Opinion

Oscar Orduno Inc v. Liberty Mutual Insurance Company

Court
District Court, N.D. Texas
Filed
Dec 14, 2021
Cited by
0 cases
Authority
More cited than 29.9%

The opinion

IN THE UNITED STATES DISTRICT COURT

FOR THE NORTHERN DISTRICT OF TEXAS

DALLAS DIVISION

OSCAR ORDUNO, INC., §

§

Plaintiff, §

§ Civil Action No. 3:20-CV-3682-D

VS. §

§

LIBERTY MUTUAL INSURANCE §

CO., §

§

Defendant. §

MEMORANDUM OPINION

AND ORDER

In this suit on a payment bond under Tex. Gov’t Code Ann. § 2253.073(a) (West

2016), the court must decide whether summary judgment on defendant’s limitations defense

is precluded by a genuine issue of material fact on plaintiff’s assertion of equitable estoppel,

and whether plaintiff is entitled to summary judgment on defendant’s limitations defense.

Concluding that neither side is entitled to summary judgment, the court denies both parties’

motions.

I

In 2019 Kevin Richeson d/b/a CES Contractor (“CES”) entered into a contract with

the Texas Department of Transportation (“TxDOT”) to make improvements and repairs to

a bridge in Johnson County, Texas (the “Project”).1 Because the contract qualified as a

1Because both sides move for summary judgment, the court will recount the evidence

that is undisputed, and, when it is necessary to set out evidence that is contested, will do so

favorably to the side who is the summary judgment nonmovant in the context of that

evidence. See, e.g., GoForIt Ent., LLC v. DigiMedia.com L.P., 750 F.Supp.2d 712, 718 n.4

public work contract, CES was required to obtain a payment bond to ensure that

subcontractors were paid. Accordingly, CES, as principal, and Developers Surety and

Indemnity Company (“DSIC”), as surety, executed and issued a payment Bond (“Bond”) to

TxDOT.

Plaintiff Oscar Orduno, Inc. (“Orduno”) later entered into a subcontract with CES

under which Orduno agreed to provide temporary special shoring for the Project. Under the

subcontract, Orduno was to submit payment applications for each month that it worked, and

CES was to make payment on the applications within 30 days of receipt.

Orduno began construction of the temporary special shoring in June 2019. It

submitted payment applications for the work it performed in June, July, and August 2019.

CES made no payments on Orduno’s payment applications. In September 2019 Orduno

notified CES that it would not complete its work under the subcontract until it received

payment in full for the outstanding payment applications. CES responded that it would only

pay upon completion of the Project. CES never paid any of the amounts it owed to Orduno,

and, as a result, Orduno never returned to the Project.

On September 16, 2019 CES sued Orduno in state court (“CES Lawsuit”) based on

Orduno’s refusal to return and complete the subcontract. On the same day CES filed suit,

Orduno mailed a notice of claim (“Notice of Claim”) to DSIC claiming that CES owed it

$236,384.69 for the labor and material Orduno furnished on the Project. Defendant Liberty

(N.D. Tex. 2010) (Fitzwater, C.J.) (quoting AMX Corp. v. Pilote Films, 2007 WL 1695120,

at *1 n.2 (N.D. Tex. June 5, 2007) (Fitzwater, J.)).

- 2 -

Mutual Insurance Company (“Liberty”), as administrator for DSIC, responded to the Notice

of Claim on September 24, 2019, requesting that Orduno provide additional documents in

support of its claim. Counsel for Orduno responded to Liberty’s letter and provided the

requested documents.

On November 11, 2019 Thomas Duke (“Duke”), Liberty’s Claims Counsel, sent an

email to Chad Johnson (“Johnson”), Orduno’s counsel, advising him that he had recently

learned about the CES Lawsuit. As pertinent to the instant summary judgment motions,

Duke stated:

[b]ased on the filing of the lawsuit, I must conclude for the time

being that a legitimate dispute exists between [CES] and Orduno

regarding the validity and/or the amount of Orduno’s claim on

the Bond. As DSIC is not required to decide disputed issues of

fact and law in responding to a claim on the Bond, DSIC may

either deny the claim or leave the claim open until such time as

the parties are able to reach a resolution of the disputed claim.

