Opinion

E & J Construction Company v. Liberty Building Systems, Inc.

Court
Court of Appeals of Tennessee
Filed
Aug 27, 2010
Status
Published
On the bench
Judge D. Michael Swiney
Cited by
0 cases
Authority
More cited than 29.3%

The opinion

IN THE COURT OF APPEALS OF TENNESSEE

AT KNOXVILLE

July 6, 2010 Session

E & J CONSTRUCTION COMPANY v.

LIBERTY BUILDING SYSTEMS, INC.

Appeal from the Circuit Court for Campbell County

No. 12757 John D. McAfee, Judge

No. E2009-01403-COA-R3-CV - FILED AUGUST 27, 2010

E & J Construction Company (“Plaintiff”) purchased a metal building from Liberty Building

Systems, Inc. (“Defendant”). The metal building was purchased by Plaintiff for one of its

customers, Camel Manufacturing Company (“Camel”). Plaintiff constructed the metal

building for Camel and connected it to an existing building. Almost from the outset, there

was a problem with leaking. Plaintiff sued Defendant raising various claims including,

among others, breach of contract. After the Trial Court granted Defendant’s motion for

partial summary judgment, the case proceeded to trial on the few remaining claims. At the

conclusion of Plaintiff’s proof, the Trial Court granted Defendant’s motion for directed

verdict. Plaintiff appeals. We reverse the grant of a directed verdict on Plaintiff’s breach of

contract claim and remand for further proceedings. The judgment of the Trial Court

otherwise is affirmed.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Circuit

Court Affirmed in Part and Reversed in Part; Case Remanded

D. M ICHAEL S WINEY, J., delivered the opinion of the court, in which H ERSCHEL P. F RANKS,

P.J., and J OHN W. M CC LARTY, J., joined.

Thomas M. Leveille, Knoxville, Tennessee, for the Appellant, E & J Construction Company.

James G. O’Kane, Knoxville, Tennessee, for the Appellee, Liberty Building Systems, Inc.

OPINION

Background

In May of 2005, Plaintiff filed a complaint asserting several causes of action

against Defendant arising from the purchase of an allegedly defective metal building.

According to the complaint:

In late 2003, [Plaintiff] issued a purchase order to

[Defendant] for a metal building which was designed and

engineered by [Defendant]. The purchase price for this building

was $102,811.90. [Plaintiff] subsequently erected this building

for its customer, [Camel Manufacturing Company (“Camel”)]

at Camel’s facility in Campbell County, Tennessee.

At the time that this building began to be erected by

[Plaintiff], [Plaintiff’s] personnel observed that the gutter for

this large building appeared to be too small. [Plaintiff] had

purchased other metal buildings from [Defendant] and

recognized that this guttering appeared to be under-sized. Prior

to the building being erected, [Plaintiff] notified [Defendant’s

personnel] and [Plaintiff] was assured that the guttering was

correctly sized.

The building was erected according to [Defendant’s]

specifications and in accordance with [Defendant’s] drawings.

[Defendant’s personnel] inspected the building and certified that

the building was erected correctly.

Shortly after the building was erected, leaks began to

occur as a result of the guttering being undersized. [Plaintiff]

had been concerned from the outset about this guttering and its

fears came true. [Defendant] was contacted and [Plaintiff] was

instructed to do various things to try to attempt to resolve the

guttering problem. [Plaintiff] utilized its personnel and

materials in attempting to repair the gutter, when [Defendant],

in fact, knew that the gutter was mis-sized and that the

replacement of the gutter was the only solution to this problem.

-2-

[Plaintiff] expended approximately $4,200.00 in labor

and materials in trying to follow [Defendant’s] instructions with

regard to these attempted repairs.

[Plaintiff] had enjoyed an excellent relationship with

Camel . . . , a business that is growing quickly in Campbell

County. In fact, [Plaintiff] had been involved in some

construction of 8 buildings at Camel’s facility at the time that

this particular building was erected. Unfortunately, the leaking

problems impacted [Plaintiff’s] relationship with Camel, making

it impossible for [Plaintiff] to bid on other Camel projects until

this problem was solved.

