Opinion

Twigg v. Admiral Ins. Co.

  • 324 Or. App. 259
  • 525 P.3d 478
Court
Court of Appeals of Oregon
Filed
Feb 15, 2023
Status
Published
On the bench
Shorr
Cited by
4 cases
Authority
More cited than 55.3%

The opinion

259

Argued and submitted April 19, 2022, affirmed February 15, petition for review

allowed July 20, 2023 (371 Or 308)

See later issue Oregon Reports

Weston TWIGG,

an individual, and

Carrie Twigg, an individual,

Plaintiffs-Appellants,

v.

ADMIRAL INSURANCE COMPANY,

a Delaware company,

Defendant-Respondent.

ADMIRAL INSURANCE COMPANY,

Third-Party Plaintiff,

v.

RAINIER PACIFIC DEVELOPMENT LLC,

an Oregon limited liability company,

Third-Party Defendant.

Multnomah County Circuit Court

19CV36547; A175084

525 P3d 478

This appeal concerns whether an insurance company, defendant Admiral

Insurance Company (Admiral), had a duty to indemnify its insured, Rainier

Pacific Development LLC (Rainier Pacific), and pay a portion of an arbitra-

tion award that plaintiffs Weston and Carrie Twigg (the Twiggs) had obtained

against Rainier Pacific on a breach of contract claim. After the Twiggs obtained

the arbitration award, they sued Admiral in court for breaching its insurance

policy with Rainier Pacific and failing to pay a portion of Rainier Pacific’s liabil-

ity to the Twiggs. That policy provided coverage for “property damage” caused by

an “occurrence” or “accident.” Following cross-motions for summary judgment by

Admiral and the Twiggs, the trial court concluded that the applicable insurance

policy did not provide coverage for Rainier Pacific’s liability to the Twiggs and

granted Admiral’s motion and denied the Twiggs’ cross-motion. The Twiggs now

appeal. Held: The Court of Appeals concluded that the trial court did not err in

granting Admiral’s motion and denying the Twiggs’ motion. An insurer’s duty

to indemnify for an insured’s liability in a prior legal proceeding is based on the

nature of the insured’s liability in the underlying legal action. Here, the Twiggs’

arbitration claim was a claim for breach of contract, and they never contended

that Rainier Pacific’s liability arose from a breach of a separate duty of care.

Thus, the liability here arose solely from breach of a contractual duty, which is

not liability arising from an accident.

Affirmed.

260 Twigg v. Admiral Ins. Co.

Stephen K. Bushong, Judge.

Emily Sarah Miller argued the cause and filed the briefs

for appellants. Also on the briefs was Miller Insurance Law

LLC.

Jacqueline Tokiko Mitchson argued the cause for respon-

dent. On the brief were R. Daniel Lindahl, John A. Bennett,

Richard L. Williams, and Bullivant Houser Bailey PC.

Before Shorr, Presiding Judge, and Mooney, Judge, and

Pagán, Judge.

SHORR, P. J.

Affirmed.

Cite as 324 Or App 259 (2023) 261

SHORR, P. J.

This appeal concerns whether an insurance com-

pany, defendant Admiral Insurance Company (Admiral), had

a duty to indemnify its insured, Rainier Pacific Development

LLC (Rainier Pacific), and pay a portion of an arbitration

award that plaintiffs Weston and Carrie Twigg (the Twiggs)

had obtained against Rainier Pacific on a breach of contract

claim. After the Twiggs obtained the arbitration award,

they sued Admiral in court for breaching its insurance

policy with Rainier Pacific and failing to pay a portion of

Rainier Pacific’s liability to the Twiggs under the arbitra-

tion award. Following cross-motions for summary judgment

by Admiral and the Twiggs, the trial court concluded that

the applicable insurance policy did not provide coverage

for Rainier Pacific’s liability to the Twiggs. The court con-

cluded that Admiral’s insurance policy with Rainier Pacific

applied to property damage caused by an “occurrence,”

meaning an “accident” caused by Rainier Pacific, but that

Rainier Pacific’s liability to the Twiggs in the arbitration

proceeding arose instead from its breach of an agreement

with the Twiggs. The court, therefore, granted Admiral’s

motion for summary judgment and dismissed the Twiggs’

claim against Admiral for breaching the insurance policy

and failing to provide coverage.

