Opinion

Law Enforcement District of Jefferson Parish Versus Mapp Construction, LLC, Abc Insurance Company, Travelers Casualty & Surety Company, Sizeler, Thompson, Brown Artchitects Project Design Group, LLC and the Xyz Insurance Company

Court
Louisiana Court of Appeal
Filed
May 29, 2020
On the bench
Frank A. Brindisi
Cited by
0 cases
Authority
More cited than 30.8%

The opinion

LAW ENFORCEMENT DISTRICT OF NO. 19-CA-543

JEFFERSON PARISH

FIFTH CIRCUIT

VERSUS

COURT OF APPEAL

MAPP CONSTRUCTION, LLC, ET AL

STATE OF LOUISIANA

ON APPEAL FROM THE TWENTY-FOURTH JUDICIAL DISTRICT COURT

PARISH OF JEFFERSON, STATE OF LOUISIANA

NO. 749-646, DIVISION "E"

HONORABLE FRANK A. BRINDISI, JUDGE PRESIDING

May 29, 2020

JUDE G. GRAVOIS

JUDGE

Panel composed of Judges Jude G. Gravois,

Robert A. Chaisson, and Hans J. Liljeberg

AFFIRMED

JGG

RAC

HJL

COUNSEL FOR DEFENDANT/APPELLANT,

G. M. HORNE, LLC

Rene S. Paysse, Jr.

Darren P. Tyus

COUNSEL FOR DEFENDANT/APPELLEE,

CENTRIA SERVICES GROUP, LLC

Michael M. Meunier

Timothy R. McGibboney

James A. Collura, Jr.

Justin Scott

GRAVOIS, J.

In this appeal, appellant, third-party plaintiff G.M. Horne Commercial and

Industrial, LLC, argues that the trial court erred in granting Centria Services

Group, LLC’s peremptory exception of peremption pursuant to La. R.S. 9:2772,

dismissing Horne’s third-party demand for indemnity against Centria with

prejudice. Horne argues that the trial court erred in categorizing the contract

between the parties as a construction contract, subject to the five-year peremptive

period found in La. R.S. 9:2772, rather than a sales contract. For the following

reasons, we affirm.

FACTS AND PROCEDURAL BACKGROUND

This matter arises out of a 2009 construction contract between the Law

Enforcement District of Jefferson Parish (“the District”), as owner, and MAPP

Construction, LLC, as contractor, for construction of the Jefferson Parish Sheriff’s

Office Forensic Crime Laboratory building. To accomplish part of said

construction, MAPP entered into a subcontract with Horne to supply and install the

“Centria Formawall Dimension System”1 for the exterior walls of the building,

along with all of the coordination drawings and shop drawings associated

therewith. Horne, a dealer in Centria products, in turn contracted directly with

Centria to furnish materials, product application drawings, and delivery of an

insulated metal panel system to be manufactured by Centria and installed on the

project by a separate contractor.

The laboratory building’s construction was accepted by the District as

substantially complete on September 23, 2010, as evidenced by a Certificate of

Substantial Completion registered in the mortgage office of Jefferson Parish on

October 1, 2010. When the laboratory building experienced substantial external

1

The record reflects that the “Centria Formawall Dimension System” is a patented system.

19-CA-543 1

water intrusion in 2012 following Hurricane Isaac, MAPP made repairs that were

later deemed to be insufficient and/or ineffective. The building thereafter

continued to experience water intrusion and leakage, ultimately leading to this suit

by the District against MAPP and others for breach of contract, filed on May 13,

2015. In turn, on June 12, 2015, MAPP filed a third-party demand against Horne,

appellant herein, and others, alleging that Horne is obligated to fully indemnify and

reimburse MAPP if and to the extent that the District proves the existence of

defects or deficiencies in any of the materials, work, or performance of Horne on

the basis of the allegations set forth in the District’s petition and for which MAPP

is held liable to the District.