Plaintiff went on to allege that Camel threatened to sue Plaintiff if the leaks

were not repaired. According to Plaintiff, in order to avoid litigation with its client, Plaintiff

designed a new guttering system and incurred expenses in the amount of $17,852.38 in the

fabrication and installation of the new gutter. Plaintiff further claimed that its business

relationship with Camel has been ruined. Plaintiff sued Defendant for: (1) breach of

contract; (2) violation of the Tennessee Consumer Protection Act, Tenn. Code Ann. § 47-18-

101 et seq.; (3) interference with business relationships; and (4) intentional and/or negligent

misrepresentation.

Defendant answered the complaint and generally denied any liability to

Plaintiff. Defendant admitted that Plaintiff purchased the metal building in question from

Defendant, but denied that the guttering was too small or otherwise improperly sized.

Defendant averred that Plaintiff negligently constructed the building and that the Tennessee

Consumer Protection Act claim was barred by the one year statute of limitations.

In August of 2007, Defendant filed a motion for summary judgment and/or

motion for partial summary judgment. Defendant claimed it was entitled to summary

judgment on Plaintiff’s claims because the undisputed material facts established that the

gutter was of a proper size. Alternatively, Defendant argued that Plaintiff’s Consumer

Protection Act claim was barred by the one year statute of limitations. Attached to

Defendant’s motion was the affidavit of David Ryan Hill (“Hill”). Hill is employed by

Defendant as an engineering manager. Hill earned a bachelor of science degree in

engineering in 1996 and has been a licensed engineer since 2002. Hill has continuously

worked in the metal building business. According to Hill:

At the request of [Defendant’s attorney], I have reviewed

the drawings of the metal buildings which [Defendant] provided

-3-

to [Plaintiff], and I have also reviewed a drawing with

dimensions, which illustrates the relationship of the existing

buildings to the new metal buildings that were constructed on

the Camel Manufacturing Company premises. I have also

reviewed the purchase order documents for this project. Finally,

I have been asked to assume that the valley gutter that was

placed between the existing building and the newly

manufactured Liberty buildings had six equally spaced down

spouts as described by [Plaintiff] in its purchase order and the

testimony of [Jack Heatherly, a licensed contractor and

Plaintiff’s director of field operations]. . . .

Based on the information I reviewed and my knowledge

and expertise as a structural engineer, experienced in the design

and manufacture of metal buildings, I have been asked to

determine whether or not in my opinion the valley gutter that

was provided to [Plaintiff] by [Defendant] was correctly sized

or whether it was too small as alleged by [Plaintiff]. I have

completed an analysis, and it is my opinion within a reasonable

degree of engineering certainty that the valley gutter

manufactured by [Defendant] and provided to [Plaintiff] was

properly sized, and was at least one inch deeper than necessary.

In addition thereto, it is my opinion within a reasonable degree

of engineering certainty that any roof leaks that occurred near

the valley gutter which is at issue in this case were not caused by

an undersized or missized valley gutter. In my opinion, as set

forth above, this valley gutter was of proper size for the

application, and [Plaintiff’s] allegation that it was too small is

incorrect. (original paragraph numbering omitted)

Plaintiff responded by filing the affidavit of Jack Heatherly (“Heatherly”),

whose wife is the owner of Plaintiff. Although Heatherly is not an engineer, he is a field

supervisor for Plaintiff. Heatherly stated that Plaintiff ordered a series of three metal

buildings that were to be connected to Camel’s existing building. When the components

were uncrated, Heatherly was concerned that the guttering was too small and contacted Ben

Barcroft, a district manager for Defendant. Barcroft supposedly contacted one of

Defendant’s engineers and was told that the guttering was the proper size. Barcroft relayed

this information to Heatherly. Relying on that representation, Heatherly proceeded to install

the gutter and complete the metal buildings. Heatherly then stated:

-4-

Had I known at that time that the gutter was incorrectly

sized, I would not have continued building the building.

[Defendant] sold [Plaintiff] a pre-engineered building which

was represented to be correctly designed and to comply with all

standards applicable in the State of Tennessee and I relied on

that representation.

