Opinion

Gooden v. County of Los Angeles

Court
California Court of Appeal
Filed
Oct 25, 2024
Status
Published
Cited by
0 cases
Authority
More cited than 31.1%

The opinion

Filed 10/24/2024

CERTIFIED FOR PARTIAL PUBLICATION*

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

SECOND APPELLATE DISTRICT

DIVISION TWO

JOHN M. GOODEN, B326446

Plaintiff and Appellant, (Los Angeles County

Super. Ct. No.

v. 21STCP01784)

THE COUNTY OF LOS

ANGELES, et al.,

Defendants and

Respondents.

APPEAL from a judgment of the Superior Court of Los

Angeles County, Kevin Brazile, Judge. Affirmed.

Robert S. Gerstein for Plaintiff and Appellant.

* Pursuant to California Rules of Court, rules 8.1100 and

8.1110, this opinion is certified for publication as to all parts

except Part II of the Discussion.

Office of the County Counsel, Dawyn R. Harrison, County

Counsel, Starr Coleman, Assistant County Counsel, Kathy H.

Park, Deputy County Counsel; The Sohagi Law Group, Margaret

M. Sohagi, R. Tyson Sohagi, and Mark J.G. Desrosiers for

Defendants and Respondents.

******

Under the California Environmental Quality Act (CEQA)

(Pub. Resources Code, § 21000 et seq.),1 a public agency must

prepare an environmental impact report if any project it is

contemplating—which can include amendments to a local

government’s general plan for land use—“may have a significant

effect on the environment.” (§§ 21100, subd. (a), 21151, subd. (a);

Cal. Code Regs., tit. 14, § 15064, subd. (a)(1).) The primary

purpose of this report is informational—that is, “to give the

public and government agencies [contemplating the project] the

information needed to make informed decisions.” (In re Bay-

Delta etc. (2008) 43 Cal.4th 1143, 1162 (Bay-Delta).) But what if

the public agency, prior to certifying the environmental impact

report, ultimately takes action in a manner that deviates from

the project described in that report? Does that deviation

undermine the informational value of the previously circulated

report and, if so, what remedy does CEQA demand? We hold that

CEQA contemplates three possible outcomes in this scenario. If

the deviation alters the very “nature of the project” and its “main

features,” the deviation retrospectively renders inaccurate and

unstable the definition of the project previously set forth in the

report, thereby necessitating a new report to evaluate what is

1 All further statutory references are to the Public Resources

Code unless otherwise indicated.

2

effectively a new project. If the deviation is less extreme, but

increases the project’s adverse environmental impact by adding

“significant new information” for consideration, the public agency

must recirculate for further public comment an amended version

of the pertinent portions of the previously circulated report. And

if the deviation does not trigger either of these duties, no further

action is required.

In this case, a county circulated an amended land use plan

for an unincorporated mountainous region that contemplated

continued heavy regulation of vineyards in that region, but the

county board ultimately imposed a ban on new vineyards. We

conclude that this deviation did not alter the very nature of the

plan amendment or its main features, and that the vintner

challenging the county board’s action waived any request for

recirculation. We accordingly affirm the trial court’s denial of the

vintner’s petition for a writ of administrative mandamus.

FACTS AND PROCEDURAL BACKGROUND

I. Facts

A. The Santa Monica Mountains North Area

The Santa Monica Mountains North Area is an

approximately 21,000-acre area of land in an unincorporated

portion of northwestern Los Angeles County in the Santa Monica

Mountains—one of the County’s “most significant ecological and

scenic resources.”

The County regulates land use in the North Area pursuant

to (1) the North Area Plan, which was first adopted in October

2000 as a part of the County’s General Plan and serves as a

“planning tool” with “area-specific policies,” and (2) the

Community Standards District, which was first adopted in

3

October 2002 and serves as a “zoning overlay” within the County

Code to implement the policies of the North Area Plan.

B. Land uses within the North Area, including

vineyards

The North Area enjoys a “long history as a rural setting.”

Most of the North Area—16,514 acres—constitutes open space,

while 4,170 acres are designated for commercial, public, and

residential uses. Only around 100 acres are used for agriculture,

which predominantly consists of vineyards along Mulholland

Highway and Kanan Dume Road, as well as in Triunfo Canyon.

The North Area’s southern boundary stops five miles from

the coast because the California Coastal Commission regulates

the land within five miles of the coastline. In October 2014, the

California Coastal Commission certified a Local Coastal

Program—which consists of land use plans and zoning

ordinances—for the five miles of land adjacent to the North

Area.2 Among other things, the Local Coastal Program

prohibited any new vineyards within its boundaries; according to

the staff report submitted in support of the ban, this ban was

necessary due to the “adverse impacts attributed” to the

operation of vineyards, “including increased erosion from removal

of all vegetation, use of pesticides, large amounts of water

2 A group of landowners in the area governed by the Local

Coastal Program unsuccessfully litigated several challenges to

the certification. (See Mountainlands Conservancy, LLC v.

California Coastal Com. (2020) 47 Cal.App.5th 214.)