On November 13, 2015, Horne filed a third-party demand against Centria,

alleging that Centria was legally obligated to fully indemnify and reimburse Horne

“[i]f, and to the extent that [the District] and/or [MAPP] prove the existence of any

defects or deficiencies with respect to [Horne’s] performance of its contractual

obligations to provide the insulated metal system manufactured by Centria and

installed on the Project by a separate contractor, and for which [Horne] is held

liable, ... .”

In due course, on December 10, 2018, Centria filed a peremptory exception

of peremption, arguing that Horne’s third-party demand for indemnification, filed

on November 13, 2015, was perempted under La. R.S. 9:2772, having been filed

more than five years after the filing of the Certificate of Substantial Completion in

the mortgage office of Jefferson Parish on October 1, 2010.

Horne opposed the exception, arguing that the contract between the parties

was one of sale, rather than one of construction, and thus the contract was not

subject to the five-year peremptive period found in La. R.S. 9:2772. Multiple reply

memoranda and sur-reply memoranda were also filed. The exception was heard on

May 22, 2019, after which the parties filed post-trial memoranda. The trial court

19-CA-543 2

ultimately rendered judgment with reasons on July 31, 2019, granting Centria’s

exception and dismissing Horne’s third-party demand against Centria with

prejudice. This timely appeal followed.

On appeal, Horne argues that the trial court erred in finding that the contract

between Horne and Centria was a construction contract, rather than a sales

contract, thereby subjecting the contract to the five-year peremptive period found

in La. R.S. 9:2772. Horne also argues that the trial court failed to view the facts in

a light most favorable to them, as required by law. Horne also seeks a de novo

review on appeal. For the following reasons, we affirm.

ANALYSIS2

Standard of review

Peremption is a period of time fixed by law for the existence of a right.

Unless timely exercised, the right is extinguished upon the expiration of the

peremptive period. La. C.C. art. 3458. The function of the peremptory exception

is to have the plaintiff’s action declared legally nonexistent, or barred by effect of

law, and hence this exception tends to dismiss or defeat the action. La. C.C.P. art.

923. Peremption may not be renounced, interrupted, or suspended. La. C.C. art.

3461.

Peremptive statutes are strictly construed against peremption and in favor of

the claim. Of the possible constructions, the one that maintains enforcement of the

claim or action, rather than the one that bars enforcement should be adopted.

Rando v. Anco Insulations Inc., 08-1163 (La. 5/22/09), 16 So.3d 1065, 1083.

The standard of review of a trial court’s ruling on a peremptory exception of

prescription generally turns on whether evidence is introduced. DeFelice v.

Federated National Insurance Company, 18-374 (La. App. 5 Cir. 7/9/19), 279

2

Horne’s arguments on appeal are interrelated and therefore are addressed together.

19-CA-543 3

So.3d 422, 426 (citing Wells Fargo Financial Louisiana, Inc. v. Galloway, 17-413

(La. App. 4 Cir. 11/15/17), 231 So.3d 793, 800). When no evidence is introduced,

appellate courts review judgments sustaining an exception of prescription de novo,

accepting the facts alleged in the petition as true. Id. (citing Wells Fargo, 231

So.3d at 800; Lennie v. Exxon Mobil Corporation, 17-204 (La. App. 5 Cir.

6/27/18), 251 So.3d 637, 642, writ denied, 18-1435 (La. 11/20/18), 256 So.3d

994). Normally, when evidence is introduced at a hearing on an exception of

prescription, the trial court’s findings of fact are reviewed under the manifest error

standard. Id. (citing Wells Fargo, 231 So.3d at 800; Tenorio v. Exxon Mobil Corp.,

14-814 (La. App. 5 Cir. 4/15/15), 170 So.3d 269, 273, writ denied, 15-1145 (La.

9/18/15), 178 So.3d 149). However, when evidence is introduced but the case

involves only the determination of a legal issue, not a dispute regarding material

facts, an appellate court must review the issue de novo, giving no deference to the

trial court’s legal determination. Id. (citing Wells Fargo, 231 So.3d at 800; Cawley

v. National Fire & Marine Ins. Co., 10-2095 (La. App. 1 Cir. 5/6/11), 65 So.3d

235, 237).

