Opinion

Bernie Cheatham d/b/a Universal Builders v. The Federal Materials Company, LLC

Court
Court of Appeals of Tennessee
Filed
Feb 21, 2012
Status
Published
On the bench
Presiding Judge Alan E. Highers
Cited by
0 cases
Authority
More cited than 29.2%

The opinion

IN THE COURT OF APPEALS OF TENNESSEE

AT JACKSON

NOVEMBER 16, 2011 Session

BERNIE CHEATHAM d/b/a UNIVERSAL BUILDERS, ET AL. v. THE

FEDERAL MATERIALS COMPANY, LLC, ET AL.

Direct Appeal from the Circuit Court for Weakley County

No. 4223 William B. Acree, Judge

No. W2011-01155-COA-R3-CV - Filed February 21, 2012

Builder was hired to construct a commercial building, and it purchased the concrete for the

building’s concrete slab from Supplier. The concrete slab developed major cracks, which

led to this lawsuit between Builder and Supplier. After a two-day bench trial, the trial court

found that Supplier had delivered defective concrete, and it entered judgment in favor of

Builder for $60,000. We affirm.

Tenn. R. App. P. 3; Appeal as of Right; Judgment of the Circuit Court Affirmed

A LAN E. H IGHERS, P.J., W.S., delivered the opinion of the Court, in which H OLLY M. K IRBY,

J., and J. S TEVEN S TAFFORD, J., joined.

Damon E. Campbell, Union City, Tennessee, for the appellant, Federal Materials Company,

LLC

James B. Webb, Brandon L. Newman, Trenton, Tennessee, for the appellees, Bernie

Cheatham and Universal Builders, LLC

OPINION

I. F ACTS & P ROCEDURAL H ISTORY

In 2005, Bernie Cheatham d/b/a Universal Builders (“Builder”) was hired by Joe

Taylor d/b/a Taylor Home Works1 to construct a commercial building in Martin, Tennessee,

that was to be used as a building supply store. As part of the project, Builder was required

to construct a six-inch-thick concrete slab for the building. Builder purchased the concrete

for the job from Federal Materials Company, LLC (“Supplier”), and the concrete was

delivered to the job site and poured on December 30, 2005. Very significant and extensive

cracks developed in the concrete slab, and the owner of the building, Joe Taylor d/b/a Taylor

Home Works, eventually sued Builder due to the defects in the concrete. In turn, Builder

filed a third party complaint against Supplier, alleging that it had supplied defective concrete

for the job.

The suit between the owner of the building and Builder was settled at mediation for

$60,000. However, the suit between Builder and Supplier went to trial. The case was tried

over the course of two days, with the parties’ presenting testimony from numerous lay

witnesses and two expert witnesses, in addition to several exhibits. At the conclusion of the

trial, the judge made lengthy findings of fact and ultimately ruled in favor of Builder, finding

that Supplier had delivered defective concrete. Accordingly, the trial court entered a

judgment against Supplier for $60,000 plus prejudgment interest.

II. I SSUES P RESENTED

Supplier presents the following issues, as we perceive them, for review:

1. Whether the evidence supports the trial court’s finding that there was something

wrong with the concrete when documentary evidence and expert testimony suggested

that the concrete was not defective; and

2. Whether the trial court failed to make a finding as to the most probable cause of the

cracking of the concrete.

For the following reasons, we affirm the decision of the circuit court.

1

According to references in the record, Taylor Home Works was formerly known as Tuck’s Home

Works and/or Tuck’s Discount Paneling and Supply Company at some times relevant to this case. However,

for ease of reference, we will refer to the business simply as “Taylor Home Works.”

-2-

III. S TANDARD OF R EVIEW

On appeal, a trial court’s factual findings are presumed to be correct, and we will not

overturn those factual findings unless the evidence preponderates against them. Tenn. R.