We reject the County’s assertion in its briefing that the

trial court should have augmented the record in this case to

include a study contained in the record of the litigation regarding

the Local Coastal Program. The County did not file a cross-

appeal.

4

required, their invasive nature, and their adverse impact to

scenic views.”

Shortly thereafter, in December 2015, the County’s Board

of Supervisors (the Board) adopted an ordinance specifically

regulating vineyards in the North Area. The 2015 ordinance

obligated anyone seeking to open a new vineyard or to expand an

existing vineyard to obtain a conditional use permit; it also

established development standards for all vineyards—existing or

new—to address the potential environmental impacts caused by

the “proliferation of vineyards” in the North Area.

C. The project

In April 2016, the Board voted to undertake a

“comprehensive update” to the North Area Plan and to the

Community Standards District. This update implicated CEQA.

The Board described the “project” to be undertaken as an update

“to provide greater protection of biological habitats, align Plan

and [Community Standards District] policies and standards with

the [Local Coastal Program], support the rural and semi-rural

character of the [North Area], and bring the land use policies for

the North Area into compliance with the General Plan.” The

update would result in a corresponding “replace[ment]” to

pertinent zoning provisions in the County Code and a rezoning of

hundreds of parcels. In other words, the project did “not include

any physical development”—instead, it “identifi[ed] land use

policies and development standards” for the North Area.

1. Draft environmental impact report

The County issued a draft environmental impact report for

the project in May 2020. The draft report identified several key

revisions to the North Area Plan and the Community Standards

District, including:

5

● Adopting various development standards to protect

sensitive biological resources, habitats, and scenic attributes;

● Imposing new permit requirements when protected trees

are affected by development;

● Setting standards for equestrian facilities;

● Limiting the use of event facilities;

● Establishing noise levels; and

● Imposing new permit requirements for grading projects.

As for viticulture, the draft proposed reducing the

minimum threshold for when the growth of grapes would be

considered a “vineyard” subject to the more stringent

development standards in the 2015 ordinance; the draft also

added standards for integrated pest management. There was no

proposed ban on new vineyards.

The County received almost 100 comments to the draft

report, with several voicing “support” of a “complete” “ban” on

vineyards “in the same fashion as in the Local Coastal Program.”

2. Final environmental impact report

The final environmental impact report was issued in

September 2020 with some changes. The final report did not

propose a vineyard ban; instead, the County responded to the

comments urging a ban by explaining that the existing

regulations governing “development standards” for vineyards

sufficed to “ensure that environmental impacts are minimized.”

Following a hearing on October 7, 2020, the County’s

Department of Regional Planning recommended that, with a few

minor modifications, the Board certify the final environment

impact report, approve the updates to the North Area Plan and

Community Standards District, and adopt an ordinance

amending the pertinent provisions of the County Code.

6

3. Certification

The Board convened a public meeting on November 4, 2020

to consider the recommendation. At the conclusion of the

meeting, the Board “indicate[d] its intent to certify” the final

report, approve the updated plan, and amend the County Code.

But the Board made one change pertinent to this appeal:3

“[P]rohibit new vineyards of any size.”

After soliciting and receiving written comments regarding

the proposed ban on new vineyards, the Board held another

public meeting on May 4, 2021 and voted unanimously to certify

the report, approve the updated North Area Plan and Community

Standards District, and adopt the ordinance amending the

pertinent provisions of the County Code. The vineyard ban is

reflected in section 22.336.070, subdivision (Y)(1)(a) of the County

Code and states: “All new vineyards, regardless of size, shall be

prohibited in this [Community Standards District].”

II. Procedural Background

The Malibu Coast Vintners and Grape Growers Alliance,

Inc. (the Alliance) and one of its members, a vintner named John

Gooden (Gooden), filed a petition for a writ of mandate on June 2,

2021. The Alliance and Gooden had submitted comments during

the CEQA proceedings opposing a vineyard ban. The writ

petition challenged the Board’s action banning all new vineyards

in the North Area Plan as violating (1) CEQA’s requirements that

(a) the project have an accurate and stable description and (b) the

report be recirculated when significant new information is added;

and (2) Government Code section 65857’s requirement that the

3 The Board identified a handful of other changes that are

not at issue here.

7

Board remand the new ban proposal for consideration by the

Department for Regional Planning.4

Following a full round of briefing and a hearing, the trial

court issued an order on November 14, 2022 denying the writ

petition.

Following the entry of judgment for the County and the

Board, the Alliance and Gooden appealed. The Alliance

abandoned the appeal, leaving only Gooden to pursue it.

DISCUSSION

Gooden argues that the County (1) violated CEQA by

certifying the report and approving the project, and (2) violated

Government Code section 65857 by amending the County Code.5

Because Gooden challenged the County’s action with a petition

for a writ of administrative mandamus, our task is to assess

whether the pertinent agency—here, the County through its

Board—has committed a “prejudicial abuse of discretion,” which

exists when the agency “has not proceeded in the manner

required by law” or the agency’s “findings are not supported by

the evidence.” (Code Civ. Proc., § 1094.5, subd. (b); Banning

Ranch Conservancy v. City of Newport Beach (2017) 2 Cal.5th

918, 935 [applying this standard in writ review of CEQA-based

4 The writ also challenged the Board’s action as contrary to

the County’s general plan, as arbitrary and capricious, and as

denying equal protection, but those theories have all been

abandoned on appeal.

