Opinion

Elvis Presley Enterprises, Inc. v. City of Memphis

Court
District Court, W.D. Tennessee
Filed
Oct 21, 2020
Cited by
0 cases
Authority
More cited than 29.7%

“The ripeness doctrine not only depends on the finding of a case and controversy and hence jurisdiction under Article III, but it also requires that the court exercise its discretion to determine if judicial resolution would be desirable under all of the circumstances.”

How later courts described this case

  • “The ripeness doctrine not only depends on the finding of a case and controversy and hence jurisdiction under Article III, but it also requires that the court exercise its discretion to determine if judicial resolution would be desirable under all of the circumstances.”
  • “[W]here, as here, the basis for the court's federal jurisdiction is the existence of a federal question, federal law governs. Therefore, the Court will analyze the ripeness of Plaintiffs’ claims under federal law.”
  • “By finality we mean that the actions of the city were such that further administrative action by [the plaintiff] would not be productive.”
  • “Pursuing this ability to appeal . . . .”

Written by the judges who cited it.

The opinion

IN THE UNITED STATES DISTRICT COURT

FOR THE WESTERN DISTRICT OF TENNESSEE

WESTERN DIVISION

)

ELVIS PRESLEY ENTERPRISES, )

INC., EPPF, LLC, AND )

GUESTHOUSE AT GRACELAND, LLC, )

)

Plaintiffs, )

)

v. ) No. 2:18-cv-2718

)

CITY OF MEMPHIS, TENNESSEE, )

)

Defendant. )

)

)

ORDER

This is an action under 42 U.S.C. § 1983 alleging

retaliation for First Amendment protected conduct. Plaintiffs

Elvis Presley Enterprises, Inc., EPPF, LLC, and Guesthouse at

Graceland, LLC (collectively “Plaintiffs” or “EPE”) allege that

the City of Memphis (“the City”), through its attorney, took an

action adverse to EPE because EPE had filed state court lawsuits

affecting the City. (D.E. No. 1 ¶¶ 71-74.) Defendant the City

moved for summary judgement (the “Motion”) on February 26, 2020.

(D.E. No. 199.) The City supplemented its Motion on July 30,

2020, and added a motion for attorneys’ fees (the Motion for

Fees). (D.E. No. 310.) The parties have responded and replied.

(D.E. No. 312; D.E. No. 314; D.E. No. 318-1.) The City moved to

exclude testimony from consideration (“Motion to Exclude”) on

September 14, 2020. (D.E. No. 316.) EPE responded to the Motion

to Exclude on September 28, 2020. (D.E. No. 320.) For the

following reasons, the Motion to Exclude is DENIED as moot, the

Motion for Fees is DENIED, and the Motion is GRANTED.

I. Background

EPE owns and operates Graceland, the former home of Elvis

Presley and a tourist attraction in Memphis, Tennessee. (Pl.’s

Statement of Additional Undisputed Material Facts, D.E. No. 312-

2 ¶ 1.)

In 2014, EPE undertook the Graceland Project, a planned

redevelopment of Graceland. (Pl.’s Resp. to Def.’s Statement of

Undisputed Material Facts, D.E. No. 312-1 ¶ 3.) To help fund

the Graceland Project, EPE submitted EPE’s Economic Impact Plan

for Graceland Economic Development Area (the “Plan”) to the City,

Shelby County, Tennessee (the “County”), and the Economic

Development Growth Engine Industrial Development Board of the

City of Memphis and County of Shelby (“EDGE”). (Id.) The Plan

included a request for tax increment financing, which would

earmark a certain amount of property taxes to support the

Graceland Project. (Id.) EDGE, the City, and the County

approved the Plan in late 2014. (Id. ¶ 5.)

In 2017, hoping to expand the Graceland Project, EPE

submitted its Supplement to Economic Impact Plan for Graceland

Economic Growth Area (the “Supplemental Plan”) to EDGE. (Id. ¶

6.) The Supplemental Plan requested approval, among other

things, of an arena capable of seating 6,200 people (the

“Arena”). (Id.)

