“[W]here language in a contract is ambiguous, summary judgment can be granted ‘if the non- moving party fails to point to any relevant extrinsic evidence supporting that party’s interpretation of the language.’”
How later courts described this case
- “[W]here language in a contract is ambiguous, summary judgment can be granted ‘if the non- moving party fails to point to any relevant extrinsic evidence supporting that party’s interpretation of the language.’”
- noting that it was “undisputed that prior to the termination of the contract, plaintiff had not voiced an objection to the invoices it received”
- “[P]laintiff was not entitled to a credit against his [contractual] obligation [to pay the defendant’s legal costs] in the amount of the payment made to the [defendant] by its insurer.”
- noting that a court may “grant some but not all of the relief requested in a summary judgment motion if it finds disputed issues of fact as to some of the issues presented”
Written by the judges who cited it.
The opinion
SOUTHERN DISTRICT OF NEW YORK
------------------------------------------------------------------x
In re: Chapter 11
NAVILLUS TILE, INC., Case No. 17-13162 (DSJ)
Debtor.
------------------------------------------------------------------x
NAVILLUS TILE, INC.,
Plaintiff,
-against- Adv. Proc. No. 17-01245 (DSJ)
CNY CONSTRUCTION 701 LLC,
Defendant.
------------------------------------------------------------------x
MEMORANDUM OPINION AND ORDER RESOLVING
NAVILLUS TILE, INC.’S MOTION FOR PARTIAL SUMMARY JUDGMENT
A P P E A R A N C E S:
PECKAR & ABRAMSON, P.C.
Counsel for Navillus Tile, Inc., d/b/a Navillus Contracting
1325 Avenue of the Americas, 10th Fl.
New York, NY 10019
By: Howard M. Rosen, Esq.
RICH, INTELISANO & KATZ, LLP
Counsel for CNY Construction 701 LLC
915 Broadway, Suite 900
New York, NY 10010
By: Daniel E. Katz, Esq.
Robert J. Howard, Esq.
Before the Court is Plaintiff Navillus Tile, Inc.’s (“Navillus”) motion for partial summary
judgment (the “Motion”). In this adversary proceeding, Navillus, a trade contractor, is suing
Defendant CNY Construction 701 LLC (“CNY”), the general contractor on a project known as
701 Seventh-Mixed Use Development, Seventh Avenue and 47th Street (the “Project”), for, inter
alia, money allegedly earned but not paid in connection with certain superstructure concrete work
and CNY (the “Contract”). [See generally ECF No. 106-9].1 CNY, in turn, is countersuing
Navillus for, inter alia, “back-charges” for costs which CNY allegedly incurred to remediate
alleged deficiencies in Navillus’s Work, and asserted “delay damages” allegedly caused by
Navillus. [ECF No. 106-10 at 9–22].
Navillus acknowledges that a trial will be required to fully resolve the parties’ dispute, but
it seeks partial summary judgment as to the following contentions: (i) Navillus is entitled to a
roughly $2,505,187 payment from CNY (the “Unpaid Total”), consisting of roughly $1,623,3282
in unpaid payment applications for Work allegedly completed (the “Unpaid Applications”)3 and
roughly $881,859 allegedly held by CNY as retainage pending completion of the Work (the
“Retainage”), all subject to a possible set-off based on disputed back-charges to be proved by
CNY at trial; (ii) CNY’s non-payment of the Unpaid Total materially breached the Contract; (iii)
CNY’s non-payment violated the New York Prompt Payment Act, N.Y. Gen. Bus. Law § 756-a et
seq. (the “PPA”); (iv) the Court should dismiss CNY’s counterclaims for delay damages on behalf
of CNY and 20 TSQ Lessee LLC, who eventually became the owner of the Project (“20 TSQ” or
the “Successor Owner”); and (v) all delay damages alleged on behalf of CNY and 20 TSQ are
contractually capped at $1,000,000. [ECF No. 105 at 1–2; ECF No. 108 at 1].
1 Unless otherwise specified, references to the Case Management/Electronic Case Filing (“ECF”) docket are to the
above-captioned adversary proceeding. Whenever possible, this Decision cites a document’s underlying pagination
in the form “ECF No. __ at __.” When that is not possible because of a document’s formatting, this Decision cites
the page number in the ECF-stamped banner at the top of the page, in the form “ECF No. __ at __ of __.” At times,
the Decision also cites paragraph or section numbers.
2 This Decision uses approximate dollar amounts due to immaterial inconsistencies and inaccuracies in Navillus’s
submissions.
3 Navillus uses the terms “payment application,” “invoice,” and “requisition” seemingly to refer to the same thing.
[E.g., Hearing Tr. at 13:3–5]. Because Navillus most frequently uses the term “payment application,” and because
the documents themselves are labeled “Application for Payment” [e.g., ECF No. 106-19 at 2 of 19], the Decision
uses that term.
2
all delay damages asserted on behalf of CNY and 20 TSQ at $1,000,000, but it is denied in all
other respects.
BACKGROUND
A. The Contract
On or about April 3, 2014, Navillus entered into the Contract with CNY to perform certain
Work on the Project. [ECF No. 116 at 1]. The scope of Navillus’s Work under the Contract
included pouring concrete and installing cast-in-place concrete columns, sheer walls, and floor
slabs on various floors of a 40-story tower. [ECF No. 108 at 1; ECF No. 106-1 at 35–53 of 78].
CNY also occasionally had Navillus perform work outside the Contract’s scope (“Extra Work”)
resulting from design changes, design issues, and differing site conditions. [ECF No. 107 at 3].
Navillus would submit “change requests” to CNY for the cost of any such Extra Work, and CNY
either would or would not approve the requests. [Id.]. The initial Contract price for Navillus’s
Work was $28,900,000 [ECF No. 108 at 1; ECF No. 106-1 at 5 of 78], but by the time Navillus
had concluded its Work the total contract price, including the price of all approved Extra Work,
was roughly $35,274,394 (the “Final Contract Price”) [ECF No. 107 at 5; ECF No. 106-19 at 2
of 19, 17 of 19].4
The Contract incorporated by reference a schedule that imposed various Project deadlines,
but, even before Navillus was to start its Work, delays from other aspects of the Project made the
originally drafted Navillus deadlines impossible. [ECF No. 108 at 11]. Even so, once Navillus
began its Work, for each month of Work, Navillus submitted a “pencil requisition” to CNY,
4 Navillus is also suing CNY for approximately $899,206 beyond the Final Contract Price for Extra Work allegedly
completed by Navillus but unapproved by CNY, but that amount is not at issue on this Motion or included in the
Final Contract Price or the Unpaid Total. [E.g., ECF No. 107 at 3–4; Tr. of Mot. Filed by the Pl. for Partial Summ.
J. (“Hearing Tr.”) at 10:3–7, June 13, 2023].
3
payment application to CNY. [ECF No. 107 at 3]. Navillus understood that CNY would then
submit Navillus’s payment applications to the owner and developer of the Project—originally, the
Witkoff Group LLC, operating as 701 Seventh Property Owner LLC (“701 Seventh” or the
“Original Owner,” and, together with the Successor Owner, the “Owners”)—along with all other
trade contractors’ payment applications as part of CNY’s own payment application. [Id.]. CNY
paid Navillus for every payment application except for the seven Unpaid Applications, which were
for a combined total of approximately $1,623,328. [Id. at 4]. According to an April 5, 2021
verified statement provided by CNY to Navillus pursuant to section 76 of the New York Lien Law,
CNY had submitted six of these seven Unpaid Applications to the Owners as part of CNY’s own
request for payment (the “Submitted Unpaid Applications”), and the Owners had paid CNY for
five of those six. [Id.; ECF No. 106-3 at 82 of 87].
By Navillus’s account as reflected in the final Unpaid Application (which Navillus
submitted to CNY on February 28, 2019, but which CNY never submitted to the Owners), all
Work was 100% complete, CNY had paid Navillus approximately $32,769,207, and CNY was
still holding approximately $881,860—2.5% of the Final Contract Price—as Retainage. [ECF No.
107 at 5; ECF No. 106-19 at 2 of 19, 17 of 19]. Thus, Navillus is seeking to recover the difference
between the $35,274,394 Final Contract Price and the $32,769,207 that CNY has already paid, or
about $2,505,187—the Unpaid Total. [ECF No. 107 at 5]. As Navillus’s counsel explained during
the Hearing, the Unpaid Total consists of “four pieces”: (i) about $914,881 for the five Submitted
Unpaid Applications for which the Owners paid CNY; (ii) about $700,022 for the one Submitted
Unpaid Application for which the Owners did not pay CNY; (iii) about $8,422 for the one Unpaid
Application which CNY did not submit to the Owners; and (iv) about $881,859 in Retainage.
[Hearing Tr. at 14:23–15:20].
