Opinion

East Tennessee Grading, Inc. v. Bank of America, N.A.

  • 338 S.W.3d 506
  • 2010 Tenn. App. LEXIS 595
  • 2010 WL 3749411
Court
Court of Appeals of Tennessee
Filed
Sep 27, 2010
Status
Published
Author
Franks
On the bench
Presiding Judge Herschel Pickens Franks
Cited by
1 cases
Authority
More cited than 44.7%

concluding that rebuttal evidence offered by the plaintiff that contradicted testimony during plaintiff’s case-in-chief was properly excluded

How later courts described this case

  • concluding that rebuttal evidence offered by the plaintiff that contradicted testimony during plaintiff’s case-in-chief was properly excluded

Written by the judges who cited it.

The opinion

IN THE COURT OF APPEALS OF TENNESSEE

AT KNOXVILLE

July 8, 2010 Session

EAST TENNESSEE GRADING, INC., v. BANK OF AMERICA, N.A., et al.

Appeal from the Chancery Court for Hamilton County

No. 07-0611 Hon. W. Frank Brown, III., Chancellor

No. E2009-02250-COA-R3-CV - FILED SEPTEMBER 27, 2010

Plaintiff brought this action to enforce a lien for excavation and road work done in a

residential development, because the owner had not paid for the construction work

performed. An agreed judgment was entered as to plaintiff's claims against defendant, Seven

Lakes Development, awarding judgment against that defendant for materials and labor

performed on the property. One parcel of property, however, totaling 6.36 acres was owned

by defendants Coughlins, which was subject to a deed of trust in favor of Bank of America.

The Trial Court held that Bank of America had priority over plaintiff as to 1.9 acres because

plaintiff had not filed its Notice of Lien timely to maintain priority over the subsequent

owners pursuant to Tenn. Code Ann. § 66-11-112. The Trial Court also held that plaintiff

had priority over Bank of America as to 4.46 acres because plaintiff's Notice of Lien was

filed before the Amended Deed of Trust in favor of Bank of America was filed. On appeal,

we affirm the Judgment of the Trial Court.

Tenn. R. App. P.3 Appeal as of Right; Judgment of the Chancery Court Affirmed.

H ERSCHEL P ICKENS F RANKS, P.J., delivered the opinion of the Court, in which C HARLES D.

S USANO, J R., J., and. D. M ICHAEL S WINEY, J., joined.

Steven M. Jacoway, Chattanooga, Tennessee, for the appellant, East Tennessee Grading, Inc.

Brett A. Oeser, Nashville, Tennessee, for the appellees, Bank of America, N.A., William B.

Coughlin, and Janet L. Coughlin.

OPINION

Background

This is a lien case that arose when defendant Seven Lakes Development, L.L.C.

(Seven Lakes), a developer of residential real estate, failed to pay plaintiff/appellant East

Tennessee Grading Company, Inc. (ETG), an excavation company, $2,036,483.27 that it

allegedly owed ETG for excavation and road work ETG had performed at a subdivision

project under development by Seven Lakes. On April 9, 2007 ETG filed a Notice of Claim

of Lien on the project to recover the $2,036,483.27 Seven Lakes owed it. On July 16, 2007

ETG filed a Complaint to Enforce Lien in the Chancery Court against Seven Lakes, William

and Janet Coughlin (the Coughlins), Bank of American, N.A. (BOA), and others.

The lien was on approximately 150 acres in, Hamilton County, Tennessee, and most

of the property was owned by Seven Lakes and subject to a deed of trust held by Northwest

Georgia Bank. One parcel of the property, totaling 6.36 acres, however, was owned by the

Coughlins. The Coughlin property was subject to a deed of trust in favor of BOA, which was

recorded on February 5, 2007, and an amended deed of trust, which was recorded on October

24, 2007. On November 24, 2008, an Agreed Judgment was entered as to ETG’s claims

against Seven Lakes awarding ETG $2,364,565.27 for labor and materials that had been

expended on the property. On February 2, 2009 another Agreed Order was entered declaring

that ETG no longer claimed priority of its lien over the property owned by Seven Lakes that

had been subject to a deed of trust held by Northwest Georgia Bank. The order explained

that Northwest Georgia Bank had foreclosed on the property on June 25, 2008 without

objection of any party to this litigation. Accordingly, the Trial Court held that the lien of

Northwest Georgia Bank established by the deed of trust was a first priority lien against the

property and that all claims asserted by ETG against the property owned by Seven Lakes

were dismissed. ETG’s claims against the Coughlin property remained viable and are the

subject of this appeal.