After the building was completed during the summer of

2004, there were problems with leaks in the building. I went

back and checked the screws and the gutter. After the problem

continued, I contacted Ben Barcroft and a series of

recommendations were made by [Defendant] for me to do

various things to the building which I did. None of those things

worked. It was not until the summer of 2004 when the building

was completed that I knew about the valley gutter overflowing.

It was not until August 2 and 3, 2004, that Daniel Moore

visited the building in question at Camel. . . . I was working on

another job at the time and my son Jack Heatherly, Jr., was

present at Camel and went up on the building with Daniel

Moore. Daniel Moore stated at that time that the gutter was too

small and that was reported to me by Jack Heatherly, Jr. That

was the first time that anyone from [Defendant] admitted that

the gutter was too small.

After that date, I continued to be called to Camel

Manufacturing Company whenever it rained because the

building leaked at the location of the valley gutter. I continued

to try to deal with this problem and my wife and I continued to

keep [Defendant] advised that the problem was not solved.

It was not until November, 2004, that Daniel Moore came

back to the site. At that time, he guaranteed that the work he

performed would stop the leaking. His work did not stop the

leaking and I continued to get complaints from Camel and

continued to contact [Defendant] regarding these problems.

* * *

-5-

I have stood on the roof of this building in question at

Camel during a rainstorm in 2004. I observed the gutter

overflowing. I checked the downspouts and none were blocked.

When I went inside the building, I observed leaks from the

valley gutter. The size of the gutter caused the gutter to

overflow and, in turn, caused leaks in the building. (original

paragraph numbering omitted)

Heatherly went on to explain that prior to this situation involving the leaking

metal building, Camel was a very good customer of Plaintiff. After the incident involving

the leaking metal building, Plaintiff no longer was asked to perform any work for Camel.

Plaintiff also filed the affidavit of Louis Cortina (“Cortina”) an engineer who

has been licensed since 1987. According to Cortina:

I have reviewed the calculations by Ryan Hill and in my

professional opinion, the gutter originally provided by

[Defendant] is too small. A gutter with the dimensions

suggested by Ryan Hill would likely overfill and cause leaks in

the building.

The design by [Defendant] and the dimensions of the

gutter suggested by Mr. Hill leave very little or no additional

capacity for blocked downspouts, heavy downpours, or debris

in the gutter. Based on my past experience with regard to the

design of gutters and roof[s], additional capacity is necessary

and as a result, I would not agree with Mr. Hill’s

recommendation.

A gutter in the dimension of 10O deep by 12O wide would

be my recommendation and it is my opinion that a gutter 11½O

wide by 6O deep is inadequate. . . . (original paragraph

numbering omitted)

The contract between Plaintiff and Defendant contained the following

provision:

Warranty: Liberty Building Systems, Inc., warrants all materials

included in our building systems package for a period of one

year from date of shipment. All materials must be properly

-6-

installed and erected in a timely fashion upon receipt of

shipment. Prolonged storage or exposure to the elements or

hazardous environments will void this warranty. Any damaged

materials discovered while unloading the shipment must be

reported and signed off by the delivery driver for validation. All

shortages and concealed damage must be reported within 10

working days of receipt of shipment.

A hearing was conducted on Defendant’s motion for summary

judgment/motion for partial summary judgment. Following the hearing, the Trial Court

entered an order stating as follows:

This cause came on to be heard . . . on defendant’s Motion for

Summary Judgment and Motion for Partial Summary Judgment.

The parties were represented by counsel and presented their

argument to the court. The court having considered defendant’s

Motion for Partial Summary Judgment, plaintiff’s response

thereto, the supporting evidence of record, and having heard the

argument and representations of counsel, the court made its

ruling from the bench with respect to defendant’s Motion for

Partial Summary Judgment.1 The court found that defendant’s

Motion for Partial Summary Judgment seeking dismissal of

plaintiff’s claims pursuant to the Tennessee Consumer

Protection Act that defendant engaged in unfair or deceptive

acts or practices pursuant to Tenn. Code Ann. § 47-18-104

should be granted. Having found that plaintiff’s Tennessee

Consumer Protection Act claims of unfair or deceptive acts or

practices should be dismissed, the court ruled that defendant’s

motion to dismiss the Tennessee Consumer Protection Act

claims pursuant to the one-year statute of limitations is moot.

