The opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of - )

)

Logistics and Rental Car SARL ) ASBCA No. 63485

)

Under Contract No. FA5422-14-P-3073 et al. )

APPEARANCES FOR THE APPELLANT: Amir Moussa, Esq.

Ahmed Abdourahman Cheik, Esq.

Republic of Djibouti, Africa

APPEARANCES FOR THE GOVERNMENT: Caryl A. Potter, III, Esq.

Air Force Deputy Chief Trial Attorney

Aaron J. Weaver, Esq.

Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE ARNETT

ON THE GOVERNMENT’S MOTION FOR SUMMARY JUDGMENT

This appeal arises from a September 16, 2022 claim submitted by Logistics and

Rental Car SARL (appellant) seeking compensation for damage to numerous vehicles

that it leased to the Air Force (Air Force or the government) under multiple contracts.

The Air Force has moved for summary judgment asserting that no genuine issues of

material fact remain for hearing arising from appellant’s claim. In support of its

motion, the Air Force makes three arguments: 1) appellant’s claim consisting of

Subclaims A through G is barred by the six-year statute of limitations; 2) Subclaims E,

F, and G are barred because they were the subject of a release of claims; and

3) Subclaims A, B, and D are barred because they were addressed in a previous

contracting officer’s final decision and not timely appealed.

Because they were addressed in a prior contracting officer’s decision and not

timely appealed, we lack jurisdiction over Subclaims A, B, C, and D. Because they

were the subject of a bilateral modification and release, we deny Subclaims E, F, and

G. For these reasons as further explained herein, the government’s motion is granted.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

The Contracts:

1. In 2014-2016, the Air Force executed several contracts with appellant to

lease vehicles in support of operations at Camp Lemonnier and Chabelley Airfield in

Djibouti, Africa (R4, tabs 2, 5, 6, 9-11). The contracts at issue include Contract

Nos. FA5422-14-P-3009, FA5422-14-P-3073, FA5422-15-P-3021, and Call Order

Nos. 10, 16, and 21 issued under Blanket Purchase Agreement (BPA) No. FA5422-15-

A-3004.

2. On March 27, 2014, the Air Force awarded Contract No. FA5422-14-P-3009

to appellant (R4, tab 2 at 1). It was a firm fixed-price contract for a twelve-month

lease of three vehicles specified by the Performance Work Statement (PWS) (id. at 2).

3. On September 25, 2014, the Air Force awarded Contract No. FA5422-14-P-

3073 to appellant (R4, tab 5 at 1). It was a firm fixed-price contract for a one-month

lease of seven specified vehicles consistent with the PWS (id. at 2).

4. On December 23, 2014, the Air Force awarded Contract No. FA5422-15-P-

3021 to appellant (R4, tab 6 at 1). It was a firm fixed-price contract for a 40-day lease

of seven specified vehicles consistent with the PWS (id. at 2).

5. On October 1, 2015, the Air Force awarded Call Order No. 10 under BPA

FA5422-15-A-3004 (hereinafter “the BPA”) to appellant (R4, tab 9 at 1). It was a firm

fixed-price contract for a three-month lease of twelve vehicles specified by the PWS

(id. at 2).

6. On April 1, 2016, the Air Force awarded Call Order No. 16 under the BPA

to appellant (R4, tab 10 at 1). It was a contract for a three-month lease of eight

specified vehicles consistent with the PWS (id. at 3-4).

7. On July 1, 2016, the Air Force awarded Call Order No. 21 under the BPA to

appellant (R4, tab 11 at 1). It was a contract for a three-month lease of four specified

vehicles in accordance with the PWS (id. at 3).

Appellant’s First Claim:

8. On June 30, 2020, appellant submitted a claim seeking $274,464.77 for

vehicle damage and repairs arising under several call orders issued against the BPA

(R4, tab 25).

9. On October 14, 2020, the contracting officer issued a final decision finding

merit associated with appellant’s June 30, 2020 claim (R4, tab 25 at 1-2).

