“[W]hether the duty of reasonable care applies depends on whether or not the danger at issue may be categorized as “incident to the work undertaken” by the independent contractor.” (footnote omitted).
How later courts described this case
- “[W]hether the duty of reasonable care applies depends on whether or not the danger at issue may be categorized as “incident to the work undertaken” by the independent contractor.” (footnote omitted).
- “In an indemnity contract, the agreement will be construed to cover all losses, damages, and liabilities which reasonably appear to have been within the contemplation of the parties, but not those which are neither expressed nor reasonably inferable from the terms.”
- “[W]hen the facts are in dispute or when more than a single inference can be drawn from the evidence, the issue of whether a duty exists is a mixed question of law and fact.”
Written by the judges who cited it.
The opinion
IN THE UNITED STATES DISTRICT COURT
FOR THE EASTERN DISTRICT OF NORTH CAROLINA
EASTERN DIVISION
No. 4:23-CV-45-FL-KS
WEYERHAEUSER COMPANY, )
)
Plaintiff, )
)
v. ) ORDER
)
DANIEL INTERNATIONAL CORPORATION, )
f/k/a Daniel Construction Company, )
)
Defendant. )
This matter is before the court on Defendant’s motion to compel written
discovery responses pursuant to Fed. R. Civ. P. 37 and for Plaintiff to designate a
corporate witness to testify on topics pursuant to a Fed. R. Civ. P. 30(b)(6) notice
[DE #36]. Plaintiff has responded in opposition [DE #38], and Defendant has replied
[DE #39].1 For the reasons stated below, Defendant’s motion to compel is granted.
BACKGROUND
On March 13, 2023, Weyerhaeuser Company (“Weyerhaeuser” or “Plaintiff”)
initiated this lawsuit against Daniel International Corporation (“Daniel” or
“Defendant”) alleging breach of a contractual indemnity provision from a contract
purportedly entered into by the parties in 1971. Weyerhaeuser asserts that it
“incur[red] damages, costs, and expenses in excess of $500,000” by defending and
settling a South Carolina state-court mesothelioma lawsuit brought by a plaintiff
1 The court held two informal discovery hearings about this discovery dispute
named Nicholas Murphy (hereinafter “the Murphy litigation”2). (Compl. [DE #1] at
4.)
Murphy sued producers of asbestos and owners of premises containing
asbestos where Murphy worked over the course of his career as a welder. (
Pl.’s Resp. Opp’n, Ex. 3 – Complaint [DE #38-4] (“
Compl.”).) In the Murphy litigation, Weyerhaeuser was sued as a premises defendant
in connection with Murphy’s work and alleged asbestos exposure at Weyerhaeuser’s
paper mill in New Bern, North Carolina. ( Compl. ¶¶ 73, 81; Compl. ¶ 11.) As
a premises defendant, Weyerhaeuser was expressly sued for negligence. (
Compl. ¶¶ 179–193.)
During the course of the Murphy litigation, Weyerhaeuser tendered its defense
to Daniel. ( Compl. ¶ 15.) These tenders do not appear to be based on the
indemnity provision at issue from the alleged 1971 contract, but rather appear to
have been made pursuant to an alleged 1970 agreement between the parties. (
Pl.’s Resp. Opp’n, Ex. 6 – Tender Correspondence [DE #38-7] (“Tender
Correspondence”) at 2–12.) Daniel rejected Weyerhaeuser’s tenders. (Compl. ¶ 16;
Tender Correspondence at 2–12.)
2 Weyerhaeuser has attached a copy of the Murphy litigation complaint. (Pl.’s
Resp. Opp’n, Ex. 3 – Complaint [DE #38-4].) The case appears to be captioned
as , No. 2020CP4001354, Court of Common Pleas,
Richland County, South Carolina (filed Mar. 6, 2020). Daniel was also sued in the
Murphy litigation.
Weyerhaeuser claims it settled the Murphy litigation for an undisclosed
amount on November 4, 2021. (Compl. ¶ 17.) Thereafter, Weyerhaeuser received
(from Daniel) a copy of the purported 1971 contract containing the indemnity
provision that forms the basis of this action. (Compl. ¶ 18.) Weyerhaeuser again
tendered the Murphy litigation to Daniel, this time on the express basis of the 1971
contract indemnity provision,3 and Daniel again rejected Weyerhaeuser’s tender.