The case was tried on July 8, 2009, and ETG offered testimony from its vice-president

in charge of field operations, Tony Boles, and defendant William B. Coughlin testified on

behalf of himself, his wife and BOA.

Pertinent to this appeal, Boles testified that the December 26, 2006 invoice was the

last invoice submitted to Seven Lakes and it reflected work performed by ETG only through

December 26, 2006. He stated that ETG stayed on the project site through February 13, 2007

to perform soil erosion maintenance work that it was required to complete pursuant to

-2-

erosion control permits issued to Seven Lakes by TDEC.1 Boles denied that any “real

production work” was performed by ETG between December 26, 2006 and February 13,

2007. He testified as follows on cross examination:

Q. Did y’all demobilize in December?

A. No, sir. We didn’t start pulling equipment off until February.

Q. Okay. But no work was done between December and February?

A. There was some maintenance work that was done to stay in compliance with

our erosion control permits, but not any real production work.

Q. That was - - why was that work done?

A. At the time we were still on the permit with TDEC and being listed on the

permit we still had responsibility for erosion control management for the site.

Q. Did TDEC actually physically come to the site and direct you to take some

action?

A. There were inspections on the site and plus our routine inspections that we are

required to do throughout the project. We maintained that until we

contractually got off the project.

Q. Okay. So what you were doing in that regard then was maintenance of erosion

control?

A. Correct.

Q. That didn’t - - that wasn’t meant to be any sort of permanent improvement to

the property?

A. That’s correct.

Q. And the only reason - - I would imagine at this point you were dissatisfied with

Seven Lakes Development since they owed you $2 million?

A. Yes, sir.

Q. Is it fair to say the only reason you went out there is because you were named

on the permit and had a obligation to the State?

A. That’s correct, yes sir.

Boles stated that the driving purpose of the soil erosion work ETG did on the property

between late December 2006 and February 13, 2007 was to stay in compliance with the State

permit and that their purpose in doing so was not to provide any permanent improvement to

the project.

Following the trial, the Trial Court entered a Memorandum Opinion, and held that

ETG had a valid and enforceable lien against the Coughlin property, but the lien was

subordinate to BOA’s deed of trust recorded on February 5, 2007. However, ETG’s lien

1

Tennessee Department of Environment and Conservation.

-3-

took priority over an amendment to the deed of trust in favor of BOA recorded on October

24, 2007. Subsequently, ETG filed its notice of appeal.

The issues presented for review are:

A. Whether the Trial Court erred in holding that pursuant to Tenn. Code Ann. §

66-11-112 ETC, a potential lienor, “abandoned” the Seven Lakes project on

or about the day it allegedly ceased its operations on the project instead of

holding that “abandonment” occurred after the “cessation of operations for a

period of sixty days”?

B. Whether the Trial Court erred in holding that ETG ceased its operations on the

Seven Lakes project on December 26, 2006 instead of February 13, 2007?

1. Whether the Trial Court erred in holding that erosion control work was

not lienable work, and thus did not serve to extend the time ETG had

to file its lien?

2. Whether the Trial Court erred in excluding testimony and business

records that showed that ETG completed other lienable work up until

February 13, 2007?

C. Whether the Trial Court erred in holding that ETG’s lien did not apply to all

of the Coughlin property because ETG did not make any “improvements”

directly to the property immediately appurtenant to the Coughlin house?

D. Whether the Trial Court erred in not holding that plaintiff’s lien was

extinguished by the Coughlins’ acquisition of the property as subsequent

purchasers for valuable consideration without notice?