10. On December 11, 2020, the parties executed Modification No. P00006 on

BPA Call Order 0029 in the amount of $293,019.63 which included “[p]ayment of

certified claim for vehicle damages and accident repairs in the amount of $274,464.77”

for the June 30, 2020 claim plus $18,554.86 for other unpaid services (R4, tab 43g

2

at 1-2). Issued under the Disputes Clause, the modification was signed by both parties

and stated,

This is the FINAL PAYMENT on this Blanket Purchase

Agreement (BPA). As a result, ALL calls will be closed

allowing for successful closeout of the entire BPA. EL

Company, Logistics & Rental Car, S.A.R.L. releases and

discharges the Government, its officers, agents and

employees, of and from all liabilities, obligations and

claims whatsoever in law and equity arising out of or by

virtue of this contract.

(Id. at 1)

11. On December 12, 2020, appellant signed a “Release of Claims” for the

BPA which stated, in consideration of the sum of $293,019.63, appellant “does release

and discharge the Government . . . from all liabilities, obligations and claims

whatsoever in law and equity arising out of or by virtue of said contract” except any

claims specified (R4, tab 47 at 1). Appellant did not list any claims to be excluded

from the Release (id.).

12. On February 16, 2021, appellant received an electronic payment of

$293,019.63 for Call Order 0029 on the BPA (R4, tab 43h at 1). On February 17,

2021, appellant confirmed receipt of the payment (R4, tab 48 at 1).

13. We find that appellant released its right to further compensation under the

BPA through its execution of Modification No. P00006, the release of claims, and

acceptance of final payment on the BPA.

Appellant’s Second Claim:

14. On October 29, 2021, appellant submitted a claim (the “Second Claim”) for

$136,757.76 for damage to vehicles leased under three contracts: Nos. FA5422-14-P-

3009, FA5422-14-P-3073, and FA5422-15-P-3021 (R4, tab 27). The Second Claim

sought payment for four invoices 1 (id.).

A. Contract No. FA5422-14-P-3009, Invoice 00132540A-14, requested

$75,776.21 (id. at 6-7). Dated October 2, 2014, this invoice was for

1

The Second Claim does not label the invoices A-D. We have added labels to identify each

subclaim of the Second Claim and listed them in the same sequence as they later

appear in the Third Claim.

3

“Cost Repair Rollover Vehicle” for two vehicles with Vehicle Plate

Nos. 405D40 and 901D41 (id.).

B. Contract No. FA5422-14-P-3073, Invoice 6232A-15, requested

$21,300.45 for Vehicle Plate No. 45D59 (id. at 8-9). Dated October 16,

2014, this invoice listed “Vehicle Wrecked” as the description (id.).

C. Contract No. FA5422-14-P-3009, Invoice 120002A-15, requested

$27,440.00 for Vehicle Plate No. 341D43 (id. at 2-3). Dated

September 1, 2015, the invoice was for “Cost Repair Vehicle Rollover-

Reform” (id.).

D. Contract No. FA5422-15-P-3021, Invoice 002400A-15, requested

$12,241.10 for Vehicle Plate No. 488D60 (id. at 4-5). Dated January 20,

2015, this invoice was for repair of “BACK WINDOW, Front Window

& Damage” (id.).

15. On November 22, 2021, the contracting officer issued a final decision

denying appellant’s Second Claim and stated the basis for denial (R4, tab 32 at 1-2).

The decision stated that it was final and set forth appellant’s right to appeal under the

Contract Disputes Act (CDA) within 90 days from receipt (id. at 1-2).

16. Appellant received the decision denying the Second Claim on

November 22, 2021 (R4, tab 31 at 1). On November 22, 2021 and November 26,

2021, appellant posed questions to which the contracting officer responded that the

claim had been denied and re-sent the final decision (R4, tabs 33-34).

17. There has been no assertion and we find no evidence that appellant

appealed the November 22, 2021 contracting officer’s final decision within the 90-day

window required by the CDA.

Appellant’s Third Claim:

18. On September 16, 2022, appellant submitted a claim (the “Third Claim”)

for $550,350.67 for damages to leased vehicles (R4, tab 13b). It sought payment for

seven invoices labelled A through G (hereinafter “Subclaims A-G”).