(Compl. ¶¶ 19–20; Tender Correspondence at 13–15.) Weyerhaeuser filed this lawsuit
shortly thereafter.
Weyerhaeuser did not attach to its complaint a copy of the purported 1971
contract with the indemnity provision, but the complaint alleges that the indemnity
provision “provides, in pertinent part,” that the “Contractor [Daniel] shall indemnify
and hold harmless the Owner [Weyerhaeuser] . . . from and against any loss, liability,
claim, demand for damages for bodily injuries . . . . arising out of or relating to the
performance of the Work under Contract . . . .” (Compl. ¶ 9) (alterations and ellipses
in original). In its response to the instant motion to compel, Weyerhaeuser has
attached excerpts from the purported 1971 contract which contain the indemnity
provision at issue. (Pl.’s Resp. Opp’n, Ex. 1 – 1971 Contract Excerpts [DE #38-2]
(“1971 Contract Excerpts”) at 7.) The unaltered text of the indemnity provision is as
follows:
3 This tender was also made in reliance on another alleged contract between
Weyerhaeuser and Daniel. (Tender Correspondence at 13–15 (referencing an
indemnity provision in a 1975 contract).)
(b) The Contractor shall indemnify and hold harmless the Owner and
Engineer from and against any loss, liability, claim or demand for
damages for bodily injuries including death and/or property damage
arising out of or relating to the performance of the Work under this
Contract, except when caused by the negligence of the Owner or
Engineer.
( )4
The gravamen of the instant discovery dispute centers on the following broad
categories of information sought by Daniel and resisted by Weyerhaeuser:
(A) Weyerhaeuser’s or its Engineer’s potential negligence in relation to Murphy’s
exposure to asbestos at the New Bern mill; (B) work performed by other contractors
at the New Bern mill for whom Murphy worked, when and for whom Murphy worked
at the New Bern mill, and under which specific contracts Murphy worked (including
other contracts between Daniel and Weyerhaeuser); and (C) Weyerhaeuser’s damages
in connection with the Murphy litigation settlement and Weyerhaeuser’s decision and
underlying reasons for settling the claims against it.
Weyerhaeuser has refused to provide discovery regarding these categories for
several reasons. First and foremost, Weyerhaeuser contends that its potential
negligence is irrelevant because, as a matter of law, it owed no duty to Murphy. (Pl.’s
4 The excerpts provided by Weyerhaeuser appear to be from different parts of
the alleged 1971 contract. For example, the indemnity provision appears to be from
an excerpt of a section called “General Conditions” (1971 Contract Excerpts at 6–7),
but other excerpts appear to be from different sections or separate documents (
at 8–12). More specifically, one section of the excerpts titled “Article V – The Contract
Documents” (which itself appears to be excerpted from a component titled “Contract
Agreement”) lists several components of the “Contract Documents,” including, among
other things, “The General Conditions” and “The Contract.” ( at 11.) The “Contract
Agreement” excerpt is not dated and only bears an unwitnessed signature from a
purported Daniel representative. ( at 9, 12.)
Resp. Opp’n at 4–6 (“Weyerhaeuser did not owe any duty to Mr. Murphy. As a result,
nothing Daniel seeks in its discovery requests ‘relating to the negligence of
Weyerhaeuser’ will ever be of any consequence in determining this action.”). In
support, Weyerhaeuser relies heavily on , 986 F.3d
482 (4th Cir. 2021) (per curiam). (Pl’s Resp. Opp’n at 4–5.) Second, Weyerhaeuser
contends that information regarding work performed by other contractors and from
the time period of 1965 through 1980 (as requested by Daniel) is irrelevant. ( at 9.)
Third, while Weyerhaeuser has repeatedly said that it will disclose the amount it
paid to settle the Murphy claims pursuant to a court order and that it has no objection
to the court “ruling partially in Daniel’s favor . . . if solely limited to disclosing the
amount for which Weyerhaeuser settled the lawsuit,” it objects to Daniel’s
requests for “extraneous information regarding the settlement that is unrelated to
the amount of damages Weyerhaeuser seeks from Daniel in this case.” ( at 6–7.)