. . . For now, I will leave the claim open to allow the parties a

reasonable time to resolve the disputed issues.

D. App. 65 (emphasis added). Johnson replied to Duke’s email on November 18, 2019,

stating, “Yes, please leave the claim open.” Id. at 67. On August 20, 2020 CES nonsuited

its claims against Orduno, and on September 2, 2020 the state court granted CES’s motion

to nonsuit and dismissed the CES Lawsuit. On October 5, 2020 Johnson emailed Duke to

inform him that the CES Lawsuit had been nonsuited and to re-assert Orduno’s claim on the

Bond. Duke responded that because “more than one year has passed and no lawsuit has been

filed . . . the claim is time-barred.” Id. at 69.

On November 19, 2020 Orduno filed the instant lawsuit against Liberty in Texas state

- 3 -

court, alleging claims for suit on the payment bond under Tex. Gov’t Code Ann §

2253.073(a), violation of various provisions of the Texas Insurance Code, and declaratory

judgment. Liberty removed the case to this court, moved to dismiss Orduno’s Texas

Insurance Code claims, and asserted a declaratory judgment counterclaim and request for

attorney’s fees and costs. Orduno later amended its complaint to omit its Texas Insurance

Code claim.

Liberty now moves for summary judgment. Orduno opposes the motion and cross-

moves for partial summary judgment. The court is deciding the motions on the briefs.

II

When a party moves for summary judgment on claims on which the opposing party

will bear the burden of proof at trial, the moving party can meet its summary judgment

obligation by pointing the court to the absence of admissible evidence to support the

nonmovant’s claims. See Celotex Corp. v. Catrett, 477 U.S. 317, 325 (1986). Once the

moving party does so, the nonmovant must go beyond its pleadings and designate specific

facts showing there is a genuine issue for trial. See id. at 324; Little v. Liquid Air Corp., 37

F.3d 1069, 1075 (5th Cir. 1994) (en banc) ( per curiam). An issue is genuine if the evidence

is such that a reasonable jury could return a verdict in the nonmovant’s favor. Anderson v.

Liberty Lobby, Inc., 477 U.S. 242, 248 (1986). The nonmovant’s failure to produce proof

as to any essential element of a claim renders all other facts immaterial. See TruGreen

Landcare, L.L.C. v. Scott, 512 F.Supp.2d 613, 623 (N.D. Tex. 2007) (Fitzwater, J.).

Summary judgment is mandatory if the nonmovant fails to meet this burden. Little, 37 F.3d

- 4 -

at 1076.

To be entitled to summary judgment on a claim or defense on which the moving party

will bear the burden of proof at trial, the movant “must establish ‘beyond peradventure all

of the essential elements of the claim or defense.’” Bank One, Tex., N.A. v. Prudential Ins.

Co. of Am., 878 F. Supp. 943, 962 (N.D. Tex. 1995) (Fitzwater, J.) (quoting Fontenot v.

Upjohn Co., 780 F.2d 1190, 1194 (5th Cir. 1986)). This means that the movant must

demonstrate that there are no genuine and material fact disputes and that it is entitled to

summary judgment as a matter of law. See Martin v. Alamo Cmty. Coll. Dist., 353 F.3d 409,

412 (5th Cir. 2003). “The court has noted that the ‘beyond peradventure’ standard is

‘heavy.’” Carolina Cas. Ins. Co. v. Sowell, 603 F.Supp.2d 914, 923-24 (N.D. Tex. 2009)

(Fitzwater, C.J.) (quoting Cont’l Cas. Co. v. St. Paul Fire & Marine Ins. Co., 2007 WL

2403656, at *10 (N.D. Tex. Aug. 23, 2007) (Fitzwater, J.)).

III

Liberty moves for summary judgment on the ground that Orduno’s suit on the Bond

is time-barred under Tex. Gov’t Code Ann. § 2253.078(b).