The Twiggs now appeal from the general judgment

of dismissal that dismissed their claim against Admiral

for breach of an insurance policy agreement. The Twiggs

assign error to the grant of Admiral’s motion for summary

judgment and the denial of their cross motion for summary

judgment.1 For the reasons explained below, we conclude

that the trial court did not err in granting Admiral’s motion

and denying the Twiggs’ motion. We therefore affirm the

trial court’s judgment dismissing the Twiggs’ breach of con-

tract claim.

1

There is a general rule that may limit our review of an order denying a

motion for summary judgment. We do not repeat that rule or its exceptions here.

We merely note that, as is the case here, “[i]n an appeal from a judgment that

results from cross-motions for summary judgment, if both the granting of one

motion and the denial of the other are assigned as error, then both are subject to

review.” Eden Gate, Inc. v. D&L Excavating & Trucking, Inc., 178 Or App 610, 622,

37 P3d 233 (2002).

262 Twigg v. Admiral Ins. Co.

I. FACTUAL AND PROCEDURAL BACKGROUND

A. The Factual Background from the Summary Judgment

Record

“On review of cross-motions for summary judgment,

we view the record for each motion in the light most favor-

able to the party opposing it to determine whether there is

a genuine issue of material fact and, if not, whether either

party is entitled to judgment as a matter of law.” O’Kain v.

Landress, 299 Or App 417, 419, 450 P3d 508 (2019). “A mate-

rial fact is one that, under applicable law, might affect the

outcome of a case.” Zygar v. Johnson, 169 Or App 638, 646,

10 P3d 326 (2000), rev den, 331 Or 584 (2001). We state the

facts consistently with that standard.

The summary judgment record in support of both

Admiral’s and the Twiggs’ motions primarily consisted of

two items: (1) key portions of the record from the arbitration

dispute between the Twiggs and their construction contrac-

tor Rainier Pacific and (2) the applicable insurance policy

between Admiral and its insured Rainier Pacific. We begin

with the relevant arbitration proceeding.

1. The arbitration proceeding

We summarize the key allegations and facts from

the arbitration proceeding between the Twiggs and Rainier

Pacific. The genesis of the dispute occurred in February 2011

when the Twiggs hired Rainier Pacific to construct a new

home on a buildable lot that they had purchased. The con-

struction process was not completed within the agreed-upon

time. Both during the construction process and after they

moved into their home, the Twiggs alerted Rainier Pacific

to a number of construction problems and deviations from

the construction plans. Among the many issues they raised,

the Twiggs complained that the garage floor was sloped and

cracked. The Twiggs spent considerable time negotiating

with Rainier Pacific to complete or redo several aspects of

the construction. Ultimately unsatisfied due to the lack of

progress, the Twiggs hired an attorney to pursue a claim

against Rainier Pacific.

The Twiggs first filed an arbitration claim against

Rainier Pacific in June 2015 (the first arbitration). That first

Cite as 324 Or App 259 (2023) 263

arbitration predated the arbitration proceeding that under-

lies the insurance coverage claim at issue here. In the first

arbitration, the Twiggs alleged that Rainier Pacific had not

constructed the home in accordance with the approved plans

and specifications. Among other things, the Twiggs alleged

that there was “[i]improper reverse sloping of the garage floor

over [the] living space, which has resulted in standing water

and leaks to the interior of the home.” The first arbitration

claim did not proceed to a hearing but rather was settled

in September 2017 by an agreement between the Twiggs

and Rainier Pacific known as the “Repair Agreement.” That

agreement is central to this insurance coverage dispute.

The Repair Agreement required Rainier Pacific to

make a number of repairs, including correcting the slope and

drainage issues of the garage floor. The Repair Agreement

required that repairs be completed by mid-December 2017.

It also provided for a number of stipulated remedies in the

event of noncompliance with the agreement. The agreement

provided that disputes would be arbitrated before a desig-

nated arbitrator.