Weyerhaeuser has specifically identified as seeking extraneous information Daniel’s
Request for Production (“RFP”) 225 and RFP 246, and more broadly, any request for
5 RFP 22 requests “[a]ll documents comprising or concerning or relating to any
and all analysis of the facts, reasons, and recommendations for settling the Nicholas
Murphy Lawsuit on behalf of [Weyerhaeuser] including, but not limited to, any
memos, pre-trial reports, asbestos case profiles, Asbestos Litigation Form (ALFs), or
similar Documents.” (Def.’s Mot. Compel, Ex. 2 – Daniel’s First Set of RFPs [DE #36-
2] at 5–6.)
6 RFP 24 requests “[c]opies of any and all agreements and correspondence with
counsel for Nicholas Murphy in the Nicholas Murphy Lawsuit, including any
settlement agreements entered by Weyerhaeuser Company and plaintiffs in the
Nicholas Murphy Lawsuit. (Def.’s Mot. Compel, Ex. 2 – Daniel’s First Set of RFPs
[DE #36-2] at 6.)
information related to Weyerhaeuser’s potential negligence as to the Murphy
litigation. ( at 7–8.)
DDISCUSSION
Rule 26 of the Federal Rules of Civil Procedure provides for a broad scope of
discovery:
Parties may obtain discovery regarding any nonprivileged matter that
is relevant to any party’s claim or defense and proportional to the needs
of the case, considering the importance of the issues at stake in the
action, the amount in controversy, the parties’ relative access to relevant
information, the parties’ resources, the importance of the discovery in
resolving the issues, and whether the burden or expense of the proposed
discovery outweighs its likely benefit. Information within this scope of
discovery need not be admissible in evidence to be discoverable.
Fed. R. Civ. P. 26(b)(1). Relevance “has been broadly construed to encompass ‘any
possibility’ that the information sought may be relevant to the claim or defense of any
party.” , No. 1:06-CV-00889, 2007 WL 1726560, at *3
(M.D.N.C. June 13, 2007); , 313 F.R.D. 1, 5
(E.D.N.C. 2016) (quoting , 2007 WL 1726560, at *3);
, No. 5:18-CV-66, 2020 WL 2311668, at *2 (W.D. Va. May 8, 2020)
(acknowledging the 2000 and 2015 amendments to Rule 26(b)(1) and concluding that
the discovery rules are to be interpreted broadly); 8 Wright & Miller, Fed. Prac. &
Proc. § 2008 (3d ed.) (summarizing history of Rule 26 and noting that the 2015
amendment “did not affect a dramatic change in the scope of discovery”).
Rule 26 requires the court to limit the frequency or extent of discovery if “the
discovery sought is unreasonably cumulative or duplicative, or can be obtained from
some other source that is more convenient, less burdensome, or less expensive”; “the
party seeking discovery has had ample opportunity to obtain the information by
discovery in the action”; or the discovery sought is outside the scope of Rule 26(b)(1).
Fed. R. Civ. P. 26(b)(2)(C). The rule also authorizes the court to impose appropriate
limitations on discovery in order “to protect a party or person from annoyance,
embarrassment, oppression, or undue burden or expense.” Fed. R. Civ. P. 26(c)(1).
Such protective orders may include, among other things, provisions “forbidding the
disclosure or discovery,” “specifying terms . . . for the disclosure or discovery,”
“prescribing a discovery method other than the one selected by the party seeking
discovery,” or “forbidding inquiry into certain matters, or limiting the scope of
disclosure or discovery to certain matters.” Fed. R. Civ. P. 26(c)(1)(A)–(c)(1)(D).
“The party resisting discovery bears the burden of showing why [the motion to
compel] should not be granted.” , 270
F.R.D. 238, 241 (E.D.N.C. 2010). “To meet this burden, the non-moving party ‘must
make a particularized showing of why discovery should be denied, and conclusory or
generalized statements fail to satisfy this burden as a matter of law.’”
, No. 5:16-CV-679-FL, 2018 WL 5831997, at *5 (E.D.N.C. Nov. 7, 2018)
(quoting , 270 F.R.D. at 241). “[T]he court has ‘substantial
discretion’ to grant or deny motions to compel discovery.” , No. 5:11-
CT-3206-D, 2014 WL 555661, at *4 (E.D.N.C. Feb. 11, 2014) (quoting
, 43 F.3d 922, 929 (4th Cir. 1995)).