5 Gooden argues that the County also violated one of its Code

provisions containing the same language as Government Code

section 65857, but it appears that the County Code provision

Gooden cites is inapplicable to the project at issue in this case.

(See L.A. County Code, § 22.232.040, subd. (B)(2)(a).)

8

claim].) As pertinent here, our task in reviewing the trial court’s

denial of the writ is to “step into the trial court’s shoes” and

independently examine for ourselves whether the agency acted

properly. (Gonzales v. California Victim Compensation Bd.

(2023) 98 Cal.App.5th 427, 441; Vineyard Area Citizens for

Responsible Growth, Inc. v. City of Rancho Cordova (2007) 40

Cal.4th 412, 427 [applying this standard in writ review of CEQA-

based claim].) We independently review any subsidiary legal

questions, including the meaning of statutes. (John v. Superior

Court (2016) 63 Cal.4th 91, 95-96; City of San Diego v. Board of

Trustees of California State University (2015) 61 Cal.4th 945,

956.) The burden of demonstrating a prejudicial abuse of

discretion rests on the party challenging the agency’s action.

(Southwest Regional Council of Carpenters v. City of Los Angeles

(2022) 76 Cal.App.5th 1154, 1172 (Southwest Regional).)

I. CEQA

Gooden argues that the Board’s action in enacting a total

ban on new vineyards retroactively renders “unstable” the

definition of the “project” set forth in the previously circulated

draft and final environmental impact reports. The County

responds that the Board’s action at most called for recirculation of

that portion of the report pertaining to agricultural land use

within the North Area, but that Gooden has abandoned on appeal

any claim for recirculation. To evaluate these arguments, we

must examine CEQA generally, the CEQA requirement that an

environmental impact report set forth an “accurate, stable and

finite” project description, and the CEQA threshold for

recirculation of environmental impact reports.

9

A. The pertinent law

1. CEQA, generally

CEQA is designed “‘to “[e]nsure the long-term protection of

the environment shall be the guiding criterion in public

decisions.”’” (Friends of College of San Mateo Gardens v. San

Mateo County Community College Dist. (2016) 1 Cal.5th 937, 944,

quoting No Oil, Inc. v. City of Los Angeles (1974) 13 Cal.3d 68,

74.) CEQA operates, not by dictating pro-environmental

outcomes, but rather by mandating that “decision makers and the

public” study the likely environmental effects of contemplated

government actions and thus make fully informed decisions

regarding those actions. (Neighbors for Smart Rail v. Exposition

Metro Line Construction Authority (2013) 57 Cal.4th 439, 447;

Bay-Delta, supra, 43 Cal.4th at p. 1162; Cal. Code Regs., tit. 14, §

15002, subd. (a)(1); accord, Vedanta Society of So. California v.

California Quartet, Ltd. (2000) 84 Cal.App.4th 517, 730 [“Projects

which significantly affect the environment can go forward, but

only after the elected decisionmakers have their noses rubbed in

those environmental effects, and vote to go forward anyway,”

italics omitted].)

The mechanism for that study is the environmental impact

report: Where a public agency contemplates a “project”—which

includes, among other things, the adoption or amendment of a

land use plan (e.g., Cal. Code Regs., tit. 14, § 15378, subd.

(a)(1))—and where that project “may have a significant effect on

the environment,” the agency must prepare an environmental

impact report analyzing those effects, and must circulate that

report to the public (to obtain comments) and to the agency’s

decisionmaking body (to ensure its decision is an informed one).

(§§ 21100, subd. (a), 21061, 21151, subd. (a); Cal. Code Regs., tit.

10

14, §§ 15064, subd. (a)(1), 15362; Tiburon Open Space Committee

v. County of Marin (2022) 78 Cal.App.5th 700, 725 (Tiburon).)

2. CEQA’s requirement that the description of the

project in the report be “accurate, stable and finite”

An “indispensable component” of an environmental impact

report is an accurate description of the project at issue. (Western

Placer Citizens for an Agricultural & Rural Environment v.

County of Placer (2006) 144 Cal.App.4th 890, 898 (Western

Placer); South of Market Community Action Network v. City and

County of San Francisco (2019) 33 Cal.App.5th 321, 332 (South of

Market).) Indeed, courts have repeatedly and uniformly

characterized “[a]n accurate project description” as “the ‘sine qua

non’ of an informative and legally sufficient [environmental

impact report].” (Southwest Regional, supra, 76 Cal.App.5th at p.