At the hearing on the exception, Centria introduced both documentary and

testimonial evidence;3 Horne introduced documentary evidence, but did not

introduce any testimonial evidence. Although evidence was introduced at the

hearing, Horne asserts on appeal that the material facts in this case are not

disputed. Horne asserts that based on the undisputed material facts presented, its

contract with Centria is a sales contract, rather than a construction contract. Thus,

the standard of review herein should be de novo, rather than manifest error, and

this Court should give no deference to the trial court’s legal conclusion, citing

DeFelice v. Federated Nat’l Ins. Co., supra. Upon review, we agree. We find that

3

At the hearing, Centria introduced the deposition testimony of Robert Rutherford, its regional

distribution manager.

19-CA-543 4

there is no dispute between the parties as to the material facts giving rise to

Centria’s peremptory exception of peremption. Horne does not dispute the extent

of Centria’s actions in complying with its subcontract with Horne. The only issue

that must be resolved is whether the undisputed facts of the case clearly present a

contract that is governed by the peremptive period found in La. R.S. 9:2772, and

accordingly, whether the trial court properly granted Centria’s peremptory

exception of peremption. Our review of the trial court’s decision on the exception

will therefore be de novo.

Construction contract versus sales contract

On appeal, Horne argues that the trial court erred in finding that the contract

between Horne and Centria was a construction contract, rather than a sales

contract, thereby subjecting the contract to the five-year peremptive period found

in La. R.S. 9:2772.

The statute at issue in this case, La. R.S. 9:2772, provides, in pertinent part:

A. Except as otherwise provided in this Subsection, no action,

whether ex contractu, ex delicto, or otherwise, including but not

limited to an action for failure to warn, to recover on a contract, or

to recover damages, or otherwise arising out of an engagement of

planning, construction, design, or building immovable or movable

property which may include, without limitation, consultation,

planning, designs, drawings, specification, investigation,

evaluation, measuring, or administration related to any building,

construction, demolition, or work, shall be brought against any

person performing or furnishing land surveying services, as such

term is defined in R.S. 37:682, including but not limited to those

services preparatory to construction, or against any person

performing or furnishing the design, planning, supervision,

inspection, or observation of construction or the construction of

immovables, or improvement to immovable property, including but

not limited to a residential building contractor as defined in R.S.

37:2150.1:

(1)(a) More than five years after the date of registry in the

mortgage office of acceptance of the work by owner.

***

B. (1) The causes which are perempted within the time described

above include any action:

19-CA-543 5

(a) For any deficiency in the performing or furnishing of land

surveying services, as such term is defined in R.S. 37:682,

including but not limited to those preparatory to construction

or in the design, planning, inspection, or observation of

construction, or in the construction of any improvement to

immovable property, including but not limited to any

services provided by a residential building contractor as

defined in R.S. 37:2150.1(9).

(b) For damage to property, movable or immovable, arising out

of any such deficiency.

***

(3) Except as otherwise provided in Subsection A of this Section,

this peremptive period shall extend to every demand, whether

brought by direct action or for contribution or indemnity or by

third-party practice, and whether brought by the owner or by

any other person.

***

(Emphasis added.)

In its extensive and detailed written reasons for judgment, the trial court

stated:

… [Centria] argues in its motion that [Horne’s] third-party

demand against Centria was untimely, pursuant to La. R.S. 9:2772,

which provides a five-year peremptive period for cases arising out of

construction contracts. The parties do not dispute that [Horne] did not

file its third-party demand until after the expiration of the five-year

peremptive period. The only issue for the Court to decide is whether

the five-year peremptive period applies in this case. This hinges on

whether the contract is a construction contract or a sales contract.

***

In support of its motion, Centria relies heavily on the testimony

of Robert Rutherford, Centria’s Regional Distribution Manager.

