Opinion

Bravo v. RPH Hotels 51st St. Owner, LLC

  • 2024 NY Slip Op 32970(U)
Court
New York Supreme Court, New York County
Filed
Aug 23, 2024
Status
Unpublished
Author
David B. Cohen
Cited by
0 cases
Authority
More cited than 30.5%

The opinion

Bravo v RPH Hotels 51st St. Owner, LLC

2024 NY Slip Op 32970(U)

August 23, 2024

Supreme Court, New York County

Docket Number: Index No. 159445/2019

Judge: David B. Cohen

Cases posted with a "30000" identifier, i.e., 2013 NY Slip

Op 30001(U), are republished from various New York

State and local government sources, including the New

York State Unified Court System's eCourts Service.

This opinion is uncorrected and not selected for official

publication.

INDEX NO. 159445/2019

NYSCEF DOC. NO. 235 RECEIVED NYSCEF: 08/23/2024

SUPREME COURT OF THE STATE OF NEW YORK

NEW YORK COUNTY

PRESENT: HON. DAVID B. COHEN PART 58

Justice

---------------------------------------------------------------------------------X INDEX NO. 159445/2019

SEGUNDO BRAVO,

06/20/2023,

Plaintiff, 06/28/2023,

MOTION DATE 04/25/2024

-v-

MOTION SEQ. NO. 005 007 008

RPH HOTELS 51ST STREET OWNER, LLC, LHOTSE

CONTRACTING CORP., LHOTSE CORP., INTERSYSTEM

INSTALLATION CORP., DECISION + ORDER ON

MOTION

Defendants.

---------------------------------------------------------------------------------X

INTERSYSTEM INSTALLATION CORP. Third-Party

Index No. 595282/2020

Plaintiff,

-against-

GERALD FAST SYSTEM CORP.

Defendant.

--------------------------------------------------------------------------------X

LHOTSE CONTRACTING CORP., LHOTSE CORP. Second Third-Party

Index No. 595083/2021

Plaintiffs,

-against-

INTERSYSTEM S&S CORP., GERALD FAST SYSTEM CORP.

Defendants.

--------------------------------------------------------------------------------X

The following e-filed documents, listed by NYSCEF document number (Motion 005) 145, 146, 147, 148,

149, 150, 151, 152, 153, 154, 155, 156, 157, 158, 159, 160, 161, 162, 163, 164, 165, 191, 195, 199, 200,

201, 202, 203, 204, 205, 206, 207, 208, 209, 210

were read on this motion to/for JUDGMENT - SUMMARY .

The following e-filed documents, listed by NYSCEF document number (Motion 007) 166, 167, 168, 169,

170, 171, 172, 173, 174, 175, 176, 177, 178, 179, 180, 181, 192, 193

were read on this motion to/for JUDGMENT - SUMMARY .

159445/2019 BRAVO, SEGUNDO vs. RPH HOTELS 51ST STREET Page 1 of 12

Motion No. 005 007 008

1 of 12

[* 1]

INDEX NO. 159445/2019

NYSCEF DOC. NO. 235 RECEIVED NYSCEF: 08/23/2024

The following e-filed documents, listed by NYSCEF document number (Motion 008) 215, 216, 217, 218,

219, 220, 221, 222, 223, 224, 225, 226, 227, 228, 229, 230, 231, 232

were read on this motion to/for SUMMARY JUDGMENT(AFTER JOINDER .

This action arises from an accident which took place on December 11, 2018, in which

plaintiff was allegedly injured while at work on a sidewalk bridge. Plaintiff began this action on

September 27, 2019, alleging that defendant RPH Hotels 51st Street Owner, LLC, owner of the

building around which the sidewalk bridge was built, its contractor, Lhotse Contracting Corp.,

and subcontractor Intersystem Installation Corp., are liable for violations of Sections 200, 240,

and 241(6) of New York’s Labor Law. Motion sequence number 005, 007, and 008 are

consolidated herein for disposition.

In motion sequence 005, RPH moves for an order granting it summary judgment on its

contractual indemnity claim against Lhotse. Lhotse opposes.

In motion sequence 007, Lhotse moves for an order granting it summary judgment on its

second third-party complaint and awarding it contractual indemnity against Intersystem and a

default judgment against Gerald Fast System Corp.

In motion sequence 008, Intersystem moves for an order dismissing plaintiff’s complaint

and Lhotse’s third-party complaint against it. Lhotse opposes.

