“a limited liability company [] takes the citizenship of each of its members”
How later courts described this case
- “a limited liability company [] takes the citizenship of each of its members”
- describing the factors considered to determine whether a non-domiciliary has transacted business in New York, including whether the defendant has an ongoing contractual relationship with a New York corporation and whether there is a choice-of-law clause in any such contract
- explaining that although the allegations in a complaint related to liability are deemed admitted upon entry of a default judgment, a default “is not considered an admission of damages” (internal quotation marks omitted)
- a contract did not extend indemnification to actions between the parties when the agreement did not expressly indicate such an intention
Written by the judges who cited it.
The opinion
UNITED STATES DISTRICT COURT
EASTERN DISTRICT OF NEW YORK
-----------------------------------X
ECO-FUELS LLC,
Plaintiff,
- against –
MEMORANDUM & ORDER
DR. MOINUDDIN SARKER and WASTE
TECHNOLOGIES, LLC, 22-CV-250(KAM)(JAM)
Defendants.
-----------------------------------X
KIYO A. MATSUMOTO, United States District Judge:
Plaintiff Eco-Fuels LLC (“Eco-Fuels” or “Plaintiff”) brought
this action against Dr. Moinuddin Sarker and Waste Technologies,
LLC (together, “Defendants”) alleging breach of contract, fraud,
and unjust enrichment. Plaintiff seeks monetary damages,
attorneys’ fees and costs, and declaratory relief. Defendants
failed to appear or otherwise defend this action. After the Clerk
of the Court entered default against defendants pursuant to Rule
55(a) of the Federal Rules of Civil Procedure, Plaintiff filed the
instant motion for entry of default judgment. For the reasons
stated herein, Plaintiff’s motion for entry of a default judgment
is granted in part and denied in part pursuant to Rule 55(b)(2) of
the Federal Rules of Civil Procedure. Default judgment is granted
against Defendants, jointly and severally, and Plaintiff is
awarded $200,000.00 in damages, $72,352.44 in pre-judgment
interest as of February 26, 2024, and post-judgment interest from
the date judgment is entered as prescribed in 28 U.S.C. § 1961.
BACKGROUND
The following facts are taken from Plaintiff’s Complaint,
Motion for Default Judgment, supporting memorandum, and supporting
declaration and affidavits. (See ECF No. 1, Compl.; ECF No. 17-
8, Memorandum in Support of Motion for Default Judgment (“Mem.”);
ECF No. 17-3, Affidavit of Moses Kahan (“Kahan Aff.”); ECF Nos. 17-
4 through 17-7, Exhibits A through D to the Kahan Affidavit (“Aff.
Exs. A-D”); ECF No. 20, Declaration of Moses Kahan (“Kahan Decl.”);
ECF Nos. 20-1 through 20-5, Exhibits A through E to the Kahan
Declaration (“Decl. Exs. A-E”).) Given Defendants’ default, the
Court accepts as true all well-pleaded factual allegations in the
Complaint, except as to damages. See City of New York v. Mickalis
Pawn Shop, LLC, 645 F.3d 114, 137 (2d Cir. 2011).
I. Factual Background
Plaintiff Eco-Fuels LLC is a New York State limited liability
company with two members – Moses Kahan (“Kahan”), the managing
member, and Diana Glenn. (Kahan Decl. at ¶¶1, 7-8.) Both members
of Eco-Fuels are New York domiciliaries. (Id. at ¶¶9-10.)
Defendant Waste Technologies LLC (“Waste Technologies”) is a
Delaware limited liability company of which Dr. Moinuddin Sarker
(“Sarker”) is the sole member1. (Id. at ¶¶11-12.) Sarker is
domiciled in Connecticut. (Id. at ¶13.)
Sarker approached the members of Eco-Fuels in 2019 and offered
to “develop, construct, and manufacture a machine that would
convert plastic waste into fuel” (the “Machine”). (Compl. at ¶29.)
Plaintiff alleges that Sarker made representations both in
meetings with Plaintiff and on the Waste Technologies website
regarding his academic credentials and background in waste
conversion to energy. (Id. at ¶¶11-20.) Plaintiff subsequently
entered into a handwritten memorandum of understanding with
Defendants in July 2019, which was replaced by a subsequent
contract in October 2019 (the “Contract”). (Id. at ¶30.) The
contract was later amended in writing by the parties on December
22, 2019, via an addendum (the “Addendum”). (Id. at ¶31.)
The Contract represented that Defendants would “build such a
[plastic-converting] Machine for [Eco-Fuels] within six (6) months
from the date of this agreement” and that Defendants would
subsequently “lease commercial space” and allow Eco-Fuels “access
to the Space to operate the Machine for twelve months out of the
space after delivery.” (Aff. Ex. A at 1.) Defendants also agreed
to “train and teach [Eco-Fuel’s] engineer with the operational and
1 The Court notes that Kahan’s sworn declaration regarding Sarker’s status as
the sole member of Waste Technologies is supported by the contract between the
parties, which states that Sarker is the “sole owner of Waste Technologies LLC.”
(Aff. Ex. A at 1.)
maintenance and upkeep of the Machine” within two months of the
signing of the agreement, and that such training would continue
for six months after delivery of the Machine to Eco-Fuels. (Id.)
The Contract further set out a payment schedule from Eco-Fuels to
Defendants, noting that $50,000 had already been paid to Defendants
by Eco-Fuels, that $100,000 would be due within three business
days of the signing of the contract, and that progress payments of
$400,000 would eventually be due following certain milestones in
the development of the Machine. (Id. at 3.)