If a motion to compel is granted, then “the court must, after giving an
opportunity to be heard, require the party or deponent whose conduct necessitated
the motion, the party or attorney advising that conduct, or both to pay the movant’s
reasonable expenses incurred in making the motion, including attorney’s fees.” Fed.
R. Civ. P. 37(a)(5)(A). A court may decline to award reasonable expenses only if one
of three exceptions apply. Fed. R. Civ. P. 37(a)(5)(A)(i)–(iii).
AA. Weyerhaeuser’s and its Engineer’s Potential Negligence is Discoverable
Weyerhaeuser takes the position, based on , 986 F.3d
482 (4th Cir. 2021) (per curiam), that its potential negligence will never be at issue
in this lawsuit. Weyerhaeuser’s position is meritless.
Assuming Weyerhaeuser’s interpretation and application of is correct,7
the text of the alleged indemnity provision contains an express carve-out for
7 The court offers no opinion as to the applicability of to the instant
discovery dispute. However, as Daniel has pointed out, there are several reasons to
question its applicability. (Def.’s Reply [DE #39] at 1–4.)
First, dealt with application of what the Fourth Circuit labeled “the
independent-contractor exception” to the general rule in North Carolina that
“landowners owe a duty of reasonable care to all lawful visitors” and said duty of care
“extends to lawfully present independent contractors and their employees.” ,
986 F.3d at 489–90 (first citing , 349 N.C. 615 (1998); and then
citing , 208 N.C. App. 711 (2010)), 492
(“independent-contractor exception to landowner liability”). However, to determine
whether this exception applies, a court must look to “the actual work undertaken by
independent contractors and their employees.” , 986 F.3d at 490 (quoting
, 208 N.C. App. at 715); , 208 N.C. App. at 714 (“[W]hether
the duty of reasonable care applies depends on whether or not the danger at issue
may be categorized as “incident to the work undertaken” by the independent
contractor.” (footnote omitted).) It is the landowner who bears the burden “to
establish that another entity in fact had ‘exclusive dominion and control of the
defective’ aspect of the property.” , 986 F.3d at 490 (quoting
, 85 N.C. App. 391, 394–95 (1987)). Here, the 1971 Contract Excerpts offer
no insight into this fact-dependent inquiry; these excerpts only indicate that the
alleged 1971 contract was for “Production Efficiency Increase” work and that the type
of project was “Plant Addition.” (1971 Contract Excerpts at 3–6.) Weyerhaeuser’s
Weyerhaeuser’s or its Engineer’s negligence. (1971 Contract Excerpts at 7.) North
Carolina law8 is clear that parties may enter into contractual agreements that except
or modify common-law duties so long as such contractual agreements are not
“contrary to public policy or prohibited by statute.”9
claim that it was “in doing this work for Daniel pursuant to contract with
Weyerhaeuser that Mr. Murphy alleges he was injured” (Pl.’s Resp. Opp’n at 6) misses
the point. The question is whether the alleged asbestos exposure was incident to the
work undertaken by Daniel pursuant to the alleged 1971 contract, or whether the
alleged asbestos exposure was still within the dominion and control of Weyerhaeuser
as landowner such that the independent-contractor exception should not apply. Given
the briefing and supporting evidence presented by Weyerhaeuser in its opposition to
the motion to compel, the court cannot say at this point.
, 101 N.C. App. 578, 588 (1991) (“[W]hen the facts are in
dispute or when more than a single inference can be drawn from the evidence, the
issue of whether a duty exists is a mixed question of law and fact.”), , 331 N.C.
182 (1992).
Other facts may render inapposite. dealt with a ground-up
construction of a new lock production facility, , 986 F.3d at 485, 490, but here
it is unclear what the “Production Efficiency Increase” work/project involved. Daniel
has proffered evidence that Murphy was exposed to insulation dust by Weyerhaeuser
employees. (Def.’s Reply, Ex. B – Murphy Deposition Excerpts [DE #39-2].) This
raises a factual issue as to whether Weyerhaeuser’s New Bern mill was in operation
while Murphy was working there pursuant to the “Production Efficiency Increase”
project. , 101 N.C. App. at 588.
