(2)(e) by being the

“regulation of the use of, and maintenance and repair of, roads, highways, streets, avenues,

[and] alleys.” (Mot. for Summ. Jgmt. at 8.) Further, Gahanna asserts the towing services

for which it sought bids falls under the provision of police services or protection, as

provided in R.C. 2744.01(C)(2)(a). In support of this position, Gahanna notes Chief Spence

stated in his affidavit that the private towing company is used to tow vehicles that are stolen

or involved in crimes to the City’s police station to be impounded and inventoried, and then

hauled to a private lot for storage and preservation of evidence. Gahanna asserts such

activity qualifies as police services under R.C. 2744.01(C)(2)(a) and is, therefore, a

governmental function.

No. 24AP-141 7

{¶ 17} Speed Way disagrees with the characterization of the towing services as a

governmental function and instead argues the evidence establishes the towing services

should be deemed a “proprietary function” under R.C. 2744.01(G)(2)(c). More specifically,

Speed Way argues the towing company contract bids show the city was looking to operate

“a busline or other transit company” for public services, making the towing services a

proprietary function rather than a governmental function. R.C. 2744.01(G)(2)(c) (“[a]

‘proprietary function’ includes, but is not limited to * * * [t]he establishment, maintenance,

and operation of a utility, including, but not limited to, a light, gas, power, or heat plant, a

railroad, a busline or other transit company, an airport, and a municipal corporation water

supply system”). In response, Gahanna argues Speed Way’s understanding of a transit

company does not comport with the listed examples in the statute and notes there is no

Civ.R. 56 evidence demonstrating it intends to operate a transit company.

{¶ 18} As the trial court noted, Speed Way did not offer counterarguments or

evidence to refute Gahanna’s evidence demonstrating it was engaged in a governmental

function both in maintaining the roadways and in providing police services under R.C.

2744.01(C)(2)(a) and (e). Thus, the trial court determined there remained no genuine issue

of material fact as to whether Gahanna was engaged in a governmental function when it

sought bids for contracts for towing services. We agree with the trial court that Gahanna

satisfied its Civ.R. 56 evidentiary burden on remand and that there remains no dispute the

city was engaged in a governmental function.

{¶ 19} Speed Way additionally argues there remains a genuine issue of material fact

as to whether Gahanna acted in bad faith in rejecting its bid. Speed Way relies on R.C.

2744.03(A)(5) which states, in pertinent part, “[a] political subdivision is immune from

liability * * * unless the judgment or discretion was exercised with malicious purpose, in

bad faith, or in a wanton or reckless manner.” We agree with the trial court, however, that

a claim of promissory estoppel against a political subdivision that involves a governmental

function does not implicate a sovereign immunity analysis and, thus, a “bad faith”

consideration is not part of the analysis. Hortman at ¶ 13 (finding of immunity separate

from the consideration of whether promissory estoppel may be applied). Instead, the

Supreme Court of Ohio is clear that the doctrine of promissory estoppel is inapplicable

against a political subdivision engaged in a governmental function. Id. at ¶ 25. Accordingly,

No. 24AP-141 8

because Gahanna demonstrated in its motion for summary judgment it was engaged in a

governmental function, the doctrine of promissory estoppel is inapplicable, and Speed

Way’s claim for promissory estoppel must fail.

{¶ 20} Having determined the trial court properly granted summary judgment to

Gahanna on the promissory estoppel claim, we overrule Speed Way’s first assignment of

error.

V. Second Assignment of Error – Declaratory Judgment

{¶ 21} In its second and final assignment of error, Speed Way argues the trial court

erred in granting Gahanna’s motion for summary judgment on the declaratory judgment

claim.

{¶ 22} “A declaratory judgment action is a civil action and provides a remedy in

addition to other legal and equitable remedies available.” Burge v. Ohio Atty. Gen., 10th

Dist. No. 10AP-856, 2011-Ohio-3997, ¶ 7, citing Victory Academy of Toledo v. Zelman, 10th

Dist. No. 07AP-1067, 2008-Ohio-3561, ¶ 8. “ ‘The essential elements for declaratory relief

are (1) a real controversy exists between the parties, (2) the controversy is justiciable in

character, and (3) speedy relief is necessary to preserve the rights of the parties.’ ” Id.,

quoting Walker v. Ghee, 10th Dist. No. 01AP-960, 2002 Ohio App. LEXIS 252 (Jan. 29,

2002).