1173; Save Our Capitol! v. Department of General Services (2023)

87 Cal.App.5th 655, 673 (Save Our Capitol!); The Claremont

Canyon Conservancy v. Regents of University of California (2023)

92 Cal.App.5th 474, 482 (Claremont Canyon); Tiburon, supra, 78

Cal.App.5th at p. 738; South of Market, at p. 332;

stopthemillenniumhollywood.com v. City of Los Angeles (2019) 39

Cal.App.5th 1, 17 (stopthemillennium); Citizens for a Sustainable

Treasure Island v. City and County of San Francisco (2014) 227

Cal.App.4th 1036, 1052 (Treasure Island); San Joaquin Raptor

Rescue Center v. County of Merced (2007) 149 Cal.App.4th 645,

655 (San Joaquin Raptor); Western Placer, at p. 898; City of

Santee v. County of San Diego (1989) 214 Cal.App.3d 1438, 1454

(City of Santee); Dusek v. Redevelopment Agency (1985) 173

Cal.App.3d 1029, 1040 (Dusek); County of Inyo v. City of Los

Angeles (1977) 71 Cal.App.3d 185, 193 (County of Inyo).) This

characterization makes sense: The whole point of an

11

environmental impact report is to give the public and

decisionmakers sufficient information about the impact of the

project at issue to make an “intelligent evaluation” of those

impacts, so the report must adequately describe what that project

is in the first place. (Save Our Capitol!, at p. 673; cf. County of

Inyo, at p. 192 [a “curtailed or distorted project description may

stultify the objectives of the reporting process”].)

Courts have thus uniformly demanded that the description

of a project in an environmental impact report be “accurate,

stable and finite.” (Claremont Canyon, supra, 92 Cal.App.5th at

p. 482; Save Our Capitol!, supra, 87 Cal.App.5th at pp. 668, 673;

Southwest Regional, supra, 76 Cal.App.5th at p. 1173; Buena

Vista Water Storage Dist. v. Kern Water Bank Authority (2022) 76

Cal.App.5th 576, 588 (Buena Vista); stopthemillennium, supra, 39

Cal.App.5th at p. 17; Tiburon, supra, 78 Cal.App.5th at p. 738;

South of Market, supra, 33 Cal.App.5th at p. 332; Washoe

Meadows Community v. Department of Parks & Recreation (2017)

17 Cal.App.5th 277, 281 (Washoe Meadows); Treasure Island,

supra, 227 Cal.App.4th at p. 1052; Communities for a Better

Environment v. City of Richmond (2010) 184 Cal.App.4th 70, 80

(Communities); San Joaquin Raptor, supra, 149 Cal.App.4th at p.

655; Western Placer, supra, 144 Cal.App.4th at p. 898; City of

Santee, supra, 214 Cal.App.3d at p. 1454; Dusek, supra, 173

Cal.App.3d at p. 1040; County of Inyo, supra, 71 Cal.App.3d at p.

193.) This means that the description must set forth “‘the

entirety of the project’” (Tiburon, at p. 738, quoting South of

Market, at p. 332; San Joaquin Raptor, at p. 654), and, as to that

entirety, must describe both the “‘nature of the project’” and its

“‘main features’” (Tiburon, at pp. 738-739, quoting South of

Market, at p. 332 and Dry Creek Citizens Coalition v. County of

12

Tulare (1999) 70 Cal.App.4th 20, 28 (Dry Creek Citizens); Save

Our Capitol!, at p. 674; Southwest Regional, at p. 1173; Treasure

Island, at pp. 1052, 1055; Communities, at p. 84). The

regulations that function as CEQA’s so-called “guidelines” specify

that a report’s project description must accordingly include (1)

“[t]he precise location and boundaries of the proposed project” on

a map, (2) “[a] statement of the objectives sought by the proposed

project,” (3) “[a] general description of the project’s technical,

economic, and environmental characteristics,” and (4) “[a]

statement briefly describing the intended uses of the

[environmental impact report].” (Cal. Code Regs., tit. 14, §

15124.) The description need not include every detail: The CEQA

guidelines eschew “extensive detail beyond that needed for

evaluation and review of the environmental impact” (ibid.), and

courts have never required the inclusion of information that is

not “reasonably feasible” for the agency to obtain and provide

(Southwest Regional, at p. 1173; Claremont Canyon, at p. 483).

By obligating public agencies to prepare and circulate

environmental impact reports, to solicit comments, and then to

respond to that feedback, CEQA necessarily contemplates that

public agencies may opt to alter projects in response to feedback

and thus to adopt projects that deviate from what was described

in prior environmental impact reports. If any and every deviation

rendered the description of projects in previously circulated

environmental impact reports retroactively inadequate or

unstable, public agencies would have a strong disincentive ever to

deviate from a project as originally articulated. This would

“freeze” projects “in the precise mold of the initial project”

(County of Inyo, supra, 71 Cal.App.3d at p. 199; Save Our

Capitol!, supra, 87 Cal.App.5th at p. 673) and “handcuff

13

decisionmakers” to the project as initially described (Dusek,

supra, 173 Cal.App.3d at p. 1041; South of Market, supra, 33

Cal.App.5th at p. 336). This is not in the spirit of CEQA, for it

would prompt agencies to ignore helpful or enlightening public

feedback—a result at odds with the entire purpose of the

information exchange triggered by CEQA’s environmental impact

report procedures.