[MAPP] lodged an objection to Mr. Rutherford’s testimony on the

grounds that it was not based on personal knowledge and was

unqualified opinion testimony. This Court finds that the objection has

merit in regards to the unqualified opinion testimony and disregards

any opinion testimony made by Mr. Rutherford regarding legal

conclusions drawn. However, a large portion of his testimony was

based on his personal knowledge of this project.

Rutherford testified that Centria uses a team of engineers and

drafters to develop designs that suit the needs of each individual

project. The panels used on the Jefferson Parish Sheriff’s Office

Forensic Crime Laboratory were specifically designed and

manufactured for this building. The drawings created for this building

cannot be used on any other project, nor can the panels manufactured

19-CA-543 6

for this building be used on any other project. Centria’s Ex. 7, pp. 16-

17. Further, the materials were not manufactured in advance of this

project. Id. at p. 17.

Rutherford’s testimony demonstrated that significant custom

design went into the panels. Engineering services were rendered to

determine span and loading structural requirements of the project. Id.

at p. 24. Engineering calculations that determine the support spans

and the size and type of tube steels that will be required to hold the

load are unique to each project. Id. at pp. 25-27. Design and drafting

services were provided to determine the fit of the panels. Id. at p. 35.

The dimensions, including the length, width, and thickness of the

panels, are unique to this particular building. Id. at pp. 36-37. Both

the engineering calculations and panel dimensions are determined by

Centria’s team, not by the architect or building designers. Id. at pp.

38, 40, 164.

The Court notes that Centria published an extensive product

catalog showcasing numerous “standard” options for many aspects of

their products, which creates an impression that their products are not

customized. However, Rutherford explained that these catalogs are

marketing tools, aimed at individuals who are not panel experts, to

explain how the system works and what features and design options

are available. Centria’s Ex. 8, p. 34. The Court also notes that a

number of parts used to make up the panels were outsourced from

third parties. However, the Court finds the extent to which Centria

furnished the custom design, engineering, and planning for the panels

outweighs these other factors and renders this a contract to build.

For these reasons, the Court finds that the primary obligation in

the contract was an obligation “to do,” rather than an obligation “to

give.” As such, La. R.S. 9:2772 applies, rendering the filing of the

third party demand untimely. For these reasons, Centria’s exception

of peremption is granted, dismissing it from this suit with prejudice.

It is undisputed that Horne filed its third-party demand for indemnity against

Centria more than five years after the Certificate of Substantial Completion of the

subject project was filed in the mortgage records of Jefferson Parish by the

District.

La. R.S. 9:2772 applies only to contracts to build, and not contracts of sale.

DeWoody v. Citgo Petroleum Corp., 604 So.2d 92, 99 (La. App. 3rd Cir. 1992);

Poree v. Elite Elevator Services, Inc., 94-2575 (La. App. 4 Cir. 11/16/95), 665

So.2d 133, 135.

When the “words of a contract are clear, unambiguous, and lead to no absurd

consequences, we may not look beyond the contract language to determine the true

19-CA-543 7

intent of the parties.” ETI, Inc. v. Buck Steel, Inc., 16-0602 (La. App. 4 Cir.

2/1/17), 211 So.3d 439, 445, writ denied, 17-0396 (La. 4/13/17), 218 So.3d 626.

In this case, in its January 6, 2009 Quotation to Horne for the subject project

(which was later accepted and confirmed through a Purchase Order from Horne to

Centria dated February 26, 2009 and an Invoice from Centria to Horne dated April

16, 2010), Centria proposed “to furnish the material, product application drawings,

and delivery for the material requirements for the above project as specified in the

Contract Documents4 for a lump sum price of: $1,392,400.00 … .”5 Among other

terms and conditions, the Quotation called for Centria to provide the following

items for the District’s laboratory building (as per detailed specifications contained

in the nine-page Quotation):

 Formawall Panels, consisting of approximately 31,320 square feet of

“Formawall Dimension Series horizontal insulated metal wall panels;”

 Formavue Windows, consisting of approximately 2,710 square feet of

“CENTRIA’s fixed and thermally broken FV-400 HRS Thru-Tube

Window System;”