The parties’ December 2019 Addendum modified the payment
schedule for the Contract, noting that $165,000 had already been
paid to Defendants by Eco-Fuels, that $35,000 would be due within
five days of the signing of the Addendum, and that the subsequent
progress payments would be modified. (Aff. Ex. B. at 1.) The
Addendum also stated that “the [plastic-converting] Machine must
be one hundred percent (100%) buil[t] and functioning within sixty
(60) days from the date the Addendum B is signed.” (Id.)
On January 31, 2020, Sarker invited Plaintiff to inspect the
Machine in order to demonstrate that prior payments had in fact
been used to purchase materials to build the Machine, and that the
Machine itself was partially complete. (Kahan Aff. at ¶30.)
Plaintiff did not find the inspection satisfying, however, finding
“limited materials strewn around the shop,” and Sarker requested
that Plaintiff return for another inspection on February 18, 2020.
(Id. at ¶¶31-32.) Upon Plaintiff’s subsequent inspection on
February 18, 2020, it appeared that “some progress had been made”
but that the Machine was still not 50% complete. (Id. at ¶33.)
Sarker informed Plaintiff that he would not be able to meet the
60-day timeframe set forth in the Addendum for assembly of the
Machine. (Id. at ¶35.) Plaintiff suspended its payments under
the Addendum and Contract at that point, and sent a notice of
default under the Contract by letter dated February 23, 2020. (Id.
at ¶36.)
Plaintiff alleges that “the bulk of the funds received from
the Plaintiff were not used for the purchase of material and
Machine assembly” but were instead utilized by Sarker to “fund his
lavish lifestyle, including but [not] limited to international
travel to the City of Mecca located in Saudia Arabia, Bangladesh,
India, and Europe.” (Id. at ¶¶38-39.) In total, Plaintiff paid
Waste Technologies a total of $200,000 pursuant to the Contract
and the Addendum. (Kahan Decl. at ¶19.)
II. Procedural Background
Plaintiff commenced this action against Defendants on January
16, 2022. (See Compl.) Plaintiff’s complaint alleges fraud,
breach of contract and unjust enrichment, and seeks damages,
attorney’s fees, and a declaratory judgment regarding ownership of
the Machine2. (See id. ¶¶ 65-97.)
Plaintiff filed affidavits stating that Sarker was personally
served with the summons and complaint twice – first on January 20,
2022, and subsequently on January 24, 2022. (ECF Nos. 5, 7.)
Plaintiff filed an affidavit stating that Waste Technologies was
served on February 9, 2022. (ECF No. 6.) Subsequently, on April
14, 2022, Plaintiff filed a request for a certificate of default
against all Defendants, based on their failure to answer or
otherwise respond to the complaint. (ECF No. 8.) The Clerk of
Court entered a certificate of default against both Sarker and
Waste Technologies on April 18, 2022. (ECF No. 9.)
Plaintiff thereafter filed a motion for default judgment on
July 25, 2022, before filing a motion to stay the instant case on
September 29, 2022, noting that Defendant Sarker had filed for
bankruptcy protection in Connecticut. (ECF Nos. 10, 11.) This
Court granted Plaintiff’s motion to stay on September 30, 2022,
and simultaneously denied Plaintiff’s motion for default judgment
without prejudice for failure to follow EDNY Local Civil Rules.
2 Because Plaintiff has not addressed its entitlement to a declaratory judgment
regarding ownership of the Machine in its motion for default judgment, the Court
concludes that Plaintiff has abandoned this cause of action. See Joe Hand
Promotions, Inc. v. Bernal, No. 18-CV-85 (ILG), 2019 WL 885930, at *3 (E.D.N.Y.
Feb. 22, 2019) (finding that although Plaintiff prayed for injunctive relief in
its complaint, it did not request such relief in its motion for default judgment,
and therefore the claim was deemed abandoned); see also Payamps v. M & M
Convenience Deli & Grocery Corp., No. 16-CV-4895 (LDH) (SJB), 2019 WL 8381264,
at *3 n.3 (E.D.N.Y. Dec. 9, 2019) (finding that claim alleged in the complaint,
but not asserted in motion for default judgment, was abandoned).
(Docket Order dated September 30, 2022.) Plaintiff subsequently
refiled its motion for default judgment on November 6, 2022,
alongside a motion to lift the previously entered stay. (ECF Nos.
12, 13.) The Court granted the Motion to lift the stay on November
7, 2022, in light of the dismissal of Sarker’s Chapter 13
bankruptcy case. (Docket Order dated November 7, 2022.)
Subsequently, Plaintiff’s motion for default judgment, filed prior
to the lifting of the stay, was terminated as improperly filed,
and Plaintiff refiled the motion for default judgment on October
26, 2023.
This Court subsequently ordered Plaintiff to show cause as to
why the action should not be dismissed for lack of subject matter
jurisdiction on December 12, 2023. (Docket Order dated December
12, 2023.) The Court requested Plaintiff to identify each member
of Plaintiff Eco-Fuels LLC and Defendant Waste Technologies LLC
and properly plead facts establishing each member’s citizenship as
of the date the complaint was filed, and also requested Plaintiff
provide additional factual evidence regarding monetary damages.
(Id.) Plaintiff responded to the Court’s Order to Show Cause on
January 2, 2024, and satisfied the Court that diversity subject
matter jurisdiction was proper. (See generally ECF 20.)
LEGAL STANDARD
Pursuant to Rule 55, courts follow a two-step process to enter
default judgment. City of New York v. Mickalis Pawn Shop, LLC,
645 F.3d 114, 128 (2d Cir. 2011). First, when the defendant fails
to plead or otherwise defend and that failure is shown by affidavit
or otherwise, the clerk of court enters the defendant’s default.