In May 2018, the Twiggs, having concluded that

the repair work was still not completed, filed the arbitration

claim against Rainier Pacific that underlies the insurance

coverage dispute before us. The arbitration claim, as is typ-

ical of the more informal arbitration process, does not set

forth numbered allegations or labelled claims. The claim is

set out in a letter to the arbitrator, which, as a whole, alleges

that Rainier Pacific failed to perform its obligations under

the Repair Agreement with respect to a number of items in

the home, including the garage floor. The letter commences

with the contention that the dispute “follows breach of a

repair-based Settlement Agreement,” which agreement was

attached as the first exhibit. Among other allegations, the

Twiggs alleged that, although Rainier Pacific had attempted

to correct the slope in the garage by installing a “concrete

overlay,” the slope had not been corrected. They further

alleged that, “[m]oreover, [Rainier Pacific] failed to carry

the slab’s control joints up through the lightweight concrete

pour, which is required by the manufacturer[,] [ARDEX].”

They contended that, as a result, the sloped garage floor

still created water issues for the house. The Twiggs sought

264 Twigg v. Admiral Ins. Co.

remedies under the Repair Agreement, including the cost

for another contractor to complete the repairs, liquidated

damages, and attorney fees. Rainier Pacific understood the

claim to be based on breach of the settlement agreement;

in its answer, it noted that it was answering the Twiggs’

allegations regarding Rainier Pacific’s breach of the Repair

Agreement.

In the arbitration, the Twiggs presented an expert

report that criticized Rainier Pacific’s installation of the

ARDEX concrete flooring product that had been intended

to level the garage floor. The expert report noted that, con-

trary to the manufacturer’s specification that required all

construction joints to be carried through the floor, “[n]one

of the construction joints have been carried through.” The

Twiggs submitted an exhibit with photos of cracking and

other issues in the garage floor. They also raised issues as to

several other defects in their home that Rainier Pacific had

failed to repair.

In October 2018, the arbitrator issued a decision.

The arbitrator first noted that the Twiggs “asserted a claim

for breach of a settlement agreement.” The arbitrator iden-

tified the Repair Agreement as “the operative contract for

this matter” and noted that the agreement had resolved

the Twiggs’ claims for defective construction that had been

alleged in the first arbitration. The arbitrator concluded

that, with the exception of the garage floor, Rainier Pacific

had “almost entirely failed to perform or complete any of”

the items in the Repair Agreement.

As to the garage floor, the arbitrator concluded that

the floor repairs had been completed, but that the installa-

tion was “defective” and contrary to the manufacturer’s spec-

ifications. The arbitrator later noted that there was evidence

that the cost to repair the garage floor was $150,000, which

“figure may serve as a starting point for the determination

of damages.” The arbitrator concluded that Rainier Pacific,

“through its consistent failure to diligently prosecute the

work, and through its defective efforts to repair the garage

slab, materially and substantially breached the [Repair]

Agreement.” The arbitrator then awarded $604,594.80,

which was based on evidence of an estimate for the total cost

Cite as 324 Or App 259 (2023) 265

of repairs for all of the items that Rainier Pacific had not

repaired, including the garage floor. The arbitrator finally

concluded that the Twiggs’ “relief is based upon common-law

principles of breach of contract.” In January 2019, the trial

court entered a judgment on the arbitration award against

Rainer Pacific for $604,594.80.

2. The relevant insurance policy

The Twiggs contend that Rainier Pacific tendered

the arbitration claim to that company’s insurer, Admiral,

but that Admiral denied coverage. The Twiggs initially

alleged that Admiral was responsible for providing cover-

age for a “large portion” of the $604,594.80 in damages that

Rainier Pacific had caused to the Twiggs’ property through

negligent repair work. When they moved for summary judg-

ment, however, the Twiggs contended that Admiral was

contractually obligated to cover $150,000, an amount they

maintained represented “accidental property damage to the

new garage floor.” In its answer, Admiral admitted that it

had received a tender of the claim from Rainier Pacific but

denied that it was obligated to cover the claim.

We turn to the relevant insurance policy that

Admiral issued to Rainier Pacific. The applicable “commer-

cial general liability coverage” policy was effective as of

August 9, 2017. The relevant “Coverage A” section of the pol-

icy covering bodily injury and property damage liability pro-

vides that it covers “ ‘property damage’ only if: (1) [t]he * * *

‘property damage’ is caused by an ‘occurrence’.” Property

damage is defined to include “[p]hysical injury to tangible

property.” Central to this dispute, an occurrence is defined

as “an accident, including continuous or repeated exposure

to substantially the same general harmful conditions.”