App. P. 13(d) (2011); Bogan v. Bogan, 60 S.W.3d 721, 727 (Tenn. 2001). For the evidence

to preponderate against a trial court’s finding of fact, it must support another finding of fact

with greater convincing effect. Watson v. Watson, 196 S.W.3d 695, 701 (Tenn. Ct. App.

2005) (citing Walker v. Sidney Gilreath & Assocs., 40 S.W.3d 66, 71 (Tenn. Ct. App. 2000);

The Realty Shop, Inc. v. RR Westminster Holding, Inc., 7 S.W.3d 581, 596 (Tenn. Ct. App.

1999)). When the resolution of the issues in a case depends upon the truthfulness of

witnesses, the fact-finder, who has the opportunity to observe the witnesses in their manner

and demeanor while testifying, is in a far better position than this Court to decide those

issues. Mach. Sales Co., Inc. v. Diamondcut Forestry Prods., LLC, 102 S.W.3d 638, 643

(Tenn. Ct. App. 2002). “The weight, faith, and credit to be given to any witness's testimony

lies in the first instance with the trier of fact, and the credibility accorded will be given great

weight by the appellate court.” Id. We review a trial court’s conclusions of law under a de

novo standard upon the record with no presumption of correctness. Union Carbide Corp.

v. Huddleston, 854 S.W.2d 87, 91 (Tenn. 1993) (citing Estate of Adkins v. White Consol.

Indus., Inc., 788 S.W.2d 815, 817 (Tenn. Ct. App. 1989)).

IV. D ISCUSSION

First, we will address Supplier’s contention that the evidence presented at trial does

not support the trial court’s conclusion that the concrete was defective. However, we must

first recount the contradictory testimony that was presented about the events of December

30, 2005, when the concrete slab was poured. Obviously, the date of the pour occurred

during the winter. The witnesses at trial agreed that it is common practice in the concrete

industry to add an accelerant, such as calcium chloride, to concrete that is poured during the

winter in order to speed up the setting or hardening process during cold weather. However,

the parties presented conflicting testimony about whether calcium chloride was actually

added to the concrete that was used for this job.

Builder had hired Mr. Robert Jackson and his concrete finishing crew to spread,

smooth, and “finish” the concrete at the Taylor Home Works site. Mr. Jackson had been in

the concrete finishing business for fifty-four years. He had worked with Builder on

numerous jobs over the past fifteen years. Mr. Jackson testified that it was he who made the

decision about whether to use an accelerant in the concrete for the Taylor Home Works job.

Mr. Jackson said that he discussed the issue with Scotty Warren, the sales representative at

Supplier, and told Mr. Warren that he wanted to use calcium chloride, at the level of two

percent, and that he wanted the bagged form of the substance brought to the job site and

-3-

poured directly into the concrete trucks there (as opposed to adding the liquid form at the

concrete plant).2 Mr. Jackson testified that when he arrived at the job site on the day of the

pour, Mr. Warren said that the calcium chloride could not be added to the trucks at the job

site because it would slow the job down and “holdup the process.” So, according to Mr.

Jackson, he told Mr. Warren to use “High-Early,” which is another accelerant that can be

added to the concrete at the concrete plant, in liquid form, as a substitute for calcium

chloride. Mr. Jackson said he knew that the High Early “wasn’t going to set it like calcium,”

but he told Mr. Warren to use it because he wanted to ensure that he could finish the job on

time.

Supplier delivered twenty-one truckloads of concrete to the job site that day,

beginning at around 7:30 a.m. Mr. Jackson explained that it is necessary to “work” the

concrete before it “sets up,” but he said that this concrete set up faster than he could keep up

with it. According to Mr. Jackson, each load of concrete would set up and harden to the

point that a man could walk on it within twenty to thirty minutes of being poured. Mr.