 Profiled Siding @ Fence, consisting of approximately 1,830 square feet

of “20 gage un-insulated BR5-36 horizontal metal siding;”

 Integrated C/S Sunshades, consisting of “Construction Specialties Model

DS100-3 Series Sunshade System;”

 Louvers, consisting of approximately 230 square feet of “Construction

Specialties Aluminum Louvers, Model DC-6174;” and

 Support Steel Framing System, consisting of “Vertical structural tubes

(6” x 2”) spaced a maximum of 6’-0” on center at the main field areas

4

The Contract Documents were identified in the Quotation as follows:

This proposal is based upon the following:

A. Drawings: See attached drawing list.

B. Specification Section: 07410 “Exterior Insulated Wall Systems” and 07620 “sheet

Metal Flashing & Trim” – no dates.

C. Addenda: Addendum #1 dated 12/2/08, Addendum #2 dated 12/5/08, Addendum #3

dated 12/10/08, Addendum #4 dated 12/19/08, Addendum #5 dated 12/30/08, and

Addendum #6 dated 1/5/09.

5

The Quotation did not include any prices per item, but rather only included a total price of all of

the items combined ($1,392,400.00, plus $25,000.00 added “to firm materials shipment to December 31,

2009”). The Invoice, which totaled $1,441,289.00, included total prices per individual item (including

“Engineering,” “Embeds,” “Extra Work,” and “Replacement DS Panels” as additional items), but did not

specifically break down the costs of labor and materials, respectively.

19-CA-543 8

and a maximum of 5’-0” on center at the corner areas to anchor the

Horizontal Formawall Panel/Formavue Window System.”

In his testimony, Mr. Rutherford stated that Centria’s contract on the

laboratory building at issue was on a lump sum basis, rather than on a unit price

basis. On lump sum contracts, the owner’s professional design team (architects

and engineers for the project) provide the plans and specifications that Centria

reviews, assesses, and applies its products to that design to determine whether its

products will work. Centria then does specific custom drawings based on the

architect and engineer plans to not only seek their approval of the layout of the

drawings and that Centria is meeting their requirements, but also to generate the

bill of materials that eventually goes into Centria’s machinery that creates the

product.

Mr. Rutherford stated that on lump sum contracts, the drawings from one

project cannot be used on another project, and likewise, the materials that are

produced for a lump sum project cannot be used on another project. As part of the

process, Centria also produces placement or installation drawings (“detailed to,

like, an eighth of an inch, so it has to be exact”) that cannot be used on another

project.6 Centria then manufactures the materials pursuant to the aforementioned

drawings. The manufacturing is specific to each project on a lump sum contract.

Centria does not manufacture the materials in advance in a lump sum project. Mr.

Rutherford specifically confirmed that Centria manufactured customized products

for this particular project.

Mr. Rutherford also confirmed that lump sum contracts include engineering

services, and that a “great deal of engineering” went into this particular project,

including the span and loading structural requirements of the project.7 Centria did

6

More than 100 pages of Centria’s detailed drawings for this particular project were introduced

into evidence at the hearing on the exception.

7

The Invoice from Centria to Horne introduced into evidence indicates that Centria billed Horne

a total of $113,000.00 for “Engineering.”

19-CA-543 9

engineering calculations that were custom for this project by determining the

support spans, which are always unique between each building. Mr. Rutherford

explained “[t]hat’s the heavy engineering on the front [end] to make sure every

part and piece is going to work, meet code, not fall off the building, keep

everybody safe and do its job.” The engineering work at issue was unique to this

particular project.

Mr. Rutherford also stated that the tube steel, insulated panels, and windows

were designed and manufactured specifically for this particular project. All

drawings, which were created by Centria’s drafting department, were unique to this

particular project. Also, all measurements were unique to this particular project.

None of these assertions made by Mr. Rutherford in his testimony were

disputed by Horne.