The Twiggs note that there is a separate “Coverage

B” section for “personal and advertising liability” coverage

that generally excludes liability “arising out of a breach of

contract.” That type of breach-of-contract exclusion does

not appear in the relevant Coverage A section. The Twiggs

further observe that the policy includes an endorsement

excluding residential construction activities, but that exclu-

sion “does not apply to repair or remodeling of single-family

266 Twigg v. Admiral Ins. Co.

dwellings which were or are certified for occupancy prior

to commencement of such repair or remodeling work per-

formed by you or on your behalf.”

Two other exclusions are relevant to this appeal.

First, the policy contains an endorsement excluding pre-

existing damages, which include “[a]ny damages arising

out of or related to * * * ‘property damage’ * * * which first

occurred prior to the inception date of this policy” and “[a]ny

damages arising out of or related to * * * ‘property damage’

* * * which are in the process of settlement, adjudgment or

‘suit’ as of the inception date of this policy.” Additionally,

Coverage A lists two exclusions at sections “j(5)” and “j(6)”

that provide that the insurance does not apply to

“j. Damage To Property

“ ‘Property damage’ to:

“* * * * *

“(5) That particular part of real property on which you

or any contractors or subcontractors working directly or

indirectly on your behalf are performing operations, if the

‘property damage’ arises out of those operations; or

“(6) That particular part of any property that must

be restored, repaired or replaced because ‘your work’ was

incorrectly performed on it.”2

B. The Parties’ Cross-Motions for Summary Judgment and

the Trial Court’s Ruling

As noted, the Twiggs contended in the trial court

that Admiral had a duty under the applicable insurance

policy to provide coverage for the damage to their garage

floor caused by Rainier Pacific’s negligent repair work. The

Twiggs alleged a breach of contract claim, contending that

Admiral had breached its duties under the applicable insur-

ance policy to provide coverage for its insured. Admiral

2

There are further definitions and limitations in the policy that are relevant

to the j(5) and j(6) exclusions. However, because neither the trial court nor we

ultimately reach any issues involving those exclusions, we do not set them forth

here. Like the trial court, we also do not reach whether Rainier Pacific’s liability

is excluded from coverage under the insurance policy’s j(5), j(6), or preexisting

damage exclusions, because we conclude that there is not coverage in the first

instance.

Cite as 324 Or App 259 (2023) 267

moved for summary judgment against that claim and raised

two issues. First, it contended that the policy provided cov-

erage only for property damage caused by an “occurrence,”

defined as an accident, and that Rainier Pacific’s liability

in the arbitration arose solely from a breach of the repair

agreement. Second, it contended that the arbitration award

resulted from the original construction work done by Rainier

Pacific in 2013, which was outside the relevant policy peri-

ods and excluded under the policy’s preexisting damage

exclusion.

The Twiggs cross-moved for summary judgment in

their favor on their breach of contract claim. They argued

that Rainier Pacific’s liability arose from its negligent repair

work on their home’s garage floor, including failing to carry

through the existing joints when pouring the new ARDEX

flooring product. They contended that the defective construc-

tion work qualified as an “occurrence” or accident under the

relevant insurance policy. They further argued that the lia-

bility arose from the repair work that occurred during the

policy period and not from the original construction work.

As a result, they argued that the damage was covered by

the policy and that the pre-existing damage exclusion did

not apply.

The trial court granted Admiral’s summary judg-

ment motion and denied the Twiggs’ cross-motion for sum-

mary judgment. The court concluded that Rainier Pacific’s

liability in the arbitration arose from its breach of contrac-

tual duties and not from a covered “occurrence” or accident.

Thus, the court concluded that the damage was not covered

under the policy.

The trial court largely relied on Oak Crest Const. Co.

v. Austin Mutual Ins. Co., 329 Or 620, 998 P2d 1254 (2000),

which we discuss below. The court provided its reasoning:

“[H]aving carefully studied the Oak Crest case, in

light of the arbitration award in this case finding that

Rainier Pacific * * * had breached its contract, the repair

contract, which was a settlement agreement of the origi-

nal construction defect claim; and that that contractual

breach was based on its * * * faulty workmanship in install-

ing the repair that it had agreed to install, in my view is

268 Twigg v. Admiral Ins. Co.

indistinguishable in any material way from the shoddy

workmanship at issue in the Oak Crest case.