Jackson said that concrete with calcium chloride will normally set up within four hours, and

that this concrete set up within about 45 minutes. Mr. Jackson explained that he expected

to start using his machines to finish the concrete at about 11:30 or 12:00 that day, but that he

had to start using them immediately because the concrete was setting up so fast. Mr. Jackson

said that he had never seen concrete set up that fast before in over fifty years of finishing

concrete, and that it was as if someone had added calcium chloride to concrete on a 90 degree

summer day. Mr. Jackson said that the concrete started cracking as soon as his crew started

working on it and that the cracks were “all over” and “going everywhere” in a manner that

he had never seen.3 Mr. Jackson testified that if Supplier had been adding calcium chloride

to the concrete trucks at the job site, as he had originally requested, he could have responded

to such a problem by asking them to reduce the amount of calcium chloride or discontinue

its use altogether.

Mr. Robert Rowan worked as the superintendent for Builder on the Taylor Home

Works job, and he similarly testified that the concrete delivered by Supplier got “harder,

2

An employee of Supplier later testified that the travel time involved in a concrete delivery impacts

the effect of the calcium chloride because “the longer it’s on there, the more heat it’s going to generate.” He

said that calcium chloride added at the concrete plant would heat up more than it would when added at the

job site. The distance from the concrete plant to the job site in this case was about seventeen miles. Mr.

Jackson explained that the concrete is delivered in large trucks with rolling barrels on the back, and that in

order to add calcium chloride at the job site, it is necessary to carry the forty to fifty pound bags of calcium

chloride up a step ladder on the truck and pour them into the drum.

3

Mr. Jackson explained that he knew something was wrong with the concrete after the first

truckload was poured, but that he basically had no choice but to continue because he would not recommend

stopping a concrete pour and then coming back later to try to pour more concrete on top of it.

-4-

quicker than what it should.” Mr. Rowan testified that he had never seen concrete set up that

quickly before, and that a man could stand on the concrete within fifteen to twenty minutes

of it being poured when it would normally take about two hours for that to happen. Mr.

Rowan said he believed that there was something wrong with the concrete and that there was

nothing that anyone could have done “to save that slab.”

Mr. Bernie Cheatham, the owner of Universal Contractors (“Builder”), testified that

he was at his office on the day of the pour when he got a call from the job site supervisor,

Mr. Rowan, about the problem with the concrete. Mr. Cheatham said he drove to the Taylor

Home Works job site and arrived sometime “before lunch,” and that the concrete had already

begun to crack by that time. Mr. Cheatham said that he had never seen concrete set up as fast

as this concrete did. Mr. Cheatham said he believed that Supplier delivered bad concrete that

was improperly mixed. Mr. Cheatham explained that the cracking of this slab is not typical

concrete cracking. He said that concrete will often have shrinkage cracks, into which a knife

could barely fit, but these cracks now measure up to 7/8" wide and are nearly the width of

a quarter.

The owner of the Taylor Home Works business, Joe Taylor, testified as well. He said

that he tried to observe as much of the construction of his building as possible, so he was

present at the job site on the day that the concrete slab was poured. Mr. Taylor said he was

there from approximately 9:00 to 11:00 and that “the first thing [he] noticed was how fast the

cracking of the concrete was taking place.” Mr. Taylor explained that he had “poured

driveways and stuff like that” in the past, and that he had never seen concrete crack as

quickly as it did on this occasion. He said that the concrete “was setting up extremely fast.”

Mr. Taylor said he immediately expressed his concern to Mr. Cheatham about the fact that

the concrete did not “seem right” to him. Mr. Taylor described the cracks on the day of the

pour as “superficial” or “spider cracks,” but he said that they had grown over time and

“haven’t stopped as of today.”

Mr. Scotty Warren testified that he was the sales representative for Supplier who “sold

the job” to Mr. Cheatham, the owner of Builder. Mr. Warren explained that he was in the

office at the concrete plant in Union City on the morning of the pour when the

superintendent, Mr. Rowan, called to tell Supplier exactly what to put in the concrete. Mr.

Warren said that Mr. Jackson (the concrete finisher) was with Mr. Rowan when he called.