In a non-jury trial, our standard of review is de novo. Wright v. City of Knoxville, 898

S.W.2d 177, 181 (Tenn.1995). There is a presumption of correctness as to the trial court's

findings of fact, unless the preponderance of the evidence is otherwise. Tenn. R. App. P.

13(d). With respect to the trial court's legal conclusions, however, there is no presumption

of correctness. Bowden v. Ward, 27 S.W.3d 913, 916 (Tenn. 2000); Tenn. R. App. P. 13(d).

The determinative issue on this appeal is when does a materialman ‘abandon” a

-4-

project under Tenn. Code Ann. §66-11-112(b)? 2 Tenn. Code Ann. § 66-11-101 et seq.

provides Tennessee’s statutory vehicle for establishment and enforcement of mechanics’ and

materialmen’s liens. The statute seeks to balance the competing interests of a landowner’s

right to encumbrance free property versus a lienor’s right to compensation for labor and

material provided to improve the landowner’s property. Arthur M. Fowler, The Art of

Perfecting Mechanics’ and Materialmen’s Liens in Tennessee, 40-Tenn. B.J. 17, (Mar.

2004)(citing Gen. Elec. Supply Co. v. Arlen Realty & Dev. Corp, 546 S.W.2d 210, 213

(Tenn. 1977). A materialman has no right to a lien except as provided by statute and the

statute must be strictly construed. Owen Lumber & Millwork, Inc. v. National Equity Corp.

940 S.W.2d 66, 67 (Tenn.App.,1996)(citing Nanz v. Cumberland Gap Park Co., 103 Tenn.

299, 52 S.W. 999 (1899)).

Further, it is well established that Tennessee courts generally require strict compliance with

the requirements of the lien statutes. Williamson County Ready Mix, Inc. v. Pulte Homes

Tennessee Ltd. Partnership, No. M2007-01710-COA-R3-CV, 2008 WL 5234730 at * 2

(Tenn. Ct. App. Dec. 15, 2008)(citing Eatherly Constr. Co. v. DeBoer Constr. Co., 543

S.W.2d 333, 334 (Tenn.1976); D.T. McCall & Sons v. Seagraves, 796 S.W.2d 457, 460

(Tenn. Ct. App.1990)). However, the court’s interpretation of the statute must not be so strict

as to defeat the purpose of the statutes. McCall at 460; Gen. Elec. Supply at 213.

Tenn. Code Ann. § 66-11-102(a) establishes ETG’s lien on the property based on the

contract between ETG and Seven Lakes and the work performed pursuant to that contract.

The statute states:

(a) There shall be a lien upon any lot of ground or tract of land upon which a house

or structure has been erected, demolished, altered, or repaired, or for fixtures or

machinery furnished or erected, or improvements made, by special contract with the

owner or the owner's agent, in favor of the contractor, mechanic, laborer, founder or

machinist, who does the work or any part of the work, or furnishes the materials or

any part of the materials, or puts thereon any fixtures, machinery, or material, and in

favor of all persons who do any portion of the work or furnish any portion of the

materials for such building; provided, that the subcontractor, laborer or materialman

satisfies all of the requirements set forth in § 66-11-145, if applicable.

2

The Mechanic’s and Materialmen’s Lien Statutes, Tenn. Code Ann. § 66-11-101 et seq. were

substantially revised by 2007 Pub. Acts, c. 189 effective May 18, 2007. As all transactions and events

pertinent to this case occurred prior to May 18, 2007, the lien statutes in effect prior to that date are

applicable. The parties so stipulated and the trial court agreed. Accordingly, all references to the lien

statutes, Tenn. Code Ann. § 66-11-101 et seq., in this opinion are to the statutes precdating the 2007

revisions.

-5-

It is undisputed that the lien took effect on September 22, 2006 when ETG had pug

material for development of the road beds delivered to the property, although ETG had done

considerable work on the property prior to that date. Tenn. Code Ann. § 66-11-104 (a)

provides that a lien takes effect from the time of “visible commencement of operations.”