See Fed. R. Civ. P. 55(a). A court considers an entry of default
against a party to be an admission of all the well-pleaded
allegations in the complaint regarding liability. Cement &
Concrete Workers Dist. Council Welfare Fund v. Metro Found.
Contractors Inc., 699 F.3d 230, 234 (2d Cir. 2012). Second, if
the defaulting party fails to appear or move to set aside the entry
of default under Rule 55(c), the opposing party may move the court
to enter a default judgment to establish liability and damages.
See Fed. R. Civ. P. 55(b)(2). Before entering a default judgment,
the court “must ensure that (1) jurisdictional requirements are
satisfied; (2) the plaintiff took all the required procedural steps
in moving for default judgment; and (3) the plaintiff's
allegations, when accepted as true, establish liability as a matter
of law.” Jian Hua Li v. Chang Lung Grp. Inc., No. 16-CV-6722 (PK),
2020 WL 1694356, at *4 (E.D.N.Y. Apr. 7, 2020) (citations omitted).
Although the court accepts as true all well-pleaded factual
allegations in the complaint, the court must still ensure the
allegations provide a basis for liability and relief, and the court
has discretion to require further proof of necessary facts. Finkel
v. Romanowicz, 577 F.3d 79, 84 (2d Cir. 2009). If the unchallenged
facts establish the defendant’s liability, the court determines
the amount of damages due. See Credit Lyonnais Sec. (USA), Inc.
v. Alcantara, 183 F.3d 151, 155 (2d Cir. 1999). The court may
determine damages without an in-person hearing based on the
plaintiff’s affidavits so long as it can ensure a basis for the
damages specified in the default judgment. Transatlantic Marine
Claims Agency, Inc. v. Ace Shipping Corp., Div. of Ace Young Inc.,
109 F.3d 105, 111 (2d Cir. 1997).
DISCUSSION
I. Jurisdiction
Title 28 U.S.C. § 1332 provides that “[t]he district courts
shall have original jurisdiction of all civil actions where the
matter in controversy exceeds the sum or value of $75,000,
exclusive of interests and costs, and is between . . . citizens of
different States.” 28 U.S.C. § 1332(a)(1). “Diversity
jurisdiction requires that all of the adverse parties in a suit be
completely diverse with regard to citizenship.” Handelsman v.
Bedford Vill. Assocs. Ltd. P'ship, 213 F.3d 48, 51 (2d Cir. 2000)
(internal quotation marks and citation omitted).
Plaintiff Eco-Fuels, a New York LLC, alleges that both of its
members are New York citizens. (Kahan Decl. at ¶¶7-10.) Plaintiff
alleges that Defendant Sarker is the sole member of Waste
Technologies LLC, a Delaware LLC, and that Sarker is a citizen of
Connecticut. (Id. at ¶¶11-13.) Plaintiff alleges that it suffered
damages of at least $200,000, the amount it paid Defendants under
the contract. (Id. at ¶14.) Thus, there is diversity jurisdiction
between Plaintiff and Defendants. See Bayerische Landesbank, New
York Branch v. Aladdin Cap. Mgmt. LLC, 692 F.3d 42, 49 (2d Cir.
2012) (“a limited liability company [] takes the citizenship of
each of its members”).
The Court may not enter a default judgment unless it has both
subject-matter jurisdiction over the action and personal
jurisdiction over each defendant. See Covington Indus., Inc. v.
Resintex A.G., 629 F.2d 730, 732 (2d Cir. 1980) (“A judgment
entered against parties not subject to the personal jurisdiction
of the rendering court is a nullity.”). Under New York's long-
arm statute, contained in New York Civil Practice Law and Rules
(“CPLR”) § 302(a), courts may exercise personal jurisdiction over
a non-domiciliary “who in person or through an agent . . .
transacts any business within [New York] or contracts anywhere to
supply goods or services in the state,” but only where the cause
of action arises from the enumerated acts. CPLR § 302(a); see
Best Van Lines, Inc. v. Walker, 490 F.3d 239, 244 (2d Cir. 2007).
Here, both Defendants were party to a contract to supply goods and
services to Plaintiff, a New York LLC, and the contract included
a choice-of-law clause providing for New York law to govern the
contract. (Aff. Ex. A at 2.) The cause of action for the instant
case is breach of the same contract, and as such, the Court finds
that Defendants transacted business within New York and are subject
to the Court’s personal jurisdiction. See McNamee v. Clemens, 762
F. Supp. 2d 584, 594 (E.D.N.Y. 2011) (describing the factors
considered to determine whether a non-domiciliary has transacted
business in New York, including whether the defendant has an
ongoing contractual relationship with a New York corporation and
whether there is a choice-of-law clause in any such contract).
This Court may also exercise jurisdiction over Defendants to
the extent they have consented to allow the Court to do so. See
Brown v. Lockheed Martin Corp., 814 F.3d 619, 625 (2d Cir. 2016)
(“an entity may contract or stipulate with another to permit
proceedings in a state's courts, notwithstanding the remoteness
from the state of its operations and organization”). Relevant to
the instant case, “parties can consent to personal jurisdiction
through forum-selection clauses in contracts.” Ramiro Aviles v.
S & P Glob., Inc., 380 F. Supp. 3d 221, 258 (S.D.N.Y. 2019)
(internal quotation marks and citation omitted). Here, the
Contract includes a forum-selection clause stating that “[b]oth
parties agree to submit to personal jurisdiction to a Federal or
State court of competent jurisdiction sitting in and for the County
of Kings in any action or proceeding arising out of this
agreement.” (Aff. Ex. A. at 2.) Both Sarker and Waste
Technologies were party to the contract in question and thus this
Court finds that Defendants are subject to its jurisdiction as
regards any dispute arising out of the Contract.
