Opinion

CIBA Specialty Chemical Corp. v. Township of Toms River

Court
New Jersey Tax Court
Filed
Feb 15, 2019
Status
Unpublished
Cited by
0 cases
Authority
More cited than 30.0%

The opinion

TAX COURT OF NEW JERSEY

10 S. Broad Street, 5th Floor

Hon. Mary Siobhan Brennan, J.T.C. Trenton, New Jersey 08608

JUDGE (609) 815-2922, Ext. 54560

February 14, 2019

Philip J. Giannuario Esquire

Garippa, Lotz & Giannuario

66 Park Street

Montclair, New Jersey 07042

John F. Casey, Esquire

Chiesa, Shahinian & Giantomasi P.C.

One Boland Drive

West Orange, New Jersey 07052

VIA eCourts

Re: CIBA Specialty Chemical Corp. v. Township of Dover

Docket Nos.: 005635-2004, 001986-2005, 001501-2006, 003458-2007

CIBA Specialty Chemical Corp. v. Township of Toms River

Docket Nos.: 005340-2008, 005210-2009, 004487-2010

BASF Corp. v. Township of Toms River

Docket Nos.: 004486-2010, 002155-2011, 002037-2012, 006367-2013,

003624-2014, 001913-2015, 003054-2016, 003686-2017, 001627-2018

Dear Mr. Giannuario and Mr. Casey:

This constitutes the court's opinion in the second of four trial phases in the above-

referenced matters.

1

These appeals challenge the local property tax assessments on a 1,211 1 acres tract of land

in Toms River Township, Ocean County, New Jersey, formerly known as Dover Township

(“Municipality”). Between 1952 and 1996, industrial activities occurring on the developed

sections of the land caused soil and groundwater contamination, so much so that the land and its

improvements were placed on the Superfund National Priorities List in 1983. Remediation has

been ongoing, continues to date, and is anticipated to continue for decades.

The first trial phase was held in November of 2017. In that proceeding, the court

determined that the valuation of the property must be based upon its existing industrial zoning. 2

The Municipality’s zoning ordinance is set forth as an attachment to this opinion. 3

This second phase of the trial focuses on the number of usable acreages during 2004

through 2018 tax years and the number of acres with future development potential within its

current zoning. The Taxpayer and the Municipality agree that a portion of the property cannot be

developed for reasons associated with environmental contamination. Where the parties differ on

development potential arises from the Taxpayer’s argument that future development of the clean

portions of the property will be largely prohibited based on regulations established by the Coastal

Area Facilities Review Act (“CAFRA”).

1

The 1,211 acres is a stipulated compromise acreage. Evidentiary testimony and submissions

provide a range of acreage from 1,201 to 1,220 acres.

2

The Honorable Patrick DeAlmeida, P.J.T.C. presided over phase one of the trial. The court’s

oral decision was placed on the record on November 17, 2017.

3

Certain amendments were adopted to the Municipality’s industrial zoning ordinance in 2006 and

2007, permitting certain commercial uses on the section of the taxpayer’s property that has

frontage on Route 37, and other commercial uses are allowed elsewhere on taxpayer’s property as

conditional uses.

2

For the reasons set forth below, the court finds that for the 2004 through 2018 tax years,

the entire 1,211 acres was development-prohibited due to its designation as a Superfund site and

the accompanying institutional controls in place. During those years, the highest and best use of

the property as both vacant and improved was its existing interim and impaired use as remedial

land 4 with future anticipated unrestricted development potential for 790 acres, and restricted,

limited, or prohibited development potential for the remaining 421 acres.

While there is documented presence of threatened and endangered (“T&E”) species and

habitat on the property that will undoubtedly trigger extensive CAFRA regulatory review, the

proofs presented at trial were insufficient to establish by a preponderance of the evidence that

future development of any portion of the unrestricted 790 acres would be prohibited by the United

States Environmental Protection Agency (“USEPA”) or the New Jersey Department of

Environmental Protection (“NJDEP”). The proofs, in fact, suggest that the Taxpayer anticipates

and is preparing for the development of the unrestricted 790 acres as depicted on various land use

planning maps. As to the remaining 421 acres, which represent a specific and well-delineated

portion of the property, environmental conditions and institutional controls such as deed

restrictions will limit or prohibit any future development of those acres.

The Superfund designation of the Taxpayer’s property results in a determination of value

based on the expectation of future development and use at the conclusion of remediation and the

delisting from the National Priorities List. The evidence presented during trial suggests that the

value to be attributed to the future development potential of the property during the fifteen years

4

The majority of improvements on the property were razed after industrial operations ceased in

1996.

3

at issue is influenced by a multitude of ever-changing factors, some positive and some negative.

Valuation of the property will require annual consideration of the status of the remediation, the

anticipated cost of continued cleanup, the stigma associated with the contamination, the presence

of T&E species and habitat requiring mitigation or accommodation, the location and size of the

property, anticipated and actual subdivision, and anticipated deed restrictions to name just a few.

Valuation, however, is not currently before the court.

I. FINDINGS OF FACT

A. Subject Property and Assessments Under Appeal

The property was initially owned and operated by the Toms River Chemical Company,

which eventually merged into the Ciba-Geigy Corporation. 5 In April 2009, BASF Corporation

acquired the assets and business from CIBA Specialty Chemical Corporation and accepted

responsibility for environmental remediation. For efficiency and clarity, the court will refer to the

property owner at all points in time as “Taxpayer.” 6

5

The manufacturing facility commenced operation in 1952 as the Toms River Chemical

Corporation (TRC), jointly owned by Society of Chemical Industry, Basle (CIBA), J.R. Geigy,

S.A., Basle (GEIGY), and Chemical Works, the predecessor of Sandoz Limited (SANDOZ). In

1970, the United States subsidiaries of CIBA and GEIGY merged to become CIBA-GEIGY

Corporation. From 1970 through 1981, TRC was jointly owned by CIBA-GEIGY Corporation

and SANDOZ. In 1981, Sandoz transferred all interest in the property as a result of a merger with

CIBA-GEIGY Corporation.

6

In the 2004 through 2009 complaints and docket number 004487-2010 the Taxpayer is identified

as CIBA Specialty Chemicals Corporation. In Docket number 004486-2010 and in the 2011

through 2018 complaints the Taxpayer is identified as BASF Corporation.

4

B. Subject Property and Assessments Under Appeal

In 1952, the Municipality was mostly rural in nature. Over the decades that have followed,

the Municipality has undergone significant development, and it serves as the county seat for Ocean

County. The Taxpayer’s property is currently the largest undeveloped tract in the Municipality.

It is bordered by large residential tracts to the north and south, and the West Dover Elementary

School is adjacent to it. Toms River is located along the eastern border. To the southeast is the

junction of State Highway 37 and Oak Ridge Parkway (“County Route 527”), and it is in close

proximity to the Garden State Parkway.

The property is identified as Block 411, Lot 6 7 on the Municipality tax map for years 2004

through 2014, and Block 411, Lot 6.01 8 for years 2015 through 2018 (“Subject Property”). For

the tax years in question, the Subject Property was assessed as follows:

Tax Year Land Improvements Total

2004 $20,219,500 $409,800 $20,629,300

2005 $20,219,500 $409,800 $20,629,300

2006 $20,219,500 $409,800 $20,629,300

2007 $20,219,500 $409,800 $20,629,300

2008 $20,219,500 $409,800 $20,629,300

2009 $80,459,000 $1,000 $80,460,000

2010 9 $79,926,300 $500,000 $80,426,300

7

Lot 6 is the lead tax lot for a line item that includes Lots 6, 84, 107, 124, 130 and 131.

8

Lot 6.01 is the lead tax lot for a line item that includes Lots 6.01, 6.02, and 6.03.