In threading the needle between ensuring that a project’s

description is accurate, stable and finite while also not robbing

public agencies of the flexibility needed to tailor projects in

response to feedback, courts have defined when a public agency’s

adoption of a project that deviates from the project’s description

in a prior environmental impact report renders that description

inadequate and unstable. That occurs when deviation is so great

that the earlier project description likely “mis[led]” the public and

“thwarted the public’s ability to participate in the process and

comment meaningfully on the [environmental impact report].”

(Save Our Capitol!, supra, 87 Cal.App.5th at p. 674; San Joaquin

Raptor, supra, 149 Cal.App.4th at p. 656; see Washoe Meadows,

supra, 17 Cal.App.5th at p. 290 [deviation means that prior

description was an “obstacle” to meaningful public comment].)

Courts have identified three scenarios in which a public

agency’s project description may be inadequate or unstable:

● When the environmental impact report does not

actually describe the “project” at all. When a report sets forth five

“dramatically different” potential projects across a “broad range”

of possibilities that have “vast[ly]” “different[]” environmental

impacts, and does not designate any of them as the project being

considered, there is no “adequate” or “stable” project description.

(Washoe Meadow, supra, 17 Cal.App.5th at pp. 281, 288-290.)

14

However, where a report defines the overall parameters and

“footprint” for a specific project such as a mixed-use commercial

and residential project, but also includes variants for that project

proposing different percentages of the mix between the two uses,

the description is stable and the inclusion of those variants does

not render the description unstable. (Southwest Regional, supra,

76 Cal.App.5th at p. 1179 [so holding]; South of Market, supra, 33

Cal.App.5th at pp. 332-336 [same].)

● When the environmental impact report’s description of

the nature of the project or its main elements is too amorphous.

When a report describes a hotel construction project but omits

“any description or detail regarding what [the developer]

intended to build” beyond “different conceptual scenarios,” the

project description is unstable. (stopthemillennium, supra, 39

Cal.App.5th at pp. 7-8, 18.) However, when the project

description gives as much detail as can be provided at the time,

there is no instability. Thus, the 20-year, “long-range

development plan” at issue in Treasure Island, supra, 227

Cal.App.4th 1036 was not unstable merely because it did not

include details that “[did] not [yet] exist.” (Id. at pp. 1052-1055.)

And the project to clear brush in Claremont Canyon, supra, 92

Cal.App.5th 474, and the project to extract up to a specific

quantity of water in Buena Vista, supra, 76 Cal.App.5th 576,

were not unstable merely because the public agencies did not

include which trees would be cut down and precisely how much

water would be extracted when the descriptions explained how

those determinations would later be made. (Claremont Canyon,

at pp. 484-490; Buena Vista, at p. 590.) The goal is “adequacy,”

not “perfection.” (Claremont Canyon, at p. 483.)

15

● When the environmental impact report’s description of

the nature of the project or its main elements is self-contradictory

or inconsistent with later articulations. When a report gives

“conflicting signals” about a project’s contours (Treasure Island,

supra, 227 Cal.App.4th at p. 1052), the project description may be

unstable and inadequate—if those inconsistencies go to the

nature of the project or its main elements. Thus, in County of

Inyo, supra, 71 Cal.App.3d 185, the environmental impact reports

inconsistently described the project as drawing water from a

lakebed to service the local community and as extracting water to

service the greater Los Angeles basin as well as installing a

pipeline to transport that water; the conflicting project

descriptions in those reports were “unstable.” (Id. at pp. 190,

198-199.) In Save our Capitol!, supra, 87 Cal.App.5th 655, the

environmental impact reports inconsistently described a remodel

to the State Capitol Building as involving disparately different

exterior design aesthetics; the conflicting project descriptions—at

least in the context of a “historical resource” where “aesthetics” is

key—rendered the project description “unstable.” (Id. at pp. 675-

676.) In San Joaquin Raptor, supra, 149 Cal.App.4th 645, the

draft environmental impact report inconsistently described the

project as having “no increases in mine production” and also

“provid[ing] for substantial increases in mine production”; the

conflicting project descriptions were “unstable.” (Id. at pp. 654-

657.) In City of Santee, supra, 214 Cal.App.3d 1438, the report

and early action by the public agency referred to the temporary

expansion of a prison as being indefinite in duration or at most

three years, while the public agency ultimately approved a

duration of seven years; the conflicting project descriptions

regarding the duration of the expansion—which would have a

16

direct bearing on its environmental impact—were unstable. (Id.

at pp. 1451, 1454-1455.) And in Communities, supra, 184

Cal.App.4th 70, the reports regarding new construction at an oil

refinery inconsistently described the type of crude oil the refinery

would process; the conflicting project descriptions were unstable.

(Id. at pp. 80-85.) However, where the description of what would

be processed at a new oil refinery was consistent in Rodeo

Citizens Assn. v. County of Contra Costa (2018) 22 Cal.App.5th

214, 220-225, the project description was sufficiently stable.