Also, the procedural juncture of is different than that here.
affirmed a summary judgment order by the district court, so there was a more fully
developed factual record upon which those courts could determine the correct
application of North Carolina law. Here, though, the factual record is undeveloped on
relevant issues. , 101 N.C. App. at 588.
8 This court’s subject-matter jurisdiction is invoked pursuant to 28 U.S.C.
§ 1332. (Compl. ¶ 4.) North Carolina substantive law is therefore applied.
, 304 U.S. 64, 78 (1938).
9 Weyerhaeuser does not contend that the negligence carve-out in the alleged
indemnity provision is contrary to public policy or prohibited by statute. (Pl.’s Resp.
Opp’n at 1–9.)
, 175 N.C. App. 423, 427 (2006) (quoting ,
353 N.C. 240, 242–43 (2000)); , 53
N.C. App. 306, 308 (1981) (“In an indemnity contract, the agreement will be construed
to cover all losses, damages, and liabilities which reasonably appear to have been
within the contemplation of the parties, but not those which are neither expressed
nor reasonably inferable from the terms.”). “[W]hen parties contract at arm’s length,
the provisions in the parties’ contract are ‘the law of their case,’ and courts are
without power to revise the contract.” , 175 N.C. App. at 427 (quoting
, 249 N.C. 383, 386 (1959)). Accordingly, the alleged
contractual indemnity provision that forms the basis of this lawsuit expressly puts
Weyerhaeuser’s and its Engineer’s negligence at issue. That Weyerhaeuser settled
the claims against it in the Murphy litigation, which presumably included the
negligence claim referenced above, only bolsters the relevance of its and its Engineer’s
potential negligence. At this procedural juncture, Daniel is thus entitled to discovery
on this issue.
Daniel contends that this issue is raised by Interrogatories 4, 5, & 7–12; RFPs
6–9, 15–17, 20–24, & 29; and Deposition Topics 4–6, 11, & 17–21. (Def.’s Mem. Supp.
Mot. Compel [DE #37] at 5.) Weyerhaeuser has not contended otherwise. (Pl.’s Resp.
Opp’n at 4–6.) Weyerhaeuser has therefore failed to carry its burden to show why
Daniel’s motion to compel should be denied. , 270 F.R.D. at
241; , 2018 WL 5831997, at *5. Daniel’s motion to compel as to
Interrogatories 4, 5, & 7–12; RFPs 6–9, 15–17, 20–24, & 29; and Deposition Topics 4–
6, 11, & 17–21 is therefore granted.
BB. Work Performed by Other Contractors for Whom Murphy Worked is
Discoverable as is Work Murphy May Have Performed for Daniel under
Other Contracts with Weyerhaeuser
Daniel also seeks discovery regarding work performed by other contractors at
the New Bern mill for whom Murphy worked, particularly a contractor known as
Brown & Root, as well as work performed by Murphy for Daniel pursuant to other
contracts/projects at the New Bern mill. (Def.’s Mem. Supp. Mot. Compel at 7–8.)
These requests are mostly summed up in Daniel’s RFP 14, which requests “[a]ll
[d]ocuments establishing when Nicholas Murphy worked at the New Bern facility,
who he was working for, and what projects he was working on.” (Def.’s Mot. Compel,
Ex. 2 – Daniel’s First Set of RFPs [DE #36-2] at 5.) In response, Weyerhaeuser argues
that Daniel’s requests are irrelevant because “Daniel did not assert as an affirmative
defense any sort of apportionment or allocation of fault by other contractors for whom
Murphy may have worked at the New Bern facility at other times.”10 (Pl.’s Resp.
Opp’n at 9.)
Daniel is entitled to discovery regarding Murphy’s potential asbestos exposure
at the New Bern mill while performing work for Daniel under another
10 In the heading of this section of its brief, Weyerhaeuser states that the time
period for which Daniel seeks information is “irrelevant.” (Pl.’s Resp. Opp’n at 9;
Def.’s Mot. Compel, Ex. 2 at 5 (RFP 13 and RFP 16 requesting information for time
period of 1965 through 1980).) Weyerhaeuser does not explain why the time period of
1965 through 1980 is irrelevant. (Pl.’s Resp. Opp’n at 9.)
contract/project (i.e. not the alleged 1971 Production Efficiency Increase project) or
for other contractors at the New Bern mill.11 Such information is relevant to whether
Murphy was exposed to asbestos at the New Bern mill while working for Daniel under
any contract containing the indemnity provision at issue in this lawsuit.