4
respects and caused an additional 94 days of delay to the Project in addition to the delays that
preceded Navillus’s Work; CNY further contends that Navillus’s delays caused CNY and 20 TSQ
to incur damages. [E.g., ECF No. 106-10 at 14–15]. Specifically, CNY argues that CNY incurred
approximately $1,788,245 in expenses to remedy Navillus’s deficient Work, which CNY seeks to
recover from Navillus as back-charges; that CNY incurred approximately $3,673,144 in actual
damages caused by Navillus’s alleged delays (or that, alternatively, CNY is owed unpaid “General
Conditions Fee and Insurance” on the Project, Navillus’s portion of which is about $896,229); and
that CNY is entitled to recover $940,000 in liquidated damages caused by Navillus’s alleged delays
on behalf of 20 TSQ. [ECF No. 106-23 at 2–3].
B. The Adversary Proceeding
On December 21, 2017, Navillus filed this adversary proceeding against CNY. [ECF No.
1]. According to the currently operative version of the Complaint, Navillus is suing CNY for (i)
breach of the Contract by virtue of CNY’s alleged nonpayment of the Unpaid Total; (ii) quantum
meruit (unjust enrichment) by virtue of CNY’s alleged disapproval of—and nonpayment for—
certain Extra Work which Navillus allegedly completed; (iii) quantum meruit (unjust enrichment)
for the amounts just described in points (i) and (ii); and (iv) violation of the PPA by virtue of
CNY’s alleged nonpayment for the Submitted Unpaid Applications. [ECF No. 106-9 at 5–8]. The
Motion concerns only the claims for breach of contract and violation of the PPA.
In its Answer, CNY asserts various defenses, including that (i) “Navillus failed to discharge
its obligations under the Trade Contract with CNY, resulting in significant back-charges that are a
setoff against the amount requested by Navillus,” (ii) “Navillus failed to perform its contractual
obligations and otherwise breached the Trade Contract, and consequently, this action is barred”;
(iii) “Navillus’ claims are barred in whole or in part by setoff and/or recoupment”; (iv) “Navillus
5
committed by CNY”; (v) “Navillus’ claims are barred because any and all duties and obligations
owed by CNY have been discharged”; and (vi) “Navillus performed its work negligently.” [ECF
No. 106-10 at 7–9]. Additionally, CNY has filed counterclaims against Navillus, including for
breach of the Contract by virtue of Navillus’s alleged failure to perform its obligations thereunder.
[Id. at 18]. According to CNY, “[a]s a result of Navillus’ failures, CNY has incurred and will
continue to incur damages, both consequential and compensatory, and remains exposed to third
parties, for damages which are the responsibility of Navillus. All such damages and resulting costs
and expenses are recoverable from Navillus under the Trade Contract, in the form of back-charges
and otherwise.” [Id.]. Thus, CNY seeks damages that include, inter alia, “actual compensatory
and consequential damages, delay/extended performance-related damages, [and] liquidated
damages.” [Id. at 23]. These include $1,788,245 of disputed back-charges, which, as the parties
agree, must be tried [e.g., Hearing Tr. at 9:8–20; ECF No. 107 at 6], and alleged delay damages of
$4,613,144 ($3,673,144 of actual delay damages on CNY’s own behalf plus $940,000 of liquidated
delay damages on 20 TSQ’s behalf) [ECF No. 106-23 at 2–3], which Navillus seeks to dismiss or,
failing that, cap at $1,000,000. [ECF No. 108 at 11–23].
C. The Motion
On March 23, 2023, Navillus filed the present Motion [ECF No. 105], along with a Brief
in Support thereof [ECF No. 108] (the “Opening Brief”), an affidavit signed by Navillus’s project
manager for the Project, Olan Kenneally [ECF No. 107], a Statement of Material Facts pursuant
to Local Bankruptcy Rule 7056-1 [ECF Nos. 109], and an attorney declaration attaching 39
exhibits [ECF Nos. 106 to 106-56]. On March 24, 2023, CNY filed a letter stating that it would
not cross-move for summary judgment. [ECF No. 110]. On April 28, 2023, CNY filed its Brief
in Opposition to the Motion [ECF No. 113] (the “Opposition Brief”), along with a response to
6
[ECF No. 114] (the “Benziger Affidavit”) and Jack Mesagno [ECF No. 115]. Mr. Benziger and
Mr. Mesagno are, respectively, current and former CNY Project Executives. On May 15, 2023,
Navillus filed its Brief in Further Support of the Motion (the “Reply Brief”) [ECF No. 117], along
with another attorney declaration attaching fifteen more exhibits [ECF Nos. 118 to 118-15]. On
June 13, 2023, the Court held a hearing on the Motion (the “Hearing”).5
During the Hearing, CNY asserted without having raised the issue in briefing that the Court
lacked subject matter jurisdiction and should therefore dismiss the case. [Hearing Tr. at 43:13–
46:12]. The Court directed CNY to analyze the jurisdictional issue and either submit a proposed
joint scheduling order providing for an anticipated motion to dismiss the case or for other relief,
or, in the alternative, inform the Court that CNY had concluded that the Court has jurisdiction after
all. [Hearing Tr. at 85:3–86:19, 89:4–92:2; ECF No. 122 at 1]. On July 7, 2023, CNY filed a
letter (dated July 10) concluding that the Court does have jurisdiction over this proceeding. [ECF
No. 123]. On July 13, 2023, Navillus filed a responsive letter agreeing that the Court has
jurisdiction. [ECF No. 125]. The same day, the Court entered a Memorandum Endorsed Order
stating that the Court considered the Motion to be fully submitted and would decide the Motion in
due course. [ECF No. 126].
DISCUSSION
II. Legal Standards
A. Summary Judgment
Federal Rule of Bankruptcy Procedure 7056 makes Federal Rule of Civil Procedure (“Civil
Rule”) 56 applicable in adversary proceedings. Fed. R. Bankr. P. 7056. Civil Rule 56, in turn,
5 Transcripts of hearings typically appear on the ECF docket after they are ordered, but, as of the time of this
Decision, the Hearing transcript does not yet appear on the docket. The Court anticipates that the transcript will
appear on the docket soon.
7
the part of each claim or defense—on which summary judgment is sought. The court shall grant
summary judgment if the movant shows that there is no genuine dispute as to any material fact and
the movant is entitled to judgment as a matter of law. The court should state on the record the
reasons for granting or denying the motion.” Fed. R. Civ. P. 56(a); see also, e.g., Fleetwood Servs.,
LLC v. Richmond Cap. Grp. LLC, No. 22-1885-CV, 2023 WL 3882697, at *1 (2d Cir. June 8,
2023) (“Summary judgment is appropriate when ‘there is no genuine dispute as to any material
fact and the movant is entitled to judgment as a matter of law.’”) (quoting Fed R. Civ. P. 56(a));
Cuello v. Target Corp., No. 22 CIV. 2013, 2023 WL 4763234, at *3 (S.D.N.Y. July 26, 2023)
(same). “A dispute about a material fact is ‘“genuine” . . . if the evidence is such that a reasonable
jury could return a verdict for the nonmoving party.’ Whether a fact is material depends on the
governing substantive law—‘[o]nly disputes over facts that might affect the outcome of the suit
under the governing law will properly preclude the entry of summary judgment.’” Cuello, 2023
WL 4763234, at *3 (quoting Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986))
(alterations in original).
On a motion for summary judgment, “‘[t]he movant bears the burden of “demonstrat[ing]
the absence of a genuine issue of material fact.”’” Fleetwood Servs., 2023 WL 3882697, at *1
(quoting Oxford Univ. Bank v. Lansuppe Feeder, LLC, 933 F.3d 99, 103 (2d Cir. 2019) (quoting
Celotex Corp. v. Catrett, 477 U.S. 317, 323 (1986))) (second alteration in original). However,
“[o]nce the movant has ‘demonstrat[ed] the absence of a genuine issue of material fact . . . the onus
shifts to the party resisting summary judgment to present evidence sufficient to satisfy every
element of the claim.[’]” Pennington v. D’Ippolito, 855 F. App’x 779, 781 (2d Cir. 2021) (quoting
Holcomb v. Iona Coll., 521 F.3d 130, 137 (2d Cir. 2008) (second and third alterations in original).
Rule 56 provides that “[a] party asserting that a fact cannot be or is genuinely disputed must
8
depositions, documents, electronically stored information, affidavits or declarations, stipulations
(including those made for purposes of the motion only), admissions, interrogatory answers, or
other materials; or (B) showing that the materials cited do not establish the absence or presence of
a genuine dispute, or that an adverse party cannot produce admissible evidence to support the fact.”
Fed. R. Civ. P. 56(c)(1); see also, e.g., Pennington, 855 F. App’x at 781–82 (same).
Thus, “[t]he non-moving party ‘may not rely on mere speculation or conjecture as to the
true nature of the facts to overcome a motion for summary judgment,’” Cuello, 2023 WL 4763234,
at *3 (quoting Hicks v. Baines, 593 F.3d 159, 166 (2d Cir. 2010)), but “may defeat summary
judgment only by producing evidence of specific facts that raise a genuine issue for trial,” Ampong
v. Costco Wholesale Corp., No. 21-CV-02049, 2023 WL 4744185, at *2 (S.D.N.Y. July 25, 2023)
(citing Fed. R. Civ. P. 56(c); Anderson, 477 U.S. at 248; Davis v. New York, 316 F.3d 93, 100 (2d
Cir. 2002)); see also, e.g., Lawrence v. NYC Med. Prac., P.C., No. 1:18-CV-8649, 2023 WL
4706126, at *4 (S.D.N.Y. July 21, 2023) (“To defeat a motion for summary judgment, the non-
movant ‘must come forward with specific facts showing that there is a genuine issue for trial.’”)