9

The 2010 assessment included two line items and broke down as follows:

2010 Block 411 Lot 6 $61,676,500 $500,000 $62,176,500

Block 411 Lot 107 $18,249,800 $0 $18,249,800

5

2011 $57,500,000 $500,000 $58,000,000

2012 $41,500,000 $500,000 $42,000,000

2013 $14,700,000 $27,300,000 $42,000,000

2014 $41,500,000 $500,000 $42,000,000

2015 $41,500,000 $500,000 $42,000,000

2016 $41,500,000 $500,000 $42,000,000

2017 $41,500,000 $500,000 $42,000,000

2018 $41,500,000 $500,000 $42,000,000

The Director’s (Chapter 123) ratio for the Municipality for each year under appeal was as

follows:

Tax Year Average Ratio

2004 60.25%

2005 51.43%

2006 44.23%

2007 38.71%

2008 37.40%

2009 10 100.00%

2010 102.01%

2011 101.08%

2012 102.58%

2013 11 101.08%

2014 80.48%

2015 88.42%

10

In tax year 2009, Toms River Township underwent a complete revaluation; therefore, the average

ratio does not apply.

11

In tax years 2013 and 2014, Toms River Township underwent a reassessment.

6

2016 86.78%

2017 83.70%

2018 83.42%

C. Historical Use of Property

Taxpayer first opened its plant in 1952 and became a major employer of local residents.

Taxpayer was perceived as a true community partner, sponsoring its own Boy Scout troop and fire

department. 12

Despite the large size of the property, only 320 acres were developed. The developed

portion was used for manufacturing operations, waste treatment, disposal activities, and

administrative and laboratory facilities. The manufacturing facility was composed of numerous

buildings, an industrial wastewater treatment plant, and a lined reservoir for emergency storage of

treated and untreated wastewater.

From 1952 until 1988, Taxpayer manufactured a variety of synthetic organic pigments,

organic dyestuffs and intermediates, and epoxy resins. Taxpayer disposed of chemical wastes on-

site in several locations, including a 5.2 acre drum disposal area (containing approximately

100,000 drums); a 3.9 acre lime sludge disposal area (used for disposal of inorganic wastes); a 12

12

The fire department entered into a 99-year lease with Taxpayer on February 20, 1968. The lease

provides for the use of one acre (39 Cardinal Drive) at an annual rent of $1.00 per year, with the

fire company being responsible for all taxes and assessments. The leased premises is improved

with a firehouse constructed in 1968 and expanded in 1980. The building presently houses a

Bucket Ariel fire truck, a fire engine with a 1,500-gallon pump, the Municipality’s emergency

medical service ambulances. In 2017, and the Municipality reclassified the property from 15F

Exempt to Class 4A Commercial Property and imposed an assessment of $206,700 for Tax year

2018. The fire company filed a tax appeal challenging the denial of the exemption on July 19,

2018. The matter was settled on January 3, 2019. Toms River Fire Company No. 1, Inc. v.

Township of Toms River, and BASF Corporation, Docket No. 011147 -2018.

7

acre filtercake disposal area (which received sludge from the wastewater treatment); five

backfilled lagoons comprising 8.5 acres; and a calcium sulfate disposal area.

The drum disposal area and lime sludge disposal area were closed and capped in 1978.

Additionally, at about the same time, the filtercake disposal area was also closed and covered with

soil. Over time, groundwater contamination migrated from these inactive disposal sites in an

easterly direction toward the Toms River.

The USEPA began investigating the landfill in 1980. The landfill was reportedly leaking

as early as 1981, precipitating remedial measures by the State of New Jersey (“State”) including

the issuance of a Consent Order forcing Taxpayer to close part of the landfill and monitor

groundwater and leachate.

While the manufacturing facility was in operation, it also generated liquid waste. The

liquid waste was treated on-site in a wastewater treatment plant before discharge to the Atlantic

Ocean. Wastewater was funneled from the plant to the Atlantic Ocean off of Ortley Beach in

Ocean County by means of a pipeline. In 1984, a break in the ocean outfall pipeline raised

concerns about what contaminants might be in the wastewater. In 1991, the New Jersey

Legislature ordered the shut-down of the pipeline.

In 1984, after discovering that the Taxpayer was illegally disposing of drums containing

liquids and hazardous waste in the landfill, the State ordered Taxpayer to remove 14,000 drums.

In 1985, leaking equalization basins associated with the wastewater treatment plant led Taxpayer

to close the basins and begin remediation of the contaminated plume from these basins.

Contaminants were leaking from drums, waste sludges, soils, and groundwater.

In 1992, Taxpayer and two of Taxpayer’s former executives pleaded guilty to illegally

dumping pollutants into two landfills on the company’s property and paid fines.

8

In 1995, researchers from the New Jersey Department of Health and the Federal Agency

for Toxic Substances and Diseases Registry became aware that Toms River children had a

significantly higher incidence of leukemia and brain and central nervous system cancers.

Specifically, from 1979 to 1995, 90 cases of childhood cancer were diagnosed in the Municipality

compared with the statistically expected number of 67 cases. Thereafter an epidemiological study

was conducted which found that exposure to contaminated drinking water from United Water

Toms River Parkway well field and polluted air from the Taxpayer’s property was associated with

leukemia development in young girls. 13

In March 1996, full–scale operation of the on-site groundwater treatment plant began. By

December 1996, all of Taxpayer’s industrial operations at the property ceased.

In 1999, a State and federal study determined that some Toms River residents had been

exposed to chemical pollutants from the Site that had leached into private wells and the public

drinking water system decades earlier. 14

To date, Taxpayer has spent in excess of 300 million dollars to treat groundwater and clean

up toxic waste on the property. In addition, there have been three lawsuits related to the

contamination resulting in the payment of millions of additional dollars in damage settlements and

fines.

13

The small number of cases included in the study made it impossible to draw any concrete

conclusions from the results. (http://nj.gov/health/eohs/ocean/toms_river_river-

dover_twp/vol_i.pdf)

14

See http://www.nj.gov/health/eoh/assess/cgc_pha_fnl.pdf.

9

D. Superfund Site

Superfund is the informal designation given to the Comprehensive Environmental

Response, Compensation, and Liability Act (CERCLA), National Priorities List. Established in

1980 in response to concerns over the health and environmental risks posed by hazardous waste

sites, Superfund is administered by the USEPA in cooperation with state and local governments.

The goals of Superfund are to protect human health and the environment by cleaning up polluted

sites, involving communities in the Superfund process, and making the responsible party pay for

the necessary removal and remedial actions.

In 1983, Taxpayer’s property was placed on the federal Superfund list of toxic waste sites

after an investigation by the USEPA found leaking drums of waste and high levels of cancer-

causing chemicals on the land. The Superfund site is known as the Ciba-Geigy Chemical

Corporation Site (EPA ID# NJD001502717) (“Site”), and it ranked at number 166 nationally

among 418 listed sites. Once Taxpayer’s operations ended in 1996, the buildings that housed the

Taxpayer’s dye-making operations were razed, and the Site is almost entirely vacant land.

The Site is bounded by industrial, commercial, residential, and recreational areas. The

Toms River, which derives surface water primarily through groundwater baseflow, runs through

the northeast sector. The aquifer system in the Site area is tapped by municipal, industrial, and

private wells. Residential neighborhoods, recreational areas, small commercial establishments,

and light industrial complexes are present near the Site. The commercial areas are situated

primarily to the southwest. The area to the west is zoned for industrial use, light manufacturing,

and warehousing operations. To the east, there is a large recreational area, which includes several

parks. Residential areas exist along the northern (Pine Lake Park) and southeastern (Oak Ridge

10

Parkway Area) portions of the Site. The entire perimeter of the Subject Property is fenced and

secured as the public is not permitted access to an active Superfund Site.

In 1984, USEPA began a Remedial Investigation (“RI”) of the Site. The results of the RI

were finalized in the initial RI report for the Site in 1988. The RI concluded that contaminated

source areas on the Site resulted in groundwater contamination. Based on this investigation,

USEPA defined two operable units: Operable Unit 1 (“OU1”) pertaining to groundwater; and

Operable Unit 2 (OU2”) pertaining to known or suspected source contamination.

USEPA focused on identifying a remedy for groundwater contamination (OU1) first as

part of a multi-phase remedy for the Site. On April 24, 1989, USEPA issued a Record of Decision

(“ROD”) for OU1 describing the selected groundwater remedy.

After the USEPA issued the ROD for OU1, public concerns related to the proposed

discharge to the Toms River resulted in a continued investigation and public involvement to

develop an alternate discharge point for treated groundwater. On September 30, 1993, USEPA

issued an Explanation of Significant Differences eliminating discharge to the Toms River and

calling for the on-site recharge of treated groundwater.