“And I do not see that there is a general breach of a

duty of due care that would distinguish this case from Oak

Crest. And so I’m required to follow the Oregon Supreme

Court’s ruling.

“I’m bound by that ruling until the [Supreme Court]

decide[s] that that ruling maybe is not quite as nuanced as

they had intended as a matter of insurance coverage law.

But they haven’t said that yet. Maybe they’ll get an oppor-

tunity to say that it in this case.”

Having concluded that there was no coverage in the first

instance, the trial court did not reach alternative argu-

ments Admiral raised under the policy’s j(5), j(6), and pre-

existing damage exclusions. After issuing its ruling on the

summary judgment motions, the court entered a judgment

of dismissal.

II. LEGAL ANALYSIS

We begin our analysis with the applicable legal

standard. When parties cross-move for summary judgment,

each party “has the burden of demonstrating that there are

no material issues of fact and that the movant is entitled

to judgment as a matter of law.” Eden Gate, Inc. v. D&L

Excavating & Trucking, Inc., 178 Or App 610, 622, 37 P3d

233 (2002). “There is no genuine issue of material fact if,

‘based upon the record before the court viewed in a manner

most favorable to the adverse party, no objectively reason-

able juror could return a verdict for the adverse party on the

matter that is the subject of the motion for summary judg-

ment.’ ” Smith v. Central Point Pawn, LLC, 296 Or App 341,

342, 438 P3d 436 (2019) (quoting ORCP 47 C).

As the parties have framed the coverage issue in

their briefing, this appeal does not involve an issue of dis-

puted fact but concerns a legal issue: namely, whether the

applicable Admiral insurance policy provides coverage for

the legal liability incurred by Rainier Pacific in the under-

lying arbitration proceeding. We agree that, at least here,

that is a legal issue. See FountainCourt Homeowners v.

FountainCourt Develop., 360 Or 341, 357-58, 380 P3d 916

Cite as 324 Or App 259 (2023) 269

(2016) (stating that whether an insurer is obligated under

a policy to cover its insured’s liability arising from litiga-

tion generally presents “questions of law” that are deter-

mined “by reference to (a) the contract [or the policy] and

(b) the judgment and record in the underlying proceeding,”

although there may be fact issues relating to coverage exclu-

sions developed in the subsequent coverage litigation). The

insured—or here, the Twiggs, standing in for the insured

Rainier Pacific—bears the burden to prove coverage, and

the insurer, Admiral, bears the burden to prove exclu-

sions from coverage. Id. at 360. Under this policy, a covered

“occurrence” is a prerequisite to coverage and, therefore, the

Twiggs bore the burden in the trial court to prove a cov-

ered occurrence. See id. (noting “no ambiguity” that prov-

ing an occurrence under the relevant policy “relate[d] to

coverage”).

When interpreting insurance policies, Oregon

courts “determine the intention of the parties based on

the terms and conditions of the insurance policy.” Hoffman

Construction Co. v. Fred S. James & Co., 313 Or 464, 469,

836 P2d 703 (1992). We interpret the policy “from the per-

spective of an ordinary purchaser of insurance.” Bighorn

Logging Corp. v. Truck Ins. Exchange, 295 Or App 819, 828,

437 P3d 287, rev den, 365 Or 195 (2019) (internal quotation

marks omitted). For defined terms in the policy, we look

to the policy’s definitions. Id. at 829. Undefined terms are

interpreted according to their plain meaning. Id. If there is

more than one plausible interpretation of an undefined term,

“we examine the word or phrase in the context in which it

is used in the policy and the broader context of the policy

as a whole.” Id. If ambiguity or reasonable doubt remains

regarding the meaning of a policy word or phrase in the con-

text of the entire policy, that doubt is resolved against the

drafter, the insurance company, and in favor of the insured.

Id.

The Twiggs contend that Admiral’s insurance pol-

icy’s definition of “occurrence,” which is defined as “an acci-

dent,” can reasonably be understood by an insured to cover

damage caused by “mistakes” in work performed pursu-

ant to a repair contract. They contend that that holds true

270 Twigg v. Admiral Ins. Co.

“irrespective of whether the liability is stated in terms of

contract damages, negligence damages, both, or another

form of damages.”