A. Contract No. FA5422-14-P-3009, Invoice 00132540A-14, requested

$75,776.21 (id. at 1, 3). Dated October 2, 2014, this invoice was for

“Cost Repair Rollover Vehicle” for vehicles with Plate Nos. 405D40 and

901D41 (app. supp. R4, tab 24e).

4

B. Contract No. FA5422-14-P-3073, Invoice 6232A-15, requested

$21,300.45 for Vehicle Plate No. 45D59 (R4, tab 13b at 1, 3; app. supp.

R4, tab 24h). Dated October 16, 2014, this invoice listed “Vehicle

Wrecked” as the description (app. supp. R4, tab 24h).

C. Contract No. FA5422-14-P-3009, Invoice 120002A-15, requested

$27,440.00 for Vehicle Plate No. 341D43. Dated September 1, 2015,

the invoice was for “Cost Repair Vehicle Rollover-Reform”. (R4,

tab 13b at 2-3; app. supp. R4, tab 24f)

D. Contract No. FA5422-15-P-3021, Invoice 002400A-15, requested

$12,241.10. Dated January 20, 2015, this invoice was for repair of

Vehicle Plate No. 488D60. (R4, tab 13b at 2-3; app. supp. R4, tab 24g)

E. BPA FA5422-15-A-3004-0010, Invoice 0060A-15, requested

$97,500.00 (R4, tab 13b at 2-3). This invoice sought payment for repair

of three wrecked vehicles (app. supp. R4, tab 24j).

F. BPA FA5422-15-A-3004-0016, Invoice 00215A-16, requested

$161,128.30 (R4, tab 13b at 2-3). This invoice was for costs associated

with four wrecked vehicles (app. supp. R4, tab 24k).

G. BPA FA5422-15-A-3004-0021, Invoice 0010A-16, requested

$154,964.61 (R4, tab 13b at 2-3). This invoice sought payment for

repair of three rollover vehicles (app. supp. R4, tab 24i).

19. We find that Subclaims A, B, C, and D of appellant’s Third Claim are

duplicative with the four items presented in appellant’s Second Claim. Thus, we find

that Subclaims A, B, C, and D of the Third Claim were denied with appellant’s Second

Claim in the final decision issued on November 22, 2021, and not timely appealed to

the Board.

20. Further, we find that Subclaims E, F, and G arise from the BPA

(No. FA5422-15-A-3004) which was the subject of bilateral Modification No. P00006,

the release of claims, and final payment to appellant in the amount of $293,019.63.

We have found that appellant released its right to further compensation under this BPA

(SOF ¶ 13).

21. On November 17, 2022, the contracting officer issued a final decision

denying appellant’s Third Claim (R4, tab 13a).

5

Appellant’s Appeal:

22. On December 16, 2022, appellant appealed the contracting officer’s

November 17, 2022 decision denying the Third Claim. The Board docketed the appeal

as ASBCA No. 63485.

23. Appellant’s Complaint seeks a total of $815,455.87 which includes the

amount sought in the Third Claim of $550,350.67 plus interest over five years in the

amount of $165,105.20 plus “damages of interest” in the amount of $100,000.

DECISION

I. The Parties’ Contentions

The Air Force asserts that no genuine issues of material fact remain in dispute

as to the seven subclaims set forth in appellant’s Third Claim which is the basis of this

appeal. First, the Air Force argues that 14 of the 15 vehicles in Subclaims A through

G are barred by the six-year statute of limitations under the CDA (gov’t mot. at 14-

16). Next, the Air Force contends that Subclaims E, F, and G are barred because they

were the subject of bilateral Modification No. P00006 and a release of claims (id.

at 16-18). Finally, the Air Force asserts that Subclaims A, B, and D 2 are barred

because they were addressed in a prior contracting officer’s final decision and not

timely appealed (id. at 18-20).

Appellant requests that the Board deny the government’s motion for summary

judgment (app. resp. at 1, 15). Appellant does not address the statute of limitations

issue and characterizes both Modification No. P00006 and the release of claims as

“deception[s]” (id. at 4-6). However, appellant acknowledges receipt of $293,019.63

associated with Modification No. P000006 (id. at 5). Appellant also admits receipt of

the contracting officer’s final decision on the Second Claim and that it “has not taken a

(sic) appeals” from the denial of that claim (id. at 6-7). Finally, Appellant contends

that it has not received payment for the items identified in its Third Claim (id. at 8-14).