On September 29, 2000, USEPA issued a ROD for OU2 describing the selected remedy

for the on-site source areas. The design of the source area remedy was completed in the summer

of 2003, and on-site construction began in October 2003. The excavation of drums from the

stacked drum disposal area began in December 2003 and was completed in November 2004. Air

monitors became operational in April 2003. Monitoring occurs in the work zone, near-source, and

at the Site Perimeter. Four different monitors are used at the perimeter stations. Soil treatment

began in July 2004.

11

More than 47,000 drums of waste were removed from the property in 2003 and 2004 and

sent for off-site disposal. By August 2010, treatment of more than 400,000 cubic yards of

contaminated soil had also been completed. The cleanup of toxic soil and the removal of waste-

filled drums was finished in 2010. USEPA states that the removal of buried waste drums and

contaminated soils has removed the property’s pollution sources.

The remaining remedial work involves resolving the OU2 equalization basin issues, and

the groundwater treatment process set forth in OU1, which is expected to continue for many years,

and most likely decades. Testing continues to show that the groundwater plume is shrinking; more

than 10 billion gallons of polluted water has been extracted and treated. Each day over a million

gallons of polluted groundwater is pumped from the aquifer beneath the property, treated to

remove contaminants, and dumped onto recharge areas near the Toms River. In 2013, a more

efficient groundwater treatment system was constructed that began operation in 2014.

As evidenced by the public comments to the OU2 ROD, some residents expressed unease

at any suggestion that the property might be eventually developed. Their concerns focused on the

40,000 to 50,000 drums of waste that will remain buried in the land even after groundwater cleanup

is complete. The Municipality sued Taxpayer in an effort to force the drums to be removed, but

the lawsuit was dismissed. Taxpayer has indicated that it has no intentions of reopening the sealed

landfill or removing the drums that are buried there. Monitoring indicates that there is no leakage

and the landfill is functioning in compliance with all applicable state regulations and legal

requirements, which include continued monitoring. Taxpayer believes that the drums should not

be disturbed as the process of removing them from the landfill could create unnecessary

environmental health and safety risks.

12

On August 22, 2016, the USEPA issued a letter approving the RAR and agreeing that

Taxpayer had completed “construction activities” related to the OU2 remediation. This letter,

however, was not a “no further action” letter that would be required to fully close out OU2. There

remains one source area of contamination in OU2, the equalization basin, that did not achieve the

cleanup goal set forth in the ROD. Taxpayer must remedy the equalization basin issue before OU2

can be closed out.

E. Oversight Documents

As describes, the Site has been the subject of ongoing oversight and remedial activity under

the authority of both the USEPA and the NJDEP. This oversight has been memorialized by, among

other things, the following instruments (“Oversight Documents”) recorded with the Ocean County

Clerk:

1. Administrative Consent Order entered In the Matter of Ciba-Geigy Corporation,

recorded in the Office of the Ocean County Clerk on April 22, 1992 in Book 4973;

Page 868;

2. Consent Decree in the matter United States of America v. Ciba-Geigy Corporation,

Civil Action No. 93-4675 (MLP) in the United States District Court for the District of

New Jersey, filed December 1, 1993; as amended by Order and Stipulation Correcting

Consent Decree filed June 8, 1994, recorded in the Office of the Ocean County Clerk

on July 7, 1994 in Book 5178, Page 104 (said Order attaching a copy of the foregoing

Consent Decree); and

3. Consent Decree in the matter United States of America v. CIBA Specialty Chemicals

Corporation and Novartis Corporation, Civil Action No., 3.01 cv 04223 (GEB) in the

United States District Court for the District of New Jersey, entered on March 21, 2002

13

for which a Declaration of Consent Decree was recorded in the Office of the Ocean

County Clerk on April 17, 2002 in Book 10803, Page 1401.

Pursuant to these Oversight Documents, the USEPA has assumed primary jurisdiction for

the remedial activities on the Site, with support from the NJDEP. Access to the property and the

groundwater is restricted for the purpose of preventing any unacceptable exposure until final

cleanup standards are achieved.

F. Regulations Impacting Redevelopment

The Subject Property is located in a coastal zone with the Toms River providing its

northeastern border. Any proposed development activity must consider the dictates of the Coastal

Area Facilities Review Act (“CAFRA”) and the Coastal Zone Management Rules (“CZM”) among

other stringent regulatory frameworks promulgated by the NJDEP. Attention must be paid to

special areas of the property where the NJDEP either discourages or prohibits development. These

special areas and associated CAFRA regulations include, but are not limited to:

- Intermittent stream corridors (N.J.A.C. §7:7E-3.32)

- Wetlands and wetland buffers (N.J.A.C. §7:7E-3.27-3.28)

- Riparian zones (N.J.A.C. §7:7E-3.26)

- Special water resource protection areas (N.J.A.C. §7:8)

- Flood hazard areas (N.J.A.C. §7:7E-3.25)

- Critical wildlife habitat (N.J.A.C. §7:7E-3.39)

- Threatened and endangered species habitat (N.J.A.C. §7:7E-3.38), and

- Special hazard areas (N.J.A.C. §7:7E-3.41)

14

Generally speaking, the CAFRA rules are designed to focus development activities in areas where

it is desired and to discourage or prohibit development where it is not. Development at the Subject

Property would require approval from the NJDEP and the issuance of a CAFRA permit.

While the CAFRA regulations are rigidly enforced, there are exceptions that allow for the

issuance of a permit to develop otherwise discouraged property in a CAFRA zone. Those

exceptions involve the following:

(1) There is a specific public interest in the specific development project;

(2) The specific project would have minimal feasible interference with the special

area/protected resource;

(3) There is no alternative location available for that specific development project; and

(4) That there is a mitigation plan in place to ensure there was no net loss of the special

area/protected resource impacted by the proposed specific development.

[N.J.A.C. §7:7E-3.39 (b); N.J.A.C. §7:7E-1.8]

There is evidence to suggest that the Subject Property would satisfy some of these articulated

exceptions, even with the documented presence of T&E species and habitat. Specifically,

influential on this issue is the placement of the Subject Property in a Redevelopment Zone

approved by the New Jersey Department of Community Affairs, and the inclusion of the Subject

Property in the Sewer Service Area of the Ocean County Water Quality Management Plan

approved by the NJDEP.

Notwithstanding the arguments advanced in these tax appeals, the Taxpayer also is

proceeding in a manner to suggest that it believes that approval will be forthcoming for future

development of the 790 unrestricted acres. In November 2009, Taxpayer requisitioned a document

entitled “Request for Engineering Planning Services, CIBA Toms River, N.J. Property, General

15

Development Plan Preparation.” The Conceptual Land Use Plan contained therein is consistent

with the subdivision plan submitted by Taxpayer to the Toms River Planning Board in 2013.

II. PROCEDURAL HISTORY

Taxpayer timely filed the Complaints in the Tax Court challenging the assessment on the

Subject Property for tax years 2004 through 2018. In 2011, 2012 and 2013 complaints, the

Taxpayer also appealed the assessment for Block 411.32, Lot 8; Block 411.34, Lot 12 and Block

409, Lot 62, however, these claims have been withdrawn.

The Municipality filed counterclaims in tax years 2004 and 2009 and also filed separate

complaints in 2005 and 2008. Both counterclaims and complaints were later withdrawn. All

appeals have been consolidated for trial.

On August 13, 2013, the Municipality moved for partial summary judgment pursuant to R.

4:46-1. The Taxpayer opposed the motion and filed a cross-motion for partial summary judgment.

The court heard oral argument on October 11, 2013. Both parties stipulated as to the expenditures

and costs associated with environmental remediation and cleanup of the Subject Property. Both

parties also acknowledged that environmental remediation was not complete. In an unpublished

opinion, 15 the Tax Court found that the land could be segmented for the purpose of determining

the highest and best uses. The Tax Court also utilized the guidance provided in Metuchen I v.

Borough of Metuchen, 21 N. J. Tax 283 (Tax Ct. 2004) and Inmar Assoc., Inc. v. Borough of

Carlstadt, 112 N.J. 593 (1988), clarifying that a contaminated property site must be viewed as a

whole, with any stigma reduction applying to the overall site. The court concluded that remediated

15

Ciba Specialty Chemicals Corp. v. Township of Dover, 2013 WL 6438501 (New Jersey Tax

Court 2013)

16

now uncontaminated portions of the land, and even portions of the property that had always been

clean, would not be free from the stigma associated with a Superfund site designation. The court

also found that any adjustment for remediation costs will be applied to the value of the entire Site,

and not just the portion of the Site that was contaminated.