II. Procedural Requirements
Before the court will enter a default judgment, the plaintiff
must show that entry of default was appropriate, which itself
requires showing that the defendant was effectively served with
process. Sik Gaek, Inc. v. Yogi’s II, Inc., 682 F. App’x 52, 54
(2d Cir. 2017) (summary order). Local Rule 55.2 imposes the
additional requirements that the plaintiff attach certain
materials to the motion and file proof that all motion papers were
mailed to the defendant.
A. Service of Process
The Court finds that Plaintiff properly served each defendant
with the summons and complaint. Under the Federal Rules, service
for a “corporation, . . . partnership, or other unincorporated
association that is subject to suit under a common name” can occur
“by delivering a copy of the summons and of the complaint to an
officer, a managing or general agent, or any other agent authorized
by appointment or by law to receive service of process.” Fed. R.
Civ. P. 4(h)(1)(B). Federal Rule of Civil Procedure 4(e)(1) and
4(h)(1)(A) also permits a party to effect service on an individual
or corporate entity in accordance with the rules of the state where
the district is located or where service is made.
As to Waste Technologies LLC, a Delaware LLC, it is unclear
from the pleadings whether the company is authorized to do business
in the State of New York. In New York, where this Court is located,
serving a foreign LLC not authorized to do business in the state
via the Secretary of State is proper “[i]n any case in which a
non-domiciliary would be subject to the personal or other
jurisdiction of the courts of [New York] under article three of
the civil practice law and rules.” NY Limited Liability Company
Law (“NY LLC Law”) § 304(a). Service via the Secretary of State
is likewise proper fo r an authorized foreign LLC. Id. § 303(a).
The Court will proceed under the assumption that Waste Technologies
is an unauthorized foreign LLC, as Plaintiff cites to NY LLC Law
§ 304 in its affidavit of process. (See ECF No. 6.)
As discussed supra, the Court has found that Waste
Technologies is subject to personal jurisdiction in New York
pursuant to CPLR § 302(a); thus, it may be served in accordance
with NY LLC Law § 304. To properly serve a foreign LLC, three
steps are required. “First, service upon the unauthorized foreign
limited liability company may be made by personal delivery of the
summons and complaint, with the appropriate fee, to the Secretary
of State.” Glob. Liberty Ins. Co. v. Surgery Ctr. of Oradell,
LLC, 59 N.Y.S.3d 751, 753 (2d Dep’t 2017) (citing NY LLC Law §
304(b)). As provided in the affidavit of service, Plaintiff
properly served the Secretary of State and paid the appropriate
fee. (See ECF No. 6.) “Second, in order for the personal delivery
to the Secretary of State to be ‘sufficient,’ the plaintiff must
also give the defendant direct notice of its delivery of the
process to the Secretary of State, along with a copy of the
process.” Glob. Liberty Ins. Co., 59 N.Y.S.3d at 753 (citing NY
LLC Law § 304(c)(2)). Plaintiff complied with the second step by
mailing, via registered mail, Waste Technologies’ registered agent
in Delaware3 a copy of the summons and complaint, along with notice
of the service on the Secretary of State. (ECF No. 6.) “Third,
after process has been delivered to the Secretary of State and
direct notice of that service has been sent to the defendant, the
plaintiff must file proof of service,” to include the “return
receipt” from the registered mailing made as part of step two, to
the clerk of the court. Glob. Liberty Ins. Co., 59 N.Y.S.3d at
753. Plaintiff attached the return receipt, showing a delivery
date of January 31, 2022, to its affidavit of service, properly
completing step three. (ECF No. 6.) As such, Plaintiff properly
complied with the requirements of NY LLC Law § 304 in serving
Defendant Waste Technologies, and service was complete 10 days
after filing the affidavit of service with the clerk of court.
3 The Court may properly take judicial notice of public records. See Haru
Holding Corp. v. Haru Hana Sushi, Inc., No. 13-CV-7705 (RWS), 2016 WL 1070849,
at *2 (S.D.N.Y. Mar. 15, 2016) (taking judicial notice of information provided
by the New York State Department of State). The Court takes judicial notice of
the public entity information provided by the Delaware Department of State,
Division of Corporations showing that “Waste Technologies, LLC” has as its
registered agent “The Company Corporation” with an address of 251 Little Falls
Drive, Wilmington, DE – the address to which Plaintiff mailed process. See
https://icis.corp.delaware.gov/Ecorp/EntitySearch/NameSearch.aspx (search
conducted using entity name “Waste Technologies, LLC” which returns file number
5395420).
Regarding Sarker, The Federal Rules of Civil Procedure
provide that an individual may be served via any means authorized
by the state in which service is attempted or by delivering service
personally, at the individual's dwelling, or to an authorized
agent. Fed. R. Civ. P. 4(e). In the instant case, Plaintiff served
the summons and complaint upon Sarker personally at his home
address in Connecticut. (ECF No. 7, Kahan Decl. at ¶13.) Thus,
Plaintiff properly served Sarker.
B. Entry of Default
The Court next finds that the Clerk of Court properly entered
a certificate of default against each defendant. Because Plaintiff
filed its affidavit of service on February 9, 2022, (see ECF
No. 6), service was complete “ten days after [the affidavit was]
filed with the clerk of the court,” see NY LLC Law § 304(e) -
February 19, 2022. Thus, Waste Technologies was required to answer
or otherwise respond to the Complaint by March 12, 2022. See
Fed. R. Civ. P. 12(a)(1)(A)(i). Likewise, because Sarker was
served on January 24, 2022, (see ECF No. 7), he was required to
answer or otherwise respond to the complaint by February 14, 2022.