As this Court stated in Alonzo v. Chifici, 526 So.2d 237, 241 (La. App. 5th

Cir. 1988), writ denied, 527 So.2d 307 (La. 6/2/88) (citing Acadiana Health Club,

Inc. v. Hebert, 469 So.2d 1186, 1189 (La. App. 3rd Cir. 1985)):

“There are three major factors in determining whether a

contract is a contract of sale or a contract to build or to work by the

job. First, in a contract to build, the “purchaser” has some control

over the specifications of the object. Second, the negotiations in a

contract to build take place before the object is constructed. Lastly,

and most importantly, a building contract contemplates not only that

the builder will furnish the materials, but that he will also furnish his

skill and labor in order to build the desired object.” (Internal citations

omitted.)8

Considering the factors set forth in Alonzo, and interpreting and construing

the language contained in La. R.S. 9:2772 and in the above-noted contract

documents between Horne and Centria, and applying the undisputed facts present

in this case, upon de novo review, for the following reasons, we find no error in the

8

The Alonzo case did not concern the applicability of La. R.S. 9:2772, but rather focused, for

other reasons, on whether the contract between the parties was one “to build” or one of sale on an open

account (a contract to give). However, its analysis of the type of contract involved therein is relevant and

pertinent to the issues in this case.

19-CA-543 10

trial court’s legal conclusion that the contract between Horne and Centria was a

construction contract, i.e., a contract “to build,” rather than a contract “of sale.”

First, the ultimate “purchaser” (here, the District, through its architect), rather than

Centria, maintained overall control over the general specifications and construction

of the project. Second, the negotiations for the subject contract between Horne and

Centria took place well before the component parts for the subject building called

for in the contract were designed, built, and delivered by Centria. Lastly and

undoubtedly, the contract contemplated not only that Centria would furnish the

component parts for the subject building, but would also furnish its skill and labor

in order to manufacture and build the component parts to the detailed

specifications developed by Centria. Alonzo, supra.9

On appeal, Horne also argues that the trial court failed to view the facts in a

light most favorable to them, as required by law. We disagree. In its arguments,

Horne focuses extensively on the fact that the contract did not provide for Centria

to test or install the subject systems at the construction site, and that such

installation was performed by a third-party contractor. We find, however, that

Horne takes a much too narrow view of the main object of the contract: for Centria

to design, build, and deliver the component parts for the subject building called for

in the contract. As confirmed by the undisputed testimony of Mr. Rutherford, the

contract, despite not including a provision for Centria to perform the installation,

was no mere sale of stock building materials to be incorporated into a building by a

third party. Rather, the evidence clearly shows that the main object of the contract

was for Centria to design, build, and deliver the wall panel system, the window

9

Alonzo also briefly mentions the “value test” for determining whether a given contract is a

contract of sale or a construction contract. Alonzo, 526 So.2d at 241. Under the “value test,” the court

determines whether the labor expended in constructing the item, or the materials incorporated therein,

constitute the “principal value of the contract.” Id. Although Horne argues in brief that the “value test”

should be used herein, upon review, we find that, in light of the fact that the subject contract is on a lump

sum basis rather than on a unit price basis, the record lacks a sufficient specific breakdown of Centria’s

cost of labor and materials, respectively, in fulfilling the subject contract, thus preventing us from

applying the “value test” herein.

19-CA-543 11

system, and the structural support steel framing system that composed much of the

building’s structure, to the particular plans and detailed specifications developed

by Centria for this particular building.

The fact that Centria did not install the items it custom manufactured for this

project does not render this contract merely one “of sale.” Horne likens Centria’s

role in this case to “simply providing minimal design services,” such as in ETI, Inc.

v. Buck Steel, Inc., supra. ETI concerned interpretation of a contract between the

parties, which result would determine whether the plaintiff was entitled to certain

types of contractual damages. Id., 211 So.3d at 443. It did not concern the issue of

La. R.S. 9:2772’s peremption defense to the suit. Defendant Buck Steel was found

to be a vendor, not a contractor, based upon the interpretation of its contested

contract, which required Buck Steel to furnish a set of “shop drawings” and steel

parts which a third party would assemble into a building. Relying on Alonzo v.