Background

RPH is and, at all relevant times, was the owner of the building located at 851 8th

Avenue in Manhattan, which it was developing as a Hampton Inn hotel (the Premises)

(complaint ¶1 [NYSCEF Doc No. 1] ¶¶9-10). On or before December 11, 2018, RPH hired

defendant Lhotse, doing business under the name Trident Contracting (Lhotse/Trident), to

perform roofing repair work at the Premises (RPH Statement of Material Facts ¶¶2-3 [NYSCEF

Doc No. 147]).

159445/2019 BRAVO, SEGUNDO vs. RPH HOTELS 51ST STREET Page 2 of 12

Motion No. 005 007 008

2 of 12

[* 2]

INDEX NO. 159445/2019

NYSCEF DOC. NO. 235 RECEIVED NYSCEF: 08/23/2024

Plaintiff alleges that, on or about December 11, 2018, while he was employed as a laborer

by Lhotse/Trident’s subcontractor, Intersystem, he was struck by a wooden plank while

dismantling a scaffold bridge surrounding the Premises, which knocked him to the ground and

caused him severe injuries (see complaint ¶¶17-25; Plaintiff deposition tr at 12:17-13:6, 16:21-

17:13, 18:7-11 [NYSCEF Doc No. 158]).

RPH’s corporate representative testified at a deposition that RPH contracted with

Lhotse/Trident to perform roof repair at the Premises and to hire any subcontractors it needed to

complete the job, specifically stating that they “hired Trident to run the project” (affirmation of

Matthew G. Corcoran, Esq. [Corcoran affirmation] [NYSCEF Doc No. 146] ¶11, citing Timothy

Dowd deposition tr [Dowd tr] [NYSCEF Doc No. 159] at 8, 10, 12 and 18). RPH denied that it

supervised any work performed in connection with the project (id. ¶12, citing Dowd tr at 11, 34).

At his deposition, Intersystem’s corporate representative stated that Intersystem hired

third-party defendant Gerald as its subcontractor to dismantle the sidewalk bridge and thus, at the

time of his accident, plaintiff was employed by Gerald (id. ¶17, citing Michael Badzio deposition

tr [Badzio tr] [NYSCEF Doc No. 161] at 10, 27 and 30-31).

The pertinent contracts provide as follows:

The main Contract (Prime Contract), written on an AIA standard form1 between RPH, as

“Owner,” and Lhotse/Trident, as “Contractor,” for “Roof Replacement” at the Premises,

provides that:

“§ 9.15.1 To the fullest extent permitted by law, the Contractor shall indemnify

and hold harmless Owner, Architect, Architect’s consultants, and the parties listed

in Exhibit F hereto and agents and employees of any of them from and against all

claims, damages, losses and expenses, including but not limited to attorneys’ fees,

1

“AIA” is an acronym for the American Institute of Architects (see https://www.aia.org).

It publishes form agreements and exhibits for use by architects, contractors, building owners, and

consultants (see https://aiacontracts.com).

159445/2019 BRAVO, SEGUNDO vs. RPH HOTELS 51ST STREET Page 3 of 12

Motion No. 005 007 008

3 of 12

[* 3]

INDEX NO. 159445/2019

NYSCEF DOC. NO. 235 RECEIVED NYSCEF: 08/23/2024

to the extent arising out of or resulting from (i) Contractor’s wrongful acts or

omissions in connection with the performance of the Work, (ii) breach of this

Agreement by Contractor, and (iii) negligence by Contractor or its

Subcontractors, regardless of whether or not such claim, damage, loss or expense

is caused in part by a party indemnified hereunder. Such obligation shall not be

construed to negate, abridge, or reduce other rights or obligations which would

otherwise exist as to a party or person described in this Section 9.15.1.

§ 9.15.2 In claims against any person or entity indemnified under this Section

9.15 by an employee of the Contractor, a Subcontractor, anyone directly or

indirectly employed by them or anyone for whose acts they may be liable, the

indemnification obligation under Section 9.15.1 shall not be limited by a

limitation on the amount or types of damages, compensation or benefits payable

by or for the Contractor or Subcontractor under workers’ compensation acts,

disability benefits acts or other employee benefit acts.”

(Corcoran affirmation ¶19, quoting Prime Contract [NYSCEF Doc No. 162] [emphasis added]).

Exhibit E to the Prime Contract required Lhotse/Trident to obtain various insurance

coverages, including a commercial general liability policy, written on a “primary and non-

contributory basis, notwithstanding any insurance maintained by [RPH]” and to extend coverage

to “Additional Insureds” under the “Commercial General Liability, Automobile, and Umbrella

policies” obtained under the Agreement (see Corcoran affirmation ¶22 and Prime Contract).