As these examples illustrate, the instability of a project’s

description can arise (1) from inadequacies in the environmental

impact reports (e.g., San Joaquin Raptor, supra, 149 Cal.App.4th

at pp. 654-656 [conflicting statements in various reports]), or (2)

from subsequent action by the public agency that deviates

sufficiently from the project described in the reports that the

deviation retroactively renders those reports’ description(s)

uncertain and hence unstable (e.g., Southwest Regional, supra, 76

Cal.App.5th at pp. 1167, 1182; Save Our Capitol!, supra, 87

Cal.App.5th at pp. 674-676).

“Whether [an environmental impact report] contains an

accurate and stable project description is a question of law

subject to de novo review.” (Save Our Capitol!, supra, 78

Cal.App.5th at p. 673; Tiburon, supra, 78 Cal.App.5th at p. 738;

South of Market, supra, 33 Cal.App.5th at p. 332;

stopthemillennium, supra, 39 Cal.App.5th at p. 16.) This

standard of review dovetails neatly with the standards of review

for CEQA review more generally: “An agency’s failure to provide

an accurate, stable, and finite project description is a failure to

proceed in a manner required by law” (Buena Vista, supra, 76

Cal.App.5th at p. 588), and appellate courts independently review

17

whether an agency failed to proceed in a manner required by law

(City of Hayward v. Trustees of California State University (2015)

242 Cal.App.4th 833, 839).

Because, as pertinent here, a project description will be

found unstable if a subsequent deviation from the originally

articulated description is sufficiently grave to thwart the

environmental impact report’s ability to serve its communicative

function, and because an agency’s failure to proceed in a manner

required by law is prejudicial “if the failure to include relevant

information precludes” “informed public comment” and “informed

decisionmaking” (Southwest Regional, supra, 76 Cal.App.5th at

pp. 1172-1183; Washoe Meadows, supra, 17 Cal.App.5th at p.

290), a finding that a project description is unstable satisfies the

requirement for writ relief that the public agency’s abuse of

discretion be prejudicial. The writ petitioner need not also show

that starting over with an accurate project description would lead

to a different outcome. (stopthemillennium, supra, 39

Cal.App.5th at p. 20.)

3. The duty under CEQA to recirculate for further

public comment

As a project moves through CEQA’s review process, the

public agency necessarily acquires new information and may opt

to alter the project in light of that information. Even if these

alterations do not destabilize the project’s definition, do they

obligate the agency to recirculate the environmental impact

report containing the new information for further public

comment? It is well settled that “recirculation is not required

simply because new information is added.” (South County

Citizens for Smart Growth v. County of Nevada (2013) 221

Cal.App.4th 316, 328; Western Placer, supra, 144 Cal.App.4th at

18

p. 899 [“no provision in CEQA . . . requires all changes made to a

project . . . be included in the [environmental impact report

through recirculation]”]; Southwest Regional, supra, 76

Cal.App.5th at p. 1184 [same].) Recirculation is the “exception,

rather than the general rule” (Laurel Heights Improvement Assn.

v. Regents of University of California (1993) 6 Cal.4th 1112, 1132

(Laurel Heights); East Oakland Stadium Alliance v. City of

Oakland (2023) 89 Cal.App.5th 1226, 1265 (East Oakland);

Southwest Regional, at p. 1184), and for good reason: If

recirculation were required every time new information was

considered or incorporated into a project, then the likely result is

an endless feedback loop of circulation-new information-

recirculation. CEQA was meant to foster informed consideration

of environmental consequences, not total paralysis. (Laurel

Heights, at p. 1132 [“the Legislature did not intend to promote

endless rounds of revision and recirculation of [environmental

impact reports]”].)

CEQA nevertheless recognizes that recirculation is

sometimes warranted. Specifically, CEQA obligates a public

agency to recirculate the pertinent portions of an environmental

impact report for further public comment when, prior to

certification of the report,6 “significant new information is added

to an environmental impact report.” (§ 21092.1; Chaparral

Greens v. City of Chula Vista (1996) 50 Cal.App.4th 1134, 1146-

1147 (Chaparral Greens); Cal. Code Regs., tit. 14, § 15088.5,

subds. (a), (c).) For these purposes, “information” is defined

6 If the public agency has already certified the environmental

impact report, whether a new report must be prepared is

governed by different provisions of CEQA. (§ 21166; accord,

Laurel Heights, supra, 6 Cal.4th at pp. 1125-1126.)

19

broadly to include “changes in the project or environmental

setting as well as additional data or other information.” (Cal.

Code Regs., tit. 14, § 15088.5, subd. (a).) As a result, new

information possibly justifying recirculation can arise from

information obtained through public comment or, as pertinent

here, the public agency’s adoption of a modified version of the

project. (E.g., Southwest Regional, supra, 76 Cal.App.5th at pp.

1181-1182 [entertaining recirculation argument where public

agency adopted a modified version of the project].)