(quoting Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 587 (1986)). However,
“[i]n deciding whether material factual issues exist, all ambiguities must be resolved and all
reasonable inferences must be drawn in favor of the nonmoving party.” In re Ampal-Am. Israel
Corp., No. 12-13689, 2015 WL 5176395, at *10 (Bankr. S.D.N.Y. Sept. 2, 2015) (citing
Matsushita, 475 U.S. at 587); see also, e.g., Cuello, 2023 WL 4763234, at *3 (same) (citing
Holcomb, 521 F.3d at 137; Anderson, 477 U.S. at 255). Additionally, although “[t]he court need
consider only the [parties’] cited materials,” the court “may consider other materials in the record.”
Fed. R. Civ. P. 56(c)(3).
9
stating any material fact—including an item of damages or other relief—that is not genuinely in
dispute and treating the fact as established in the case.” Fed. R. Civ. P. 56(g); see also, e.g., In re:
Residential Cap., LLC, 533 B.R. 379, 395 (Bankr. S.D.N.Y. 2015) (noting that a court may “grant
some but not all of the relief requested in a summary judgment motion if it finds disputed issues
of fact as to some of the issues presented”) (citing Fed. R. Civ. P. 56(g)). Further, the Court may
“grant summary judgment for a nonmovant” or “on grounds not raised by a party,” or “consider
summary judgment on its own.” Fed. R. Civ. P. 56(f).
B. Choice of Law
A court “need not undertake a choice of law analysis sua sponte where parties apply the
law of one state and do not dispute application of that state’s law.” 120 Greenwich Dev. Assocs.,
L.L.C. v. Admiral Indem. Co., No. 08 CIV. 6491, 2013 WL 12331487, at *5 n.4 (S.D.N.Y. Sept.
25, 2013) (citing Lehman v. Dow Jones & Co., 783 F.2d 285, 294 (2d Cir. 1986)). Here, the parties
have applied the law of only one state, New York [see generally ECF Nos. 108, 113, 117], and
when asked during the Hearing, counsel for both parties agreed that New York law governs the
issues in this New York-centered dispute [Hearing Tr. at 82:1–8]. Thus, the Court will apply New
York law without undertaking a choice of law analysis.
III. Navillus Is Not Entitled to Summary Judgment on Its Breach of Contract Claim
Navillus moves for summary judgment on its breach of contract claim. Under New York
Law, a breach of contract claim requires proof of (1) an agreement, (2) adequate performance by
the plaintiff, (3) breach by the defendant, and (4) damages. Anhui Konka Green Lighting Co. v.
Green Logic LED Elec. Supply, Inc., 625 F. Supp. 3d 269, 279 (S.D.N.Y. 2022) (citing Diesel
Props S.r.l. v. Greystone Bus. Credit II LLC, 631 F.3d 42, 52 (2d Cir. 2011)). “A party will not
be able to prevail on its breach of contract claim unless it . . . proves, by a preponderance of the
10
VSP Techs., Inc., 176 F. Supp. 3d 305, 317 (S.D.N.Y. 2016) (quotation marks and citation
omitted). “The measure of whether a party has adequately performed under a contract is
substantial performance.” Express Freight Sys. Inc. v. YMB Enters. Inc., 623 F. Supp. 3d 39, 54
(E.D.N.Y. 2022).
Navillus and CNY do not dispute that an agreement existed between them. Nor do they
dispute that CNY has not paid the Unpaid Applications, or that Navillus suffered financial loss, or
damages, from that nonpayment. Rather, at issue here is whether Navillus performed its
obligations under the Contract.
“A fundamental principle of contract law provides that the material breach of a contract by
one party discharges the contractual obligations of the non-breaching party.” Bear, Stearns
Funding, Inc. v. Interface Grp.–Nev., Inc., 361 F. Supp. 2d 283, 291 (S.D.N.Y. 2005). The
question of whether a party materially breached a contract is synonymous with whether that party
“has substantially failed to perform its side of the bargain.” Merrill Lynch & Co. Inc. v. Allegheny
Energy, Inc., 500 F.3d 171, 186 (2d Cir. 2007). Thus, “[i]f a party ‘has substantially failed to
perform its side of the bargain . . . ,’ then the other party may be excused from its breach or
nonperformance.” Body Glove IP Holdings, LP v. Exist, Inc., No. 1:21-CV-01181, 2023 WL
3568955, at *7 (S.D.N.Y. May 17, 2023) (quoting Merrill Lynch, 500 F.3d at 186).
“Substantial performance is performance, the deviations permitted being minor,
unimportant, inadvertent, and unintentional.” Bank of N.Y. Mellon Tr. Co. v. Morgan Stanley
Mortg. Cap., Inc., 821 F.3d 297, 311 (2d Cir. 2016) (citations omitted). Several fact intensive
factors bear on whether a party has substantially performed, including “the ratio of the performance
already rendered to that unperformed, the quantitative character of the default, the degree to which
the purpose behind the contract has been frustrated, the willfulness of the default, and the extent
11
Innovative Biodefense, 176 F. Supp. 3d at 317 (citation omitted). Thus, “[t]he issue of whether a
party has substantially performed is usually a question of fact and should be decided as a matter
of law only where the inferences are certain.” Merrill Lynch, 500 F.3dat 186.
For Navillus “to prevail on its motion for summary judgment with respect to its breach of
contract claim, ‘it must be clear at the outset that there are no genuine issues of material fact that
either [Navillus] did not breach an agreement, or if it did, that its breach does not rise to the
appropriate level of materiality to justify termination of the agreement.’” Body Glove, 2023 WL
3568955, at *7 (quoting Bear, Stearns., 361 F. Supp. 2d at 291). The Court therefore considers
whether there is a material dispute of fact concerning whether Navillus substantially performed
under the Contract, or whether it materially breached, as CNY contends.
Here there are material disputes of fact as to Navillus’s performance that preclude an award
of summary judgment in Navillus’s favor.
Navillus argues that its documentary evidence establishes that Navillus performed its
obligations under the Contract, meaning Navillus is legally entitled to the Unpaid Total (subject to
any disputed back-charges to be proved at trial), and CNY breached by not paying it. [See ECF
No. 108 at 9]. In support of its Motion, however, Navillus provides no direct evidence of the
quality of its Work. Rather, Navillus argues that its “burden of proof is met by the submission of
the parties’ agreement [the Contract] and unpaid invoices [the Unpaid Applications].” [ECF No.
117 at 2]. CNY disputes that it approved the Work listed in the Unpaid Applications and contends
that Navillus’s Work was of such a deficient quality that it could not have been approved under
the Contract or at common law. [See, e.g., ECF No. 113 at 6–15].
Navillus’s Unpaid Applications are clearly certified by Navillus itself, yet there is no
indication on the face of the applications that CNY approved them. [See ECF No. 106-13 to 106-
12
manager Olan Kenneally, who explained that “[e]ach month, [Navillus] would first submit a
‘pencil requisition’ and then discuss any billing issues raised by CNY. After [Navillus] reached
agreement with CNY on all billing line items, [Navillus] would certify the finalized application
for payment requisition, which would then be sent to CNY's accountant for payment.” [ECF No.
107 at 3]. Navillus appears to suggest that the Navillus-certified Unpaid Applications alone are
proof that CNY approved the Work described therein, whether because CNY forwarded them on
to the Owners, because CNY failed to dispute them with Navillus in real time, or because, in one
instance, CNY attempted to pay Navillus with a check that ultimately bounced. This contention
is not otherwise supported by the record: for example, Navillus points to no evidence that CNY
had an established practice of approving Navillus-certified payment applications by failing to
object or by submitting them to the Owners, and the Court is aware of no Contract term providing
for such approval.
Navillus also cites various cases for the proposition that submission of a signed contract
and unpaid invoices constitute prima facie evidence of breach of contract which shifts the burden
to the defendant to show a triable dispute exists. [ECF No. 108 at 8]. Each of these cases, however,
is distinguishable from the present case. See Digesare Mech., Inc. v. U.W. Marx, Inc., 176 A.D.3d
1449, 1451 & n.1, 1455, 112 N.Y.S.3d 306 (3d Dep’t 2019) (holding summary judgment should
have been granted because the subject contract expressly required the contractor to provide
“written notice” of any disapproval of a payment application, and because the defendant had made
“no showing that the contract’s written notice provisions were complied with”); George S. May
Int’l Co. v. Thirsty Moose, Inc., 19 A.D.3d 721, 722, 796 N.Y.S.2d 196 (3d Dep’t 2005) (affirming
summary judgment because the plaintiff’s invoices, which “were signed and accepted by
defendant’s president without objection,” “reflect[ed] that defendant failed to pay for services that
13
A.D.2d 617, 617, 737 N.Y.S.2d 403 (3d Dep’t 2002) (noting that it was “undisputed that prior to
the termination of the contract, plaintiff had not voiced an objection to the invoices it received”);
In re Stone Cast, Inc., No. 11-1045-1, 2014 WL 6435717, at *4 (Bankr. S.D.N.Y. Nov. 17, 2014)
(deciding breach of contract claim following trial, not on a motion for summary judgment); At&T
Corp. v. Publ’g Concepts L.P., No. 08 Civ. 7658, 2010 U.S. Dist. LEXIS 32871, at *5, *9
(S.D.N.Y. Mar. 29, 2010) (noting that defendant “acknowledges that it owes [plaintiff] some
amount” and granting summary judgment because defendant’s argument was based on plaintiff’s
failure to honor certain “oral promises” that were inadmissible in light of the subject contract’s
integration clause); Ironwoods Troy, LLC v. Optigolf Troy, LLC, 204 A.D.3d 1130, 1131, 166
N.Y.S.3d 730, 734 (3d Dep’t 2022) (granting summary judgment based on the evidence tendered,
which included, “as relevant” to the court, an affidavit, deposition testimony, the executed
agreements, and a signed statement by the nonmovant accepting delivery of all assets as-is—
submission of invoices or other unapproved payment applications was not at issue).