Weyerhaeuser fails to appreciate that this information is relevant to the question of
whether injuries suffered by Murphy “arose from” or “are related to” work performed
by Murphy for Daniel under the alleged 1971 contract. ( 1971 Contract Excerpts
at 7.) Such information is critical to Weyerhaeuser’s contractual indemnity claim;
Daniel need not have pleaded an affirmative defense of apportionment to discover
such information. Lastly, the time period for which Daniel seeks this information
appears reasonable. ( Pl.’s Resp. Opp’n at 9; Def.’s Mem. Supp. Mot. Compel at 9
(arguing that the timeframes are relevant).)
Daniel’s requests for information related to work performed by Brown & Root
at the New Bern mill are also relevant under Rule 26(b)(1). If Murphy was exposed
to asbestos while working for Brown & Root at the New Bern mill, that would be
relevant to the contractual indemnity claim at issue in this lawsuit. Accordingly,
Daniel’s discovery requests seeking such information are relevant. Similarly relevant
11 Daniel has pointed to evidence that Murphy worked at the New Bern mill
for other contractors (Brown & Root and Cost Effective Maintenance). (Def.’s Mem.
Supp. Mot. Compel at 7–8; Def.’s Reply at 5–6). The Social Security records for
Murphy provided by Weyerhaeuser also show that Murphy worked for Daniel both
before and after the likely time period for the 1971 Production Efficiency Increase
project. (Pl.’s Resp. Opp’n, Ex. 4 – Murphy Social Security Records [DE #38-5]; Def.’s
Reply, Ex. A – Daniel’s Notification of Contract for Production Efficiency Project
[DE #39-1] at 2 (indicating schedule dates for project).)
would be any information, requested in RFP 16, provided by Weyerhaeuser to Daniel
or Brown & Root regarding asbestos exposure at the New Bern mill.12
Daniel contends that RFPs 13, 14, & 16, and Deposition Topics 3, 4, 8, & 10
seek such information. (Def.’s Mem. Supp. Mot. Compel at 5.) Weyerhaeuser does not
contend otherwise, arguing only irrelevancy based upon the time period and lack of
an apportionment argument. (Pl.’s Resp. Opp’n at 9.) Weyerhaeuser has therefore
failed to carry its burden to show why Daniel’s motion to compel should be denied.
, 270 F.R.D. at 241; , 2018 WL 5831997, at *5.
Accordingly, Daniel’s motion to compel responses to RFPs 13, 14, & 16, and
Deposition Topics 3, 4, 8, & 10 is therefore granted.
CC. Weyerhaeuser’s Settlement of the Murphy Litigation and Related
Information is Discoverable
Daniel further seeks to compel discovery concerning the Murphy litigation.
Murphy sued Weyerhaeuser for negligence. ( Compl. ¶¶ 179–193.)
Weyerhaeuser purportedly settled for an undisclosed amount. (Compl. ¶ 17.)
Weyerhaeuser claims to have paid approximately $621,195.50 in legal fees defending
and settling the Murphy litigation. (Pl.’s Resp. Opp’n at 7 (citing Pl’s Resp. Opp’n, Ex.
7 [DE #38-8] (Pl.’s Initial Discl.) at 3).) Weyerhaeuser now seeks to recover from
Daniel the undisclosed amount of settlement plus its legal fees.
Weyerhaeuser states that it “has no objection to the Court ruling partially in
Daniel’s favor . . . if solely limited to disclosing the amount for which Weyerhaeuser
12 This is also relevant to the potential negligence of Weyerhaeuser.
settled the lawsuit” but contends that “[a]ll other discovery sought by Daniel
regarding Weyerhaeuser’s damages and settlement of the lawsuit is
irrelevant under Rule 26(b)(1).” (Pl.’s Resp. Opp’n at 8.) In its brief, Weyerhaeuser
only specifically discusses Daniel’s RFP 22 and RFP 24. (Pl.’s Resp. Opp’n at 6–8.)