Our Supreme Court defined when new information is

“significant” for purposes of pre-certification recirculation in

Laurel Heights, supra, 6 Cal.4th 1112. Specifically, the court

noted that new information not in a prior environmental impact

report is “significant” when that information “discloses: (1) a new

substantial environmental impact resulting from the project or

from a new mitigation measure proposed to be implemented . . . ;

(2) a substantial increase in the severity of an environmental

impact unless mitigation measures are adopted that reduce the

impact to a level of insignificance . . . ; (3) a feasible project

alternative or mitigation measure that clearly would lessen the

environmental impacts of the project, but which the project’s

proponents decline to adopt . . . ; or (4) that the draft

[environmental impact report] was so fundamentally and

basically inadequate and conclusory in nature that public

comment on the draft was in effect meaningless.” (Laurel

Heights, at pp. 1129-1130.) The CEQA guidelines formally

adopted the definition articulated by the Supreme Court. (Cal.

Code Regs., tit. 14, § 15088.5, subd. (a); Laurel Heights, at p.

1130, fn. 15 [language in definition under consideration by

administrative agency at time of Supreme Court’s decision].)

20

Upon closer inspection, this definition deems new

information to be “significant” only if that information (1) is

significantly different than what was previously circulated, and

(2) tends to show that the project will have a more adverse

environmental impact than stated or implied in the previously

circulated reports. (Laurel Heights, supra, 6 Cal.4th at pp. 1120,

1129-1130; East Oakland, supra, 89 Cal.App.5th at p. 1265; Cal.

Code Regs., tit. 14, § 15088.5, subd. (a).) Information that

“‘merely clarifies or amplifies [citation] or makes insignificant

modifications’” does not warrant recirculation. (Laurel Heights,

at p. 1128, quoting Sutter Sensible Planning, Inc. v. Board of

Supervisors (1981) 122 Cal.App.3d 813, 822-823; Cal. Code Regs.,

tit. 14, § 15088.5, subd. (b); cf. Southwest Regional, supra, 76

Cal.App.5th at p. 1185 [information that is “substantially

similar” to previously disclosed information does not warrant

recirculation].) All of the examples listed in Laurel Heights

involve the omission of new information tending to indicate a

worse environmental impact, including the example of an

“inadequate and conclusory” draft in Mountain Lion Coalition v.

Fish & Game Com. (1989) 214 Cal.App.3d 1043, 1051-1053,

where the previously circulated report completely omitted any

analysis of the cumulative effect of the project on the

environment.

Although a public agency’s failure to recirculate pertinent

portions of an environmental impact report constitutes a failure

to proceed in the manner required by law when there is

“significant new information” that satisfies the above-stated

definition, the threshold determination of whether new

information qualifies as “significant” is for the public agency to

make in the first instance; courts review the agency’s

21

determination in this regard under the deferential substantial

evidence standard. (Laurel Heights, supra, 6 Cal.4th at p. 1135;

Southwest Regional, supra, 76 Cal.App.5th at p. 1184; Chapparal

Greens, supra, 50 Cal.App.4th at p. 1147.)

B. Analysis

As the pertinent law indicates, a public agency’s approval

of a project that deviates from how the project was described in

previously circulated environmental impact reports can

potentially implicate the CEQA rule requiring the project

description in the report be “stable” and the CEQA rule requiring

recirculation of a report. (Accord, Save Our Capitol!, supra, 87

Cal.App.5th at p. 674 [noting the close relationship between these

two doctrines]; Southwest Regional, supra, 76 Cal.App.5th at pp.

1181-1182 [same].) Although both CEQA rules are implicated in

this scenario, it is critical to determine which applies because

they call for vastly different remedies: A public agency’s adoption

of a modified project that retroactively destabilizes the project’s

description by itself qualifies as a “prejudicial abuse of discretion”

that ostensibly obligates the public agency to start over with the

CEQA review process, while the adoption of a modified project

does not call for recirculation unless substantial evidence fails to

support the agency’s implied finding that the modification does

not qualify as “significant new information.”

Thus, CEQA effectively erects a three-tiered system when

it comes to a public agency’s adoption of a modified project. First,

the modification can be so fundamentally significant that it calls

into question—and hence destabilizes—the description of the

project itself, thereby warranting a reboot of the CEQA review

process. Second, the modification can be not so significant as to

destabilize the project’s description, but significant enough to

22

constitute “significant new information,” thereby warranting

recirculation for further public comment on the new information.

Third and lastly, the modification can be insignificant, in which

case no further action need be taken.

Here, because Gooden has abandoned any claim that the

Board’s action warrants recirculation, the sole question before us

is whether the Board’s action in approving the project to update

the North Area Plan and Community Standards District as

amended to include a ban on all new vineyards renders the

description of the project set forth in the previously circulated

environmental impact reports unstable.

We independently conclude that it does not.

In this case, the project is the revision of the North Area

Plan as well as the Community Standards District in their

entirety, along with a corresponding overhaul to the County Code

provisions governing the North Area. The portion of the North

Area Plan and Community Standards District devoted to

agricultural land uses is very small: It encompasses one-half of

one page of the 91-page Plan and one small subsection of the

innumerable-section standards in the Community Standards

District. What is more, the topic of agricultural land use—and,

indeed, the regulation of vineyards—within the North Area Plan

was unmistakably part of the “project.” In this context, the

Board’s decision to adopt a total ban on new vineyards in the area

rather than to adopt the previously proposed plan to heavily

regulate all vineyards does not alter the “‘nature of the project’”

or any of its “‘main features.’” (Tiburon, supra, 78 Cal.App.5th at

pp. 738-739, quoting South of Market, supra, 33 Cal.App.5th at p.