The statute specifically excludes from “visible commencement of operations” the type of

activities ETG had performed between July 2006 and September 22, 2006, such as

demolition, excavating, clearing filling or grading, placement of sewers. Tenn. Code Ann.

§ 66-11-104(a). Tenn. Code Ann. 66-11-101(17) provides the statutory definition for

“visible commencement of operations” as “ the first actual work of improving upon the land

or the first delivery to the site of the improvement of materials which remain thereon until

actually incorporated in the improvement, of such manifest and substantial character as to

notify interested persons that an improvement is being made or is about to be made on the

land.” Thus, the lien on the property was effective prior to the Coughlin’s acquisition of part

of the property in January 2007. The lien statutes provide protection to a lien holder should

the property be sold in whole or in part after attachment of a lien, as happened here. Tenn.

Code Ann. 66-11-112 provides such protection as follows:

(a) In order to preserve the virtue of the lien, as concerns subsequent purchasers or

encumbrancers for a valuable consideration without notice thereof, though not as

concerns the owner, such lienor, who has not so registered such lienor's contract, is

required to file for record in the office of the register of deeds of the county where the

premises, or any part affected lies, a sworn statement similar to that described in § 66-

11-117, and pay the fees. The register shall file, note and record same, as provided in

§ 66-11-117. Such filing for record is required to be done within ninety (90) days after

the building or structure or improvement is demolished, altered and/or completed, as

the case may be, or is abandoned and the work not completed, or the contract of the

lienor expires or is terminated or the lienor is discharged, prior to which time the lien

shall be effective as against such purchasers or encumbrancers without such

registration; provided, that the owner shall give thirty (30) days' notice to contractors

and to all of those lienors who have filed notice in accordance with § 66-11-145 prior

to the owner's transfer of any interest to a subsequent purchaser or encumbrancer for

a valuable consideration.

(b) A building, structure or improvement shall be deemed to have been abandoned for

purposes of this chapter when there is a cessation of operation for a period of sixty

(60) days and an intent on the part of the owner or contractor to cease operations

permanently, or at least for an indefinite period.

-6-

Tenn. Code Ann. § 66-11-112(a) and (b)(emphasis added).3

The parties do not dispute that Tenn. Code Ann. § 66-11-112, prior to the 2007

revisions, is the controlling statute here. Also, the parties do not dispute that the Coughlins

are “subsequent purchasers or encumbrancers” as contemplated by section 66-11-112.

According to Tennessee cases, the courts have consistently construed “subsequent purchasers

or encumbrancers” to mean those persons who have purchased or encumbranced property

subsequent to the attachment of the material supplier's lien. Vulcan Materials Co. v.

Kitsmiller and Co., No. E2001-02044-COA-R3-CV, 2002 WL 1033143 at * 8 (Tenn. Ct.

App. May 22, 2002). Thus, the Coughlin’s qualify as “subsequent purchasers or

encumbrancers”. Nor is there a dispute as to whether ETG properly recorded its notice of

lien and put the Coughlins and BOA on notice of the recordation. What is disputed, is

whether the Trial Court properly interpreted the statute as to when the project became

“abandoned” and when the ninety day period for filing notice of the line commenced to run.

Appellant argues that the Chancery Court incorrectly calculated the deadlines set forth

in Tenn. Code Ann. § 66-11-112. Under that section, a lien has priority over a subsequent

purchaser or encumbrancer, such as the Coughlins, without the filing of the contract if notice

of the lien is recorded within ninety days after completion of the improvement, termination,

discharge or expiration of the contract or “abandonment” of the work. There is no question

that ETG had intentionally abandoned the Seven Lakes project based on the developer’s

failure to make payments. The issue is when the project was “deemed abandoned” and when

the ninety-day period in which ETG had to file its lien commenced. ETG maintains that the

statute provides for two separate and distinct relevant time periods: (1) a sixty-day period that

established the abandonment status of the project provided in subsection (b); and (2) a

ninety-day period that follows the date when the project is “deemed” abandoned in which

ETG had to file notice of the lien as provided in subsection (a). Under the interpretation of