Here, by contrast, even if the submission of the Contract and the Unpaid Applications does
establish a prima facie case of breach, CNY has met its shifted burden “to provide competent
evidence raising a question of material fact.” In re Stone Cast, 2014 WL 6435717, at *4 (quoting
At&T, 2010 U.S. Dist. LEXIS 32871, at *8).
CNY argues that its satisfaction with Navillus’s Work was a condition of the Contract and
that triable issues of fact remain concerning whether Navillus’s Work satisfied that condition.
[ECF No. 113 at 12–13]. Under New York law, a contract may establish conditions precedent to
performance “that affect a party’s duty to render a promised performance.” Diffusion Fin. S.A.R.L.
v. Smith, No. 95 CIV. 2140, 1997 WL 272391, at *3 (S.D.N.Y. May 22, 1997). If the condition
precedent does not occur and is not excused according to the express or implied terms of the
14
LLC, No. 15-CV-7426, 2023 WL 2552831, at *7 (E.D.N.Y. Mar. 17, 2023) (“Summary judgment
should be granted in favor of a defendant accused of breach of contract where the defendant’s
contractual obligations were subject to an unsatisfied condition precedent.”). “[W]hen contract
duties are contingent upon a particular condition being ‘satisfactory’ to one party . . . that party’s
rejection of the condition is to be judged by an objective standard of reasonableness.” Blask v.
Miller, 186 A.D.2d 958, 960, 588 N.Y.S.2d 940, 942 (3d Dep’t 1992) (citations omitted); see
Rachmani Corp. v. 9 E. 96th St. Apartment Corp., 211 A.D.2d 262, 269, 629 N.Y.S.2d 382, 386
(1st Dep’t 1995) (“a party may not frustrate the performance of an agreement by bringing about
the failure of a condition precedent”).
Here, as CNY observes, the Contract expressly conditions CNY’s obligation to pay
Navillus on CNY’s satisfaction with Navillus’s Work. [See, e.g., ECF No. 106-2 at ¶¶ 5.18 (“Upon
acceptance of [Navillus’] work by [CNY] . . . [CNY] shall then forward [Navillus’] application for
final payment”) (emphasis added), 5.24 (“[CNY] expressly reserves the right to withhold from
[payment] an amount sufficient in [CNY’s judgment] to compensate it . . . where it has reason to
believe that . . . [Navillus’] Work is defective or incomplete [or] [Navillus] has failed to perform
as per the Contract”) (emphasis added), 8.04 (“Should [Navillus] fail to properly remove and
replace any rejected Work, [CNY] shall have the right to [remove and replace the work] and the
cost thereof . . . may be deducted from any payment or payments due or to become due to
[Navillus]”) (emphasis added), 18.03 (“Should [Navillus] following written notice from [CNY]
fail to correct, remove, replace and/or repair . . . defects and/or damages within the time required
by [CNY] . . . [CNY] has the right to . . . correct defects . . . and [] to deduct such costs from any
payments due [Navillus]”)] (emphasis added). Similarly, Section 8.01 of the Contract provides
that “[CNY] shall have the authority at all times to inspect and reject Work and materials which
15
Moreover, under section 8.02, Navillus is “bound by the decision of . . . [CNY] as to quality of
Work . . . [and] performance of Work.” [Id.] Indeed, according to sections 5.25 and 5.28,
respectively, the parties agreed that “[p]ayment to [Navillus] . . . is specifically agreed not to
constitute or imply acceptance [by CNY] . . . of any portion of [Navillus’s] Work,” and, similarly,
that “[n]o payment made hereunder shall . . . constitute acceptance by [CNY] of any element of
the Work. . . .” [Id.].
Thus, Navillus’s contentions are refuted and the case law Navillus cites distinguishable
because CNY was entitled to inspect and reject Navillus’s Work “at all times” and Navillus had
expressly agreed that payment of a payment application would not constitute approval of the paid-
for Work. Unlike in Digesare (relied upon by Navillus), there is no Contract provision requiring
that CNY “shall provide written notice to” Navillus “[u]pon the partial or entire disapproval by
[CNY] of [Navillus’s] application for payment,” Digesare Mech., 176 A.D.3d at 1451 n.1, and
Navillus points to no Contract provision requiring any specified form or timing of notice of
perceived deficient performance.
CNY also points to sufficient evidence to establish additional triable disputes about the
sufficiency of Navillus’s performance, such as whether CNY rejected the Work and/or the Unpaid
Applications, and whether CNY notified Navillus of any such rejections (even assuming such
notice was required). For example, Navillus itself has filed as an exhibit an excerpt of CNY’s
expert report that summarizes Navillus’s apparent delays [ECF No. 106-24], and according to
CNY “there are more specific findings in the rest of the expert report” regarding delays allegedly
caused by Navillus’s deficient Work—specifically, “concrete sagging” [Hearing Tr. at 63:11–21].
Similarly, the Benziger Affidavit details various defects in Navillus’s Work and indicates that
“[o]n numerous occasions, Navillus was notified that its work proceeded slowly and that its
16
Navillus’s exhibits—a November 20, 2017 email chain between Navillus and CNY—Navillus was
aware that CNY’s refusal to reissue the previously bounced check was because of “a potential back
charge ($800K).” [ECF No. 106-20 at 2 of 2]. Even if CNY bears the burden as to Navillus’s
performance, all of this evidence clearly presents a triable issue of fact that precludes summary
judgment.
In fact, Navillus even acknowledges as much. Navillus concedes that CNY’s interest in
certain back-charges is “disputed” and must be “proven against Navillus at trial.” [See ECF 108
at 1, 7; ECF No. 107 at 3 (Navillus’s project manager conceding same)]. Because back-charges
accrue when Navillus fails to adequately perform, a dispute of fact over back-charges equates to a
dispute of fact over Navillus’s performance sufficient to defeat summary judgment. At a
minimum, the issues appear so intertwined that the resolution of one without the other would be
inefficient, and for that reason alone the Court would exercise its discretion to deny summary
judgment even in the absence of the material fact disputes. See Toyoshima Corp. of Cali. v. Gen.
Footwear, Inc., 88 F.R.D. 559, 560 (S.D.N.Y. 1980) (quoting Fine v. City of New York, 71 F.R.D.
374, 375 (S.D.N.Y. 1976)) (“Even where the summary judgment criteria appear to be satisfied . .
. ‘the Court may deny summary judgment as a matter of discretion’ [including] where a part of the
matter which is ripe for summary judgment is intertwined with additional claims that must be
decided at trial.”); see also Indus. Tech. Ventures LP v. Pleasant T. Rowland Revocable Tr., No.
08-CV-6227, 2015 WL 1924924, at *14 (W.D.N.Y. Apr. 28, 2015) (quoting 11 Moore’s Federal
Practice, § 56.41[3][d]) (“The trial court has the right to exercise its discretion to deny a motion
for summary judgment, even if it determines that a party is entitled to it, if, in the court’s opinion,
the case would benefit from a full hearing.”).
17
denied.
IV. Navillus Is Not Entitled to Summary Judgment on Its Prompt Payment Act Claim
Navillus is not entitled to summary judgment on its PPA claim. Moreover, to the extent
that Navillus seeks damages on that claim beyond its requested recovery of statutory prejudgment
interest, the Court sua sponte holds that such damages are not available under the PPA and grants
partial summary judgment in favor of CNY on that limited issue.
A. Navillus’s Request for Summary Judgment on Its PPA Claim Is Denied
Navillus argues that it “is entitled to recovery on its Fourth Cause of Action . . . in the
amount of the non-payment plus interest at the statutory rate of 1% percent [sic] a month of the
underpayments [sic] pursuant to § 756-b(1)(b) of the PPA.” [ECF No. 108 at 10]. According to
Navillus, “[p]ursuant to PPA § 756-a(b)(ii),[6] CNY was required to pay Navillus’ payment
applications within 7 days after receipt of payment from the owner. . . . CNY failed to pay
Navillus’ payment applications within the 30 days[7] required under the PPA, and as CNY never
provided Navillus with any written communication explaining why payments were being withheld,
under § 756-a, the invoices were required to be paid in full.” [Id. at 9–10].