The settlement information sought by Daniel is relevant and proportional to
the claims of this action. The basis of Murphy’s suit was negligence. By seeking
indemnification of the amount paid in settlement of the Murphy litigation,
Weyerhaeuser has put into question the terms of the settlement. The contractual
indemnity provision upon which Weyerhaeuser relies expressly excludes damages
resulting from Weyerhaeuser’s or its Engineer’s negligence. Furthermore, any
obligation to indemnify Weyerhaeuser is limited to work performed by Daniel
pursuant to the alleged 1971 contract. The terms of the settlement agreement are
relevant to an important issue in this case (Daniel’s alleged liability under the
indemnification provision), and Daniel does not have access to the information.
Accordingly, Daniel is entitled to discovery of the settlement agreement.
Communications between Weyerhaeuser and Murphy are also relevant and
discoverable under Rule 26(b)(1). Such communications are not privileged as they are
not between Weyerhaeuser and its counsel. , 696 F.2d
1069, 1072 (4th Cir. 1982) (per curiam); , No. 4:07-CV-156-D,
2008 WL 1766753, at *1 (E.D.N.C. Apr. 17, 2008) (“The attorney-client privilege
applies to confidential communications between an attorney and a client, but does
not necessarily apply to all documents or correspondence that are in an attorney’s
possession.” (citations omitted)). Accordingly, Weyerhaeuser’s objections to Daniel’s
RFP 24 are rejected. ( Pl.’s Resp. Opp’n at 7; Def.’s Mot. Compel, Ex. 4 – Daniel’s
First Set of RFPs at 14 (RFP 24 and Weyerhaeuser’s objections to RFP 24).)
Daniel’s RFP 22 does request some information which may be attorney-client
privileged and/or protected under the attorney work-product doctrine. RFP 22
demands documents containing “analysis of the facts, reasons, and recommendations
for settling the Nicholas Murphy Lawsuit . . . including, but not limited to, any
memos, pre-trial reports, asbestos case profiles, Asbestos Litigation Forms (ALFs), or
similar Documents.” (Def.’s Mot. Compel, Ex. 4 – Daniel’s First Set of RFPs [DE #36-
4] at 13 (RFP 22).) Such information would be relevant to Weyerhaeuser’s potential
negligence for the reasons discussed above. To the extent RFP 22 requests legal
analysis of facts and recommendations based on that analysis, such information may
be privileged or protected.13 However, privileged communications between an
attorney and a client “may be inapplicable to facts incorporated in the
communications.”14 , 32 F.3d 851, 862
(3d Cir. 1994) (citing , 449 U.S. 383, 395–96 (1981)).
Weyerhaeuser has not submitted a privilege log in connection with its briefing, so the
13 Weyerhaeuser raised attorney-client privilege and attorney work-product
protection in its objections to RFP 22 (Def.’s Mot. Compel, Ex. 4 – RFP 24 [DE #36-4]
at 14), but only hinted at attorney work product protection in its briefing (Pl.’s Resp.
Opp’n at 7 (arguing that RFP 22 seeks “Weyerhauser’s mental impressions
concerning the lawsuit”)).
14 A waiver of attorney-client privilege can also occur when a party asserts a
claim or defense that puts its attorney’s advice at issue. , 32
F.3d at 863–64; , 68 F.R.D. 574, 581 (E.D. Wash. 1975).
court is unable to determine whether the documents and communications requested
in RFP 22 are, in fact, privileged or protected. Accordingly, Daniel’s motion to compel
as to RFP 22 is granted. Weyerhaeuser may produce a sufficiently detailed privilege
log, , 281 F.R.D. 270, 276–77 (E.D.N.C. 2012), with respect
to RFP 22 if it believes certain components of its response are privileged or protected
and the parties may proceed as they normally would in such circumstances, seeking
the court’s intervention only after complying with the procedures outlined in the case
management order that governs this lawsuit.
Daniel contends that this issue is relevant to RFPs 7, 17, & 20–25, and
Interrogatories 3, 4, 6, & 8–12. (Def.’s Mem. Supp. Mot. Compel at 4, 7.)
Weyerhaeuser has not contended otherwise. (Pl.’s Resp. Opp’n at 6–9.) Overruling
Weyerhaeuser’s relevancy objection to these requests, the court determines that
Weyerhaeuser has failed to carry its burden to show why Daniel’s motion to compel
should be denied. , 270 F.R.D. at 241; , 2018 WL
5831997, at *5. Daniel’s motion to compel as to RFPs 7, 17, & 20–25, and
Interrogatories 3, 4, 6, & 8–12, is therefore granted.