Exhibit F to the Prime Contract lists RPH as an indemnitee and additional insured, together with

“each of [its] parents, subsidiaries and affiliates” (id. ¶21 and Prime Contract).

The Subcontract at issue (Intersystem Subcontract) is also written on an AIA standard

form (see ex Q to Corcoran affirmation [NYSCEF Doc No. 164]), and it identifies RPH as the

“Owner,” Lhotse/Trident as the “Contractor,” and Intersystem S&S Corp. (S&S) as

Lhotse/Trident’s “Subcontractor” (id.).

Section 4.6 of the Intersystem Subcontract provides that Subcontractor must indemnify

Owner, Contractor, and certain others from “all claims, damages, losses and expenses” they

incur, including attorney’s fees, arising from Subcontractor’s Work under the Subcontract, “but

159445/2019 BRAVO, SEGUNDO vs. RPH HOTELS 51ST STREET Page 4 of 12

Motion No. 005 007 008

4 of 12

[* 4]

INDEX NO. 159445/2019

NYSCEF DOC. NO. 235 RECEIVED NYSCEF: 08/23/2024

only to the extent caused by negligent acts or omissions of the Subcontractor” and any sub-

subcontractors engaged to perform the Subcontractor’s Work (id. § 4.6.1).

Section 13 specifies the Subcontractor’s insurance procurement requirements. Exhibit A

to the Intersystem Subcontract contains additional indemnity and insurance procurement

requirements. Section 1(a) to this Exhibit, relating to indemnification, mirrors the provision in

the Intersystem Subcontract, obligating the Subcontractor to indemnify only to claims and losses

arising from Subcontractor’s Work, and only when caused by the Subcontractor’s negligent acts

or omissions (id.).

In Section 2 of Exhibit A, the Subcontractor agrees to maintain a variety of insurance

coverage, including commercial general liability, workers’ compensation and employer’s

liability, and requires the Subcontractor to “name Contractor, Owner and all related and (sic)

Indemnitees as Additional Insureds thereunder” (id).

On January 17, 2023, plaintiff’s motion for summary judgment on the issue of liability

against RPH, Lhotse/Trident and Lhotse was granted as to his claim under Labor Law § 240(1)

and denied as to his claim under Labor Law § 241(6). As pertinent here, it was determined that

plaintiff was injured by an unsafe elevation-related hazard for which RPH and Lhotse were

strictly liable, as he was required to stand on wooden boards in the bed of a truck while

dismantling a scaffold and slipped and fell when his foot slipped on a wet board (NYSCEF Doc

No. 132).

Discussion

“The proponent of a summary judgment motion must make a prima facie showing of

entitlement to judgment as a matter of law, tendering sufficient evidence to eliminate any

material issues of fact from the case. Failure to make such showing requires denial of the motion,

159445/2019 BRAVO, SEGUNDO vs. RPH HOTELS 51ST STREET Page 5 of 12

Motion No. 005 007 008

5 of 12

[* 5]

INDEX NO. 159445/2019

NYSCEF DOC. NO. 235 RECEIVED NYSCEF: 08/23/2024

regardless of the sufficiency of the opposing papers” (Winegrad v New York Univ. Med. Ctr., 64

NY2d 851, 853 [1985] [internal citations omitted]). Once the movant has made its showing,

“‘the party opposing the motion must demonstrate by admissible evidence the existence of a

factual issue requiring a trial of the action or tender an acceptable excuse for his failure so to do .

. ..’” (Fuller v KFG Land I, LLC, 189 AD3d 666, 669 [1st Dept 2020], quoting Zuckerman v City

of New York, 49 NY2d 557, 560 [1980]).

In deciding a motion for summary judgment, the court must “[v]iew[] the evidence in a

light most favorable” to the nonmovant (Summer H. v New York City Dept. of Educ., 19 NY3d

1030, 1031 [2012] [citation omitted]). As summary judgment is a drastic remedy, it should be

granted only when the movant has “’tendered sufficient evidence to demonstrate the absence of

any material issues of fact.’” (Vega v Restani Constr. Corp., 18 NY3d 499, 503 [2012], quoting

Alvarez v Prospect Hosp., 6 NY2d 320, 324 [1986]).

Motion Sequence No. 005

RPH’s notice of motion reflects its application for summary judgment on its contractual

indemnity claim against Lhotse/Trident (see notice of motion [NYSCEF Doc No. 145]).