The court further found that defendant’s Motion for Partial

Summary Judgment seeking dismissal of plaintiff’s claim for

tortious interference with a business relationship should be

granted. The court further found that defendant’s Motion for

Partial Summary Judgment seeking dismissal of plaintiff’s claim

for lost profits should be granted. Finally, the court denied at

1

For obvious reasons, we should have been provided a transcript from this hearing, but the record

contains no such transcript. Thus, we cannot ascertain what “representations” were made to the Trial Court

and by whom.

-7-

this time defendant’s Motion for Partial Summary Judgment

seeking dismissal of plaintiff’s intentional/negligent

misrepresentation claims, and further withheld ruling on

plaintiff’s Motion for Summary Judgment seeking dismissal of

plaintiff’s suit, pending submission by defendant of a

supplement to the Motion for Summary Judgment on or before

Monday, March 10, 2008, or defendant’s announcement of a

withdrawal of the Motion for Summary Judgment. . . . (footnote

added)

Following entry of the order partially granting Defendant’s motion for

summary judgment, Defendant withdrew its motion on the remaining claims and this case

proceeded to trial. For the most part and except as discussed below, the testimony of

Plaintiff’s witnesses at trial was consistent with that set forth in their respective affidavits.

At the close of Plaintiff’s proof, Defendant moved for and the Trial Court

granted a motion for a directed verdict. According to the Trial Court:

After the plaintiff rested, the jury was excused and defendant

moved for a directed verdict in its favor. After hearing

arguments of counsel and considering the evidence and record

as a whole, the court found that defendant’s Motion for a

Directed Verdict in its favor with respect to plaintiff’s claim of

negligent or intentional misrepresentation and punitive damages

is well-taken, because the plaintiff presented no competent proof

of a negligent or intentional misrepresentation that would entitle

the plaintiff to recover compensatory or punitive damages; and

the court further found that defendant’s Motion for a Directed

Verdict with respect to the remaining issue of a breach of

contract and breach of the implied warranty of fitness for a

particular purpose was well-taken, because there was no

competent expert testimony presented that the gutter at issue

was not fit for a particular purpose or that defendant breached its

contract with the plaintiff. . . .

After entry of the directed verdict for Defendant, Plaintiff filed a motion for

a new trial. In this motion, Plaintiff claimed that not only was it pursuing a claim for breach

of an implied warranty of fitness for a particular purpose, it also was seeking relief for breach

of an implied warranty of merchantability. In addition, Plaintiff asserted that there was

sufficient proof to withstand a motion for directed verdict as to whether Defendant breached

-8-

the contract and implied warranties, as well as whether Defendant had committed negligent

and/or intentional misrepresentations. The Trial Court denied the motion, and Plaintiff

appeals challenging both the granting of Defendant’s motion for partial summary judgment

as well as the granting of Defendant’s motion for directed verdict following the close of

Plaintiff’s proof at trial.

Discussion

We first discuss whether the Trial Court properly granted Defendant’s motion

for partial summary judgment. Our Supreme Court reiterated the standard of review in

summary judgment cases as follows:

The scope of review of a grant of summary judgment is

well established. Because our inquiry involves a question of

law, no presumption of correctness attaches to the judgment, and

our task is to review the record to determine whether the

requirements of Rule 56 of the Tennessee Rules of Civil

Procedure have been satisfied. Hunter v. Brown, 955 S.W.2d 49,

50-51 (Tenn. 1997); Cowden v. Sovran Bank/Cent. S., 816

S.W.2d 741, 744 (Tenn. 1991).

A summary judgment may be granted only when there is

no genuine issue of material fact and the moving party is entitled

to judgment as a matter of law. Tenn. R. Civ. P. 56.04; Byrd v.

Hall, 847 S.W.2d 208, 214 (Tenn. 1993). The party seeking the

summary judgment has the ultimate burden of persuasion “that

there are no disputed, material facts creating a genuine issue for

trial . . . and that he is entitled to judgment as a matter of law.”