When both Defendants failed to respond, Plaintiff filed a request
for a certificate of default on April 14, 2022. (See ECF No. 8.)
The Clerk of Court entered a certificate of default against both
Defendants on April 18, 2022. (ECF No. 9.)
C. Local Rule 55.2
Local Rule 55.2(b) requires that a plaintiff attach to a
motion for default judgment the Clerk’s certificate of default, a
copy of the complaint, and a proposed form of default judgment.
Local Rule 55.2(c) requires that all papers submitted in connection
with a motion for a default judgment be mailed to the “last known
residence” of an individual defendant or “last known business
address” of a corporate defendant.
Plaintiff’s Motion for Default Judgment is supported by an
affirmation that declares Waste Technologies and Sarker were
served with all required documents at the addresses at which they
were originally served. (See ECF No. 17 at 3.) Likewise,
Plaintiff’s response to the Court’s Order to Show Cause was
supported by an affirmation that the response and its exhibits
were served upon Defendants at the same addresses. (ECF No. 22.)
Accordingly, Plaintiff has met the requirements of Local Rule
55.2(c).
III. Liability
Having assured itself that the jurisdictional and procedural
prerequisites to enter a default judgment are met, the Court now
must assess whether Plaintiff’s well-pleaded factual allegations
establish Defendants’ liability as a matter of law.
A. Choice of Law
The parties agreed pursuant to the Contract that their
agreement “shall be governed by and construed under the laws of
the State of New York.” (Aff. Ex. A at 2.) “The validity of a
contractual choice-of-law clause is a threshold question that must
be decided not under the law specified in the clause, but under
the relevant forum's choice-of-law rules governing the
effectiveness of such clauses.” Fin. One Pub. Co. v. Lehman Bros.
Special Fin., 414 F.3d 325, 332 (2d Cir. 2005). Thus, this Court,
sitting in diversity, is bound to apply New York law to determine
the validity and scope of the choice-of-law clause. When a choice-
of-law provision exists “and the jurisdiction chosen by the parties
has a substantial relationship to the parties or their performance,
New York law requires the court to honor the parties’ choice
insofar as matters of substance are concerned, so long as
fundamental policies of New York law are not thereby violated.”
Woodling v. Garrett Corp., 813 F.2d 543, 551 (2d Cir. 1987) (citing
A.S. Rampell, Inc. v. Hyster Co., 144 N.E.2d 371, 379 (N.Y. 1957)).
Plaintiff, a party to the Contract, is a New York limited liability
company, and there is no evidence that enforcement of the choice
of law provision would violate the fundamental policies of New
York. Accordingly, the Court will apply New York substantive law
to Plaintiff’s claims arising out of the Contract.
B. Breach of Contract Claim
“To state a claim for breach of contract under New York law,
the complaint must allege: (i) the formation of a contract between
the parties; (ii) performance by the plaintiff; (iii) failure of
defendant to perform; and (iv) damages.” Orlander v. Staples,
Inc., 802 F.3d 289, 294 (2d Cir. 2015) (internal quotation marks
omitted). The Court finds that Plaintiff has alleged adequate
facts to satisfy each of these four elements: (i) Plaintiff agreed
to pay Defendants a total of $500,000 in exchange for Defendants
building “a machine that converts assorted plastic into fuel”
within six months of the signing of the Contract or sixty days of
the signing of the Addendum (ii) Plaintiff performed under the
parties’ agreements by paying a total of $200,000, all payments
required prior to a demonstration by Sarker that the Machine
“properly functions,” (iii) Defendants breached the agreements by
failing to demonstrate a properly functioning Machine, and failing
to deliver the Machine; and (iv) Plaintiff has been damaged in the
amount of $200,000. (Kahan Aff. at ¶¶5-7, 15, 17-19; Aff. Exs. A,
B.) Thus, the Court finds that Plaintiff has sufficiently pled
that the Defendants are liable for breach of contract.
The Court also finds that it is appropriate to hold both
Defendants jointly and severally liable for any damages awarded to
Plaintiff on its breach of contract claim because both Defendants
signed the Contract and Addendum. See Todtman, Nachamie, Spizz &
Johns, P.C. v. Ashraf, 241 F.R.D. 451, 457 (S.D.N.Y. 2007), aff'd,
316 F. App'x 51 (2d Cir. 2009) (entering judgment against corporate
defendant and individual defendant jointly and severally on breach
of contract claim where both were party to contract at issue).
“Under the doctrine of joint and several liability, when two (2)
or more defendants act together to cause an injury, each defendant
is liable to the victim for the total damages.” Ainbinder v. Money
Ctr. Fin. Grp., Inc., No. 10-CV-5270 (SJF), 2014 WL 1220630, at *3
(E.D.N.Y. Mar. 24, 2014) (citing Zapico v. Bucyrus–Erie Co., 579
F.2d 714, 718 (2d Cir. 1978)). Both Sarker and Waste Technologies
were party to the Contract and the Addendum, and both Defendants
were referred to “[c]ollectively” throughout the Contract as
“Doctor.” (See Aff. Exs. A, B.) Thus, Defendants Sarker and Waste
Technologies are collectively bound by the terms of the Contract
and are jointly and severally liable for any damages incurred as
a result of a breach of that agreement.
C. Unjust Enrichment
The Complaint also asserts an unjust enrichment claim against
the Defendants. The Court finds that this claim is duplicative of
Plaintiff's breach of contract claim and therefore denies
Plaintiff's motion as to the unjust enrichment claim.