Mr. Warren testified that he was not involved in the decision to add calcium chloride to the

concrete. However, he said that when he heard that the order was for “straight cement mix

with two percent calcium flake and hot water,” he immediately told the acting plant manager

who was taking the order that “they do not need to put all of that stuff in there that day,

because [he] knew it was going to be up in the 50s and sunny. And that was too much, in

[his] opinion, to put in it, under the weather conditions that day.” Mr. Warren testified that

-5-

adding calcium chloride on such a warm day when the wind is blowing “pretty hard” will

make the concrete set “excessively quick,” which can cause cracking. According to Mr.

Warren, the acting plant manager “tried talking them out of it,” but Mr. Jackson wanted the

calcium chloride, and “that was pretty much the end of the story.” Mr. Warren said “we put

every bag of flake calcium that we had in the [company] pickup, and it was driven to the job

site.”

Although Mr. Warren was employed as a sales representative at Supplier, he testified

that he delivered concrete in one of the concrete trucks on the day of the pour at the Taylor

Home Works site. Mr. Warren testified that calcium chloride was added at the job site to all

four of the loads that he delivered that day. When asked who dumped the calcium chloride

into his truckloads, he replied, “I can’t exactly remember, it’s been so long, but I knew it was

put in on every load. I’m almost – most of the time, I’m the one who put it in.” Mr. Warren

said he could not remember whether he went over to the pickup truck and picked up the bags

for each of his loads.

Mr. Warren testified that the best way of adding calcium chloride to concrete at the

job site is to mix it with water and let it dissolve, then pour the solution into the drum.

However, he explained that the “normal procedure,” and the one preferred by most concrete

finishers, is to “just take the bag, dump it in the drum, have your drum in full-mix and wash

your hopper down and wash your blades down and let it mix, you know, about 8 to 10

minutes; 8 to 10 minutes is what I have always been told; about 8 minutes to mix it; that’s

what we recommend.” Mr. Warren said that for the Taylor Home Works job, the calcium

chloride was not mixed with water but was simply added to the trucks. The delivery tickets

filled out by each of the concrete truck drivers that day listed the exact times when each truck

left the plant, arrived at the job, started discharging concrete, finished discharging concrete,

left the job, and arrived back at the plant.4 According to those delivery tickets, thirteen of

the twenty-one trucks were at the job site for only ten minutes or less before they started

discharging concrete. Some of the delivery tickets indicated that trucks began discharging

concrete within five, four, three, or zero minutes of arriving on site. Mr. Warren conceded

that it would have been impossible to take the necessary steps to add the bagged calcium

chloride to the trucks and let it mix for the proper duration within such short periods of time.

Nevertheless, he testified that sometimes the times listed on the delivery tickets are not

4

Mr. Warren acknowledged that his name was not listed on any of the delivery tickets under

"Operator," but he said that was because he does not usually drive a concrete truck and the tickets were

printed with the regular driver's name on them. Mr. Jackson, the concrete finisher, testified that he had

known Mr. Warren for a long time and that he did not see him driving a concrete truck that day. Mr.

Cheatham also testified that Mr. Warren did not come to the job site while he was there for an hour before

lunch, even though a delivery ticket indicated that the truck Mr. Warren claimed to have driven was at the

job site from 11:10 to 11:45.

-6-

accurate, and also, he said, the concrete finishers sometimes get in a hurry and insist that the

drivers start pouring the concrete before the mixing process is completed. Mr. Warren

testified that poor mixing could cause discoloration, lumps, or “hot spots” where one area

sets up more than the other, but to his knowledge, it would not cause cracking. Mr. Warren

testified that he got a phone call from Mr. Cheatham during the afternoon of the date of the

pour about the cracks forming in the concrete, so he went back to the job site to look at them.