332 and Dry Creek Citizens, supra, 70 Cal.App.4th at p. 28; Save

Our Capitol!, supra, 87 Cal.App.5th at p. 674; Southwest

23

Regional, supra, 76 Cal.App.5th at p. 1173; Treasure Island,

supra, 227 Cal.App.4th at pp. 1052, 1055; Communities, supra,

184 Cal.App.4th at p. 84.)

The propriety of this result is confirmed when comparing

the Board’s deviation from the project described in the prior

reports in this case to the scenarios where courts have found

project descriptions to be unstable. This is not a case where the

reports did not describe the project at all. This is not a case

where the description of the project was too amorphous. And this

is not a case where the prior description of the project is

inconsistent with the adopted version in a manner that alters the

nature of the project or its main elements. To be sure, the

treatment of new vineyards under the North Area Plan and

Community Standards District changed, but, as noted above, this

change was but a small part of a much more comprehensive

revision of the North Area Plan and Community Standards

District as a whole; this change did not alter the nature of that

project or any of its main elements. To be sure, this change was

significant to potential new vintners, but if that were sufficient to

destabilize a project’s description, then any and every deviation

from a prior project description would be grounds for hitting the

reset button under CEQA; as noted above, that is not the law.

Gooden responds with what boils down to two arguments.

First, he points to Save Our Capitol!, supra, 87 Cal.App.5th 655

as directly on point. It is not. The court in Save Our Capitol!

took pains to explain that, where the project itself was a remodel

to a historical capitol building complex, the change in the

aesthetic design of the complex was integral to the status of the

complex as a historical resource. (Save Our Capitol!, at pp. 675-

676.) By contrast, the shift from heavy regulation of new

24

vineyards to an outright ban—when current use for vineyards

accounted for less than one percent of the North Area’s total

acreage—was not integral to the project’s updates to the land use

policies affecting the entire North Area. Second, Gooden asserts

that the shift to a total ban is significant because “most

agriculture in the North Area currently consists of vineyards.”

This may be true, but it does not eclipse the fact that the total

amount of acreage dedicated to this use is miniscule or, more to

the point, the fact that agricultural land use was a small part of

the project of revising the entire North Area Plan.7

II. Government Code Section 65857

Gooden argues that the Board violated Government Code

section 65857 when its adoption of an ordinance banning new

vineyards deviated from the recommendation of the Department

for Regional Planning without giving the Department an

opportunity to provide its input. This statute provides that “any

modification of [a] proposed ordinance or amendment by [a]

legislative body not previously considered by the planning

commission during its hearing[] shall first be referred to the

planning commission for report and recommendation.” (Gov.

Code, § 65857; accord, id., § 65356, subd. (a) [adopting the same

rule when a legislative body makes modifications to its general

plan].) We will assume that the Board violated Government Code

section 65857 when it adopted the vineyard ban without first

remanding the matter back to the Department for Regional

Planning for its report and recommendation on a ban.

7 In light of our conclusion, we need not address the County’s

alternative arguments for affirmance, some of which are

impenetrable.

25

We nonetheless must still reject Gooden’s argument

because he failed to demonstrate that this procedural misstep

was prejudicial. Government Code section 65010 requires that

the actions of public agencies may not be invalidated “unless the

court finds that the error was prejudicial” and “that a different

result would have been probable if the error had not occurred.”

(Gov. Code, § 65010, subd. (b).) The burden of showing a

different outcome is probable rests with the party challenging the

agency’s action. (Rialto Citizens for Responsible Growth v. City of

Rialto (2012) 208 Cal.App.4th 899, 920; Roberson v. City of Rialto

(2014) 226 Cal.App.4th 1499, 1508.) Here, Gooden offers nothing

but speculation that the Board would adopt a different ordinance

if the Department of Regional Planning had weighed in on a ban

of new vineyards. Indeed, such a different outcome is unlikely

because, regardless of any updated recommendation, the Board

already had before it public comments favoring and disfavoring a

ban, and ultimately decided a ban was in the public interest.

Gooden responds that a different outcome is likely because the

Department of Regional Planning opted not to recommend a ban

in the first instance, but this fact alone cannot be sufficient to

constitute prejudice because it is necessarily true in every case

where the decisionmaker deviates from a planning commission’s

prior recommendation; we decline to read the requirement of a

prejudice showing mandated by section 65010 out of the

Government Code.

DISPOSITION

The judgment is affirmed. The County and the Board are

entitled to costs on appeal.

CERTIFIED FOR PARTIAL PUBLICATION.

26

______________________, J.

HOFFSTADT

We concur:

_________________________, P. J.

LUI

_________________________, J.

CHAVEZ

27