3

Tenn. Code Ann. § 66-11-117 referenced in Section 66-11-112 provides as follows: A mechanic's

lien shall have precedence over all other subsequent liens or conveyances during such time; provided, that

a sworn statement of the amount due and/or approximating that to accrue for such work, labor, or materials,

and a reasonably certain description of the premises, shall be filed, within the ninety-day period referred to

in § 66-11-115(b), or in the case of liens acquired by contract executed on or after April 17, 1972, by virtue

of § 66-11-141, within ninety (90) days after completion of the structure which is or is intended to be

furnished water by virtue of drilling a well, or abandonment of work on the structure, as the case may be,

with the county register, who shall note the same for registration, and put it on record in the lien book in the

office of the register, for which the register shall be entitled to the sums specified in § 8-21-1001, which sums

shall be paid by the party filing the same; but such fees shall be receipted for on the statement of account,

and shall be part of the indebtedness or charge secured by the lien, and this registration shall be notice to all

persons of the existence of such lien.

-7-

the statute urged by ETG, the lienor would have had one hundred and fifty days from the last

day of work in which to file its notice of lien rather than the ninety days it would have had

to file the notice if the project had been completed, the contract had expired or ETG had been

discharged. In other words, ETG maintains that if it had stopped work on the project on

December 26, 2006, as appellees claim, the project would not have been deemed

“abandoned” until sixty days later, on February 26, 2007. If, as ETG claims, its last day of

work was February 13, 2007, the project would have been deemed “abandoned” sixty days

later, on April 27, 2007. Under either scenario, ETG contends that the ninety-day time frame

in which it had to file its notice of lien did not start to run until the last day of the sixty day

period.

The Trial Court determined that the “60 days is within the 90 days”, and reasoned that

this was so because of the fact that “‘90' is a number that the general assembly has prescribed

in Tenn. Code Ann. § 66-11-115 and other lien statutes for filing a notice of lien and/or a

lawsuit to enforce the lien etc.” The Trial Court further addressed this issue in its October

2, 2009 order denying ETG’s motion to alter or amend and stated that there was no appellate

decision regarding the interpretation of subsection (b) of Tenn. Code Ann. 66-11-112. The

Court reiterated its finding in its earlier order and stated that the statutory definition of

abandonment does not “mean that the lienor has 90 days after the 60 days within which to

file a notice of lien’. The Court supplied a rationale for its interpretations:

Any interpretation which gave a lienor 150 days to file a notice of lien would

not be consistent with the other lien notices. The 150 day period would actually result

in persons “abandoning” their work having a longer time to file a notice of lien than

a lienor who finishes a job. Such would be contrary to public policy. Statutes should

be construed together.

The Trial Court concluded that based on the evidence presented by Mr. Boles, that

ETG did not work on the project after December 26, 2006 that could count as a permanent

improvement to the property, thus that day was the date of “abandonment”. As ETG did not

file its notice of lien within ninety days of December 26, 2006, the Court said that ETG lost

is claim of priority over the Coughlins as subsequent purchasers.

The appellant argues that the Trial Court erred when it determined that Tenn. Code

Ann. § 66-11-112 means that the sixty day period referenced in subsection (b) is to be

included as part of the ninety day period referenced in subsection (a). The Tennessee

Supreme Court, in Hayes v. Gibson County, 288 S.W.3d 334, 337 (Tenn. 2009), recently

restated the well established rules of statutory construction followed by the courts of

Tennessee as follows:

The primary rule governing our construction of any statute is to ascertain and give

-8-

effect to the legislature's intent. Walker v. Sunrise Pontiac-GMC Truck, Inc., 249

S.W.3d 301, 309 (Tenn.2008). To that end, we begin by examining the language of

the statute. Curtis v. G.E. Capital Modular Space, 155 S.W.3d 877, 881 (Tenn.2005).