The delivery ticket from the very first truck to arrive at the job site on the day of the

pour listed Scott Dennison as the operator, and he was the driver who was allegedly replaced

by Mr. Warren. That first delivery ticket lists, in addition to the concrete delivery, 38 fifty-

pound bags of calcium chloride. The space on the delivery ticket labeled “taken by” was

signed, “Bear,” who was an employee of the finishing crew. Mr. Warren testified that two

bags of calcium chloride were added to each of the first nineteen trucks, and then when they

ran out of bags, liquid calcium chloride was added at the concrete plant to each of the last

two trucks. When asked whether it was possible that liquid calcium chloride could have been

added to all of the trucks in addition to bagged calcium chloride, Mr. Warren said he did not

think so, and that he assumed that someone simply called and asked for the liquid calcium

chloride toward the end of the job. However, he said that he really could not say what

happened because he was driving a truck and not in the office that day.

Mr. Robert Jackson, the concrete finisher, testified that he never saw any bags of

calcium chloride at the job site that day, whether on a concrete truck, a palate, or a company

pickup. He said he knew that no calcium chloride was added at the job site because of how

fast the trucks were coming and the fact that he did not see the drivers get out of the trucks

“to turn the mix around before discharging the mix.” Mr. Jackson said he did not know how

the drivers could have added calcium chloride without him noticing it.

Mr. Cheatham, the owner of Builder, testified that during the hour that he was at the

job site before lunch, he walked around the entire job site and did not see any empty bags or

unopened bags of calcium chloride. Mr. Rowan, the superintendent on the job for Builder,

testified that he was the first person to arrive at the job site that morning and the last one to

leave that evening, and he said that he did not see any bags of calcium chloride on the job site

that day, nor did he see the drivers mixing it in the trucks.

Finally, Mr. Taylor, the owner of the Taylor Home Works business, who visited the

site for two hours that day, said he did not see any fifty-pound bags at the job site. Mr.

Taylor said he saw five to ten concrete trucks come and go while he was there, and he did

not see anyone tearing open sacks and pouring them into the back of the concrete trucks.

-7-

Two expert witnesses testified as well. Dr. Ashraf Elsayed testified for Builder. Dr.

Elsayed had a Ph.D in civil engineering and was licensed as a professional engineer in fifteen

states. He was a professor of civil engineering at Arkansas State University and also the

chief engineer of geotechnology at a geotechnical firm in Memphis that does soil and

foundation engineering. Dr. Elsayed testified that he deals with the materials that go into

making and mixing concrete on a daily basis. He was also involved in concrete evaluation

and construction at his previous job in the engineering department of a company that did

highway and airport construction.

Dr. Elsayed testified that he had reviewed numerous documents and tests in

preparation for testifying in this case. He explained that calcium chloride is heavily used in

the concrete industry, and that if used correctly, it normally will not cause any problems. He

stated that the maximum recommended dosage of calcium chloride is two percent of the dry

weight of the cement. He testified that an “overdose” of calcium chloride can cause

problems like the ones in this case. Dr. Elsayed explained that he could not be 100% certain

as to the cause of these cracks because he was not at the job site on the day of the pour, “but,”

he added, “what I’ve seen indicates an overdosage of calcium chloride.” Dr. Elsayed said

that the cracks at the Taylor Home Works site are indicative of drying shrinkage, and that an

overdose of calcium chloride can accelerate and increase the amount of drying shrinkage and

cause shrinkage cracks. Dr. Elsayed testified that an overdose of calcium chloride can cause

rapid stiffening, rapid increase in drying shrinkage, and loss of strength at later ages. He also

said that improper mixing of calcium chloride can lead to concentrations of calcium chloride

in the mix which can also increase the chance of having cracks.

Dr. Elsayed testified that it normally takes two to four hours before a man can walk

on concrete after it is poured, and if calcium chloride is added, it could, depending on the

dosage, shorten that time to one hour. However, he said that if a man could walk on the

concrete at the Taylor Home Works site after thirty minutes, that would not be typical of

normal concrete and “[t]hat would be a case of an overdosage of calcium chloride.”