The plain language of the PPA forecloses Navillus’s request for summary judgment on this
basis. Section 756-b(1)(b) of the PPA provides that “[n]otwithstanding any contrary agreement,
if any interim or final payment to a subcontractor is delayed beyond the due date established in
paragraph (b) of subdivision three of section seven hundred fifty-six-a of this article [i.e., Section
6 Navillus repeatedly refers to “PPA § 756-a(b)(ii),” which does not exist. Context makes clear, however, that
Navillus intended to refer to PPA § 756-a(3)(b)(ii), which is the provision governing payments from contractors to
subcontractors.
7 As Navillus itself notes just a few lines earlier, PPA § 756-a(3)(b)(ii) refers to a time limit of “seven days,” not “30
days.” The only reference to a 30-day time limit in the PPA appears in Section 756-a(3)(a)(iii), which governs
payments from owners to contractors (not from contractors to subcontractors), and is thus inapplicable here.
18
next day, at the rate of one percent a month or fraction of a month on the unpaid balance, or at a
higher rate consistent with the construction contract.” N.Y. Gen. Bus. Law § 756-b(1)(b).
Therefore, Navillus is entitled to relief under Section 756-b(1)(b) only if CNY violated Section
756-a(3)(b), which provides, in relevant part, as follows:
The contractor or subcontractor’s payment of subcontractor or material supplier’s
interim or final invoice shall be made on the basis of a duly approved invoice of the
work performed and materials supplied during the billing cycle.
. . .
(ii) When a subcontractor has performed in accordance with the provisions of its
construction contract, the contractor shall pay to the subcontractor, and each
subcontractor shall in turn pay to its subcontractors, the full or proportionate
amount of funds received from the owner for each subcontractor’s work and
materials based on work or services provided under the construction contract, seven
days after receipt of good funds for each interim or final payment, provided all
contractually required documentation and waivers are received.
N.Y. Gen. Bus. Law § 756-a(3)(b)(ii) (emphasis added). Thus, by the very terms of the PPA, any
violation of Section 756-a(3)(b)(ii) is necessarily premised on both (a) the contractor’s approval
of an invoice, and (b) the subcontractor’s performance in accordance with the provisions of the
contract.
As discussed above, there exist several genuine issues of material fact regarding both (a)
whether CNY approved Navillus’s Unpaid Applications, and (b) whether Navillus performed in
accordance with the provisions of the Contract. See supra § III. Thus, Navillus has not shown
that it is entitled to summary judgment declaring that CNY has violated PPA § 756-a(3)(b)(ii), or
that Navillus is entitled to relief under PPA § 756-b(1)(b).
This outcome is not changed by Navillus’s observation that “[r]egarding CNY’s non-
payment of Navillus’ pay application #20 in the amount of $700,022.91, CNY testified that 701
Seventh never disapproved CNY’s invoicing of the Navillus payment, yet the owner failed to
19
or disapprove CNY’s invoice within 12 business days and issue a written statement describing the
items that are not approved.” [ECF No. 108 at 9–10]. This argument appears to be directed at the
Original Owner, but considering the Original Owner is not a party to this dispute, the argument’s
intended significance is unclear. Even construing Navillus to be arguing that a breach by the
Original Owner of its duties to CNY results in a derivative breach by CNY as to Navillus, (i)
Navillus cites no support for that argument (and the Court is aware of none), and (ii) summary
judgment is still foreclosed by the factual disputes discussed in the preceding paragraph.
Similarly, beyond the language of the Contract discussed above, the PPA itself refutes
Navillus’s complaint that “CNY never provided Navillus with any written communication
explaining why payments were being withheld, [such that,] under § 756-a, the invoices were
required to be paid in full” [id.]—in other words, that the failure to provide a written
communication (as opposed to the failure to timely pay) triggered an obligation to pay in full.
According to PPA § 756-b(2)(b)(i)(D), the remedy for “a contractor or subcontractor fail[ing] to
approve or disapprove a subcontractor’s invoice within the time limits established in paragraph (b)
of subdivision three of section seven hundred-fifty-six-a [i.e., Section 756-a(3)(b)]” is not full
payment of the invoice, but, instead, that the “subcontractor may suspend contractually required
performance . . . [but] only after providing written notice and an opportunity to cure consistent
with subparagraph (ii) of this paragraph.” N.Y. Gen. Bus. Law § 756-b(2)(b). By Navillus’s own
account, it did not avail itself of this remedy, even though it knew it was entitled to suspend
performance of the Contract. [See, e.g., ECF No. 108 at 6 (“Despite the unexcused failure of CNY
to make payments of approved applications, which entitled Navillus to suspend performance,
Navillus continued in good faith to perform the Subcontract work.”)].
20
“[d]espite the [PPA’s] strict language, New York courts have sharply limited its effect. For
example, in a Second Department case, . . . a defendant that did not respond to an invoice within
the allotted twelve days was able to present evidence that the invoiced amount was ‘subject to
various deductions for, inter alia, back charges, incorrect invoicing, and improper performance of
the work.’ The defendant’s failure to issue a written disapproval on the invoices did not bar it
from asserting defenses.” Layout, Inc. v. Heavy Metal Corp., No. 16-CV-2531, 2018 WL
2244684, at *3 (E.D.N.Y. Apr. 17, 2018) (quoting Donninger Constr., Inc. v. C.W. Brown, Inc.,
979 N.Y.S.2d 133, 135 (2d Dep’t 2014)). Therefore, summary judgment is not warranted even if
CNY did not respond to the Unpaid Applications as required by the PPA.
Accordingly, Navillus’s Motion for summary judgment on its PPA claim is denied.
B. CNY’s Informal Request for Dismissal of the PPA Claim Is Denied
In its Opposition Brief, CNY argues that, in Layout, the Eastern District “dismissed the
Prompt Payment Act claim on its own motion because ‘[t]he act has no effect on the claims and
defenses available on the underlying breach of contract claim . . . and will serve to confuse the jury
if presented as a claim separate from the underlying breach of contract [claim].” [ECF No. 113 at
20 (alterations in original) (quoting Layout, 2018 WL 2244684, at *5)]. CNY urges this Court to
“follow the Layout Court and dismiss the Prompt Payment Act claim as duplicative of the
contested breach of contract claim.” [Id.]. The Court declines to do so.
Layout determined that “[b]efore, during, and after the period when Layout invoiced Metal,
the parties exchanged emails about serious errors and met with one another, in effect
acknowledging that Metal complained in detail about Layout’s work. As a matter of law, this
satisfies the written notice requirement of the Act as it has been construed by the New York courts.
These writings and meetings put Layout on notice that its bills were disputed and why.” Layout,
21
“[t]he statute ha[d] no application to the dispute, and [would] serve to confuse the jury.” Id.
Here, it is not clear that CNY has satisfied the requirements of the PPA, so summary
judgment dismissing the PPA claim would be just as inappropriate as summary judgment in favor
of Navillus on the PPA claim. This is especially so considering that CNY not only did not file a
cross-motion for summary judgment seeking such relief, but affirmatively filed a letter with the
Court indicating that it would not cross-move for summary judgment. [ECF No. 110]. Thus,
CNY’s informal request for dismissal of the PPA claim is denied. As the Court noted during the
Hearing, any concerns about confusion at trial may be addressed through a motion in limine or
other pre-trial motion. [Hearing Tr. at 59:6–13].
C. The Court Sua Sponte Grants Summary Judgment Limiting Any Damages Under
Navillus’s PPA Claim to Statutory Interest
Although the Court declines CNY’s invitation to dismiss the PPA claim, the Court does
hold, on its own motion, that any damages recovered on the PPA claim are limited to statutory
interest provided for by the PPA.
As noted above, Navillus argues that it “is entitled to recovery on its Fourth Cause of
Action . . . in the amount of the non-payment plus interest at the statutory rate of 1% percent [sic]
a month of the underpayments [sic] pursuant to § 756-b(1)(b) of the PPA.” [ECF No. 108 at 10]
(emphasis added). Taken literally, then, Navillus’s PPA claim seeks both the Unpaid Total, and
statutory interest of 1%. Elsewhere, Navillus’s submissions suggest it may not be seeking the
Unpaid Total on its PPA claim. For example, Navillus’s Reply Brief regarding the PPA says only
that “Navillus is entitled to interest of 1% per month on its open invoices, under the Prompt
Payment Act,” [ECF No. 117 at 8], and during the Hearing, Navillus never challenged the
22
that may arise at post-trial” [Hearing Tr. at 58:20–24].
For the avoidance of doubt, the Court holds the only PPA remedy that may be available
here is the interest award that the statute requires in certain circumstances. PPA § 756-b(1)(b)
provides only for “interest, beginning on the next day, at the rate of one percent a month or fraction
of a month on the unpaid balance, or at a higher rate consistent with the construction contract.”
N.Y. Gen. Bus. Law § 756-b(1)(b). Neither this provision—which is the only PPA remedy
provision invoked by Navillus—nor any other provision of the PPA that the Court has identified
provides for recovery of the total amount invoiced. Indeed, courts have characterized the PPA as
providing only three remedies, depending on the violation: (i) statutory interest; (ii) suspension of
performance under the contract; and (iii) referral of the matter to the American Arbitration
Association. See, e.g., Layout, 2018 WL 2244684, at *3; Bank of Am., N.A. v. ASD Gem Realty
LLC, 205 A.D.3d 1, 10, 164 N.Y.S.3d 566 (1st Dep’t 2022).