On November 7, 2013, the Municipality moved for bifurcation of trial pursuant to R. 4:38-

2(a). The Taxpayer opposed the motion. On December 6, 2013, the court granted the

Municipality’s motion to bifurcate the trial into two phases. The first phase of the trial was to

determine the development potential of the property, including the amount of developable land.

The second phase of the trial was to determine value.

On May 12, 2014, the Municipality moved for partial summary judgment on whether the

existence of T&E species and critical wildlife habitat at the property could be considered as a legal

bar to the future development of the Subject Property. The Taxpayer filed a cross-motion for

partial summary judgment. Both parties acknowledged that there is evidence of T&E species and

habitat on the Subject Property, and that NJDEP had been advised of their presence. It was also

undisputed that the NJDEP did not place the Subject Property on its map of T&E species and

habitat, and furthermore the NJDEP had approved sewer service for the area.

Oral argument was heard on July 29, 2014. The court found that the failure of NJDEP to

acknowledge the presence of T&E species and habitat by including the Subject Property on its

T&E species map, and the NJDEP’s inclusion of the property in an approved sewer service area,

is not a definitive declaration by the agency that T&E species and habitat are not present on the

property. The court also found that any reasonable purchaser and would consider the potential

limitation on the development of the Subject Property due to NJDEP interest in protecting T&E

species and habitat. However, the court also found that any presence of T&E species and habitat

17

will not in and of itself preclude development of some or all of the Subject Property, it is simply

one of the multiple factors to be considered.

Thereafter the Taxpayer and the Municipality became entrenched in highly contentious

motion practice involving a number of substantive and procedural issues regarding the first phase

of the trial. The court entered several Case Management Orders (“CMO”) during this process.

On April 18, 2017, the Taxpayer moved for partial summary judgment on a zoning issue.

The question presented was whether valuation could include the reasonable probability that there

could have been a change in zoning to permit a portion of the Subject Property to be developed for

residential use on the relevant valuation dates. The Municipality opposed. A hearing was held on

May 26, 2017, and the court denied the Taxpayer’s motion for summary judgment. Trial on the

issue of the probability of a zoning change was held on October 30, 2017. On November 17, 2017,

the court held that the valuation would be determined based on the permitted zoning on the relevant

assessment dates.

The second trial phase was held on October 15 through October 23, 2018. At the

conclusion of trial, the court requested additional submissions relating to the USEPA and the

institutional controls in force at the Site. The parties were given until January 14, 2019 to submit

closing briefs and supplemental submissions.

III. TRIAL TESTIMONY

A. Taxpayer

The Taxpayer called three expert witnesses to testify at the trial.

The first expert offered by Taxpayer (TX1) was deemed qualified without objection in the

field of T&E, associated T&E habitats, and regulatory impacts on development potential. TX1

was first contacted by the Taxpayer in February of 2008 to address the potential issue of T&E

18

species and critical habitats, and its related regulatory impacts on the future development of the

Subject Property. TX1 contacted NJDEP, and his firm was approved to conduct a T&E habitat

evaluation on the Subject Property from May 2008 to October 2009.

At the conclusion of his evaluation, TX1 had not identified any endangered species on the

Subject Property, but he had discovered some threatened species. Specifically, TX1 documented

the presence of the northern pine snake, grasshopper sparrow, Cooper’s hawk, and the red-headed

woodpecker. All four species were listed as threatened at the time of the study, and except for

Cooper’s hawk 16, the remaining three animals continue to be listed as a threatened species in the

State.

During the course of the study, TX1 captured four northern pine snakes. Based on the age

and sex of these four snakes and their winter dens, TX1 concluded that there is a sustaining and

reproducing population of northern pine snakes inhabiting the Subject Property on a year-round

basis. However, TX1 testified the time period for evaluation is inadequate for a complete study of

the snake. In his opinion, an adequate period of time will be two years, but NJDEP might require

for three-year study. TX1 also observed nesting grasshopper sparrows inhabiting the fields. The

Cooper’s hawk and red-head woodpecker he concluded were migratory birds.

After completing a detailed survey of the physical habitat structure at the Subject Property

and reviewing historical property records, including aerial photography and landscape maps, the

TX1 concluded that virtually all of the Subject Property would be classified by the NJDEP as

documented T&E species habitat. The only exception was the central portion of the property

16

In 2012, the status of the Cooper’s hawk was reclassified from threatened to special concern.

19

where there are existing structures comprising of the water treatment plant and ongoing remedial

activities.

The second expert offered by Taxpayer (“TX2”) was qualified without objection as an

expert in the field of wildlife biology and land use permitting. TX2 was retained by Taxpayer in

2009 to determine the amount of development that would be permitted on the Subject Property

under NJDEP land use regulations and local zoning.

After reviewing the findings of TX1 and discussion with Taxpayer’s third expert (“TX3”),

TX2 performed an allowable land disturbance analysis. TX2 relied on NJDEP mapping

information and field inspections. His analysis began with the 1,211 total acreages of the property,

to which he then deducted regulated special areas where NJDEP Coastal Zone Management rules

prohibit or discourage development. The table below shows TX2’s conclusion of the acreage of

each special areas:

Gross acres Net acres

Intermittent Streams Corridors (N.J.A.C 7:7E-3.32) 43.7 43.7

Wetlands (N.J.A.C 7:7E-3.37 and N.J.A.C 7:7A) 32.6 4.8

Wetlands Buffers (N.J.A.C 7:7E-3.28 and N.J.A.C 7:7A) 6.4 5.1

Riparian Zones (N.J.A.C 7:7E-3.36 and N.J.A.C 7:13) 198.4 148.5

Special Water Resource Protection Area (N.J.A.C 7:8) 195.4 0

Flood Hazard Areas (N.J.A.C 7:7E-3.25 and N.J.A.C 7:13) 28.3 0.6

Critical Wildlife Habitat (N.J.A.C 7:7E-3.39) 1066.8 883.4

Endangered and Threatened Species Habitat (N.J.A.C 7:7E-3.38) 1066.8 0

Special Hazard Areas (N.J.A.C 7:7E-3.41) 108.5 69.5

Total Area of Land disturbance permitted 55.4

20

TX2 also testified that without a specific development plan, it is unclear what impervious

coverage 17 ratio would apply.

TX3 was qualified without objection as an expert in the field of herpetology and T&E

species and associated habitats. His firm was retained by Taxpayer to conduct a habitat evaluation

of the Subject Property. TX3 reviewed TX1 and TX2’s analysis and then conducted a habitat

evaluation of the property to determine its suitability to support a population of northern pine

snakes. 18

TX3 agreed with the findings of TX1 and TX2 and testified that NJDEP would require a

minimum of 1,066.8 acres of critical wildlife habitat. TX3 also studied the Subject Property from

May 23, 2018 to October 2018 to evaluate whether it was suitable critical life habitat for the

northern pine snake. In his opinion, the NJDEP would require at least one full season, one full

year of study of a particular population, which means late March to early November for northern

pine snake. He concluded from his examination of the available habitat and the physical evidence

of northern pine snake presence that the Subject Property compares favorably with other known

northern pine snake habitat.

B. Municipality

The Municipality called one fact witness and four experts to testify on its behalf during the

trial.

17

An impervious surface is an area that has been covered by a layer of material that is highly

resistant to infiltration by water. Impervious surfaces include concrete, asphalt, driveways,

basketball courts, concrete patios, swimming pools and buildings.

18

TX3 was recognized as being the foremost authority on northern pine snakes in the State.

21

Steven Havlick began working for Taxpayer in 1983. He was involved in the 1983 USEPA

initial five-year review in 2003 and the second five-year review in 2008. Since 2008, he has held

the position of senior remediation project manager for Taxpayer at the Toms River Site. As such,

he is responsible for overseeing the environmental remediation work at the Site, and he is the main

point of contact for Taxpayer, the USEPA, NJDEP, and other regulators regarding Taxpayer’s

environmental obligations at the Site.