However, in its supporting papers, RPH expands its prayer for relief to include summary

judgment on its contractual indemnity claim against Intersystem, and a judgment declaring that

RPH is entitled to common-law indemnification and additional insured status from

Lhotse/Trident, Lhotse Corp., Intersystem, and S&S (see Corcoran aff., supra [NYSCEF Doc

No. 146]).

While CPLR 2214(a) requires that a notice of motion list “the relief demanded and the

grounds therefor,” and RPH’s notice did not list the additional relief it requests, as opposing

159445/2019 BRAVO, SEGUNDO vs. RPH HOTELS 51ST STREET Page 6 of 12

Motion No. 005 007 008

6 of 12

[* 6]

INDEX NO. 159445/2019

NYSCEF DOC. NO. 235 RECEIVED NYSCEF: 08/23/2024

defendants do not argue that they were prejudiced by RPH’s failure to satisfy CPLR 2214(a), the

additional arguments are considered.

RPH contends that it is entitled to contractual indemnification from Lhotse/Trident, under

the terms of the Prime Contract, and from Intersystem, based on the terms of the Intersystem

Subcontract. Alternatively, RPH contends that it should be granted common-law

indemnification from Intersystem, as RPH’s potential liability for plaintiff’s injuries is purely

vicarious, based solely on its status as owner of the Premises, without any proof of its negligence

or actual supervision. RPH further argues that the Prime Contract and the Intersystem

Subcontract required that Lhotse/Trident as its contractor and Intersystem as Lhotse/Trident’s

subcontractor name RPH as an “additional insured” under their respective general liability

insurance policies and that they failed to do so.

In opposition, Intersystem argues it cannot be bound by the terms of the Intersystem

Subcontract as it was not counterparty to that agreement. Rather, S&S was the entity described

in, and which executed, it (citing NYSCEF Doc No. 164). RPH did not reply to Intersystem’s

opposition.

Lhotse/Trident and Lhotse Corp. (collectively, Lhotse) argue that RPH’s contractual

indemnification claim fails because plaintiff’s accident was not caused by any “wrongful acts or

omissions” on their part, as required to trigger the indemnification provision of the Prime

Contract. Lhotse also contends that, should RPH’s claim for contractual indemnity against them

succeed, they are entitled to a “pass through,” which would impose the contractual duty to

indemnify upon their subcontractor S&S, and its sub-subcontractor Gerald.

RPH submits no evidence demonstrating that Lhotse or Intersystem committed “wrongful

acts or omissions” in performance of their Work as Contractor or Subcontractor, as required to

159445/2019 BRAVO, SEGUNDO vs. RPH HOTELS 51ST STREET Page 7 of 12

Motion No. 005 007 008

7 of 12

[* 7]

INDEX NO. 159445/2019

NYSCEF DOC. NO. 235 RECEIVED NYSCEF: 08/23/2024

trigger the Prime Contract’s indemnity provision (see Estevez v SLG 100 Park LLC, 215 AD3d

566 [1st Dept 2023] [as there was no evidence subcontractor was negligent, contractual

indemnity claim asserted against it was properly dismissed]).

Moreover, S&S was the counterparty to the Prime Contract, not Intersystem. “The

obligations of contracts are usually limited to the parties making them; only those who are

parties to the contract are liable for its breach, and parties to a contract cannot impose any

liability upon a stranger to the contract under its terms” (NY Jur 2d Contracts § 253, citing, inter

alia, Manhattan Real Estate Equities Group LLC v Pine Equity NY, Inc., 27 AD3d 323, 323 [1st

Dept 2006] [“conclusory assertions” that nonparty was extension of defendant held insufficient

to justify “departure from the general rule that nonparties to an agreement are not bound

thereby”] [citations omitted]). RPH thus fails to demonstrate that it is entitled to contractual

indemnity from Lhotse or Intersystem.

For common-law indemnity to apply “in the construction context,” as RPH seeks in the

alternative, it must show that Intersystem or Lhotse’s negligence were “the actual cause of the

loss” plaintiff suffered (Corcoran ¶41 quoting Board of Mgrs. of Porter House Condominium v

Delshah 60 Ninth LLC, 192 AD3d 415, 415 [1st Dept 2021] [internal quotation marks and

citation omitted]). Absent evidence of negligence by Intersystem or Lhotse, summary judgment

on RPH’s claim for common-law indemnification is also denied.