Thus, the Court sua sponte grants summary judgment limiting any recovery on Navillus’s
PPA claim to statutory interest, if Navillus establishes entitlement to such an award at trial.
V. Navillus Is Not Entitled to Summary Judgment on CNY’s Delay Damages
Counterclaims
Navillus argues that it is entitled to summary judgment dismissing CNY’s counterclaims
to the extent they seek delay damages—whether on CNY’s own behalf or on behalf of 20 TSQ—
on the grounds that (i) there is no contractual basis for CNY’s recovery of delay damages from
Navillus, and (ii) neither CNY nor 20 TSQ has incurred any damages resulting from any alleged
delays. [ECF No. 108 at 11–22]. For the reasons discussed below, the Court concludes triable
disputes of fact exist as to both of these two points, precluding summary judgment.
A. Navillus Fails to Establish That There Is No Contractual Basis for CNY’s Recovery
of Delay Damages
23
Navillus argues there is no contractual basis for CNY’s recovery of delay damages from
Navillus for three reasons: first, on the theory that Section 3.02 of the Contract—which,
according to Navillus, is “convoluted,” “ambiguous,” and the only possible contractual basis for
recovery of delay damages—had been rendered “obsolete” by the time Navillus started its Work;
second, on the ground that the 94-day delay alleged by CNY is not based on Section 3.02; and
third, that CNY assertedly waived any reliance on the Contract’s “time-of-the-essence”
provisions by allowing Navillus to continue working and failing to notify Navillus of its having
caused delays to substantial completion. [ECF No. 108 at 12–14].
CNY responds that (i) Navillus’s contention that the delay damages provision is
“ambiguous” is fatal to its Motion because it establishes the existence of a triable dispute
regarding the Contract’s meaning; (ii) issues of fact exist regarding CNY’s claim that Navillus
caused 94 days of unexcused delay; (iii) earlier Project delays did not make the Contract’s time-
of-the-essence provision inapplicable to Navillus; and (iv) the Contract did not require
contemporaneous notice of delay. [ECF No. 113 at 21–25].
The Court concludes that Navillus has not shown the absence of a genuine issue of
material fact regarding possible delay damages under the Contract.
First, as Navillus acknowledges, Section 3.02 is ambiguous. That ambiguity precludes
summary judgment here for claims under that provision. “[A] motion for summary judgment
may be granted in a contract dispute only when the contractual language on which the moving
party’s case rests is found to be wholly unambiguous and to convey a definite meaning.” Topps
Co. v. Cadbury Stani S.A.I.C., 526 F.3d 63, 68 (2d Cir. 2008). “If the language is susceptible to
different reasonable interpretations . . . , then the contract’s meaning becomes an issue of fact
precluding summary judgment.” Burke v. Ulico Cas. Co., 165 F. App’x 125, 127 (2d Cir. 2006)
24
(2d Cir. 1993)); see Fed. Ins. Co. v. Am. Home Assur. Co., 639 F.3d 557, 567 (2d Cir. 2011)
(“[W]here language in a contract is ambiguous, summary judgment can be granted ‘if the non-
moving party fails to point to any relevant extrinsic evidence supporting that party’s
interpretation of the language.’”) (quoting Compagnie Financiere de CIC et de L’Union
Europeenne v. Merrill Lynch, Pierce, Fenner & Smith Inc., 232 F.3d 153, 158 (2d Cir. 2000)).
Thus, as is true here, if Section 3.02 is “ambiguous” and susceptible to more than one reading,
summary judgment is inappropriate.
Section 3.02 reads, in relevant part, as follows:
3.02 Liquidated Damages
3.02.1 Trade Contractor acknowledges that its failure to progress the Work in
accordance with the Project Schedule and the Schedule and durations shown in its
Scope of Work will result in extreme hardship to Contractor and Owner and will
irreparably interfere with Contractor's and Owner's obligations and commitments.
3.02.2 Accordingly, the parties hereby stipulate and agree that if Trade Contractor
shall fail to prosecute and complete its Work in accordance with the Project
Schedule and the Trade Contractor Schedule and fixed durations of time shown in
the Exhibit B Scope of Work including any milestone or Trade Contractor
substantial completion date, or to sufficiently progress the Work and maintain the
progress of the Project so that Other Trade Contractors, subcontractors and others
at the project may fully complete their work without acceleration to allow a
Temporary Certificate of Occupancy to be issued and the Project to achieve
Substantial, Completion no later than March 31, 2017, then Contractor can recover
its actual damages from Trade Contractor and for the benefit of Owner, liquidated
damages in the amount of Ten Thousand Dollars ($10,000) per day for each
calendar day of delay beyond that agreed to total days of Work in the Trade
Contractor’s Schedule in Exhibit B until substantial completion and its Work is
completed and accepted by Owner and Contractor. Trade Contractor acknowledges
that the liquidated damages that may be assessed against it are reasonable under the
circumstances. Owner is a third party beneficiary of this provision and may seek
recovery of said liquidated damages directly against Trade Contractor. Liquidated
damages and/or actual damages as a result of Trade Contractor’s delays shall be
capped at one million dollars ($1,000,000).
[ECF No. 106-1 at 4–5 of 78].
25
12], and when asked during the Hearing whether, “if there’s an ambiguous term with competing
possible interpretations, then you have a trial as to the appropriate meaning; yes?”, Navillus
responded, “Yes.” [Hearing Tr. at 36:1–5]. Navillus argues, however, that it is nonetheless
entitled to summary judgment because CNY “fails to provide an unambiguous interpretation of
the Trade Contract that would sustain its burden.” [ECF No. 117 at 9]. But Navillus is simply
wrong. CNY contends that, where the start date of Navillus’s Work was delayed by earlier
Project delays, the Contract’s timeliness requirement for Navillus nevertheless survives and
requires timely completion of Navillus’s Work. This is, at a minimum, a plausible reading of
Section 3.02.
This reality undermines Navillus’s position, which appears to be that, despite its
acknowledgment that Section 3.02 is “convoluted and ambiguous,” the only reasonable reading
of it is that, if Navillus itself deviated from the amount of time set forth for its Work in the
Project Schedule and Trade Contract Schedule, thus delaying Substantial Completion of the
Project beyond March 31, 2017, then Navillus would be liable for delay damages for each such
day of delay. [ECF No. 108 at 12–13]. Under this reading, because previous delays already
made the Project Schedule unrealizable before Navillus began its Work, Section 3.02 was void or
unenforceable as to Navillus by the time it started working on the Project. [Id. at 14].
Navillus’s reading may be viable, but Navillus has not shown that it is the only way to
interpret Section 3.02, nor that CNY’s competing interpretation is not also permissible.
According to CNY, “Navillus agreed that, in the event of delays to the project which are outside
Navillus’s control, the stipulated remedy is an extension of the contractual project schedule.”
[ECF No. 113 at 23–24]. CNY reasons that “[b]ecause the Contract specifically states that
Navillus is not responsible for project delay caused by others and is not being charged with any
26
and is contractually responsible for all 94 days of project delay it concedes are its own fault.”
[Id. at 25]. In other words, under CNY’s reading of Section 3.02, the references to the “Project
Schedule” and the “Trade Contract Schedule” are flexible and may be adjusted as required, and
if Navillus is responsible for additional delays to that adjusted schedule, then Navillus is liable
for delay damages that it caused.
Finally on this issue, Navillus argues that even if CNY’s reading of Section 3.02 is
correct (or at least viable), Navillus is still entitled to summary judgment because CNY never
provided Navillus an updated schedule. [Hearing Tr. at 33:10–17]. During the Hearing,
however, when asked whether Navillus “ha[d] any law saying that a failure of a general
contractor to provide a modified schedule precludes their asserting delay damages,” Navillus
responded, “I don’t think it’s a question of law providing that. It’s a question of whether or not
they can sustain their claim under this provision. This is the provision.” [Id. at 33:18–25]. But
Section 3.02 does not unambiguously require such notice. Thus, Navillus’s argument merely
presents yet another contractual ambiguity rendering summary judgment inappropriate—namely,
whether CNY was contractually obligated to provide notice of any updated schedules caused by
delays outside of Navillus’s control, as well as whether the provision is as narrow and rigid as
Navillus contends, or as flexible as CNY contends.
In sum, the parties’ competing readings of Section 3.02 are each reasonable
interpretations of the Contract, and, as a result, a trial is required and summary judgment is not
appropriate on this issue.
This conclusion is not overcome by Navillus’s other arguments. Navillus argues that
CNY waived any reliance on contractual “time-of-the-essence” provisions by allowing Navillus
to continue working without notifying Navillus of alleged delays. [ECF No. 108 at 14]. But this
27
example, whether CNY was under any obligation to notify Navillus of alleged delays [Id. at 14;
ECF No. 113 at 25]; whether Navillus’s argument is barred by the Contract’s “no-waiver”
provision [ECF No. 113 at 25–26]; and whether CNY waived its reliance on the “no-waiver”
provision [ECF No. 117 at 10]. Moreover, it may be that CNY is not even relying on a “time-of-
the-essence” provision, which appears in Section 3.01 of the Contract [ECF No. 106-1 at 4 of
78]. That section is never cited or referenced in CNY’s counterclaims. [See generally ECF No.