“[T]o succeed on a claim for unjust enrichment under New York
law, a plaintiff must prove that ‘(1) defendant was enriched, (2)
at plaintiff's expense, and (3) equity and good conscience militate
against permitting defendant to retain what plaintiff is seeking
to recover.’” Diesel Props S.r.l. v. Greystone Bus. Credit II
LLC, 631 F.3d 42, 55 (2d Cir. 2011) (quoting Briarpatch Ltd., L.P
v. Phoenix Pictures, Inc., 373 F.3d 296, 306 (2d Cir. 2004)).
Although Plaintiff has satisfied the unjust enrichment elements,
“when a ‘matter is controlled by contract,’ the plaintiff has no
valid claim for unjust enrichment under New York law.” Marshall
v. Hyundai Motor Am., 51 F. Supp. 3d 451, 471 (S.D.N.Y. 2014)
(quoting Goldman v. Metro. Life Ins. Co., 841 N.E.2d 742, 746 (N.Y.
2005)); see also Cont'l Cas. Co. v. Contest Promotions NY, LLC,
No. 15-CV-501 (MKB), 2016 WL 1255726, at *3-4 (E.D.N.Y. Mar. 28,
2016) (collecting cases). Here, the Complaint alleges a valid
contract that existed between the parties, which the Defendants
breached, causing damage to Plaintiff. Because the dispute is
“governed by a valid contract, Plaintiff is not entitled to recover
on an unjust enrichment theory.” Cont'l Cas. Co., 2016 WL 1255726,
at *4.
D. Fraud
“Under New York law, to state a cause of action for fraud, a
plaintiff must allege a representation of material fact, the
falsity of the representation, knowledge by the party making the
representation that it was false when made, justifiable reliance
by the plaintiff and resulting injury.” Lerner v. Fleet Bank,
N.A., 459 F.3d 273, 291 (2d Cir. 2006) (internal quotation marks
and citation omitted). In a diversity action such as this, “to
comply with [Federal Rule of Civil Procedure] 9(b), the complaint
must: (1) specify the statements that the plaintiff contends were
fraudulent, (2) identify the speaker, (3) state where and when the
statements were made, and (4) explain why the statements were
fraudulent.” Id. at 290 (internal quotation marks omitted). In
addition, a fraud claim must also “allege facts that give rise to
a strong inference of fraudulent intent.” Id. A plaintiff may
establish a “strong inference” of fraud “(a) by alleging facts to
show that defendants had both motive and opportunity to commit
fraud, or (b) by alleging facts that constitute strong
circumstantial evidence of conscious misbehavior or recklessness.”
Id. at 290–91.
As an initial matter, Plaintiff’s fraud claim is duplicative
of its breach of contract claim. “‘[A] cause of action for fraud
may be maintained where a plaintiff pleads a breach of duty
separate from, or in addition to, a breach of the contract.’”
Sotheby's, Inc. v. Stone, 388 F. Supp. 3d 265, 275 (S.D.N.Y. 2019)
(quoting First Bank of Americas v. Motor Car Funding, Inc., 690
N.Y.S.2d 17, 21 (1st Dep't 1999)). “But where ‘the promise
concerned the performance of the contract itself, the fraud claim
is subject to dismissal as duplicative of the claim for breach of
contract.’” Id. (quoting Fairway Prime Est. Mgmt., LLC v. First
Am. Int'l Bank, 952 N.Y.S.2d 524, 527 (1st Dep't 2012)). Here,
the allegedly false promises on which Plaintiff bases its fraud
claim “concern[] the performance of the contract itself[.]” Id.
Plaintiff alleges that Sarker falsely represented that he had
the sole ownership rights to a company which owned patents related
to converting plastic waste into fuel, and that those
representations were made as a means to induce Plaintiff into
entering into the Contract. (Compl. at ¶¶67-68, Kahan Aff. at
¶¶9-13.) The representations in question were made as part of the
language of the contract itself, and therefore, Plaintiff’s fraud
claim is duplicative of its breach of contract claim. See
Bridgestone/Firestone, Inc. v. Recovery Credit Servs., Inc., 98
F.3d 13, 19 (2d Cir. 1996) (finding fraud claim duplicative of
breach of contract claim where the defendant's allegedly
fraudulent “representations were intended to lull [the plaintiff]
into a false sense of security and ... amount[ed] to little more
than intentionally-false statements by [the defendant] indicating
his intent to perform under the contract”); see also Spinelli v.
Nat'l Football League, 903 F.3d 185, 209 (2d Cir. 2018)
(“Misrepresentations made to induce a party to enter a contract
are not actionable as fraud . . . unless they are ‘collateral’ to
the contract induced.”). Because Plaintiff’s fraud claim is
duplicative of its breach of contract claim, it must be dismissed,
and the Court need not analyze whether it would otherwise meet the
heightened pleading requirements of Federal Rule of Civil
Procedure 9(b).
IV. Damages
Having determined Defendants’ liability, the Court must
determine whether Plaintiff has provided sufficient evidence to
support its claims for damages, or whether a hearing is necessary
to determine the amount of damages. Transatlantic Marine Claims
Agency, Inc. v. Ace Shipping Corp., Div. of Ace Young Inc., 109
F.3d 105, 111 (2d Cir. 1997). “Although the default establishes
a defendant’s liability, unless the amount of damages is certain,
the court is required to make an independent determination of the
sum to be awarded.” US All. Fed. Credit Union v. M/V Kamara Fam.,
No. 20-CV-1733 (AMD) (SJB), 2023 WL 5622067, at *8 (E.D.N.Y. Aug.