Supplier presented the testimony of its own expert witness, Mr. John McCord, who

held a bachelor’s degree in civil engineering and was employed as Director of Engineering

for the Kentucky Ready Mixed Concrete Association. Mr. McCord had previously worked

for the Kentucky Department of Highways as Director of Division Materials. Mr. McCord

testified that he teaches classes that allow certification for concrete testing technicians for

the American Concrete Institute. Based upon his inspection of the slab and review of various

exhibits, Mr. McCord opined that the excessive cracking of the Taylor Home Works floor

was caused by a combination of factors that created “a perfect storm.” He discussed the

preparation of the ground before the slab was poured, the design of the building, the type of

footers used for the foundation, the spacing and depth of the saw joints in the concrete, the

-8-

depth of the wire mesh reinforcement used in the concrete, the temperature of the concrete,

and the wind speed and temperature on the day of the pour as possible contributing factors

to the cracks in the concrete.

Mr. McCord said he did not believe that calcium chloride had anything to do with the

cracking; however, he based that opinion upon his belief that two percent calcium chloride

was added at the job site as requested, and he clarified that a two percent addition of calcium

chloride would not cause the floor to crack. When asked about the possibility that a “double

dose” of calcium chloride was used, Mr. McCord said that he did not see any evidence to

suggest that a double dose was added here, and that if the calcium chloride was “doubled

up,” it would have likely caused the concrete to set up in the concrete truck before it could

be poured. However, when questioned further about this testimony, Mr. McCord conceded

that he did not know what would happen if calcium chloride was added twice because he had

never heard of anyone adding that much accelerant to concrete. He said that concrete with

a double dose of calcium chloride would have such a short set up time that no one would

want to use it.5

Upon questioning by Builder’s counsel, Mr. McCord conceded that Supplier is one

of the “top ten members” of the Kentucky Ready Mixed Concrete Association, Mr.

McCord’s employer, “in terms of yards of production and equipment.” He explained that

members of the association pay annual dues based upon factors such as how many plants and

trucks they have. He also testified that the first time he went to observe the cracks at the

Taylor Home Works site, he did so as a favor to Supplier. He explained that he was in town

that day teaching a class that Supplier’s employees attended, and for which Supplier paid

attendance fees to Mr. McCord’s employer. Mr. McCord also acknowledged that “one of

the folks from [Supplier]” is on the Board of the Kentucky Ready Mixed Concrete

Association.

The trial judge made lengthy findings of fact in this case and specifically stated that

he had “a problem with Mr. McCord’s testimony.” The trial judge noted Mr. McCord’s

opinion that there was a design error involved, yet Mr. McCord admitted that he had not seen

the design plans, which were drawn up by a professional structural engineer and submitted

in accordance with local ordinances to the City of Martin. The judge said that fact “severely

impeache[d] Mr. McCord’s testimony.” The judge also discussed and rejected some of Mr.

McCord’s numerous other theories about possible causes, finding that Mr.

5

Mr. McCord acknowledged that when asked during his deposition about what would happen if

calcium chloride was added once at the plant and then again at the job site, he simply said, "the more calcium

chloride you put in, the more chance you have for . . . . probably some conditions that would be found on the

job, that kind of condition being more – again, I think being something related to a cosmetic situation."

-9-

McCord failed to provide an “adequate explanation” to support the theories. The judge

described Mr. McCord as “quite reluctant to answer a number of questions” and said he

“seemed quite evasive.” We will not belabor this discussion by explaining in detail why it

was proper for the trial judge to reject each of the many theories mentioned by Mr. McCord.

Suffice it to say that the trial judge was “‘best situated to determine the credibility of the

witnesses and to resolve factual disputes hinging on credibility determinations.’” ARC

LifeMed, Inc. v. AMC-Tennessee, Inc., 183 S.W.3d 1, 25 (Tenn. Ct. App. 2005) (quoting

Mitchell v. Archibald, 971 S.W.2d 25, 29 (Tenn. Ct. App. 1998)). We will not

“‘second-guess a trial court's credibility determinations unless there is concrete, clear, and

convincing evidence to the contrary.’” Id. We find no such evidence to contradict the

judge’s credibility determination here.

The trial judge also made an express finding that calcium chloride was not added at

the job site. The judge listed several reasons for his finding, including the fact that Mr.