As explained below, we disagree with that conten-

tion, in the context of this case, because the issue of cover-

age necessarily depends on the nature of the insured’s lia-

bility in the prior litigation, or here, arbitration. As noted

above, the policy provides that it covers “ ‘property damage’

only if” the “ ‘property damage’ is caused by an ‘occurrence.’ ”

Property damage is defined to include “physical injury to

tangible property,” and an occurrence is defined as “an acci-

dent, including continuous or repeated exposure to substan-

tially the same general harmful conditions.”

There is no doubt that a repair contractor’s negligent

work that accidentally caused damage to physical property

could give rise to an occurrence under the policy, namely

“an accident, including continuous or repeated exposure to

substantially the same general harmful conditions.” See,

e.g., FountainCourt Homeowners, 360 Or at 348, 361-65 (con-

cluding that a jury’s finding that an insured subcontractor

negligently damaged physical property gave rise to coverage

under a policy that required proof of an “occurrence,” which

was also defined as “an accident, including continuous or

repeated exposure to substantially the same general harm-

ful conditions”); cf. Kisle v. St. Paul Fire & Marine Ins., 262

Or 1, 6, 495 P2d 1198 (1972) (concluding that the term “acci-

dent” “has a tortious connotation” such that “[d]amage solely

caused by failure to perform a contract is not recoverable

in tort” (emphasis added)). But an insurer’s duty to indem-

nify for an insured’s liability in a prior legal proceeding is

based on the nature of the insured’s liability in the underly-

ing legal action. “In order for the duty to indemnify to arise,

the insured must be liable for harm or injury that is cov-

ered by the policy.” Ledford v. Gutoski, 319 Or 397, 405, 877

P2d 80 (1994). “[T]he facts proved at trial on which liability

is established may give rise to a duty to indemnify if the

insured’s conduct is covered.” Id. at 403. The duty to indem-

nify is independent of the duty to defend, which may arise

merely if the underlying complaint could “impose liability

for conduct covered by the policy” or the “complaint provides

any basis for which the insurer provides coverage.” Id. at

Cite as 324 Or App 259 (2023) 271

400 (emphasis in original). The duty to indemnify following

a legal determination of the insured’s liability is different.

As the Supreme Court has explained:

“What the insured is legally obligated to pay as damages

can be determined only by reference to the underlying

action, which determined the insured’s legal obligation to

pay damages. Thus, in the subsequent proceeding, [a party]

is not * * * entitled to second-guess or retry ‘the nature of

[the insured’s] liability.’ ”

FountainCourt Homeowners, 360 Or at 357 (emphasis in

original).

The court continued:

“[T]he subsequent proceeding requires the court to eval-

uate—as a matter of contract law—what, precisely, the

insured has become legally obligated to pay as damages

in the prior proceeding, in order to determine whether the

policy covers those damages. In other words, [a party] can-

not, in a subsequent proceeding, retry [the] insured’s lia-

bility, or alter the nature of the damages awarded in that

proceeding.”

Id. With that in mind, we turn to the nature of the insured

Rainier Pacific’s liability and damages that arose in the

prior legal proceeding.

As we noted at the outset, the Twiggs’ arbitration

claim was presented as a claim for breach of contract. It was

defended by Rainier Pacific as a breach of contract claim.

And, significantly, the arbitrator understood it to be a breach

of contract claim. It concluded that Rainier Pacific, “through

its consistent failure to diligently prosecute the work, and

through its defective efforts to repair the garage slab, mate-

rially and substantially breached the [Repair] Agreement.”

It is true that the Twiggs presented issues regarding

Rainier Pacific’s negligence in its original construction work

as context for the claim, and further presented allegations

regarding Rainier Pacific’s subsequent defective repair

work done pursuant to the Repair Agreement. However,

those allegations sought to prove the sole breach-of-contract

claim, and the arbitrator ultimately agreed that Rainier

Pacific breached its contractual duties under the Repair

272 Twigg v. Admiral Ins. Co.

Agreement. Indeed, the Twiggs acknowledge in their brief-

ing before us that they “had pled a single contract claim for

the purpose of invoking the Repair Contract’s ‘Stipulated

Remedies’ provision.”