31, 2023) (internal quotation marks and citation omitted); see
also Cement & Concrete Workers Dist. Council Welfare Fund v. Metro.
Found. Contractors Inc., 699 F.3d 230, 234 (2d Cir. 2012)
(explaining that although the allegations in a complaint related
to liability are deemed admitted upon entry of a default judgment,
a default “is not considered an admission of damages” (internal
quotation marks omitted)). “The court must determine the amount
of damages, actual or statutory, that may be assessed,” and “ensure
that there is a reasonable basis for the damages specified in a
default judgment.” Santillan v. Henao, 822 F. Supp. 2d 284, 290
(E.D.N.Y. 2011) (citation omitted).
In response to the Court’s Order to Show Cause, Plaintiff has
annexed a declaration of the managing member of Eco-Fuels which
includes as supporting exhibits bank statements and photographs of
checks reflecting the various payments made to Defendants pursuant
to the Contract and the Addendum. (Decl. Exs. A-E; Kahan Decl. at
¶¶1, 14-19 (Kahan attesting to his knowledge of and the accuracy
of the attached bank statements and photographs of checks).) The
Court finds that Plaintiff has met its evidentiary burden and that
a hearing to determine damages is unnecessary because the
submissions constitute a “sufficient basis from which to evaluate
the fairness of” Plaintiff’s damages request without the need for
a hearing. Fustok v. ContiCommodity Servs., Inc., 873 F.2d 38, 40
(2d Cir. 1989). The Court will next analyze the appropriate amount
of contract damages and pre- and post-judgment interest, as well
as Plaintiff’s request for attorneys’ fees and costs.
A. Contract Damages
The breach of contract in this action relates to the
Defendants’ failure to deliver the Machine, which would
purportedly convert plastic waste into fuel – a good governed by
the Uniform Commercial Code. See N.Y. U.C.C. Law (“UCC”) § 2-105
(“‘[g]oods’ means all things (including specially manufactured
goods) which are movable at the time of identification to the
contract for sale”); see also id. § 2-106 (“‘Contract for sale’
includes both a present sale of goods and a contract to sell goods
at a future time.”) Although the Contract in the instant case
also included services such as training, when those services are
“incident to the sale of goods,” the contract is still “subject to
the UCC.” KSW Mech. Servs. v. Johnson Controls, Inc., 992 F. Supp.
2d 135, 141 (E.D.N.Y. 2014) (citing Richard A. Rosenblatt & Co.,
Inc. v. Davidge Data Sys. Corp., 743 N.Y.S.2d 471, 472 (1st Dep't
2002)). Thus, the Court finds as a matter of law that the UCC
applies to the Contract and the Addendum because they predominately
involved a sale of goods, and any services were incidental to that
sale.
“When a buyer contracts to purchase goods and the seller fails
to deliver, UCC § 2-711(1) allows the frustrated buyer to recover,
among other things, ‘so much of the price as has been paid.’”
Ethereum Ventures LLC v. Chet Mining Co. LLC, No. 19-CV-7949 (LLS)
(KHP), 2021 WL 9036270, at *4 (S.D.N.Y. Oct. 20, 2021), report and
recommendation adopted, 2022 WL 2531588 (S.D.N.Y. Jan. 28, 2022)
(quoting Kashi v. Gratsos, 790 F.2d 1050, 1056 (2d Cir. 1986)).
Plaintiff has provided evidence showing that it paid a total of
$200,000, out of an overall purchase price of $500,000, to
Defendants pursuant to the Contract and the Addendum, (see Kahan
Decl at ¶¶14-20; Decl. Exs. A-E), and that Defendants failed to
deliver the Machine by February 22, 2020, as promised, (see Kahan
Aff. at ¶¶16-21, 35-37.) Accordingly, Plaintiff is entitled to
recover $200,000 as refund damages under the contract.
B. Pre-judgment Interest
Plaintiff requests pre-judgment interest. (Mem. at 12.) In
New York, “[a] plaintiff who prevails on a claim for breach of
contract is entitled to pre-judgment interest as a matter of
right.” Hounddog Prods., L.L.C. v. Empire Film Grp., Inc., 826 F.
Supp. 2d 619, 630 (S.D.N.Y. 2011) (internal quotation marks
omitted) (citing U.S. Naval Inst. v. Charter Commc'ns, Inc., 936
F.2d 692, 698 (2d Cir. 1991)). Under New York law, pre-judgment
interest accrues at a rate of nine percent per annum and is
calculated “from the earliest ascertainable date the cause of
action existed ... to the date the verdict was rendered or the
report or decision was made.” CPLR §§ 5001(b)–(c), 5004. Courts
calculate the “earliest ascertainable date” as the date of the
contract breach. See Guilbert v. Gardner, 480 F.3d 140, 149 (2d
Cir. 2007) (holding that “cause of action for breach of contract
ordinarily accrues and the limitations period begins to run upon
breach”).
In the instant case, the Court finds that the earliest
ascertainable date that the cause of action existed was February
20, 2020, based on the Contract and Addendum. Pursuant to the
terms of the original Contract, the Machine was required to be
built “within six (6) months from the date of this agreement,”
which, based on the signing date of October 4, 2019, would be April
4, 2020. (Aff. Ex. A at 1.) However, that deadline was
subsequently modified by the Addendum dated December 22, 2019, to
require the Machine to be “one hundred percent (100%) buil[t] and
functioning within sixty (60) days from the date Addendum B is
signed.” (Aff. Ex. B at 1.) Sixty days after December 22, 2019,
is February 20, 2020, and Defendants were in breach of the contract
when they failed to deliver the Machine by that deadline.