A

Tex. Gov’t Code Ann. § 2253.078(b) provides that “[a] suit on a payment bond may

not be brought by a payment bond beneficiary after the first anniversary of the date notice

for a claim is mailed under this chapter.” The parties have stipulated, for purposes of the

pending cross-motions for summary judgment, that Orduno submitted its Notice of Claim on

September 16, 2019 and filed the instant suit on the payment Bond on November 19, 2020,

- 5 -

more than one year after Orduno filed its Notice of Claim. Orduno’s claim is therefore

time-barred under § 2253.078(b) unless, as Orduno argues, Liberty is estopped from asserting

the statute of limitations as a bar to Orduno’s claims.

B

Under Texas law, “[a] plaintiff may invoke equitable estoppel to prevent an opponent

from prevailing on limitations if the opponent, his or her agent, or representatives make

representations that induce the plaintiff to delay filing suit within the applicable limitations

period.” Hill v. Bartlette, 181 S.W.3d 541, 545 (Tex. App. 2005, no pet.) (citations omitted);

see also Rendon v. Roman Catholic Diocese of Amarillo, 60 S.W.3d 389, 391 (Tex. App.

2001, pet. denied) (“It is beyond dispute that estoppel may be invoked to defeat a claim of

limitations . . . [if] the defendant engaged in conduct that induced the plaintiff to forego a

timely suit regarding a cause of action that the plaintiff knew existed.”); Vaughn v.

Sturm-Hughes, 937 S.W.2d 106, 108 (Tex. App. 1996, writ denied) (“Equitable estoppel may

bar a limitations defense when a party, his agent, or representative makes representations that

induce a plaintiff to delay filing suit until the limitations period has run.”). “Unlike deferring

accrual under the discovery rule or tolling under fraudulent concealment, the effect of

equitable estoppel is to prevent a party from raising the statute of limitation as a defense

altogether.” Centralian Controls Pty., Ltd. v. Maverick Int’l, Ltd., 2018 WL 1415650, at *6

(E.D. Tex. Feb. 23, 2018) (citing Leonard v. Eskew, 731 S.W.2d 124, 129 (Tex. App. 1987,

writ ref’d n.r.e.) (“The effect of such estoppel . . . is simply to preclude the defendant’s

interposing the limitations bar when he has induced the plaintiff not to file suit.”)). A

- 6 -

plaintiff seeking to invoke equitable estoppel as an affirmative defense in avoidance of a

defendant’s limitations defense must prove the following required elements: (1) a false

representation or concealment of material facts; (2) made with knowledge, actual or

constructive, of those facts; (3) with the intention that it should be acted on; (4) to a party

without knowledge or means of obtaining knowledge of the facts; (5) who detrimentally

relies on the representations. Exxon Mobil Corp. v. Rincones, 520 S.W.3d 572, 593-94 (Tex.

2017) (citing Johnson & Higgins of Tex., Inc. v. Kenneco Energy, Inc., 962 S.W.2d 507,

515-16 (Tex. 1998)). “When equitable estoppel is alleged in avoidance of a limitations

defense, the failure to file suit must be ‘unmixed’ with any want of diligence on the

plaintiff’s part.” Forrest v. Vital Earth Res., 120 S.W.3d 480, 487 (Tex. App. 2003, pet.

denied) (citing Lenoard 731 S.W.2d at 129; Jim Walter Homes, Inc. v. Mora, 622 S.W.2d

878, 880 (Tex. App. 1981, no writ)).