106-10]. Finally, even assuming CNY is relying on a time-of-the-essence provision, the only
case cited by Navillus in support of its waiver argument actually holds that allowing work to
continue following a delay does not waive the ability to recover damages for those delays.
Schenectady Steel Co. v. Bruno Trimpoli Gen. Constr. Co., 43 A.D.2d 234, 237–38 (3d Dep’t
1974), aff'd 34 N.Y.2d 939 (1974) (“By [permitting the contract to continue,] respondent at that
time waived its right to cancel for an untimely performance . . . , although it retained its right to
seek damages for the delay.”) (emphasis added).
Thus, the Court denies the Motion to the extent it seeks to dismiss CNY’s counterclaims
seeking delay damages on contractual grounds.
B. Navillus Fails to Establish That It Did Not Cause Any Delay Damages
Navillus also argues that it is entitled to summary judgment because (i) it “did not cause
any delay to Project Completion,” and (ii) even assuming Navillus did cause delays, “neither CNY
nor the Owner incurred any damages proximately caused thereby.” [ECF No. 108 at 15]. Neither
argument presents a viable basis to award summary judgment.
First, fact issues exist as to whether Navillus delayed Project Completion. Indeed, just a
few sentences before arguing that “Navillus’ schedule expert BRG, examined CNY’s schedule
updates . . . and determined that Navillus caused no delays to the Project,” Navillus notes that
28
substantial completion, contends that the Project Completion was delayed by 490 days, 94 days of
which are allocated to Navillus.” [Id.]. A factual dispute could hardly be more starkly put.
Triable fact questions also exist as to whether CNY or the Owner suffered damages
proximately caused by Navillus, notwithstanding Navillus’s contentions.
As noted above, Section 3.02 of the Contract provides that “Contractor can recover its
actual damages from Trade Contractor and for the benefit of Owner, liquidated damages in the
amount of Ten Thousand Dollars ($10,000) per day for each calendar day of delay.” [ECF No.
106-1 at 4–5 of 78]. Tracking this provision, CNY seeks actual damages on its own behalf and
liquidated damages “on behalf of the Owner 20 TSQ as successor and assign of 701 Seventh.”
[ECF No. 106-23 at 2–3]. As to 20 TSQ’s liquidated damages, CNY clams that it is entitled to
$940,000 because “[l]iquidated damages are calculated at the rate [of] $10,000.00 per day for each
day Navillus delayed completion of the project,” and Navillus allegedly caused 94 days of delay.
[Id.]. As to its own actual damages, CNY offers two alternative theories, both of which are based
on CNY’s operating costs—referred to as “General Conditions.” [Id. at 3–4]. First, CNY seeks
“actual delay damages” of $3,673,144, which CNY contends are “actual costs [] chargeable against
Navillus as a ‘Cost of the Work,’” and which was calculated by multiplying 94 days of alleged
Navillus delays by a “Daily General Conditions rate” of $39,076 (which, in turn, was “determined
by taking as a representative and typical baseline sample the General Conditions for [six] monthly
Requisitions [spanning November 30, 2016 to August 31, 2018] and computing a Daily General
Conditions rate based on those months”). [Id.]. Second, “[a]s an alternative to CNY’s actual delay
damages,” CNY seeks $896,229.33 from Navillus on the basis that “Navillus caused 19% of the
delay to the Project . . . , so Navillus is responsible for 19%” of the $4,716,996.50 “total of the
unpaid General Conditions Fee and Insurance through Requisition 75 (period ending July 31,
29
these theories, but factual questions preclude summary judgment on the issue.
First, Navillus argues that its alleged delays could not have proximately caused any of
CNY’s alleged actual delay damages because those damages are based on CNY’s “General
Conditions,” and even though CNY has not been paid all of its General Conditions for the entire
Project, CNY did “receive[] payment of its General Conditions costs” during “the period in which
Navillus allegedly delayed the Project.” [ECF No. 108 at 16–17]. This argument fails because it
ignores the possibility that substantial delays may cause damages that are not fully realized until
later on in the Project. CNY contends just that:
[A]n analysis of delay damages first requires an analysis of the total project delay
followed by an allocation of the total delay to the responsible parties. As of the
date of the February 13, 2018 purchase and sale agreement [between the Original
Owner and the Successor Owner (the “PSA”)], work on the project was still
proceeding and total project delay was still accruing. Moreover, as set forth in
CNY’s expert delay analysis, the final window period of project delay by Navillus
was still accruing between September 27, 2017 through November 13, 2018 (Nav.
Ex. 22). It was thus impossible to even ascertain the length of project delay caused
by Navillus at the time of the [PSA].
[ECF No. 113 at 32 (citing ECF No. 106-24)]. Navillus acknowledges this argument in its Reply
Brief but responds that it “ignores CNY’s Verified Second Supplemental Responses to
Interrogatories stating that all of the delays attributed to Navillus had occurred by March 3, 2018,
before the sale of the Project to 20 TSQ.” [ECF No. 117 at 11–12 (citing ECF No. 106-23)]. This
response misses CNY’s point that, regardless of the calculated end date of Navillus’s alleged
delays, neither the total project delay, the total damages attributable to those delays, nor the portion
of those damages allocable to Navillus could be calculated until all work on the Project—not just
Navillus’s—had concluded.
In further support of its argument, Navillus emphasizes that “[w]hen questioned during his
deposition, CNY’s Steve Colao did not deny that CNY received payment of its General Conditions
30
No. 108 at 17 (citing ECF No. 106-39)]. But Navillus ignores that, in the very same deposition
excerpt (which Navillus itself filed as an exhibit), Mr. Colao explained that Navillus may have
caused actual delay damages to CNY notwithstanding CNY’s receipt of its General Conditions
during the period of Navillus’s alleged delays, because delays and delay damages must be viewed
with respect to the Project as a whole, and CNY did not receive all of its General Conditions for
the entire Project:
[T]here’s a delay. Therefore there’s an extension of time. But during that time,
yes, we’re [CNY] billing your [Navillus’s] GCs [General Conditions], but there’s
an extension of time for the schedule. So there are GCs that then had to cover that
extension of time, and it’s not necessarily that you look at it where but I paid you
for April 4th, and now you’re saying there’s a delay on April 4th. It doesn’t work
that way. There’s a delay—it looks like that way—there’s an overall delay, so
there’s an extra 94 days to the schedule that at the end of the job somebody owes
me those 94 days. And our position is Navillus owes that 94 days. You’re trying
to pinpoint that those 94 days were from this date to that date. That’s used for our
calculation to be fair that this was the time period it happened, but still an extra 94
days of general conditions of which I can take the position that I have not been paid
for those 94 days because I’m still owed 5–, 6–, 7 million, whatever the number is
of general conditions at the end of this project. So—and then 94 days doesn’t
necessarily capture that whole amount, so to the extent I’m still owed that whole. I
would argue that I’m not paid those 94-day delays.
. . .
Q Now, [the $3,673,144 in actual damages alleged on CNY’s own behalf] consist
of the payments that CNY received in the period of the 94 days of delay?
A I respectfully disagree. The difference is that we are calculating the amount
using those periods. But the 94-day delay still exists and still needs to be covered.
Q It’s not a question of—what I’m asking you is: Who has incurred the damages
that are represented in that 3,674,144?
A It’s a method of calculation to say that the 94 days—the 94 days of general
conditions are the result of Navillus’s delay, and it has a value of 3.67,144 [sic] and
that we should be the beneficiary of that damage. . . . You still have to capture the
94-day delay. If—if—you know, today’s if I was paid by the owner 100 percent
GCs to the end of the job and I got captured inclusive of those the 94 days’ delay,
31
the case.
[ECF No. 106-39 at 175:5–177:18]. Whether Navillus’s alleged delays caused CNY
damages after the alleged end date of those delays is a fact question for trial, not summary
judgment.
CNY also cites cases for the proposition that “[a]ny payments that CNY has received or
may receive from any party, including Ownership, does not serve as a credit against Navillus’
liability for damages it admittedly caused by reason of 94 days of unexcused project delay.” [ECF
No. 113 at 27 (citing Isaacs v. Jefferson Tenants Corp., 270 A.D.2d 95, 704 N.Y.S.2d 71 (1st
Dep’t 2000) (“[P]laintiff was not entitled to a credit against his [contractual] obligation [to pay the
defendant’s legal costs] in the amount of the payment made to the [defendant] by its insurer.”);
Sch. Dist. of Niagara Falls v. CrossPointe, LLC, No. 08-CV-020, 2012 WL 1144618, at *2
(W.D.N.Y. Apr. 4, 2012) (“[D]amages must be calculated based on the full amount that [Plaintiff]
paid [Defendant], regardless of the fact that some of those payments were later reimbursed by [a
third party].”); ADM Inv. Servs., Inc. v. Collins, 515 F.3d 753, 755 (7th Cir. 2008) (“That a third
party reimburses part of a loss does not disable the injured person from recovering under tort or
contract law. . . . How [Plaintiff] and [a third party] settle accounts between themselves is none
of [Defendant’s] business.”))]. Navillus responds that these cases “are distinguishable in that they
involve reimbursement of a loss by a third-party,” whereas “CNY never incurred a loss because a
party to the project paid for its work.” [ECF No. 117 at 13]. This response fails because, like
Navillus’s other arguments, it ignores the possibility that Navillus’s alleged delays caused damages
which were not incurred until later.