As to RPH’s claim regarding failure to procure insurance, “‘[a] party moving for

summary judgment on its claim for failure to procure insurance meets its prima facie burden by

establishing that a contract provision requiring the procurement of insurance was not complied

with’” (Dorset v 285 Madison Owner LLC, 214 AD3d 402, 404 [1st Dept 2023], quoting

Benedetto v Hyatt Corp., 203 AD3d 505, 506 [1st Dept 2022]). “A moving party may make that

159445/2019 BRAVO, SEGUNDO vs. RPH HOTELS 51ST STREET Page 8 of 12

Motion No. 005 007 008

8 of 12

[* 8]

INDEX NO. 159445/2019

NYSCEF DOC. NO. 235 RECEIVED NYSCEF: 08/23/2024

showing by submitting, for example, copies of the contract requiring the procurement of

insurance and of correspondence from the insurer of the party against whom summary judgment

is sought indicating that the moving party was not named as an insured on any policies issued”

(id., citing DiBuono v Abbey, LLC, 83 AD3d 650, 652 [2d Dept 2011]).

Here, RPH does not show that Lhotse failed to name it as an additional insured on its

policies or otherwise failed to comply with the insurance provision of the Prime Contract.

Accordingly, RPH’s motion for summary judgment is denied in all respects.

Motion Sequence No. 007

In sequence number 007, Lhotse moves for summary judgment on its third-party claim

for contractual indemnification against Intersystem and Gerald, and a default judgment against

Gerald, which has not appeared or answered Lhotse’s second third-party complaint (see notice of

motion [NYSCEF Doc No. 166]).

The indemnification clause in Section 4.6.1 of the Intersystem Subcontract (submitted on

this motion as ex M [NYSCEF Doc No. 181] to the affirmation of Christopher M. Carafora, Esq.

[NYSCEF Doc No. 167]), provides:

“To the fullest extent permitted by law, the Subcontractor shall indemnify and

hold harmless the Owner, Contractor, Architect, Architect’s consultants, and

agents and employees of any of them from and against claims, damages, losses

and expenses, including but not limited to attorney’s fees, arising out of or

resulting from performance of the Subcontractor’s Work under the Subcontract,

provided that any such claim, damage, loss or expense is attributable to bodily

injury, sickness, disease or death, or to injury or destruction of tangible property

(other than the Work itself), but only to the extent caused by the negligent acts or

omissions of the Subcontractor, the Subcontractor’s Sub-subcontractors, anyone

directly or indirectly employed by them or anyone for whose acts they may be

liable, regardless of whether or not such claim, damage, loss or expense is caused

in part by a party indemnified hereunder. Such obligation shall not be construed to

negate, abridge, or otherwise reduce other rights or obligations of indemnity

which would otherwise exist as to a party or person described in this Section 4.6.”

159445/2019 BRAVO, SEGUNDO vs. RPH HOTELS 51ST STREET Page 9 of 12

Motion No. 005 007 008

9 of 12

[* 9]

INDEX NO. 159445/2019

NYSCEF DOC. NO. 235 RECEIVED NYSCEF: 08/23/2024

Based on this provision, Lhotse concludes that, as Contractor, it is entitled to contractual

indemnification from Intersystem, as its Subcontractor, and from Gerald, as its Sub-

subcontractor.

However, Lhotse’s counterparty to the Intersystem Subcontract is S&S, not Intersystem,

and Lhotse did not identify any provision of the Intersystem Subcontract or applicable authority

that would require a non-signatory such as S&S to indemnify it, even if it is an entity related to

or affiliated with its Subcontractor (see Manhattan Real Estate Equities Group LLC v Pine

Equity NY, Inc., 27 AD3d 323 [1st Dept 2006] [“conclusory assertions” that nonparty was

extension of defendant held insufficient to justify “departure from the general rule that

nonparties to an agreement are not bound thereby”] [citations omitted]).

Similarly, Gerald is not identified as the Sub-subcontractor in the Intersystem

Subcontract, and Lhotse does not provide a copy of Gerald’s subcontract or any other

documentary evidence of its terms, its breach, or even its existence.

Moreover, as Lhotse served Gerald with the second third-party complaint in March 2021,

and as Gerald’s default occurred in April 2021, Lhotse was required by move for a default

judgment against Gerald by April 2022 (CPLR 3215[c]). As the instant motion was not filed

until March 2023, Lhotse’s delay requires dismissal of its claims against Gerald (U.S. Bank N.A.

v Nunez, 190 AD3d 660 [1st Dept 2021]).