In our examination of statutory language, we must presume that the legislature

intended that each word be given full effect. Lanier v. Rains, 229 S.W.3d 656, 661

(Tenn. 2007). When the language of a statute is ambiguous in that it is subject to

varied interpretations producing contrary results, Walker, 249 S.W.3d at 309, we

construe the statute's meaning by examining “the broader statutory scheme, the history

of the legislation, or other sources.” State v. Sherman, 266 S.W.3d 395, 401

(Tenn.2008). However, when the import of a statute is unambiguous, we discern

legislative intent “from the natural and ordinary meaning of the statutory language

within the context of the entire statute without any forced or subtle construction that

would extend or limit the statute's meaning.” State v. Flemming, 19 S.W.3d 195, 197

(Tenn.2000); see also In re Adoption of A.M.H., 215 S.W.3d 793, 808 (Tenn.2007)

(holding that “where the statutory language is not ambiguous ... the plain and ordinary

meaning of the statute must be given effect”). We presume that the General Assembly

is aware of its prior enactments and of decisions of the courts when enacting

legislation. Carter, 279 S.W.3d at 564.

The meaning of Tenn. Code Ann. § 66-11-112 as to when the ninety day period for

filing the notice of lien following abandonment of the project by the lienor starts to run is not

a model of clarity. In considering subsection (a) of the statute, it is clear that the triggering

event for the ninety day period is tied to the lienor’s last work, whether the lienor has

completed the project, the contract has terminated or the lienor has abandoned the project.

Subsection (a) provides: “ Such filing for record is required to be done within ninety (90)

days after the building or structure or improvement is demolished, altered and/or completed,

as the case may be, or is abandoned and the work not completed, or the contract of the lienor

expires or is terminated or the lienor is discharged . . . .” Thus, the first triggering event set

forth is “when the building, structure or improvement is demolished altered or complete."

This event clearly contemplates that the lienor has finished the work. The third triggering

event is in the event the contract has expired or the lienor is discharged. This provision

contemplates that the lienor can no longer perform the work as of the date of the discharge

or expiration of the contract. The second triggering event, set out within the same sentence

as the first and third triggering event, is that the project has been abandoned by the lienor.

When the project has been abandoned by the lienor, the lienor can no longer complete the

work as of the date of abandonment.

It is well established that courts are to construe a statute as a whole and read them in

conjunction with their surrounding parts, and view them consistently with the legislative

-9-

purpose. Kradel v. Piper Indsu., Inc., 60 S. W. 3d 744, 750 (Tenn. 2001)(citing State v.

Turner, 913 S.W.2d 158, 160 (Tenn.1995)). When subsection (a) is considered as a whole,

the second triggering event, abandonment with the work not completed, must be calculated

from the date that the lienor ceases to work. To find otherwise would create an inconsistency

in the treatment of the lienor based on the reason that the work had ceased. To interpret

subsection (a) as ETG urges, would give a lienor who abandons its work, fairly or unfairly,

an additional sixty days beyond the time afforded to a lienor who completes the work or who

is discharged before completing the work. Such an interpretation would lead to inconsistent

results and disparate treatment of otherwise similar lienors. Moreover, if the legislature had

intended that a lienor who abandoned the work be treated differently than a lienor who

completed the work or who is discharged prior to completion, the circumstance of

abandonment would not have been placed in the middle of subsection (a), between

completion and discharge. Based on the inclusion of the triggering event of abandonment

in the same sentence as the triggering events of completion and termination it is a fair

interpretation of the statute that the ninety day period for filing the notice of lien begins to

run on the date the lienor stopped work on the project. In other words, the passing of sixty

days without further work on the project causes the project to be “deemed” abandoned as of

the last day of work. As appellees point out in their brief, this interpretation of the statute

is bolstered by the following definition of the word “deem” in Black’s Law Dictionary:

deem, vb. 1. To treat (something) as if (1) it were really something else, or (2) it had

qualities that it does not have <although the document was not in fact signed until

April 21, it explicitly states that it must be deemed to have been signed on April 14>.