Mr. Havlick testified that from 2008 to 2011, USEPA representatives would visit the site

on a regular basis, and meetings were held with United States Army Corps engineers and Taxpayer

representatives. After 2011, when the soil remediation work was completed, the United States

Army Corps engineers ceased participation at the Site and interaction with USEPA representatives

became less frequent. He credits the reduced presence of the USEPA to substantial remedial

progress but maintains that regular and detailed monitoring and reporting is ongoing.

During the third five-year review in 2013, the Taxpayer asked the USEPA to consider

delineation of a portion of the Subject Property on the Site that could be delisted from Superfund.

Specifically, Taxpayer was referring to the 790 acres outside the area requiring remediation and

no restrictions on their future. With this purpose, Taxpayer’s request to the Municipality to

subdivide the Subject Property into three parcels.

Mr. Havlick was directly involved in the subdivision of the Subject Property. The property

was subdivided in December 2013 resulting in the consolidation of tax parcels and the creation of

three new tax parcels. The parcels were delineated based on their soil and groundwater conditions,

with the goal of segregating the more contaminated parcels from the less contaminated parcels.

The purpose of the subdivision was to minimize the economic impact of parcels that have less risk

for Taxpayer to sell, lease, or reuse. The intent was also to pave the path for partial or full delisting

22

of the Subject Property from Superfund. The Taxpayer’s strategy was to end up with at least one

parcel of unrestricted land void of any deed restrictions resulting from its prior Superfund

designation.

The fourth five-year review was conducted in 2018. Taxpayer presented a PowerPoint

report to the USEPA and NJDEP representatives in attendance. The PowerPoint presentation

outlines the advances and accomplishments of the remedial work performed on the Site and

clarifies the work still to be done. The USEPA final report from the meeting states that deed

restrictions will be required on Lots 6.02 and 6.03 but does not mention Lot 6.01.

With respect to T&E species and habitat on the Subject Property, Mr. Havlick testified that

he observed grasshopper sparrows, but never the northern pine snake. Additionally, he was not

aware of any active program to document the presence of any T&E species on the property.

The Municipality’s first expert (“MX1”) was qualified without objection in the field of

land use planning, civil engineering, and land development entitlement. MX1 testified that

development potential is approximately 745 acres, which is consistent with Taxpayer’s own

general development plan prepared in 2009. MX1 believes this assessment is a more accurate

assessment of the development potential of the Subject Property since it was derived subsequent

to the TX1’s study of T&E species on the property.

MX1 reviewed TX2’s conclusions regarding development potential and found that the 55.4

acres conclusion is a worst-case scenario of all the environmental and regulatory constraints that

may impact the development potential of the property. Specifically, TX2’s scenario is calculated

with the assumption that T&E species and the critical wildlife habitat will constrain 95% of the

property.

23

MX1 testified that the T&E habitat regulations found at N.J.A.C 7:7E-3.38, require that

T&E habitats be mapped on the NJDEP’s Landscape Maps, and the New Jersey Natural Heritage

Program. MX1 found it significant that the NJDEP was put on notice of T&E species and habitat

at the Subject Property, but nonetheless chose not to include it on the maps. MX1 opined that once

the deduction for T&E was removed, 863.50 acres of the Subject Property are developable.

The Municipality’s second expert (“MX2”) was qualified without objection in the field of

ecology, environmental biology, and CAFRA regulations. Upon review of the TX2’s expert

report, MX2 found the TX2’s position on developable acreage deficient for two reasons.

First, MX2 testified that TX2 incorrectly calculated the amount of impervious coverage

allowed under the CAFRA rules. MX2 believes that the allowable impervious coverage should be

80 percent instead of TX2’s assumption of 30 percent. Second, MX2 disagreed with TX2’s

assessment of acreage to be constrained from development due to the presence of T&E species

and critical wildlife habitat. MX2 based his opinion of the NJDEP’s lack of including the Subject

Property on its T&E maps, and because NJDEP approved of the inclusion of the property in its

approval of the municipal sewer service area. MX2 testified that the NJDEP could not approve

the inclusion of the Subject Property into the sewer service area if it had determined that the

property contained critical wildlife habitat.

MX2 concluded that between 475 acres and 650 acres on the western side of the Subject

Property could be developed after considering all of the mitigation requirements.

The Municipality’s third expert (“MX3”) was qualified without objection in the field of

brownfield remediation and cleanup under both state and federal law. MX3 reviewed the 2000

ROD and other USEPA and NJDEP documents, and he came to the conclusion that the USEPA

placed no development restrictions on the unrestricted use area of the Site and that Taxpayer could

24

have subdivided the property as early as 2000. He further offered the net opinion that the ROD

did not require the completion of remediation before Taxpayer could delist the unrestricted area.

The fourth and final expert offered by the Municipality (“MX4”) was qualified without

objection in the field of herpetology, wildlife ecology (as limited by experience), and regulatory

compliance (as limited by experience) including CAFRA. MX4 reviewed the expert reports of

Taxpayer’s experts and also conducted his its own T&E species and habitat evaluation. In his

opinion, NJDEP would at least require two-year study for northern pine snake which can be

nonconsecutive years. Incorporating the data used by the Taxpayer’s experts, MX4 concluded that

after mitigation measures were applied, at least 375 acres can be developed, and an additional 50

acres (425 acres) available with additional mitigation.

IV. ISSUES PRESENTED

1. What number of acres could have been developed on the Subject Property during tax

years 2004 through 2018?

2. What was the development potential for the Subject Property during the tax years 2004

through 2018?

V. LEGAL ANALYSIS

The court’s analysis is without the benefit of testimony from representatives of the USEPA

or NJDEP, as neither party called any witnesses from those agencies during the trial.

A. Developable acreage during tax years 2004 through 2018

The court finds that the determination of the number of acres that were available for

development during the tax years in question is directly related to the Subject Property’s Superfund

designation.

25

The use, and therefore development, of property that has suffered contamination may be

altered temporarily or permanently. As provided in the Advisory Opinion 9 (AO-9) of Uniform

Standards of Professional Appraisal Practice:

[T]he appraisal of properties with environmental contamination

usually involves extensive highest and best use analysis for impaired

value. The high and best use should consider the limitation on the

property due to the environmental contamination, and any legal use

restrictions associated with the cleanup of the contamination source.

Environmental contamination and its remediation to appropriate

regulatory standards may affect the feasibility of site development

or redevelopment, use of the site during remediation, use of the site

after remediation, marketability of the site, and other economic and

physical characteristics of a contaminated property. The appraiser

should consider the possibility that site remediation and any

remaining limitations on the use of the site following remediation

may alter or limit its highest and best use in the impaired condition.

In addition, excessive environmental risk and stigma may deter site

development or redevelopment and thereby limit the highest and

best use until the property’s environmental risk is reduced to levels

acceptable to the relevant market participants.

[Id.]

The Subject Property’s location within a Superfund Site, subjects it to Institutional Controls (“IC”)

from the USEPA and NJDEP. These institutional controls limit the use of the property during

remediation and may restrict future use of portions of the property after remediation. Specifically,

the institutional controls effecting the Subject Property made development during the 2004 through

2018 tax years impermissible.

The USEPA defines institutional controls as “non-engineered instruments, such as

administrative and/or legal controls intended to minimize the potential for human exposure to

contamination by limiting land or resource use.” U.S. EPA Office of Solid Waste and Emergency

Response, EPA 500-R-05-001, Long Term Stewardship: Ensuring Environmental Site Cleanups

26

Remain Protective Over Time, Challenges and Opportunities Facing EPA’s Cleanup-Programs

(September 2005). This definition was expanded in 2012 and now reads:

EPA defines ICs as non-engineered instruments, such as

administrative and legal controls, that help to minimize the potential

for exposure to contamination and/or protect the integrity of a

response action. ICs typically are designed to work by limiting land

and/or resource use or by providing information that helps modify

or guide human behavior at a site. ICs are a subset of Land Use

Controls (LUCs). LUCs include engineering and physical barriers,

such as fences and security guards, as well as ICs.

[U.S. EPA Office of Solid Waste and Emergency Response, EPA

540-R-09-001, Institutional Controls: A Guide to Planning,

Implementing, Maintaining, and Enforcing Institutional Controls at

Contaminated Sites (December 2012).]