Id. at 215. If that motion is properly supported, the burden to

establish a genuine issue of material fact shifts to the

non-moving party. In order to shift the burden, the movant must

either affirmatively negate an essential element of the

nonmovant’s claim or demonstrate that the nonmoving party

cannot establish an essential element of his case. Id. at 215 n.5;

Hannan v. Alltel Publ’g Co., 270 S.W.3d 1, 8-9 (Tenn. 2008).

“[C]onclusory assertion[s]” are not sufficient to shift the burden

to the non-moving party. Byrd, 847 S.W.2d at 215; see also

Blanchard v. Kellum, 975 S.W.2d 522, 525 (Tenn. 1998). Our

state does not apply the federal standard for summary judgment.

The standard established in McCarley v. West Quality Food

-9-

Service, 960 S.W.2d 585, 588 (Tenn. 1998), sets out, in the

words of one authority, “a reasonable, predictable summary

judgment jurisprudence for our state.” Judy M. Cornett, The

Legacy of Byrd v. Hall: Gossiping About Summary Judgment

in Tennessee, 69 Tenn. L. Rev. 175, 220 (2001).

Courts must view the evidence and all reasonable

inferences therefrom in the light most favorable to the

non-moving party. Robinson v. Omer, 952 S.W.2d 423, 426

(Tenn. 1997). A grant of summary judgment is appropriate only

when the facts and the reasonable inferences from those facts

would permit a reasonable person to reach only one conclusion.

Staples v. CBL & Assocs., Inc., 15 S.W.3d 83, 89 (Tenn. 2000).

In making that assessment, this Court must discard all

countervailing evidence. Byrd, 847 S.W.2d at 210-11.

Recently, this Court confirmed these principles in Hannan.

Giggers v. Memphis Housing Authority, 277 S.W.3d 359, 363-64 (Tenn. 2009).

We begin by addressing the grant of Defendant’s motion for summary

judgment with regard to Plaintiff’s Tennessee Consumer Protection Act (“TCPA”) claim.

Plaintiff cites very little evidence and no law whatsoever in the argument section of its brief

addressing the grant of Defendant’s motion for partial summary judgment. Plaintiff’s entire

argument as to the dismissal of the TCPA claim comprises one paragraph in the argument

section of its brief. Plaintiff cites Heatherly’s affidavit twice and improperly attempts to rely

on trial testimony pertaining to Plaintiff’s misrepresentation claim.2 According to Plaintiff,

Jack Heatherly’s statements in his affidavit: (1) that he was advised by Defendant that the

guttering was the correct size; and (2) that Heatherly would not have continued building the

building had he known the gutter was not the correct size, are sufficient to create a fact issue

on the TCPA claim. As noted, Plaintiff cites absolutely no law supporting his claim that

these two facts, standing alone, are sufficient to create a genuine issue of material fact as to

its TCPA claim. Plaintiff does not even discuss what is required to properly set forth a

TCPA claim. Plaintiff even fails to cite to the TCPA.

2

Plaintiff cites trial testimony when discussing the misrepresentation claim. Testimony at trial is

irrelevant when ascertaining whether the pre-trial motion for partial summary judgment should have been

granted.

-10-

The entire discussion in Plaintiff’s argument section of its brief addressing the

grant of summary judgment on its claim for interference with business relationship is as

follows:

There was also a fact issue with regard to the claim for

interference with the business relationship with Camel

Manufacturing. The Affidavit and deposition testimony showed

that Liberty contacted representatives of Camel Manufacturing

directly and placed blame on the Plaintiff for the problems with

the gutter system. Affidavit of Jack Heatherly ¶ 21.

Again, Plaintiff cites no law setting forth the elements necessary to state a

claim for intentional interference with a business relationship or any law supporting its

argument that the two alleged facts set forth in Heatherly’s affidavit, standing alone, are

sufficient to withstand a properly supported motion for summary judgment on such a claim.

The same can be said for Plaintiff’s argument as to the grant of summary judgment for lost

business profits.