Jackson (the finisher), Mr. Cheatham (the owner of Builder), and Mr. Rowan (Builder’s

superintendent) all testified that they did not see any bags of calcium chloride being added

to the nineteen truckloads of concrete. The judge also noted Mr. Jackson’s testimony that

Mr. Warren (Supplier’s sales representative) told him that he could not add the calcium

chloride as requested because it would take too long. Although Mr. Warren had testified that

calcium chloride was added at the job site, the judge explicitly stated, “I do not believe Mr.

Warren’s testimony. I do not think he is credible.” Because the factual dispute regarding

whether calcium chloride was added at the job site hinged on credibility determinations, we

will defer to the trial court’s finding that calcium chloride was not added at the site as

requested. The evidence certainly does not preponderate against such a finding.

Regarding the cause of the cracks in the concrete, Supplier claims that “the trial court

did not make a determination as to the most probable cause for the condition[.]” Supplier also

insists that “the trial court did not specifically find that [Supplier] had improperly mixed the

concrete.” We disagree with both of these assertions. Early in the trial court’s findings, the

judge did state:

In short, The Court finds that the calcium chloride was not added at the site,

which, that means no one knows exactly how it was added, whether or not it

was added properly, how much was added or whether or not that mixture was

proper. We do not know.

However, the Court went on to discuss the fact that it was undisputed that the concrete set

up very quickly and that cracks formed in the concrete extremely quickly at numerous

locations, and that the witnesses testified they had never seen that happen before. The judge

noted the testimony that a man could stand on the concrete within fifteen to twenty minutes,

-10-

and that the concrete eventually developed “really significant” cracks. The judge then stated,

“The Court concludes that from the testimony of the cracks appearing so quickly and so

severely and the fact that the concrete setup so quickly, that there was something wrong with

the concrete.” After again noting that the concrete set up “way too fast” and cracked much

more quickly and extensively than it should have, the judge recounted the testimony from

Builder’s expert witness that “an improper mixture likely caused the problem.” The judge

then stated his conclusion that Builder had proven by a preponderance of the evidence that

“the concrete was defective,” and that “it was because of the improper mixture of [the]

concrete.” As such, we find no merit in Supplier’s contentions that the trial court “did not

make a determination as to the most probable cause for the condition” and “did not

specifically find that [Supplier] had improperly mixed the concrete.”

Supplier argues on appeal that the trial judge should have given more weight to the

“reports and documents” in the record that suggested that calcium chloride was not the cause

of the cracks. Specifically, Supplier points to a report prepared by Construction Materials

Laboratory, Inc., who visited the job site and inspected the cracks in the floor slab just a few

days after the pour, at the request of Builder. The report states, in relevant part:

The slab had several areas of cracking. We were not on site at the time of the

placement of the concrete and can only list some possibilities causing the

cracking problems.

1) Windy conditions often cause these problems by allowing the concrete

to dry on the surface while the underlying mix is still in a plastic

condition.

2) Pouring the mix at a high slump.

3) Not getting the control joints sawn immediately after the finishing was

completed.

Most of the cracks appeared to be of the plastic shrinkage variety. These do

not usually present a problem as long as the reinforcement is embedded in the

concrete slab. Special attention should be given in watching for areas where

spalling of the surface of the slab might occur.

Mr. Cheatham testified that when this inspection was performed, the worst cracks were only

about 1/8" wide, and there were many other smaller, superficial “plastic cracks.” He said that

at the time of the inspection, “they didn’t dream these cracks would get as wide as they

did[.]” Regarding the possible causes listed in the report, Dr. Elsayed testified that the wind

speed on the day of the pour, which was five to fifteen miles per hour, was “not going to be

much of a factor” and was “unlikely” to cause cracks such as these. With regard to the saw

-11-

joints, there was testimony from several witnesses that the crew started cutting saw joints

before the finishing was even completed, which was earlier than usual, and that the cracking

had already begun by that time. Finally, there was no testimony presented about anyone

pouring the mix at a high slump in this case. Thus, we find no error in the trial court’s

implicit decision to give little to no weight to this report.