DD. Costs and Fees
Daniel has requested the court award costs and fees in connection with the
instant motion to compel. (Def.’s Mot. Compel at 3.) Subject to enumerated
exceptions, Rule 37 requires the court, upon granting a motion to compel, to award
expenses and fees incurred making the motion. Fed. R. Civ. P. 37(a)(5)(A);
, 285 F.R.D. 350, 365 (D. Md. 2012). These exceptions
are where “(i) the movant filed the motion before attempting in good faith to obtain
the disclosure or discovery without court action; (ii) the opposing party's
nondisclosure, response, or objection was substantially justified; or (iii) other
circumstances make an award of expenses unjust.” Fed. R. Civ. P. 37(a)(5)(A). None
of the exceptions apply.
Daniel attempted in good faith to obtain the discovery from Weyerhaeuser
prior to filing its motion to compel. Daniel tried numerous times to address these
issues with Weyerhaeuser (Mot. Compel at 2–3), and the court held two informal
discovery conferences in an attempt to address the dispute. It was only after the
conferences that Daniel was given authorization to and filed the motion to compel.
Fed. R. Civ. P. 37 (a)(5)(A)(i).
Weyerhaeuser’s position was not substantially justified. As explained by Judge
Grimm,
[a] party satisfies the “substantially justified” standard “if there is a
‘genuine dispute’ as to proper resolution or if ‘a reasonable person could
think [that the failure to produce discovery is] correct, that is, if it has a
reasonable basis in law and fact.’”
, 311 F. App’x 586, 599 (4th Cir. 2009) (quoting ,
487 U.S. 552, 565 (1988)). “Courts have concluded that ‘substantial
justification’ could include making meritorious objections to requested
discovery, or even engaging in a legitimate dispute over the sequence of
discovery.” , 263 F.R.D. 293, 296–97 (D. Md. 2009)
(citations omitted). However, to avoid the imposition of costs, “parties
must sufficiently argue that they were substantially justified in their
actions.” . at 297 (citing , 62
F.R.D. 392, 394 (D. Md. 1974)).
, 285 F.R.D. at 365. The bulk of Weyerhaeuser’s refusal to provide the sought-
after discovery stems from its position that its potential negligence is not relevant.
(Pl.’s Resp. Opp’n at 6.) Plaintiff can only reach that conclusion by ignoring15 the plain
text of the indemnity provision upon which it relies. These errors permeate
Weyerhaeuser’s refusal to provide discovery on factual issues regarding when and for
whom Murphy worked at the New Bern mill and Weyerhaeuser’s settlement of the
Murphy litigation. Weyerhaeuser also chose not to provide specific objections and/or
privilege log documentation regarding a potentially meritorious position regarding
RFP 22. Thus, Weyerhaeuser has not shown it was substantially justified in resisting
discovery. Fed. R. Civ. P. 37 (a)(5)(A)(ii).
Lastly, the court discerns no other circumstances that would render an award
of costs and fees unjust. Fed. R. Civ. P. 37 (a)(5)(A)(iii). Accordingly, the court
grants Daniel’s request for attorney’s fees and expenses, the amount of which will be
determined by separate order. Daniel shall have fourteen (14) days from the date of
this order to file a notice with accompanying affidavit of its costs and fees incurred in
bringing the motion to compel. Weyerhaeuser shall have ten (10) days to file written
objections to the costs and fees requested. Daniel shall have seven (7) days to respond
to any objections.
CCONCLUSION
For the reasons explained above, Defendant’s motion to compel [DE #36] is
GRANTED. Plaintiff shall have thirty (30) days from the date of this order to provide
the requested information. Defendant shall file its notice and affidavit of costs and
15 Plaintiff’s decision to elide key text from the alleged indemnity provision only
underscores that its position is not substantially justified. ( Compl. ¶ 9 (omitting
express exclusion for negligence).)
fees within fourteen (14) days. Plaintiff shall have ten (10) days to object to the costs
and fees requested, and Defendant shall have seven (7) days to respond thereto.
This 28th day of June 2024.
Dorm bol Araick
KIMBERIY A. SWANK
United States Magistrate Judge
19