2. To consider, think, or judge <she deemed it necessary>.

“ ‘Deem’ has been traditionally considered to be a useful word when it is necessary

to establish a legal fiction either positively by ‘deeming’ something to be what it is

not or negatively by ‘deeming’ something not to be what it is.... All other uses of the

word should be avoided .... Phrases like ‘if he deems fit’ or ‘as he deems necessary’

or ‘nothing in this Act shall be deemed to ... ’ are objectionable as unnecessary

deviations from common language. ‘Thinks' or ‘considers' are preferable in the first

two examples and ‘construed’ or ‘interpreted’ in the third.... ‘Deeming’ creates an

artificiality and artificiality should not be resorted to if it can be avoided.” G. C.

Thornton, Legislative Drafting 99 (4th ed. 1996).

Black's Law Dictionary (8th ed. 2004).

Tenn. Code Ann. § 66-11-112(b) provides that “[a] building, structure or improvement

shall be deemed to have been abandoned . . . when there is a cessation of operation for a

period of sixty (60) days . . . .” We conclude that the legislature’s use of the word “deem”

-10-

was used to create the legal fiction that an improvement is to be considered abandoned as of

the last day of work if the work was not resumed for a period of sixty days following that

date.

Further, if the legislature had intended that a project not be considered abandoned

until the passing of sixty days after the last day of work, the legislature would have used the

word “after” in the statute as in “an improvement will be considered abandoned sixty days

after there is cessation of operation”. The legislature, however, did not use the word “after”

in § 66-11-112(b), although other sections of the lien statutes consistently calculate time

periods as happening “after” a specific event. See, Tenn. Code Ann. § 66-11-106; Tenn.

Code Ann. § 66-11-112(a); and Tenn. Code Ann. § 66-11-115(a); and at least seven other

sections of the lien statutes employ the word “after” in connection with the calculation of

time periods. See Tenn. Code Ann. § 66-11-108; Tenn. Code Ann. § 66-11-112; Tenn.

Code Ann. § 66-11-1174 ; Tenn. Code Ann. § 66-11-130; Tenn. Code Ann. § 66-11-134

(b)(1); Tenn. Code Ann. § 66-11-135.

We conclude the Trial Court did not err when it held that ETG was obligated to file

its notice of lien with ninety days of the last day of lienable work on the project.

Next, appellant argues that the Trial Court erred when it refused to hold that appellant

did lienable work up to February 13, 2007.

The Trial Court, in its first Opinion, found that although ETG did erosion control

work on the property until February 13, 2006 and did not remove its equipment until

February 13, 2006, there was no permanent improvement to the property as a result of ETG’s

efforts after December 26, 2006. The Court further noted that ETG had not invoiced Seven

Lakes for any work it performed after December 26, 2006.

At trial, ETG relied on Mr. Boles’ testimony and ETG’s timesheets from February

7 through February 13, 2007 to show that it had conducted lienable work during that time

period. This testimony and the time sheets were presented by plaintiff in rebuttal. When Mr.

Boles testified as a rebuttal witness, he stated the soil erosion work done between February

7 and February 13 was work pursuant to the original contract between the parties and to his

knowledge not directed by TDEC. He characterized the soil erosion work as “new work”

and not repairs. He admitted that none of the work performed in February was invoiced to

Seven Lakes.

4

Repealed by 2007 Pub. Acts, c. 189, § 16, eff. May 18, 2007.

-11-

Although the Trial Court permitted Boles to testify as a rebuttal witness, the Court

held in the August 12, 2009 Opinion that Boles rebuttal testimony would be excluded as

“[t]echnically, the attempt to include such testimony and the exhibit was not rebuttal

testimony. It was an effort ‘to build’ ETG’s claim regarding the last day worked on the

project.” The Court also found that the rebuttal testimony contradicted Boles’ testimony

made during the case in chief, and that his testimony regarding when ETG “last worked” was

cancelled by the contradicted testimony.

The Trial Court determined that as the erosion control work Mr. Boles testified that

ETG did after December 26, 2006 was not the type of work that would qualify as “visible

commencement of operations” under Tenn. Code Ann. § 66-11-101 (17)5 , it could not qualify

as lienable work and could not be used to extend the time when the abandonment of the

project actually occurred. The evidence does not preponderate against this finding. Tenn.