Liability for damages arising from breach of a

contract is not covered under the insurance policy. As dis-

cussed, the insurance policy covers property damage caused

by an “occurrence,” which is defined as “an accident, includ-

ing continuous or repeated exposure to substantially the

same general harmful conditions.” The liability here arises

solely from breach of a contractual duty, which is not liabil-

ity arising from an accident. Of course, liability could arise

from both breach of a contractual duty and breach of an

independent duty of care not to tortiously damage property.

But, as the trial court concluded, the Supreme Court’s deci-

sion in Oak Crest Const. Co. guides the resolution of that

problem. In that case, the plaintiff was a contractor who

had agreed to provide a custom home, including cabinets

and other woodwork, to homeowners. 329 Or at 622-23. The

plaintiff had hired a subcontractor to paint the cabinets and

woodwork, but the paint had not cured properly. Id. at 624.

As a result, the plaintiff spent $10,000 stripping and refin-

ishing the cabinets and woodwork. Id. The plaintiff sued its

insurer, which had provided the plaintiff with a commercial

liability policy, seeking to require the insurer to cover the

$10,000 expense under the policy. Id. at 622-23. That policy,

like the one at issue here, provided that the insurer would

cover property damage caused by an occurrence, which

was nearly identically defined as “an accident and includes

repeated exposure to similar conditions.” Id. at 622. The

Supreme Court held that the plaintiff’s damages were not

covered under the policy, because they arose from the plain-

tiff’s contractual duty to the homeowners, and there was no

evidence in the record to support that they were caused by

an “accident” or the subcontractor’s breach of a duty of care.

Id. at 624, 628-29. “This court has indicated that there can

be no ‘accident,’ within the meaning of a commercial liabil-

ity policy, when the resulting damage is merely a breach of

contract.” Id. at 626. Considering the indistinguishable cir-

cumstances presented in this case, we agree with the trial

court that Admiral was entitled to summary judgment as a

Cite as 324 Or App 259 (2023) 273

matter of law because Rainier Pacific’s liability in the arbi-

tration was based solely on the breach of a contractual duty

and not the result of an accident.

Oak Crest Const. Co. clearly acknowledges that lia-

bility in some cases involving a contract may arise under

both contract and tort theories, which could give rise to cov-

erage under a policy covering property damage arising from

an accident. Id. at 627-28. For instance, there may be cover-

age where the insured’s liability arose from an independent

breach of the duty of care. Id. at 629; see also Abraham v.

T. Henry Construction, Inc., 350 Or 29, 40, 249 P3d 534 (2011)

(concluding that a party to a contract may bring a claim in

negligence for property damage if the claim is cognizable

in the absence of a contract and the contract’s terms do not

supplant the common law duty of care or otherwise limit the

right to such a claim). Here, however, although the Twiggs’

arbitration claim raised issues regarding Rainier Pacific’s

defective construction in making repairs under the Repair

Agreement, they never contended that Rainier Pacific’s lia-

bility arose from a breach of a separate duty of care. Rather,

the arbitration claim alleged that Rainier Pacific’s liability

arose solely from breach of its contractual duties.

Finally, the Twiggs contend that reliance on Oak

Crest Const. Co. is misplaced here because the interpretation

of this insurance policy depends on its particular text and

the common understanding of its terms to an ordinary pur-

chaser of insurance. See Botts v. Hartford Acc. & Indem. Co.,

284 Or 95, 101, 585 P2d 657 (1978) (stating that, in interpret-

ing insurance policies, the court is “guided by the principle

that it is the common understanding of the term which must

be used and not its technical meanings”). But our opinion is

based on consideration of the policy’s defined and undefined

terms, namely, that liability resulting from a contract claim

is not property damage caused by an “occurrence,” defined

in the policy as an “accident.” We have reviewed the policy,

and nothing in the text of the relevant coverage provisions

or those provisions in the context of the entire policy could

reasonably be understood to provide for coverage of Rainier

Pacific’s liability that arose solely from its breach of its con-

tractual duties under the Repair Agreement. As a result,

274 Twigg v. Admiral Ins. Co.

the trial court did not err in granting Admiral’s motion for

summary judgment and denying the Twiggs’ cross-motion

for summary judgment after concluding that the insurance

policy did not cover Rainier Pacific’s liability for contract

damages resulting from the arbitration claim.

Affirmed.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.