The USEPA divides institutional controls into four categories: proprietary controls;

government controls; information devices; and the agency issued enforcement orders or

agreements. 19 Generally speaking, proprietary controls are private agreements that are recorded

in a property’s chain of title. Government controls refer to local ordinances or state statutes that

restrict or condition land use. Information Devices provide notice of residual contamination and,

in some cases, notice that certain future land uses should not occur. One informational device is a

deed notice which is included in the chain of title. These documents are intended to put others on

notice that residual contamination and land use restrictions exist. They do not however actually

restrict land use.

19

U.S. EPA Office of Solid Waste and Emergency response, EPA 540-R-09-001, Institutional

Controls: A Guide to Planning, Implementing, Maintaining, and Enforcing Institutional Controls

at Contaminated Sites (December 2012).

27

The final category of institutional controls involves environmental agency orders and

agreements concerning cleanup. This category includes enforcement orders or agreements entered

into by or between an environmental agency and a property owner (usually the party responsible

for causing the contamination).

1. Taxpayer’s Oversight Documents

Taxpayer’s Oversight Documents are legally enforceable institutional controls. A

prerequisite to any determination of the number of acres that could have been developed during

2004 through 2018 tax years is that such development had to have been permissible.

The Oversight Documents executed between the Taxpayer, USEPA and NJDEP that were

filed with the Ocean County Clerk legally restrict any development on the property absent USEPA

and NJDEP written approval, or partial or full delisting of the Site.

The 1992 Consent Order in Paragraph 1 defines the Site as Block 411, Lots 6, 84, and 124,

in Dover Township, which by definition includes the Subject Property. The court interprets

Paragraphs 35, 36 and 37 of that document as prohibiting development on the Site without NJDEP

approval. Those paragraphs read as follows:

35. In addition to the Department’s statutory and regulatory rights

to enter and inspect, Ciba-Geigy shall allow the Department and its

authorized representatives access to the Site at all times for the

purpose of monitoring Ciba-Geigy’s compliance with this

Administrative Consent Order and/or to perform any remedial

activities Ciba-Geigy fails to perform as required by this

Administrative Consent Order.

36. Ciba-Geigy shall not construe any informal advice, guidance,

suggestions or comments by the Department, or persons acting on

behalf of the Department, as relieving Ciba-Geigy of its obligation

to obtain written approvals as required herein, unless the

Department specifically relieves Ciba-Geigy of such obligations, in

writing.

28

37. No modification or waiver of this Administrative Consent Order

shall be valid except written amendment to this Administrative

Consent Order duly executed by Ciba-Geigy and the Department.

The 1994 Consent Decree with the USEPA defines the terms “On-Site” and “Site” at

Paragraph 4 (m) and (z) as:

m. “On-site” shall mean the areal extent of contamination and all

suitable areas in very close proximity to the contamination

necessary for implementation of the response action, as specified in

Section 121(e) of CERCLA and Sections 300.5 and 300.400 (e) of

the NCP. . . .

z. “Site” shall mean the former Toms River Chemical Corporation

plant, now the Ciba-Geigy Corporation plant, formally designated

on the NPL as the Ciba-Geigy Superfund Site, located in Toms

River, Ocean County New Jersey, as referred to in EPA’s ROD as

modified by the ESD, and depicted generally on the map attached as

Exhibit C. The Site includes the areal extent of contamination where

hazardous substances have migrated or are migrating, and all

suitable areas in very close proximity to the contamination

necessary for implementation of the response action.

[Emphasis added.]

The 1994 Consent Decree further states that the Site includes approximately 1400 acres,

320 of which are developed.

Other paragraphs of the 1994 Consent Decree delineate the jurisdiction of the USEPA over

all activity occurring on the Site. For example, Paragraph 8 provides that “as provided in Section

121(e) of CERCLA and Section 300.5 a and Section 300.400 (e) of the NCP, no permit shall be

required for any portion of the Work conducted entirely On-Site.” Paragraph 9 sets forth that the

obligations of Taxpayer with respect to the provision of access under Section X (Access) shall be

binding upon Taxpayer and any and all persons who subsequently acquire any such interest or

portion thereof.

29

Paragraph 26 provides that Taxpayer must provide the USEPA and its representatives and

contractors access to the Site for the purpose of conducting any activity related to the Consent

Decree, including but not limited to:

a. Monitoring the Work;

b. Verifying any data or information submitted to the United

States;

c. Conducting investigations relating to contamination at or near

the Site;

d. Obtaining samples;

e. Assessing the need for, planning, or implementing additional

response actions at or near the Site;

f. Inspecting and copying records, operating logs, contracts, or

other documents maintained or generated by Settling

Defendants or their agents, consistent with Section XXV

(Access to Information); and

g. Assessing Settling Defendant’s compliance with this Consent

Decree.

Furthermore, Paragraph 28 states that “Notwithstanding any provision of this Consent

Decree, the United States retains all of its access authorities and rights, including enforcement

authorities related thereto, under CERCLA, RCRA and any other applicable statute or regulations.

The 2002 Consent Decree contains the broadest language regarding access to the Site.

After adopting the identical definition of the term Site as is found in the 1994 Consent Decree,

Paragraph 26 sets forth the access and institutional controls as follows:

If the Site, or any other property where access and/or land/water use

restrictions are needed to implement this Consent Decree, is owned

or controlled by any of the Settling Defendants, such Settling

Defendants shall:

a. commencing on the date of lodging of this Consent Decree,

provide the United States, and their representatives, including EPA,

the State and its contractors, with access at all reasonable times to

the Site, or such other property, for purpose of conducting any

activity related to this Consent Decree including but not limited to,

the following activities:

30

(1) Monitoring the work;

(2) Verifying any data or information submitted to the

United States (or the State);

(3) Conducting investigations relating to contamination at or

near the Site;

(4) Obtaining samples;

(5) Assessing the need for planning, or implementing

additional response actions at or near the Site;

(6) Implementing the Work pursuant to the conditions set

forth in Paragraph 88 of this Consent Order;

(7) Inspecting and copying records, operating logs,

contracts, or other documents maintained or generated

by Settling Defendants or their agents, consistent with

Section XXIV (Access to Information);

(8) Assessing Settling Defendant’s compliance with this

Consent Decree; and

(9) Determining whether the Site or other property is being

used in a manner that is prohibited or restricted, or that

may need to be prohibited or restricted, by or pursuant to

Consent Decree;

b. commencing on the date of lodging of this Consent Decree,

refrain from using the Site, or other such property, in any manner

that would interfere with or adversely affect the integrity or

protectiveness of the remedial measures to be implemented pursuant

to this Consent Decree.

Finally, Paragraph 30 provides that notwithstanding any provision of the Consent Decree,

“the United States and the State retain all of their access authorities and rights, as well as all of

their rights to require land/water use restrictions, including enforcement authorities related thereto,

under CERCLA, RCRA and any other applicable statute or regulation.”

31

The Oversight Documents convincingly establish that any real estate use of the Site

is entirely subordinate to the USEPA's and NJDEP’s authority to carry out remedial investigation

and action. The designated access to the Site by its very nature restricts the development and use

of the property. As evidenced by the Consent Decrees, Taxpayer’s property cannot be used in a

manner that would interfere with the remediation activities being overseen by the USEPA and

NJDEP. Consequently, access to the property is prohibited to the public, and development would

be prohibited as well. Any attempt to develop any portion of the Subject Property would have

required USEPA and NJDEP approval, or a delisting of the portion of the property to be developed.

In the absence of USEPA and NJDEP testimony to the contrary, development on the Site was

prohibited.

2. USEPA Guidelines for Redevelopment, Delisting and Reuse

The USEPA’s process when returning Sites to productive use involves a number of steps

as well as involvement from the community.

Returning Sites to Productive Use.

As early in the process as possible, EPA works with communities

through an array of communication techniques and partnerships to

help to return sites to productive use.

These uses can be industrial or commercial, such as factories and

shopping malls. Some sites can be used for housing, public works

or healthcare facilities, transportation, and other community

infrastructure. Sites could be redeveloped as recreational facilities

such as golf courses, parks and ball fields; or for ecological

resources, such as wildlife preserves and wetlands. Sites could even

be used for generating energy from renewable sources such as wind

turbines or solar panels.