Lhotse’s motion for summary judgment against Intersystem and Gerald is therefore

denied.

Motion Sequence No. 008

In their notice of motion, Intersystem and S&S seek dismissal of plaintiff’s complaint

against Intersystem (NYSCEF Doc No. 215), but they do not mention plaintiff’s claims against

159445/2019 BRAVO, SEGUNDO vs. RPH HOTELS 51ST STREET Page 10 of 12

Motion No. 005 007 008

10 of 12

[* 10]

INDEX NO. 159445/2019

NYSCEF DOC. NO. 235 RECEIVED NYSCEF: 08/23/2024

Intersystem in their papers, nor do they submit evidentiary proof in admissible form sufficient to

warrant granting summary judgment in their favor. Thus, this facet of their motion must be

denied, notwithstanding plaintiff’s failure to submit opposition papers (Winegrad v New York

Univ. Med. Ctr., 64 NY2d 851, 853 [1985]).

Intersystem and S&S’s motion seeking dismissal of Lhotse’s second third-party

complaint is also insufficient as they do not address Lhotse’s individual causes of action, except

for the contractual indemnity claim.2 As to that claim, since Intersystem is not a party to the

Intersystem Subcontract, and only S&S is bound thereby, movants are entitled to dismissal of

Lhotse’s contractual causes of action as they relate to Intersystem on that ground.

Intersystem and S&S also contend that Lhotse’s failure to present any evidence of

negligent or wrongful conduct on their part is fatal to Lhotse’s claims for indemnification from

S&S under the terms of the Intersystem Subcontract. Lhotse argues that plaintiff’s alleged

injuries were solely caused by S&S and Gerald (second third-party complaint, ¶¶20, 22

[NYSCEF Doc No. 28]).

As there is no evidence of negligence or wrongdoing on the part S&S, it is entitled to

dismissal of Lhotse’s contractual indemnity claim against it.

However, as movants did not address the four remaining third-party claims, they are not

dismissed.

Conclusion and Order

For the foregoing reasons, it is hereby

2

The Second Third-Party Complaint (NYSCEF Doc No. 28) sets forth five causes of

action: i) common law indemnity; ii) negligence; iii) contractual indemnification; iv) breach of

agreement to procure insurance; and v) breach of agreement to defend Lhotse in claims arising

from work performed by S&S and Gerald under the Intersystem Subcontractor Agreement.

159445/2019 BRAVO, SEGUNDO vs. RPH HOTELS 51ST STREET Page 11 of 12

Motion No. 005 007 008

11 of 12

[* 11]

INDEX NO. 159445/2019

NYSCEF DOC. NO. 235 RECEIVED NYSCEF: 08/23/2024

ORDERED, that the motion for summary judgment by defendant RPH Hotels 51st Street

Owner, LLC (seq. 005) is denied in all respects; it is further

ORDERED, that the motion for summary judgment by defendants Lhotse Contracting

Corp. and Lhotse Corp. (seq. 007) is denied in all respects; it is further

ORDERED, that pursuant to CPLR 3215(c), Lhotse Contracting Corp. and Lhotse

Corp.’s second third-party claims asserted against second third-party defendant Gerald Fast

System Corp. are severed and dismissed, and the clerk is directed to enter judgment accordingly;

it is further

ORDERED, that the motion for summary judgment by defendants Intersystem

Installation Corp. and Intersystem S&S Corp. (seq. 008) is granted with respect to second third-

party plaintiffs Lhotse Contracting Corp. and Lhotse Corp.’s causes of action for contractual

indemnification against defendants Intersystem Installation Corp. and Intersystem S&S Corp.,

and is otherwise denied, and it is further

ORDERED that counsel for the parties shall appear for a trial scheduling/settlement

conference on September 25, 2024, at 11:00 a.m. at 71 Thomas Street, Room 305, New York,

New York.

8/23/2024

DATE DAVID B. COHEN, J.S.C.

CHECK ONE: CASE DISPOSED X NON-FINAL DISPOSITION

GRANTED DENIED X GRANTED IN PART OTHER

APPLICATION: SETTLE ORDER SUBMIT ORDER

CHECK IF APPROPRIATE: INCLUDES TRANSFER/REASSIGN FIDUCIARY APPOINTMENT REFERENCE

159445/2019 BRAVO, SEGUNDO vs. RPH HOTELS 51ST STREET Page 12 of 12

Motion No. 005 007 008

12 of 12

[* 12]

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.