{¶ 23} In Speed Way I, we explained that a declaratory judgment action may lie

against a political subdivision where the political subdivision does not adhere to the terms

of its own request for proposal or where the political subdivision abused its discretion in

making its contract award. Specifically, we noted Gahanna did not have unfettered

discretion to award the towing contract but was limited by the terms of its request for

proposal. Speed Way I at ¶ 30. If the contract decision is “based on the criteria expressly

set forth in the request for proposal,” the political subdivision does not abuse its discretion

awarding the contract, and the “disappointed bidder [is] not entitled to injunctive relief in

the form of an order requiring the [political subdivision] to execute a contract with it.” Id.

at ¶ 29, citing Danis Clarkco Landfill Co. v. Clark Cty. Solid Waste Mgt. Dist., 73 Ohio St.3d

590, 604-06 (1995). We further explained that “[w]hile Ohio courts do not have the

discretion to make procurement decisions for a municipality, they do review such decisions

for an abuse of discretion.” Speed Way I at ¶ 32, citing Cedar Bay Constr., Inc. v. Fremont,

No. 24AP-141 9

50 Ohio St.3d 19, 21-22 (1990). “If a municipality abuses its discretion in awarding a public

contract, a court may grant injunctive relief.” Id. at ¶ 32, citing Cementech, Inc. v.

Fairlawn, 109 Ohio St.3d 475, 2006-Ohio-2991, ¶ 10 (“the granting of an injunction should

be done with caution,” particularly where a court is asked to “control the action of another

department of government”) (internal quotations omitted). An abuse of discretion

connotes a decision that is unreasonable, arbitrary, or unconscionable. Blakemore v.

Blakemore, 5 Ohio St.3d 217, 219 (1983); State ex rel. Deblase v. Ohio Ballot Bd., 173 Ohio

St.3d 191, 2023-Ohio-1823, ¶ 27.

{¶ 24} Our remand in Speed Way I instructed the trial court to conduct further

proceedings for consideration of whether Gahanna adhered to the terms of its request for

proposal and/or abused its discretion in not awarding Speed Way the contract. Speed Way

I at ¶ 30. Because Gahanna moved for summary judgment on the declaratory injunction

claim, the pertinent question is whether there remained a genuine issue of material fact

that Gahanna adhered to the terms of its request for proposal or abused its discretion in

not accepting Speed Way’s bid.

{¶ 25} To support its motion for summary judgment, Gahanna relied on the express

terms of the request for proposal, which states “[t]he City of Gahanna shall have the sole

responsibility of making the final judgment as to accessibility of the equipment and the

facilities preferred by the bidder and shall have full option to reject all bids.” (Mot. for

Summ. Jgmt., Ex. 1 at 6.) From this language, Gahanna asserts it had the sole discretion to

accept or reject any or all bids. Chief Spence averred in his affidavit that the city received,

considered, and reviewed Speed Way’s bid materials in the same way it evaluated the other

businesses applying for the towing contracts. When it ultimately decided not to accept

Speed Way’s bid, Gahanna took the additional step of sending the August 14, 2017 letter

explaining why it did not accept the bid. Gahanna asserts this evidence demonstrates it

adhered to the terms of its request for proposals, gave due consideration to Speed Way’s

bid, and exercised, but did not abuse, its provided discretion in rejecting Speed Way’s bid.

{¶ 26} In response, Speed Way argues Gahanna acted in bad faith when it repeatedly

recommended modifications Speed Way could make to its business only to ultimately reject

Speed Way’s bid for towing services. Speed Way also argues there remains a genuine issue

of fact as to whether Gahanna abused its discretion because, it alleges, some of the

No. 24AP-141 10

successful bidders also had unpaved surface lots, rendering Gahanna’s proffered

explanation for its rejection of Speed Way’s bid lacking in credibility. Despite these

allegations, however, Speed Way did not provide any Civ.R. 56 evidence with any specific

information about these other businesses. Further, we note that Gahanna’s acceptance of

an imperfect bid from another entity does not render its rejection of Speed Way’s bid an

abuse of discretion where the city expressly had the discretion to accept or reject any or all

bids. See Danis Clark Landfill Co. at 604 (where a municipality “substantially complie[s]”

with the criteria it announced in its request for proposals and makes its award decision

based upon the criteria expressly set forth in the bidding proposal, the municipality does

not abuse its discretion in making its award).

{¶ 27} From the Civ.R. 56 evidence presented, the trial court determined there was

no genuine issue of material fact related to Gahanna abiding by the terms of its request for

proposal or showing Gahanna abused its discretion in making its contract award

determination. We agree. Though Speed Way disagrees with Gahanna’s decision, Speed

Way does not point to any evidence demonstrating an abuse of discretion or refuting the

express language in the request for proposals giving Gahanna full discretion to accept or

reject any or all bids. Because Speed Way did not demonstrate that a question of fact

remains as to whether Gahanna acted unreasonably, arbitrarily, or unconscionably when it

did not accept Speed Way’s bid or that Gahanna otherwise did not abide by the terms of its

request for proposal, the trial court did not err in granting Gahanna’s motion for summary

judgment on the declaratory judgment claim.

{¶ 28} We overrule Speed Way’s second and final assignment of error.

VI. Disposition

{¶ 29} Based on the foregoing reasons, the trial court did not err in granting

Gahanna’s motion for summary judgment on Speed Way’s claims of promissory estoppel

and declaratory judgment. Having overruled Speed Way’s two assignments of error, we

affirm the decision of the Franklin County Court of Common Pleas.

Judgment affirmed.

MENTEL, P.J., and BEATTY BLUNT, J., concur.