whether contractual provisions are ambiguous is a legal question
How later courts described this case
- whether contractual provisions are ambiguous is a legal question
Written by the judges who cited it.
The opinion
650
Argued and submitted January 6, 2021, affirmed February 16, 2022
BROWN CONTRACTING, INC.,
an Oregon corporation,
Plaintiff-Appellant,
v.
OREGON DEPARTMENT OF TRANSPORTATION,
Defendant-Respondent.
Marion County Circuit Court
18CV52643; A172658
504 P3d 1195
Mary Mertens James, Judge.
Jacob A. Zahniser argued the cause for appellant. Also
on the briefs were Ryan C. Hall and Miller Nash Graham &
Dunn LLP.
Robert M. Wilsey, Assistant Attorney General, argued
the cause for respondent. Also on the brief were Ellen F.
Rosenblum, Attorney General, and Benjamin Gutman,
Solicitor General.
Before Tookey, Presiding Judge, and Aoyagi, Judge, and
Armstrong, Senior Judge.
PER CURIAM
Affirmed.
Cite as 317 Or App 650 (2022) 651
PER CURIAM
Plaintiff Brown Contracting, Inc. (Brown) appeals
the supplemental judgment in which the trial court
granted summary judgment in favor of defendant Oregon
Department of Transportation (ODOT). ODOT hired Brown
to retrofit sidewalk ramps and corresponding sidewalks
and driveways. This dispute arises from Brown’s claim for
payment for some of that work under Bid Item #0240 of the
contract it had with ODOT. When ODOT denied the claim,
with the understanding that it had paid Brown for the work
under Bid Item #0290, Brown brought this breach of contract
action. ODOT moved for partial summary judgment, argu-
ing that there was no material dispute of fact that ODOT
had paid Brown under the terms of the contract. Brown
responded that the contract was ambiguous as to whether
it should be paid under Bid Item #0290 or Bid Item #0240.
The trial court sided with ODOT, and Brown reraises its
argument on appeal that the contract was ambiguous.
We have concluded that the trial court did not err
in granting summary judgment to ODOT. We have reached
that conclusion after having reviewed the summary judg-
ment record, drawing all reasonable inferences in Brown’s
favor, Whalen v. American Medical Response Northwest, 256
Or App 278, 280, 300 P3d 247 (2013); reviewing the issue
for legal error, Yogman v. Parrott, 325 Or 358, 937 P2d 1019
(1997) (whether contractual provisions are ambiguous is
a legal question); and applying our principles of contract
interpretation, Yogman, 325 Or 358; Batzer Construction,
Inc. v. Boyer, 204 Or App 309, 129 P3d 773, rev den, 341 Or
366 (2006). Once those standards are applied, there is no
genuine issue of material fact (ORCP 47 C) as to whether
Brown had been paid for the work for which it sought pay-
ment under Bid Item #0240, and ODOT was entitled to sum-
mary judgment.
Affirmed.