No matter what use is appropriate for a site, the community benefits

from restoring the site to productivity, because the property can once

again add to the economic, social, and ecological value of the

community.

32

[EPA, “This Is Superfund, A Community Guide To EPA’s

Superfund Program” at 10 (2011).]

The brochure encourages local residents to “work with EPA, your local government, and

your community to plan the redevelopment of the site. Explore the redevelopment ideas and

resources provided by EPA.”

The brochure also discusses maintenance of a Superfund site after remediation is

completed.

Maintaining the Site Cleanup Over the Long Term

After EPA determines that the physical construction at a site is

complete, activities are put in place to ensure that the cleanup

actions will protect human health and the environment over the long

term. For example, these activities may include routine

maintenance at the site such as making sure signs and fences are

intact or soil treatment systems are running smoothly.

EPA is also required to conduct a review of the site cleanup every

five years. This Five-Year review may include examining site data,

inspecting the site, taking new samples, and talking with affected

residents about site conditions, problems or concerns.

EPA is required to notify the community and other interested parties

when a Five-Year review will be conducted at the site.

[Id. at 11.]

Finally, the brochure describes the delisting process.

Deleting a Site from NPL

EPA may delete a site or a portion of a site (sometimes called an

operable unit) from the NPL if all cleanup goals have been met and

no further cleanup action is required to protect human health and the

environment.

EPA publishes a notice of its intention to delete the site, or portion

of the site, from the NPL in the Federal Register, and notifies the

community of the opportunity for comment. EPA then accepts

comments from the public and formally responds to public

33

comments received. If, after the formal comment period, the site or

portion of the site still qualifies for deletion, EPA publishes a formal

deletion notice in the Federal Register and places a final deletion

report in the administrative record for the site.

[Id.]

The Municipality argues that because there is designated acreage on the Site that has never

been contaminated, those acres could have been developed within the current industrial zoning

during the 2004 through 2018 tax years. The court disagrees and finds that the institutional

controls in place prohibited such development.

The procedurally appropriate mechanism to advance development of the unrestricted acres

on the Site would have been to apply for partial delisting of those acres. The Partial Deletions

Rule allows the USEPA to delete portions of Superfund sites where contamination was not found,

or where property was incorrectly included in the site boundaries. In addition to the property

owner, this relief is available to developers, municipalities, States, individuals and other groups.

The criteria for site deletion are outlined in 40 C.F.R. § 300.425 (e). Partial deletions are an

effective way to communicate remediation success, and to promote the reuse and development of

Superfund sites.

3. Limitations on Anticipated Future Development Based on T&E Species and Habitat

NJDEP Landscape Project Mapping does not indicate the presence of T&E species or

habitat, however, a wildlife study conducted in 2008 that included tracking the movements of

individual animals has identified the presence of the northern pine snake, a New Jersey threatened

species on the property. The wildlife study also identified Cooper’s hawk, grasshopper sparrow

and red-headed woodpeckers on the property.

34

The Taxpayer argues that even if the USEPA were to relinquish some level of control and

jurisdiction over a portion of the property, CAFRA regulations designed to protect T&E species

and associated habitat areas are just as restrictive and would prohibit development. Taxpayer

posits that since T&E species have been documented to be present on the Subject Property, it is

therefore home to a number of T&E species and in particular it contains extensive habitat areas

suitable for northern pine snakes. Taxpayer’s position is that, when applying the applicable

CAFRA regulations and established NJDEP mapping protocols, only 55.4 acres are available for

development.

Taxpayer has the burden of proof by a preponderance of the evidence to demonstrate the

number of acres with development potential for each year from 2004 through 2018. The

preponderance of evidence standard is defined as:

[E]vidence which is of greater weight or more convincing than the

evidence that is offered in opposition to it; a party proves a fact by

a preponderance of the evidence when it proves that the fact’s

existence is more likely than not; it is only necessary that the

circumstance established by the evidence be such as would lead a

reasonably prudent man to that belief.

[GGI Props., LLC v. City of Millville (In re GGI Props., LLC), 588

B.R. 401, 417 (Bankr. D.N.J. 2018)]

To ask this court to determine developable acreage that would be permitted by the NJDEP

without any testimony from the NJDEP would be total and complete speculation on the court’s

part. The court also notes that the Taxpayer doesn’t reference T&E species and habitat except in

the context of these tax appeals. The Taxpayer highlights the presence of coyotes, deer, foxes and

sparrows in Taxpayer’s 2018 PowerPoint presentation as part of the USEPA Five-Year Review,

but does not reference northern pine snakes. Furthermore, Mr. Havlick when testifying stated that

35

he didn’t see any snakes on the property, nor was he aware of anyone working at the property who

had seen snakes.

While the court has no doubt that there are T&E species and habitat present on the Subject

Property, the court is not satisfied that NJDEP would prohibit development of the 790 unrestricted

acres, as opposed to requiring some mitigation or adaptation, such as moving the snakes to another

and perhaps more suitable habitat. The difference of opinion amongst the experts also leads the

court to doubt whether NJDEP will be satisfied with the current study of the snakes on-site. The

court is more inclined to think that NJDEP will require a more extensive study before it makes a

determination on critical wildlife habitat for the northern pine snake thereby prohibiting proposed

development on the Subject Property.

In making its decision, the court gives great weight to the documents submitted as part of

the USEPA Fourth Five Review documents and the Taxpayer’s accompanying PowerPoint

presentation, dated January 23, 2018. In the section entitled Institutional Control’s and NPL

Depletion, there is included a Deed Notice Map. The map highlights areas requiring deed

restrictions with a notation “framework developed through consultation with NJDEP and

USEPA.” The presentation incudes a NPL Deletion Map containing the following three notations:

USEPA Final Source Control Remedial Investigation Report

(December 1994):

- The analytical data support the conclusion that the background

locations are representative of relatively undisturbed areas.

- VOCs and SVOCs are generally absent in both the surface and

subsurface background soil samples.

- The detection of trace (less than 6 ug/kg) concentrations of

pesticides is not unexpected and likely due to aerial spraying of

farms, cranberry bogs and other agricultural areas in the past, as

well as aerial spraying for mosquito and other insect control.

- The concentrations of inorganic analy[s]es are relatively

consistent throughout the surface and subsurface soils.

36

USEPA FIVE-YEAR REVIEW REPORT (JULY 2008)

- Based on soil sampling, approximately 790 acres are outside the

area requiring remediation and no restriction on their future use

is necessary.

AMO 20 Data Review & Field Reconnaissance (May/August 2011)

AMO’s review and evaluation of data relative to USEPA and

NJDEP standards finds agreement with conclusions presented in the

1994 RI Report.

- 2011 Field Reconnaissance:

- ATV inspection of all accessible past/present roadways

identified through historical aerial survey analysis.

- No areas of environmental concern identified (two areas were

investigated through test pits or wildlife-biologist assessment).

The court finds this document to be demonstrative not only of Taxpayer’s anticipated ability to

develop the 790 unrestricted acres, but also indicates that the USEPA and Taxpayer were still

conducting monitoring activities on the 790 unrestricted acres up until at least August of 2011.

The court also finds supportive language for its conclusions in the USEPA’s earlier Five-

Year Reviews. Specifically, Page 10 of the Third Five-Year Review includes the following:

[T]he OU2 ROD contained three conceptual future land use area for

the Site based on anticipated conditions following remedy

implementation: unrestricted use area, restricted waste management

area, and restricted commercial/industrial/recreational use area.

Unrestricted Use Area – This area had no known industrial activity.

This area which is currently locally zoned as commercial/industrial,

requires no land use restrictions.

Restricted Waste Management Area – This area which includes the

footprint of the groundwater treatment facilities, DDSA, Standpipe

Burner Area, Lime Sludge Disposal Area, FCD and industrial

20

AMO is the acronym for Advanced GeoServices, an engineering company retained by Taxpayer

to oversee the remediation at the Site.

37

landfill, requires land use restrictions to prevent any intrusive

activities in the capped areas of the Site.

Restricted Commercial/Industrial/ Recreational Area – This area

which includes the historical industrial production area requires land

use restrictions to prevent the construction of residential structures.

The deed restriction for the property to ensure future land use,

consistent with the OU2 ROD is expected to be implemented by

2016.