In Bean v. Bean, 40 S.W.3d 52 (Tenn. Ct. App. 2000) we observed:

Courts have routinely held that the failure to make appropriate

references to the record and to cite relevant authority in the

argument section of the brief as required by Rule 27(a)(7)

constitutes a waiver of the issue. See State v. Schaller, 975

S.W.2d 313, 318 (Tenn. Crim. App. 1997); Rampy v. ICI

Acrylics, Inc., 898 S.W.2d 196, 210 (Tenn. Ct. App. 1994); State

v. Dickerson, 885 S.W.2d 90, 93 (Tenn. Crim. App. 1993). . . .

As noted in England v. Burns Stone Company, Inc., 874 S.W.2d

32, 35 (Tenn. Ct. App. 1993), parties cannot expect this court to

do its work for them.

Bean, 40 S.W.3d at 55-56.

Because Plaintiff has failed to cite any authority whatsoever with respect to its

argument that the Trial Court improperly granted Defendant’s motion for partial summary

judgment as to the various claims at issue in that motion, we find that Plaintiff has waived

these issues on appeal. Accordingly, we affirm the Trial Court’s grant of partial summary

judgment to Defendant.

-11-

The next issues surround the Trial Court’s granting of a directed verdict to

Defendant. With respect to the Trial Court’s granting of Defendant’s motion for directed

verdict, our standard of review is different from that related to a summary judgment. In

Johnson v. Tennessee Farmers Mut. Ins. Co., 205 S.W.3d 365 (Tenn. 2006), our Supreme

Court set forth the standard of review with regard to directed verdicts, stating:

In reviewing the trial court’s decision to deny a motion

for a directed verdict, an appellate court must take the strongest

legitimate view of the evidence in favor of the non-moving

party, construing all evidence in that party’s favor and

disregarding all countervailing evidence. Gaston v. Tenn.

Farmers Mut. Ins. Co., 120 S.W.3d 815, 819 (Tenn. 2003). A

motion for a directed verdict should not be granted unless

reasonable minds could reach only one conclusion from the

evidence. Id. The standard of review applicable to a motion for

a directed verdict does not permit an appellate court to weigh the

evidence. Cecil v. Hardin, 575 S.W.2d 268, 270 (Tenn. 1978).

Moreover, in reviewing the trial court’s denial of a motion for

a directed verdict, an appellate court must not evaluate the

credibility of witnesses. Benson v. Tenn. Valley Elec. Coop.,

868 S.W.2d 630, 638-39 (Tenn. Ct. App. 1993). Accordingly,

if material evidence is in dispute or doubt exists as to the

conclusions to be drawn from that evidence, the motion must be

denied. Hurley v. Tenn. Farmers Mut. Ins. Co., 922 S.W.2d

887, 891 (Tenn. Ct. App. 1995).

Johnson, 205 S.W.3d at 370.

Plaintiff claims Defendant violated both the implied warranty of fitness for a

particular purpose and the implied warranty of merchantability. Neither of these warranty

claims was specifically asserted in the complaint, and we were unable to find in the record

an amended complaint setting forth these claims. Plaintiff does not direct us to anywhere in

the record where breach of either implied warranty actually was pled. As to the implied

warranty of merchantability, the Trial Court obviously did not believe that Plaintiff was

pursuing this un-pled claim. The pleadings support this conclusion. We hold that a claim

for breach of the implied warranty of merchantability never was properly raised.

As to the implied warranty of fitness for a particular purpose, at trial Plaintiff’s

expert, Louis Cortina, expressly testified that the gutter at issue was fit for its particular

purpose. While Cortina testified that the gutter would have been more effective had it been

-12-

deeper, he, nevertheless, acknowledged to the Trial Court that the gutter was built according

to industry guidelines and was fit for its particular purpose. Specifically, Cortina stated:

THE COURT: Do you agree or disagree, was that gutter fit for

the particular purpose and that purpose would be to handle the

water volume coming off that roof line for a 50-year rain. . . .

THE WITNESS: Based on the volume, it meets the minimum

guidelines.

THE COURT: Which would be fit for the particular purpose in

which it was designed.

THE WITNESS: For handling quantity of water, yes.