C

1

Liberty moves for summary judgment on Orduno’s equitable estoppel defense,

primarily contending that the undisputed evidence shows that Liberty made no false

representation to, or concealed any material fact from, Orduno. Liberty contends that it

specifically responded to Orduno’s counsel that (1) it appeared that a legitimate dispute

existed between Orduno and CES regarding the validity and/or amount of Orduno’s claim

on the Bond, (2) that, under such circumstances, Liberty could either deny the claim or leave

it open, and (3) that Liberty decided to leave the claim open to allow the parties a reasonable

- 7 -

time to resolve the disputed issues; that Liberty made no promise or agreement to the effect

that Orduno did not have to timely file suit or that it was agreeing to toll the one-year statute

of limitations; that Liberty did not request that Orduno refrain from joining Liberty as a party

to the pending CES Lawsuit or from filing a separate suit under the Bond, did not

acknowledge the validity or amount of the claim on the Bond, and did not promise to pay

Orduno’s claim at some point in the future; that, if Orduno disagreed with Liberty’s position

stated in the November 11, 2019 email, or if Orduno was unable to resolve its claim against

CES within a reasonable period of time, Orduno had ample time to join Liberty as a party to

the pending CES Lawsuit or to file a separate suit against Liberty on the Bond; that nothing

in the November 11, 2019 email was false or misleading; and that it is difficult to imagine

that Orduno’s counsel interpreted the November 11, 2019 email as a promise to toll the

applicable one-year limitations period and relied “on such a faulty understanding without so

much as a single telephone call or return email . . . confirming his understanding,” D. 7/16/21

Br. 11-12.

Orduno responds and cross-moves for summary judgment, contending that where, as

here, a defendant causes a plaintiff to delay filing suit past the relevant limitations period by

stating that it will address the plaintiff’s claim after the related pending litigation is resolved,

the defendant is, without exception, estopped from asserting the statute of limitations as a bar

to the plaintiff’s claims; that Liberty promised to address Orduno’s claims after the

underlying litigation had been resolved, Orduno accommodated Liberty by delaying filing

suit until after the underlying litigation had been resolved, and the court should refuse to

- 8 -

validate Orduno’s broken promise; that it is immaterial that Orduno and Liberty did not enter

into a tolling agreement; and that there was no lack of diligence on the part of Orduno’s

counsel.

Liberty maintains in response to Orduno’s cross-motion that neither the statement of

its claims counsel that “[f]or now, I will leave the claim open to allow the parties a

reasonable time to resolve the disputed issues,” nor the context of this statement expressly

or impliedly promised to leave Orduno’s claim open until after the underlying litigation was

resolved, pay the claim once the litigation had been resolved, toll the running of the one-year

limitations period, or request that Orduno forbear pursuing its claim on the Bond or filing suit

against Liberty; that the cases Orduno cites are distinguishable on their facts because each

involved (1) a claim that was valid and undisputed, (2) an unqualified promise or agreement

to pay the claim by the defendant, and (3) delay in bringing the suit in reliance on the

defendant’s promise or agreement to pay, and none of these facts is present here; and that

Orduno did not exercise diligence after receiving the November 11, 2019 email because,

inter alia:

[f]or almost 11 months, there were no follow up conversations

or communications by Orduno or its counsel with [Liberty]

regarding its claim on the Bond or to inquire about or clarify

[Liberty’s] position on the application of the statute of

limitations until after the limitations period had expired, despite

the fact that CES dismissed its lawsuit against Orduno on

September 2, 2020 before the statute of limitations expired on

September 16, 2020,

D. Resp. 11-12 (citation omitted).

- 9 -

2

As stated above, Liberty and Orduno have stipulated that, after Orduno submitted its

Notice of Claim, Liberty’s Claims Counsel responded in a November 11, 2019 email as

follows:

[b]ased on the filing of the [CES L]awsuit, I must conclude for

the time being that a legitimate dispute exists between [CES]

and Orduno regarding the validity and/or the amount of

Orduno’s claim on the Bond. As DSIC is not required to decide

disputed issues of fact and law in responding to a claim on the

Bond, DSIC may either deny the claim or leave the claim open

until such time as the parties are able to reach a resolution of

the disputed claim. . . . For now, I will leave the claim open to

allow the parties a reasonable time to resolve the disputed

issues. Until then, DSIC is not in a position to determine either

the validity or the amount of the claim submitted by Orduno.

D. App. 65 (emphasis added).

For largely the reasons explained in Liberty’s motion and response, see D. 7/16/21 Br.