Plaintiff argues that pre-judgment interest should be
computed from October 4, 2019, the date the Contract was signed,
because Defendants made “material misrepresentation[s] to the
Plaintiff and therefore defaulted under the Contract.” (Mem. at
12.) Plaintiff’s breach of contract damages are based not on
fraudulent misrepresentations included in the contract itself,
however, but rather on Defendant’s failure to deliver a completed,
functioning machine, as discussed supra. Accordingly, the Court,
which is granted “wide discretion in determining a reasonable date
from which to award pre-judgment interest,” finds that February
20, 2020, the date Defendants failed to deliver the Machine, is an
appropriate date to utilize for calculating pre-judgment interest.
Conway v. Icahn & Co., 16 F.3d 504, 512 (2d Cir. 1994). Plaintiff
is thus entitled to an award of pre-judgment interest at a rate of
nine percent per year, $49.324 per day, calculated from February
20, 2020, through the date the Court enters judgment, for a total
4 Yearly interest of $18,000 ($200,000 x 0.09) divided by 365 days.
of $72,352.445, assuming judgment is entered on the same date as
this order – February 26, 2024.
C. Post-judgment Interest
Plaintiff also requests post-judgment interest. (Mem. at
12.) Post-judgment interest is mandatory and governed by federal
statute. See 28 U.S.C. § 1961(a). Therefore, the Court finds
that Plaintiff is entitled to post-judgment interest using the
federal rate set forth in 28 U.S.C. § 1961(a), and calculated from
the date the Clerk of the Court enters judgment in this action
until the date of payment.
D. Attorneys’ Fees and Costs
Plaintiff also requests attorneys’ fees and costs, to be
determined at an inquest. However, the Court finds such an inquest
to be unnecessary, because, as compared to pre-judgment interest,
“[t]here is no similar right to an award of attorney's fees on an
ordinary claim of breach of contract.” U.S. Naval Inst. v. Charter
Commc'ns, Inc., 936 F.2d 692, 698 (2d Cir. 1991). Plaintiff argues
that it is entitled to attorneys’ fees based on the indemnification
provision in the Contract, which reads in relevant part as follows:
[Defendants Waste Technologies and Sarker] hereby
agree[] to indemnify, hold harmless and defend [Eco-
Fuels] its employees, officers, directors, attorneys,
agents, successors and assignors against any and all
expenses, costs of defense (including, without
limitation, attorneys' fees, witness fees, damages,
judgments, fines and amounts paid in settlement) and any
amounts [Eco-Fuels] becomes legally obligated to pay
5 Daily interest of $49.32 multiplied by 1,467 days.
because of any claim or claims against [Eco-Fuels], to
the extent that such claim or claims (i) result from
[Defendants’] acts or failure to act under this
agreement, (ii) arise out of the breach or alleged breach
of this agreement or any representation by [Defendants]
hereunder . . .
(Aff. Ex. A. at 3 (emphasis added).) Plaintiff misreads the
indemnification clause, however, which the Court finds applies
only to claims against Plaintiff that Plaintiff is legally
obligated to pay, and not to a claim brought by Plaintiff against
Defendants for breach of contract.
“[W]hile parties may agree that attorneys' fees should be
included as another form of damages, such contracts must be
strictly construed to avoid inferring duties that the parties did
not intend to create.” Oscar Gruss & Son, Inc. v. Hollander, 337
F.3d 186, 199 (2d Cir. 2003) (citing Hooper Assocs., Ltd. v. AGS
Computers, Inc., 548 N.E.2d 903, 905 (N.Y. 1989)). As a result,
under New York law, “‘the court should not infer a party’s
intention’ to provide counsel fees as damages for a breach of
contract ‘unless the intention to do so is unmistakably clear’
from the language of the contract.” Id. (quoting Hooper Assocs.,
Ltd., 548 N.E.2d at 905). The Court reads the section of the
Contract excerpted above as referring only to third-party claims
against Plaintiff, given the reference only to indemnification for
claims against Eco-Fuels. See Bourne Co. v. MPL Commc'ns, Inc.,
751 F. Supp. 55, 57-58 (S.D.N.Y. 1990) (a contract did not extend
indemnification to actions between the parties when the agreement
did not expressly indicate such an intention). There is no
language in the Contract that obligates a party to pay attorneys’
fees to the other. Because it is not “unmistakably clear” from
the language of the Contract that attorneys’ fees were intended to
be included as another form of damages for a breach, this Court
will not infer the parties’ intention to do so. Thus, the Court
finds that an award of attorneys’ fees is not appropriate in the
instant case.
CONCLUSION
For the reasons stated above, Plaintiff’s Motion for Default
Judgment is granted in part and denied in part. The Court grants
default judgment as to Plaintiff’s breach of contract claim and
denies default judgment as to its other claims.
Default judgment is entered against Defendants, jointly and
severally, and Plaintiff is awarded (i) contract damages of
$200,000; (ii) pre-judgment interest at the daily rate of $49.32,
calculated from February 20, 2020, through the date the Court
enters judgment, for a total of $72,352.44 as of February 26, 2024;
and (iii) post-judgment interest at the rate set forth in 28 U.S.
§ 1961(a), from the date of the entry of judgment until the date
of payment in full.
The Clerk of Court is respectfully directed to enter judgment
in accordance with this Memorandum and Order. Plaintiff is ordered
to serve a copy of this Memorandum and Order and the Judgment on
Defendants and file declarations of service for each defendant
within two days after the Clerk of Court enters the Judgment.
SO ORDERED.
Dated: February 26, 2024 b “7
Brooklyn, New York - —
□ - eo eee ewe
KIYO A. MATSUMOTO
United States District Judge
Eastern District of New York
31