On appeal, Plaintiff argues that we should simply ignore the testimony of its

own expert. This, we cannot do. We affirm the Trial Court’s judgment granting a directed

verdict to Defendant on Plaintiff’s claim that Defendant violated the implied warranty of

fitness for a particular purpose.3

Next we address the Trial Court’s grant of a directed verdict for Defendant on

Plaintiff’s claims for negligent and intentional misrepresentation. In Robinson v. Omer, 952

S.W.2d 423 (Tenn. 1997), the Supreme Court discussed the essential elements of a negligent

misrepresentation claim as follows:

Tennessee has adopted Section 552 of the Restatement (Second)

of Torts “as the guiding principle in negligent misrepresentation

actions against other professionals and business persons.”

Section 552 provides, in pertinent part, as follows:

(1) One who, in the course of his business, profession or

employment, or in any other transaction in which he has

a pecuniary interest, supplies false information for the

guidance of others in their business transactions, is

subject to liability for pecuniary loss caused to them by

their justifiable reliance upon the information, if he fails

3

Due to our resolution of this issue, we pretermit Defendant’s argument that Plaintiff never pled a

violation of the implied warranty of fitness for a particular purpose.

-13-

to exercise reasonable care or competence in obtaining or

communicating the information. . . .

Id. at 427.

The only alleged “misrepresentation” of Defendant at issue on appeal occurred

when Plaintiff was told that the gutter was the correct size after concerns were initially raised

by Mr. Heatherly. However, there was no proof offered by Plaintiff that Defendant or one

of its representatives failed to exercise reasonable care when informing Plaintiff that the

gutter was the correct size. Even Plaintiff’s expert agreed that the gutter met minimum

industry standards and was fit for its particular purpose. Accordingly, the Trial Court

correctly granted Defendant’s motion for directed verdict as to the negligent and intentional

misrepresentation claims.

The final issue is whether the Trial Court correctly granted Defendant’s motion

for a directed verdict as to the breach of contract claim. As set forth previously, the contract

between the parties contained the following express warranty:

Warranty: Liberty Building Systems, Inc., warrants all materials

included in our building systems package for a period of one

year from date of shipment. All materials must be properly

installed and erected in a timely fashion upon receipt of

shipment. Prolonged storage or exposure to the elements or

hazardous environments will void this warranty. Any damaged

materials discovered while unloading the shipment must be

reported and signed off by the delivery driver for validation. All

shortages and concealed damage must be reported within 10

working days of receipt of shipment.

At trial, Heatherly testified that he installed the metal building according to

Defendant’s specifications and that it, nevertheless, repeatedly leaked. The leaks began well

before one year had elapsed from the date of shipment. Heatherly’s attempted repairs were

unable to stop the leak, and eventually a new and deeper gutter was installed.

As noted previously, when reviewing the grant of a motion for directed verdict,

we “must take the strongest legitimate view of the evidence in favor of the non-moving party,

construing all evidence in that party’s favor and disregarding all countervailing evidence.”

Johnson, 205 S.W.3d at 370. When viewing the evidence in this light, we believe Plaintiff

did present sufficient evidence to withstand Defendant’s motion for a directed verdict on

Plaintiff’s breach of contract claim asserting that Defendant violated the express warranty

-14-

contained in the contract. Viewing the evidence in the light most favorable to Plaintiff,

Plaintiff purchased the building from Defendant; Defendant instructed Plaintiff how to install

the building; Plaintiff installed the building as directed by Defendant; and the building leaked

despite being installed as directed by Defendant. In short, construing this evidence in

Plaintiff’s favor, the building bought from Defendant leaked despite the fact that it was

installed as directed by Defendant. We believe this evidence to be sufficient such that doubt

exists as to the conclusions to be drawn from this evidence. We reverse the judgment of the

Trial Court on this sole issue. Any remaining issues are pretermitted.

Conclusion

The judgment of the Trial Court granting Defendant’s motion for a directed

verdict on Plaintiff’s breach of contract claim is reversed. In all other respects, the judgment

of the Trial Court is affirmed. This case is remanded to the Campbell County Circuit Court

for further proceedings consistent with this Opinion and for collection of the costs below.

Costs on appeal are taxed one-half to the Appellant, E & J Construction Company, and its

surety, and one-half to the Appellee, Liberty Building Systems, Inc., for which execution may

issue, if necessary.

________________________________

D. MICHAEL SWINEY, JUDGE

-15-

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.