Next, Supplier claims that the trial court failed to give appropriate weight to a

petrographic examination of a sample of the concrete that indicated that the sample was

“good concrete.” Dr. Elsayed testified that he did not give the petrographic examination

much weight in forming his opinion because he was unable to discern where the sample was

removed from the concrete. He explained that it was possible to take good samples and bad

samples from the same concrete. The report itself states that the test was performed on one

concrete core sample that was approximately 7" in length and 2.75" in diameter. The report

also stated that “due to damage during the core extraction process, no portion of the top

surface of the core was evident; core damage extended to a depth of at least 1 ½".” The

report further stated that due to the lack of a top surface on the sample, the laboratory was

unable to evaluate “any near-surface features” such as “shrinkage cracks, etc.” The

“conclusion” section of the report lists three findings, which appear to indicate that no

problems with the concrete sample were discovered, and then it states, “Given the lack of a

top surface, . . . [we] cannot draw any other conclusions at this time.” Due to the limitations

of the petrographic examination, we cannot say that it was error for the trial court to conclude

that something was wrong with the concrete despite the results of this test.

Finally, Supplier argues that a report prepared by another expert, Mr. Richard

Chesteen, Jr., does not support the trial court’s conclusion that the concrete was defective.

Mr. Chesteen had prepared a written report for Supplier four years prior to trial, and it was

introduced as an exhibit to Dr. Elsayed’s testimony because it was one of the documents that

he had reviewed in preparation for testifying in this matter. However, Mr. Chesteen did not

testify at trial. Mr. Chesteen’s report describes him as a “Consulting Engineer.” Mr.

Chesteen’s report stated his opinion that two things “attributed to the cause of the random

cracking, spalling and joint opening of the existing floor slab.” First, he opined that it was

improper to use calcium chloride on a day when the high temperature was forecast to be 53

degrees with a wind speed of 10-15 miles per hour.6 However, as previously explained, Dr.

Elsayed testified that it was unlikely that the wind caused the cracking at issue. Dr. Elsayed

further testified that a temperature of 53 degrees would not cause the concrete to cure rapidly,

and that 53 degrees was an allowable temperature for working the concrete. The second

contributing cause listed in Mr. Chesteen’s report was that the saw joint layout and

6

At another point in Mr. Chesteen’s report he lists the wind speed on the day of the pour as 5-10

mph.

-12-

construction did not comply with industry recommendations. Mr. Chesteen said that the saw

joints were basically cut too far apart and not deep enough. However, as we have previously

mentioned, several witnesses testified that the cracking began before the saw cuts were made,

even though the crew started making the saw cuts earlier than usual. Mr. Chesteen’s report

states that “[c]ontrol joints are typically saw cut within 4 hours of fin[a]l finishing

operations,” but the number 4 is marked through, and the number 24 is handwritten beside

it. Regardless of whether the control joints are typically cut within 4 or 24 hours of final

finishing operations, however, the evidence was undisputed that the crews started the saw

cuts on this slab before the finishing crews completed their work, as soon as the cracking

began. Furthermore, as Dr. Elsayed noted, the cutting of the saw joints had absolutely

nothing to do with the concrete setting up too fast.

Even after reviewing Mr. Chesteen’s report, Dr. Elsayed continued to believe that the

main cause of the cracking was due to the addition of an improper amount of calcium

chloride. The trial court clearly agreed. We find no error in that decision.

V. C ONCLUSION

Having reviewed the entire record in this case, we find that the evidence supports the

trial court’s conclusion that Supplier delivered defective concrete that was improperly mixed.

Consequently, we affirm the trial court’s decision in its entirety. Costs of this appeal are

taxed to the appellant, Federal Materials Company, LLC, and its surety, for which execution

may issue if necessary.

_________________________________

ALAN E. HIGHERS, P.J., W.S.

-13-

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.