10-11; D. Resp. 5-7, the court concludes that a reasonable jury could find on the basis of the

November 11, 2019 email that Liberty only committed to hold Orduno’s claim open for “a

reasonable time,” and did not promise to hold the claim open or otherwise imply that Liberty

would hold the claim open beyond the one-year statute of limitations.

But a reasonable jury could also find based on the same evidence (i.e., the November

11, 2019 email) that Liberty represented that it would keep Orduno’s claim open until

Orduno and CES resolved their underlying dispute. This is because in the sentence

immediately preceding the statement that Liberty would leave the claim open “for now . . .

to allow the parties a reasonable time to resolve the disputed issues,” Liberty stated that

- 10 -

because a legitimate dispute existed between Orduno and CES, Liberty had the option of

either denying the claim or “leav[ing] the claim open until such time as the parties are able

to reach a resolution of the disputed claim.” D. App. 65 (emphasis added). Orduno argues

that Liberty “presented its two alternatives to Orduno: (1) deny the claim, or (2) keep the

claim open until the dispute was resolved. In its next sentence [Liberty] stated that it was

selecting the latter, to which Orduno agreed by responding ‘yes, please keep the claim

open.’” P. Reply 7 n.2.

The court concludes that this is also a reasonable interpretation of the November 11,

2019 email. And under Orduno’s reading of the November 11, 2019 email, a reasonable jury

could also find that Liberty’s representation that it would hold Orduno’s claim open until

Orduno resolved the underlying dispute with CES was misleading if Liberty only intended

to keep the claim open until the statute of limitations expired and not, as it represented, until

the parties reached a resolution of the disputed claim. See, e.g. Forrest, 120 S.W.3d at 487

(“The cases finding equitable estoppel are cases that involve promises by a defendant, which

are not intended to be fulfilled, but instead are intended to induce the plaintiff to delay filing

of the suit until after limitations has run.” (citing cases)). Because there are at least two

reasonable views of the summary judgment evidence,2 the court concludes that a genuine

2“When this court denies rather than grants summary judgment, it typically does not

set out in detail the evidence that creates a genuine issue of material fact.” Valcho v. Dall.

Cnty. Hosp. Dist., 658 F.Supp.2d 802, 812 n.8 (N.D. Tex. 2009) (Fitzwater, C.J.) (citing

Swicegood v. Med. Protective Co., 2003 WL 22234928, at *17 n.25 (N.D. Tex. Sept. 19,

2003) (Fitzwater, J.)).

- 11 -

issue of material fact precludes the entry of summary judgment with regard to the first

element of Orduno’s equitable estoppel defense, i.e., whether Liberty made a false

representation or concealment of material fact. Accordingly, because Orduno has raised a

genuine issue of material fact, but has not established the first element of its estoppel defense

beyond peradventure, the court denies Orduno’s motion for summary judgment.

3

Liberty also appears to move for summary judgment on the ground that Orduno did

not exercise diligence in pursuing its claim. It maintains in its motion that Orduno had ample

time to join Liberty as a party to the pending CES Lawsuit or to file a separate suit against

Liberty on the Bond and that

[f]rankly, it is also quite difficult to conceive of Johnson, a

licensed Texas attorney, being “ . . . a party without knowledge

or the means of knowledge of the real facts . . .” or as a person

who, when he received the Nov. 11 E-mail, would have

interpreted anything Duke said as a promise to toll the

applicable one-year limitations period and, thereafter, have

relied on such a faulty understanding without so much as a

single telephone call or return email to Duke confirming his

understanding. . . . An allegation of inducement to delay filing

suit cannot be mixed with any want of diligence on Orduno’s

part.

D. 7/16/21 Br. 11-12.

Orduno responds that it did not exercise a lack of diligence, but

it merely relied on the promise of a fellow member of the bar to

keep the claim open until the underlying lawsuit was resolved .

. . [and] then did exactly what Defendant asked [by] wait[ing]

until the underlying Lawsuit was resolved and promptly

reach[ing] back out to Defendant to reassert Orduno’s claim

- 12 -

once the order dismissing the underlying Lawsuit was final.