II. Standard of Review

Summary judgment should be granted if it has been shown that there is no

genuine issue of material fact and the moving party is entitled to judgment as a matter

of law. Celotex Corp. v. Catrett, 477 U.S. 317, 322 (1986). All significant doubt over

2

Through an apparent oversight, the government omitted Subclaim C from its argument.

However, a comparison of the Second Claim to the Third Claim reveals that

Subclaims A, B, C, and D are included in both (R4, tabs 27, 13b).

6

factual issues must be resolved in favor of the party opposing summary judgment.

Mingus Constructors v. United States, 812 F.2d 1387, 1390 (Fed. Cir. 1987); United

States v. Diebold, Inc., 369 U.S. 654, 655 (1962). Our job is to “ascertain whether

material facts are disputed and whether there exists any genuine issue for trial.”

Holmes & Narver Constructors, Inc., ASBCA Nos. 52429, 52551, 02-1 BCA ¶ 31,849

at 157,393 (quoting Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 249 (1986)). To

avoid summary judgment, the nonmoving party must do more than make mere

allegations; it must assert facts sufficient to show a dispute of material fact. Mingus

Constructors, 812 F.2d at 1390-91.

Because the government’s motion raises a jurisdictional challenge to several

subclaims in this appeal, we must address the issue of jurisdiction first.

III. The Board Lacks Jurisdiction Over Subclaims A, B, C, and D.

We do not possess jurisdiction over Subclaims A, B, C, or D. The Board’s

jurisdiction is governed by the CDA which requires that each claim by a contractor be

submitted to the contracting officer for a final decision. 41 U.S.C. § 7103(a)(1). A

contractor may appeal a contracting officer’s final decision to an agency board if the

appeal is initiated within 90 days of receipt of the decision. 41 U.S.C. § 7104(a). The

90-day window is set forth by statute and cannot be waived or extended. Cosmic

Constr. Co. v. United States, 697 F.2d 1389, 1390-91 (Fed. Cir. 1982). Once a

contracting officer’s final decision is issued, that decision “is final and conclusive and

is not subject to review by any forum, tribunal, or Federal Government agency, unless

an appeal or action is timely commenced.” 41 U.S.C. § 7103(g). Therefore, the Board

lacks jurisdiction over any appeal that is untimely filed after the 90-day period. Id.

Here, Subclaims A, B, C, and D of appellant’s Third Claim were first asserted

in appellant’s Second Claim and denied by the contracting officer on November 22,

2021 (SOF ¶¶ 14, 15, 19). It is undisputed that, on November 22, 2021, appellant

received the contracting officer’s final decision denying the Second Claim (SOF ¶ 16).

The 90-day window for appellant to file a timely appeal of that decision to an agency

board elapsed on or about February 20, 2022 (SOF ¶ 17). Appellant does not allege 3

nor have we found any evidence that appellant filed a timely appeal of the decision

denying its Second Claim (app. resp. at 8; SOF ¶ 17).

Since it is undisputed that appellant did not appeal the denial of its Second

Claim, we conclude that the contracting officer’s November 22, 2021 decision

3

In para. 29 of the Statement of Undisputed Material Facts included in its motion, the

government asserts that appellant did not appeal the contracting officer’s decision

denying the Second Claim (gov’t mot. at 7). Appellant does not expressly dispute the

proposed fact (app. resp. at 8).

7

became, as a matter of law, final and conclusive, and not subject to review by this

Board. We have found that the issues asserted in appellant’s Second Claim are

duplicative with and were resubmitted as Subclaims A, B, C, and D in appellant’s

Third Claim (SOF ¶ 19). Appellant may not revive the substance of the Second Claim

by resubmitting it as Subclaims A, B, C, and D of the Third Claim. See HGI Skydyne,

ASBCA Nos. 56108, 56664, 09-2 BCA ¶ 34,303 at 169,451; Santa Fe Eng’rs, Inc.,

ASBCA No. 26883, 82-2 BCA ¶ 16,030 at 79,439 (having failed to appeal timely a

contracting officer’s final decision on one issue, the contractor could not renew the

claim later by merging it into other claims which are the subject of another final

decision). Thus, we conclude that appellant’s appeal of Subclaims A, B, C, and D is

untimely, and the Board lacks jurisdiction over Subclaims A, B, C, and D.