This same language appears in the Fourth Five-Year Review at Page 9, with the addition of “In

preparation of the deed restrictions, in 2013, the Township subdivided the property into three lots

with Block 411, Lot 6.01, 6.02 and 6.03.” On Page 10 of that same report, the USEPA divides its

Protectiveness Statement into three categories: OU1, OU2 and Sitewide. The court interprets the

Sitewide category as an indication that the USEPA is actively monitoring and utilizing the

unrestricted 790 acres in its remediation of the Site.

Additionally, Page 14 of Third Five-Year Review contains a statement that “Actions such

as the fencing around the Site and the continuous security activities are in place to interrupt

exposures to potential trespassers.” On Page 15 under the technical assessment summary it states,

“Access to the property and the groundwater is currently restricted and is preventing unacceptable

exposure until final cleanup standards are achieved.”

VI. CONCLUSION

The court finds that for the 2004 through 2018 tax years, the entire 1,211 acres was

development-prohibited due to its designation as a Superfund site and the accompanying

institutional controls in place. During those years, the Subject Property was remedial mostly

vacant land, with future anticipated unrestricted development potential for 790 acres, and

restricted, limited, or prohibited development potential for the remaining 421 acres.

38

The court further finds that based on the documents generated by the USEPA and the

NJDEP, and the current subdivision of the Subject Property, there is insufficient evidence for the

court to find that CAFRA regulations concerning T&E species and habitat would prohibit

development of Block 411 Lot 6.01 within the current industrial zoning, once development

approval is received from USEPA and NJDEP or the property is delisted.

The court looks forward to the trial on valuation for tax years 2004 through 2011 scheduled

for May 13, 2019, and the trial on valuation for tax years 2012 through 2018 scheduled for

December 9, 2019.

/s/ Mary Siobhan Brennan, J.T.C.

39

Ordinance § 348-10.31

I. Industrial Zone.

A. Permitted uses.

(1) Research and testing laboratories, such as aerodynamic, biological,

chemical, dental, electronic, pharmaceutical and general.

(2) Manufacturing of light machinery, such as carburetors and small

machine parts, cash registers, sewing machines and typewriters,

calculators and other office machines.

(3) Fabrication of metal products, such as baby carriages, bicycles and

other vehicles; metal foil, such as tin, aluminum, etc., metal

furniture; musical instruments; sheet metal products; and toys.

(4) Fabrication of paper products, such as bags, book bindings, boxes

and packaging material, office supplies and toys.

(5) Fabrication of wood products, such as boats, boxes, cabinets and

woodworking, furniture and toys.

(6) Food and associated industries, such as bakeries, bottling of food and

beverages, food and cereal mixing and milling, food processing,

food sundry manufacturing, ice cream manufacturing and

manufacturing of spirituous liquor.

(7) Truck terminals and the warehousing or storage of goods and

products, excluding the warehousing and storage of hazardous

chemicals.

(8) Other permissible industry, such as brush and broom manufacturing;

concrete and plastic products; electrical, light and power and other

utility company installation; electronic products; farm industry,

manufacturing and service; glass products manufacturing; jewelry

manufacturing, including gem polishing; laundering and cleaning

establishments; leather goods manufacturing, except curing, tanning

and finishing of hides; motion-picture exchange; pharmaceutical

products manufacturing; cosmetic products manufacturing; photo

finishing; pottery and ceramic products manufacturing; thread and

yarn manufacturing; plastics and chemical manufacturing; and

computer data services.

(9) Wholesale building material supply yards, yards of contractors in the

construction and building trades and similar operations requiring

40

bulk storage of materials and equipment, such as building

construction supplies and the equipment, vehicles and supplies of

heavy equipment contractors.

(10) Wholesaling or distributing establishments.

(11) Bulk storage of petroleum and fuels.

(12) Contractor's or craftsman's shop or equipment storage area, including

general repair shop, except automobile dismantling or cannibalizing.

(13) Federal, state, county and municipal buildings and grounds.

(14) Essential services.

(15) Aboveground public utilities.

(16) Motor vehicle repair garages.

(17) Child-care centers.

(18) Hotels and motels containing 100 or more units.

(19) Quasi-public and private club recreation areas.

(20) Mini warehouse facilities, including one dwelling unit.

(21) Offices for members of a recognized profession as defined in this

chapter. (Added 11-24-1998 by Ord. No. 3387-98; amended 12-27-

2006 by Ord. No. 4064-06)

(22) Offices of a business or public utility not involving the retail sale of

goods. (Added 11-24-1998 by Ord. No. 3387-98; amended 12-27-

2006 by Ord. No. 4064-06)

(23) An office building with 5,000 square feet or more of gross floor area

may utilize a portion of the first floor, not to exceed 10% of the gross

floor area of the office building, for types of retail trade which are

ancillary to the office use and/or service workers during normal

working hours. Such retail use must be located on the first floor of

the office building, shall not be permitted in a separate building on

the site, and shall not have a separate exterior access or outdoor

identification signage. The types of retail uses permitted include:

(Added 11-24-1998 by Ord. No. 3387-98; amended 12-27-2006 by

Ord. No. 4064-06)

41

(a) Restaurants and luncheonettes, but not including drive-in nor

drive-through restaurants or restaurants which depend largely on

a take-out service for off-premises consumption.

(b) Retail uses which are normally and/or continually utilized by

offices and office workers during normal working hours and do

not primarily service the non-office worker and/or evening

shopper.

(24) Banks and financial institutions. (Added 11-24-1998 by Ord. No.

3387-98; amended 12-27-2006 by Ord. No. 4064-06)

(25) Medical and dental clinics. (Added 11-24-1998 by Ord. No. 3387-

98; amended 12-27-2006 by Ord. No. 4064-06)

(26) Adult-care centers. (Added 11-24-1998 by Ord. No. 3387-98;

amended 12-27-2006 by Ord. No. 4064-06)

(27) Retail and office uses, restaurants, lunchrooms, bars and other eating

and drinking establishments on properties with frontage on NJ Route

37 only. (Added 12-27-2006 by Ord. No. 4064-06; amended 12-18-

2007 by Ord. No. 4123-07)

(28) Veterinary clinics or hospitals. (Added 10-14-2014 by Ord. No.

4459-14)

B. Required accessory uses.

(1) Off-street parking subject to the provisions of § 348-8.20.

(2) Off-street loading subject to the provisions of § 348-8.19.

C. Permitted accessory uses.

(1) Fences subject to the provisions of § 348-8.13.

(2) Signs subject to the provisions of § 348-8.26.

(3) Bulk storage subject to the provisions of § 348-8.6.

(4) Other customary accessory uses and buildings which are clearly

incidental to the principal use and building.

(5) Outdoor display of goods subject to §§ 348-5.20 and 348-5.37.

42

D. Conditional uses subject to the provisions of Article IX of this chapter.

(1) (Reserved)

(2) Boatyards (§ 348-9.10).

(3) (Reserved).

(4) (Reserved). (Editor's Note: Former Subsection D (4), concerning

shopping centers on the south side of NJ Route 37 West, as

amended, was repealed 12-27-2006 by Ord. No. 4064-06.)

(5) (Reserved). (Editor's Note: Former Subsection D (5), quasi-public

and private club recreation areas, was repealed 8-14-1991 by Ord.

No. 2848-91. See now Subsection A (19).)

(6) Farmers' markets or auction markets (§ 348-9.20).

(7) Retail and office uses (§ 348-9.21). (Amended 11-24-1998 by Ord.

No. 3387-98; 12-27-2006 by Ord. No. 4064-06.)

(8) Billboards (§ 348-9.23) along the frontage of properties on NJ Route

No. 37 only.

(9) Trailers, excluding boat and construction trailers, used for storage

(but not including loading or unloading operations) or sale of goods

or merchandise or in which commercial or professional services are

rendered for a period not exceeding two months. No more than one

extension for reasons of hardship may be granted, except that

applications for 30 days or less may be made directly to the

Township Committee without payment of fees and without a

showing of hardship where the granting of such application would

not be detrimental to interests of the public or in conflict with the

Master Plan.

(10) Animal care facilities, other than veterinary clinics or hospitals.

(Added 10-14-2014 by Ord. No. 4459-14.)

43

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.