R. App. P. 13(d).

The Trial Court was correct when it held in its August 2009 opinion that Boles’

“rebuttal testimony” and Exhibit 20 should by excluded because “[t]echnically, the attempt

to include such testimony and the exhibit was not rebuttal testimony. This Court, in Jessee

v. American General Life and Acc. Ins. Co., No. E2002-00182-COA-R3-CV, 2003 WL

165777 at * 10 (Tenn. Ct. App. Jan. 24, 2003) provided a definition for rebuttal evidence as

follows:

The phrase “rebuttal evidence” may be defined as evidence “which tends to explain

or controvert evidence produced by an adverse party.”... This phrase encompasses

“[a]ny competent evidence which explains or is a direct reply to, or a contradiction

of, material evidence introduced by an adverse party.... Rebuttal evidence is properly

admitted for the purpose of impeaching a witness through the use of a prior

inconsistent statement. Questions concerning the admission or rejection of rebuttal

evidence rest within the sound discretion of the trial court; and an appellate court will

not interfere with the exercise of this discretion unless it is clear on the face of the

record that the trial court has abused its discretion.

5

Tenn. Code Ann. § 66-11-101(17) defines “visible commencement of operations” as “the first

actual work of improving upon the land or the first delivery to the site of the improvement of materials which

remain thereon until actually incorporated in the improvement, of such manifest and substantial character

as to notify interested persons that an improvement is being made or is about to be made on the land.”

-12-

Jessee at * 10 (citing State v. Braden, 867 S.W.2d 750, 760 (Tenn. Cr. App.1993)).

The erosion control was not for the benefit of the Seven Lakes development but for

the benefit of ETG. Mr. Boles agreed that the maintenance work done was not a permanent

improvement. Mr Coughlin offered absolutely no testimony regarding work he observed

being done on the property by ETG after he moved into the house located on 6.36 acres of

the 150 acre subdivision on February 5, 2007. Mr. Coughlin’s sole testimony on the

condition of the property was limited to what he observed. The following colloquy was part

of his direct examination:

Q. What did your tract of property look like when you bought it?

A. Surrounding acreage it was kind of a mess. By the time I got there it was

pretty much an abandoned subdivision. I mean, there was no actual

construction work done on the surrounding acreage, the four acres that

surround the house.

Nothing in his testimony contradicts or confirms Mr. Boles’ testimony regarding the

limited maintenance work ETG performed on the property during the week of February 6 th

to February 13th of 2007. Accordingly, the “rebuttal” evidence offered by ETG through Mr.

Boles’ additional, and contradictory testimony was correctly excluded by the Trial Court.

See, Tenn. Code Ann. § 66-11-102(a).

Appellant also appeals the Trial Court’s finding that ETG’s lien did not apply to the

Coughlin home because ETG did not make any “improvements’ to the property immediately

appurtenant to the Coughlin home. This issue is pretermitted because this matter was not a

basis for the Trial Court's final judgment.

Appellee’s raise the issue of whether the Trial Court erred in not ruling that ETG’s

lien was extinguished by the Coughlin’s acquisition of part of the Jolley tract as subsequent

purchasers for valuable consideration. This issue was not raised at trial, as this Court will

not consider it on appeal. Correll v. E.I. DuPont de Nemours & Co., 207 S.W.3d 751, 757

(Tenn. 2006)(citing Simpson v. Frontier Cmty. Credit Union, 810 S.W.2d 147, 153

(Tenn.1991).

We affirm the Judgment of the Trial Court. BOA has priority over ETG as to the 1.9

acres described in Exhibit B to the Trial Court’s August 12, 2009 Memorandum Opinion and

Order. ETG has priority over BOA as to the 4.46 acres described in Attachment A, less the

real estate described in Attachment B to the Trial Court's Order.

-13-

The cost of the appeal is assessed one-half to East Tennessee Grading, Inc., and one-

half to the Coughlins and Bank of America, N.A.

_________________________________

HERSCHEL PICKENS FRANKS, P.J.

-14-

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.