Second, Navillus argues that its alleged delays could not have proximately caused CNY’s
“alternative” alleged actual delay damages because, when the Original Owner sold the Project to
32
according to Navillus, provided that the Successor Owner would “pay all of CNY’s costs of the
work, including all past due and future General Conditions costs,” with “no carve out or exception
to this obligation for any General Conditions attributable to the Navillus delays to the Project,”
meaning that any unpaid General Conditions were caused by the Successor Owner’s breach of the
Closeout Agreement, not by Navillus. [ECF No. 108 at 17–20]. This is a mischaracterization of
the Closeout Agreement, which actually provided that the Successor Owner would pay CNY, “on
an ongoing basis,” for “all costs and expenses of the Work, including, among other things, all
general conditions” “[w]ith respect to [CNY’s] work, labor and services performed after
December 31, 2018 (the ‘Work’).” [ECF No. 106-42 at 2 of 60] (emphasis added). By these
express terms, 20 TSQ had no obligation to pay CNY for any General Conditions incurred before
December 31, 2018, including any caused by Navillus’s alleged delays. Even if 20 TSQ had such
an obligation, Navillus cites no authority for the proposition that a party waives its ability to seek
damages merely because a third party agreed to reimburse those damages and then did not do so.
The Court declines to adopt such a rule in this case, particularly in light of the cases referenced
above, which hold that even actual reimbursement by a third party does not waive a party’s ability
to seek damages.
Third, Navillus argues that it could not have caused CNY or 20 TSQ8 to incur any actual
damages because, to help obtain financing for the sale of the Project from the Original Owner to
the Successor Owner, CNY provided the lending bank a document (the so-called “Estoppel
Certificate”) in which CNY “represent[ed] that its Work [was] in compliance with the critical path
8 Navillus also argues that, because 20 TSQ has suffered no actual damages, the Contract’s liquidated damages
provision is unenforceable, and CNY may recover no liquidated damages on behalf of 20 TSQ. [ECF No. 108 at 22
(collecting cases)]. The Court need not engage with the parties’ dueling caselaw on this issue, however, because, as
discussed below, Navillus has failed to eliminate factual issues regarding whether 20 TSQ has suffered actual
damages.
33
emphasizes that “[t]here is no reference in this document to delays to project completion by
Navillus or any other contractor” and that “Paragraph 10 of the Estoppel . . . represents that the
only known claims are listed in Exhibit E to the document,” which does not “refer to any delay
damage claim issued to Navillus.” [ECF No. 108 at 19, 21]. Thus, Navillus contends that the
Estoppel Certificate shows that “the Project was on schedule as it existed in April 2018, which
was later than the period of delays that CNY subsequently allocated to Navillus.” [Id.]. CNY
responds, however, that “[t]he April 25, 2018 schedule given to the Lender incorporates and
reflects the project delay that had then already occurred.” [ECF No. 113 at 22]. Thus, while the
Estoppel Certificate could suggest that any alleged delays by Navillus had been cured, it could
also suggest that CNY had merely updated the Project schedule to account for those alleged delays.
Similarly, while the omission of any delay damages claims from the list of CNY’s “known claims”
could suggest that CNY had (and has) no such claims, it could also suggest that CNY simply did
not incur those damages (or did not know the extent of them) until later, as discussed above.
Navillus’s reliance on the Estoppel Certificate therefore does not eliminate triable fact questions.
Fourth, Navillus argues that it could not have proximately caused 20 TSQ to incur any
actual delay damages because the PSA between the Original Owner and the Successor Owner did
not “reserv[e] any delay claims,” and, therefore, “the consideration paid by [the Successor Owner]
for the Project, by necessity, included (and was presumably adjusted for) the delayed completion
of the Project, including the 94 days of delay allegedly caused by Navillus.” [ECF No. 108 at 21–
22]. As CNY points out in response, “Navillus has not pointed to any contractual provision or
legal authority which would have required buyer and seller to ‘refer’ or ‘reserve’ their claims
against Navillus for project delay,” especially considering that “neither CNY nor Navillus are even
a party to the purchase and sale agreement.” [ECF No. 113 at 32]. Further, as CNY at least
34
Navillus] and the fact that Navllus’ delay was still accruing and had not yet been calculated,
Ownership had no duty or obligation to ‘reference’ or ‘reserve’ its delay claims against Navillus
at the time of the purchase and sale agreement.” [Id. at 33].
Finally, Navillus argues that the “Liquidating Agreement” between CNY and 20 TSQ—
that is, the separate agreement enabling CNY to pursue recovery of liquidated damages on behalf
of 20 TSQ—is “inconsistent with the Assignment of the Owner’s Navillus Claim to CNY” because
“[a]n assignment connotes a conveyance of the claim to CNY for consideration whereas a
liquidating agreement constitutes a passing through of a claim still owned by the Owner,” so the
Liquidating Agreement “is neither a legitimate pass-through claim [n]or an assignment of the
Owner’s claims.” [ECF No. 108 at 22]. This appears to be a standing argument (or something
like one), but Navillus cites no authority and provides no additional context for it, and the Court
finds it hard to follow—particularly considering that the Liquidating Agreement itself contains a
very explicit “Assignment of Claims and Causes of Action” from 20 TSQ to CNY that, by its
terms, almost certainly encompasses 20 TSQ’s right to liquidated delay damages. [ECF No. 106-
48 at 7–9 of 9 (“Assignor hereby transfers and assigns all of Assignor’s right, title, and interest in
and to all Claims . . . and causes of action . . . of every nature and description which it now has or
may hereafter have against Navillus . . . in connection with construction of the project . . . ,
including without limitation claims and causes of action against Navillus for any and all losses and
damages sustained by the Assignor, including without limitation, for all actual damages,
compensatory damages, consequential damages, liquidated damages arising out [of] or related to
Navillus’ acts or omissions arising out of, or in any way related to, the Project, whether for
deficient or non-conforming work or materials, for delays, for interference with the efficient
completion of the Project, and including Claims for breach of contract . . . .”)]. For present
35
the legitimacy and effect of the Liquidating Agreement.
Thus, for the reasons discussed above, Navillus is not entitled to summary judgment
dismissing CNY’s claims for delay damages.
VI. Navillus Is Entitled to Summary Judgment Capping Delay Damages Alleged on
Behalf of CNY and 20 TSQ at $1,000,000
Finally, Navillus is entitled to summary judgment capping any delay damages that may
ultimately be awarded to CNY and/or 20 TSQ at $1,000,000. In its Opening Brief, Navillus’s
entire argument on this point reads as follows: “Paragraphs 3.02 and 6.02 [of the Contract] provide
that any delay damage claims of CNY and the Owner are capped at $1,000,000. Since CNY has
so far refused to acknowledge this cap on delay damages, Navillus seeks a finding enforcing this
limit, only in the event, of course, that the delay claims are not dismissed.” [ECF No. 108 at 22–
23]. Navillus is correct that ¶¶ 3.02.2 and 6.02 of the Contract both provide, “Liquidated damages
and/or actual damages as a result of Trade Contractor’s delays shall be capped at one million
dollars ($1,000,000).” [ECF No. 106-1 at 5 of 78; ECF No. 106-2 at 25 of 65].
CNY appears to concede this point in its Opposition. [ECF No. 113 at 4 (referring to
“$1,000,000 in ‘capped’ delay damages”); id. at 23 (“Pursuant to Article 6 and identical provisions
of Article 3 to the Contract, based on 94 days of project delay admitted by Navillus, Navillus is
liable to CNY for liquidated damages of $10,000 per day, which is $940,000, plus ‘actual damages’
to be proven at trial, subject to an aggregate cap of $1,000,000.”). And CNY expressly conceded
the point during the Hearing [Hearing Tr. at 59:21–60:9 (CNY’s Counsel: “[T]here’s really no
legal dispute that the delay damages are capped at a million dollars. . . .” The Court: “It’s
liquidated and actual [delay damages] combined.” CNY’s Counsel: “You’re right. It is. It is
both. It’s both categories of [delay] damages are capped at a million dollars.”)].
36
grants the Motion to the limited extent that all delay damages asserted on behalf of CNY and 20
TSQ are capped at $1,000,000. This holding concerns delay damages only; it does not affect
CNY’s rights to pursue recovery of back-charges or any other types of alleged damages.
CONCLUSION
For the reasons stated above, Navillus’s Motion is denied in part and granted in part
solely as to the contractual $1,000,000 cap on delay damages; CNY’s informal request for partial
summary judgment is denied; and the Court, on its own motion, grants partial summary judgment
in favor of CNY precluding any PPA-based award to Navillus for anything other than statutorily
required interest.
It is so ordered.
Dated: New York, New York
August 7, 2023
s/ David S. Jones
Honorable David S. Jones
United States Bankruptcy Judge