Chifici, cited above, the court held that the contract between ETI and Buck Steel

was not a construction contract because it failed to contain any requirements that

the alleged builder, Buck Steel, would furnish skills and labor to actually build the

product. Id. at 445. The case further fails to describe the nature of the steel parts

Buck Steel was to supply. As previously found, the product that Centria contracted

to provide to Horne, the custom-designed wall, window, and support systems for

the laboratory building, including the engineered drawings associated therewith,

was considerably more specific than the “steel parts” and “shop drawings”

germane in ETI.

Horne also argues that the materials and processes used by Centria to make

these particular systems were “standard” ones used by Centria in every order it

receives. However, it is the actual design, construction, and providing of the

systems that is material to the contract, not the nature and substance of the raw

materials used in the construction thereof. This assertion is simply an attempt by

19-CA-543 12

Horne to downplay the fact that the finished systems manufactured by Centria for

the contract were not “stock” items, but rather were ordered by Horne to be

manufactured to the particular detailed specifications developed by Centria.

Horne also argues that La. R.S. 9:2772 was enacted only to protect

architects, contractors, and surveyors, not suppliers and manufacturers such as

Centria, citing Burmaster v. Gravity Drainage District No. 2 of St. Charles Parish,

366 So.2d 1381 (La. 1978). However, Burmaster, wherein the Supreme Court

considered a constitutional challenge to La. R.S. 9:2772 on the basis that it was a

“special” law creating a special privilege or immunity for architects and

contractors, drew a distinction between the former group on one hand, and owners,

lessors, or tenants on the other hand. In finding the law constitutional, the

Supreme Court found that there was “a valid distinction between persons

performing or furnishing the design, planning, supervision, inspection or

observation of construction or the construction of an improvement to immovable

property and a person in possession or control, as owner, lessor, tenant or

otherwise, of such improvement at the time of the incident giving rise to the cause

of action.” Id. at 1385. The Burmaster court found that it was reasonable that

those with access to and control of improvements to immovable property (owners,

lessors, or tenants) should not be accorded the protection of the peremptive period

established by La. R.S. 9:2772. Id. at 1385-86. Considering Burmaster, Centria is

clearly not an owner, lessor, tenant, or “otherwise” someone who maintained

control over their product after its incorporation into the immovable. Thus,

Burmaster does not stand for the position that an entity such as Centria may not

invoke the peremption found in the statute.

Moreover, it is significant that the statute in question does not use specific

characterizations such as “architect” or “contractor.” By its own terms, the statute

states that “no action … shall be brought against any person performing … the

19-CA-543 13

construction of immovables, or improvement to immovable property, … .”

(Emphasis added.) Clearly, because it designed and manufactured custom

components incorporated into an immovable, Centria is the type of entity

contemplated by La. R.S. 9:2772. This was also the conclusion of the court in the

similar case of Poree v. Elite Elevator Services, Inc., 98-0032 (La. App. 4 Cir.

4/8/98), 711 So.2d 816. In Poree, Dover Elevator Services, Inc. (“DES”) was the

designer of an elevator which was found to be an improvement and a component

part of a building. A third-party subcontractor installed and constructed the

elevator that became a part of the immovable property, in accordance with the

plans and specifications prepared by DES. Id. at 818. The court noted that

elevators are not a prepackaged, stock product, but are a construction involving

multiple components that are assembled into and made part of the building in

which they are installed. In Poree, the various parts of the elevator were shipped

to the installing contractor to be constructed into the building in accordance with

the design prepared by DES. Id. at 819. Significantly, DES was not involved with

the construction, installation, or inspection of the elevator, and provided only its

design and engineering. Nevertheless, the court found that DES fell within the

ambit of La. R.S. 9:2772’s prescriptive period and affirmed the trial court’s

judgment granting DES’s exception and motion for summary judgment. Id.