P. 8/6/21 Br. 13.3

As stated above, when equitable estoppel is alleged in avoidance of a limitations

defense, the failure to file suit must be “unmixed” with any want of diligence on the

plaintiff’s part. Leonard, 731 S.W.2d at 129. But whether Orduno was diligent or whether

it reasonably relied on Liberty’s alleged misrepresentations is a fact question for the jury.

See Tech Pharm. Servs., LLC v. Alixa Rx LLC, 2017 WL 3167652, at *3 (E.D. Tex. July 25,

2017) (citing Quintel Tech. Ltd. v. Huawei Techs. USA, Inc., 2016 WL 5423178, at *9 (E.D.

Tex. Sept. 27, 2016) (“[T]he exercise of reasonable diligence is usually a question of fact.”)).

Because a reasonable jury could find, based on the evidence,4 that Orduno acted diligently

in pursuing its claim under Tex. Gov’t Code Ann § 2253.073(a),5 the court denies Liberty’s

motion for summary judgment to the extent Liberty maintains that Orduno failed to exercise

diligence in pursuing its claim.

3In its reply, Orduno explains that “the court in the underlying lawsuit had plenary

power for thirty days after the dismissal on September 2, 2020, meaning the dismissal order

was not final until Friday, October 2, 2020. Orduno reached back out to Defendant to

reassert its claim on the bond on Monday, October 5, 2020—the first business day after the

order was final.” P. Reply 2.

4As stated above, see supra note 2, “[w]hen this court denies rather than grants

summary judgment, it typically does not set out in detail the evidence that creates a genuine

issue of material fact.” Valcho, 658 F.Supp.2d at 812 n.8 (citing Swicegood, 2003 WL

22234928, at *17 n.25).

5Under Tex. Gov’t Code Ann. § 2253.073(a), Orduno had a right to sue on the

payment bond if its claim “[wa]s not paid before the 61st day after the date the notice for the

claim is mailed.”

- 13 -

4

Although Liberty broadly states in its motion for summary judgment that “[t]here is

no evidence of the required elements of the affirmative defense of equitable estoppel,” D.

7/16/21 Br. 10, it does not specifically point to the absence of evidence with respect to any

of the remaining elements of Orduno’s estoppel defense.6 Accordingly, because Orduno has

created a genuine issue of material fact with respect to the first element of its estoppel

defense and with respect to the question of diligence, the court concludes that Liberty is not

entitled to summary judgment on Orduno’s claim under Tex. Gov’t Code Ann § 2253.073(a)

or request for declaratory judgment.

6For example, Liberty’s motion does not specifically address the fourth and fifth

elements of Orduno’s collateral estoppel defense, i.e., that plaintiff was a party without

knowledge or means of obtaining knowledge of the facts who detrimentally relied on

defendant’s representations. Johnson & Higgins of Tex., Inc., 962 S.W.2d at 515-16. At

least one Texas court of appeals has observed that there appears to be no Texas “case holding

that a genuine issue of material fact existed concerning the fourth and fifth elements of the

equitable-estoppel defense to avoid application of the statute of limitations when the ‘party

without knowledge or means of [obtaining] knowledge of the facts’ was a party represented

by counsel.” Woods v. Soules, 2018 WL 2248488, at *2 (Tex. App. May 17, 2018, pet.

denied) (alteration in original) (citing cases). But because Liberty does not clearly move for

summary judgment with respect to the fourth and fifth elements of Orduno’s estoppel

defense—it states only that “it is . . . quite difficult to conceive of Johnson, a licensed Texas

attorney, being ‘ . . . a party without knowledge or the means of knowledge of the real facts,”

D. 7/16/21 Br. at 11—the court will not address what impact, if any, the presence of counsel

has on Orduno’s ability to satisfy the estoppel elements.

- 14 -

os * os

For the reasons explained, the court denies Liberty’s motion for summary judgment

and denies Orduno’s cross-motion for summary judgment.

SO ORDERED.

December 14, 2021.

SIpNIA A.

SENIOR JUDGE

-15-

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.