IV. Appellant Released Subclaims E, F, and G.

It is undisputed that appellant signed Modification No. P00006 and a release of

claims on the BPA which expressly provided for final payment and closeout of the

BPA (SOF ¶¶ 10-11). It is also undisputed that appellant received payment in the

amount of $293,019.63 as final payment on the BPA (SOF ¶ 12). We have found that

appellant released its right to further compensation under the BPA (SOF ¶ 13).

“A release is a contract whereby a party abandons a claim or relinquishes a

right that could be asserted against another.” Colorado River Materials, Inc. d/b/a

NAC Constr., ASBCA No. 57751, 13-1 BCA ¶ 35,233 at 172,991. It is interpreted in

the same manner as any other contract term or provision. See JAAAT Tech. Servs.,

ASBCA No. 61792 et al., 21-1 BCA ¶ 37,878 at 183,970 (citing Metric Constr., Inc. v.

United States, 314 F.3d 578, 579 (Fed. Cir. 2002)). When a release is clear,

unequivocal, and unconditional, the release “must be given its plain meaning and

effect.” New Iraq Ahd Co., ASBCA No. 59304, 15-1 BCA ¶ 35,849 at 175,292. Such

a release “bars any and all claims for additional compensation based upon events

occurring prior to the execution of the release.” Id. Generally, a release is binding on

both parties if it is complete on its face and reflects the contractor’s unqualified

acceptance and agreement with its terms. JAAAT Tech. Servs., 21-1 BCA ¶ 37,878

at 183,970; Inland Empire Builders, Inc. v. United States, 424 F.2d 1370, 1376 (Ct. Cl.

1970).

Here, the release language in Modification No. P000006 demonstrated the

parties’ mutual intent to “closeout” the BPA and expressly stated that appellant

“releases and discharges the Government . . . from all liabilities, obligations and

claims whatsoever in law and equity arising out of or by virtue of this contract”

(SOF ¶ 10). Contemporaneously, appellant executed a “Release of Claims” which was

appellant’s opportunity to identify any claims excluded from the release. However,

appellant accepted consideration in the amount of $293,019.63 in exchange for a full

release of claims and identified no claims to be excluded from the release. (SOF ¶ 11)

8

We find the release to be clear, unequivocal, and unconditional. Such a release bars

any and all claims for additional compensation arising from the BPA. This appeal

includes Subclaims E, F, and G which arise from the BPA. Since appellant did not

exclude these claims from the Release of Claims, we conclude that appellant released

Subclaims E, F, and G when it executed Modification No. P000006 and the Release of

Claims in December 2020. The government is entitled to summary judgment as a

matter of law. 4

CONCLUSION

The Board dismisses Subclaims A, B, C, and D for lack of jurisdiction. As to

Subclaims E, F, and G, we grant summary judgment in favor of the government. All

relief sought by appellant under its appeal is denied.

Dated: June 24, 2024

LAURA J. ARNETT

Administrative Judge

Armed Services Board

of Contract Appeals

I concur I concur

OWEN C. WILSON MICHAEL N. O’CONNELL

Administrative Judge Administrative Judge

Acting Chairman Vice Chairman

Armed Services Board Armed Services Board

of Contract Appeals of Contract Appeals

4

Having dismissed Subclaims A-D and rendered judgment in favor of the government as to

Subclaims E-G, we find it unnecessary to address the statute of limitations issue.

9

I certify that the foregoing is a true copy of the Opinion and Decision of the

Armed Services Board of Contract Appeals in ASBCA No. 63485, Appeal of Logistics

and Rental Car SARL, rendered in conformance with the Board’s Charter.

Dated: June 24, 2024

PAULLA K. GATES-LEWIS

Recorder, Armed Services

Board of Contract Appeals

10