In sum, upon de novo review, for the foregoing reasons, based on the

undisputed facts presented and the applicable law, we find no error in the trial

court’s legal conclusion that the contract between Horne and Centria was a

construction contract, i.e., a contract “to build,” rather than a contract “of sale,”

and thus, the five-year peremptive period found in La. R.S. 9:2772 is applicable

thereto. Accordingly, the trial court did not err in granting Centria’s peremptory

exception of peremption.

19-CA-543 14

CONCLUSION

For the foregoing reasons, we affirm the trial court’s judgment in favor of

Centria Services Group, LLC, and against G.M. Horne Commercial and Industrial,

LLC, dismissing Horne’s third-party demand for indemnity against Centria as

perempted under La. R.S. 9:2772 with prejudice.

AFFIRMED

19-CA-543 15

SUSAN M. CHEHARDY CURTIS B. PURSELL

CHIEF JUDGE CLERK OF COURT

MARY E. LEGNON

FREDERICKA H. WICKER

CHIEF DEPUTY CLERK

JUDE G. GRAVOIS

MARC E. JOHNSON

ROBERT A. CHAISSON SUSAN BUCHHOLZ

STEPHEN J. WINDHORST

FIRST DEPUTY CLERK

HANS J. LILJEBERG

JOHN J. MOLAISON, JR. FIFTH CIRCUIT

MELISSA C. LEDET

JUDGES 101 DERBIGNY STREET (70053)

DIRECTOR OF CENTRAL STAFF

POST OFFICE BOX 489

GRETNA, LOUISIANA 70054 (504) 376-1400

(504) 376-1498 FAX

www.fifthcircuit.org

NOTICE OF JUDGMENT AND CERTIFICATE OF DELIVERY

I CERTIFY THAT A COPY OF THE OPINION IN THE BELOW-NUMBERED MATTER HAS BEEN DELIVERED

IN ACCORDANCE WITH UNIFORM RULES - COURT OF APPEAL, RULE 2-16.4 AND 2-16.5 THIS DAY

MAY 29, 2020 TO THE TRIAL JUDGE, CLERK OF COURT, COUNSEL OF RECORD AND ALL PARTIES NOT

REPRESENTED BY COUNSEL, AS LISTED BELOW:

19-CA-543

E-NOTIFIED

24TH JUDICIAL DISTRICT COURT (CLERK)

HONORABLE FRANK A. BRINDISI (DISTRICT JUDGE)

CHRISTOPHER K. TANKERSLEY (APPELLEE) DENNIS J. PHAYER (APPELLEE) RENE S. PAYSSE, JR. (APPELLANT)

ROBERT I. SIEGEL (APPELLEE) TIMOTHY R. MCGIBBONEY (APPELLEE) MICHAEL M. MEUNIER (APPELLEE)

ELLIOT W. SCHARFENBERG (APPELLEE) DAVID J. KREBS (APPELLEE)

MAILED

CHRISTOPHER R. TESKE (APPELLEE) JOHN G. YADAMEC (APPELLEE) ELTON F. DUNCAN, III (APPELLEE)

ATTORNEY AT LAW DANIEL M. REDMANN (APPELLEE) MICHAEL T. WAWRZYCKI (APPELLEE)

1100 POYDRAS STREET ATTORNEY AT LAW ATTORNEY AT LAW

SUITE 1800 3838 N. CAUSEWAY BOULEVARD 400 POYDRAS STREET

NEW ORLEANS, LA 70163 SUITE 2900 SUITE 1200

METAIRIE, LA 70002 NEW ORLEANS, LA 70130

BRETT M. BOLLINGER (APPELLEE)

L. PETER ENGLANDE (APPELLEE) DARREN P. TYUS (APPELLANT) MATTHEW K. BROWN (APPELLEE)

ATTORNEY AT LAW ATTORNEY AT LAW ATTORNEY AT LAW

406 NORTH FLORIDA STREET 701 POYDRAS STREET 909 POYDRAS STREET

SUITE 2 SUITE 4700 SUITE 2600

COVINGTON, LA 70433 NEW ORLEANS, LA 70139 NEW ORLEANS, LA 70112

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.