While EDGE considered the Supplemental Plan, Memphis

Basketball, LLC (“Memphis Basketball”) contacted the City.

(Def.’s Statement of Undisputed Material Fact, D.E. No. 199-1 ¶

7.) Memphis Basketball owns and operates the Memphis Grizzlies,

a National Basketball Association franchise. (Id. ¶ 1.) Memphis

Basketball contended that the City’s approval of the Arena would

violate a contract between Memphis Basketball and the City (the

“Arena Use Agreement”), prohibiting the City from providing

public financing for competing entertainment facilities. (Id.

¶ 7.)

EDGE told EPE that EDGE would not move forward with the

approval process for the Supplemental Plan based on Memphis

Basketball’s concerns. (See id. ¶ 11.)

EPE responded by filing a declaratory judgment action in

Tennessee Chancery Court. (D.E. No. 312-1 ¶ 12.) EPE asked the

court to interpret the Arena Use Agreement. (Id.) EPE contended

that the Agreement did not prohibit the City from approving the

Arena. (Id.) The Chancery Court dismissed the case, concluding

that EPE had to demand that EDGE consider and vote on the

Supplemental Plan before EPE could seek a declaratory judgment.

(Id. ¶ 13.)

In February 2018, after the Chancery Court’s decision, EPE

asked EDGE to vote on the Supplemental Plan at its next meeting.

(D.E. No. 312-2 ¶ 18.) EDGE did not do so. (See D.E. No. 312-

1 ¶ 15.) EPE sued EDGE attempting to force EDGE to vote on the

Supplemental Plan. (Complaint, D.E. No. 1 ¶ 56.) Eventually,

however, EDGE approved the Supplemental Plan but conditioned its

approval on a court order or written agreement declaring that

approval of the Arena would not breach the Arena Use Agreement.

(Id. ¶ 14)

The County also approved the request in the Supplemental

Plan for increased tax increment financing to support the

expanded Graceland Project. (Id. ¶ 16.) As EDGE had done, the

County conditioned its approval on a court order or written

agreement declaring that approval of the Arena would not breach

the Arena Use Agreement. (Id.)

In late June 2018, EPE filed a declaratory judgment action

in Tennessee Chancery Court against the City, Memphis Basketball,

and the County to determine whether approval of the Arena would

violate the Arena Use Agreement. (Id. ¶ 17)

While that case was pending, EPE sought to move forward

with parts of the expanded Graceland Project. (See D.E. No.

312-1 ¶ 19.) EPE submitted its Application for Planned

Development Approval (the “Development Application”) to the

Memphis and Shelby County Office of Planning and Development

(the “OPD”) in August 2018. (Id.) The Development Application

included the Arena. (Id. ¶ 21.)

The OPD neither approved nor denied the Development

Application. (See id. ¶ 27.) Instead, it decided to table

consideration of the Application indefinitely, until the

Chancery Court litigation over the Arena had concluded. (Id.)

The OPD’s decision followed instructions from the Memphis City

Attorney. (See id.) In an email, the OPD planning director

told EPE that:

Earlier this week, the City Attorney requested

that [the Development Application] be deferred

until the pending litigation in Chancery Court

is concluded. I have conferred with my in-

house Division attorney and he agrees.

Therefore, [the Development Application] will

not be considered . . . until such time as the

pending legislation [sic] is concluded.

(Id.)

EPE had two administrative options following deferral of

the Development Application. (Id. ¶ 35.) EPE could resubmit

the Development Application without including the Arena as part

of the application. (Id.) EPE could also appeal the decision

to defer consideration of the Development Application by the OPD

planning director. (Id.) EPE has not taken either

administrative action. (See id. ¶ 36.)

EPE filed its complaint in this case on October 16, 2018.

(D.E. No. 1.) EPE alleges that the City, through the city

attorney, blocked the OPD from considering the Development

Application. (D.E. No. 1 ¶ 82.) EPE alleges that the City did so

for two reasons. (Id. ¶¶ 82, 91.) The first is punitive. The

City wanted to punish EPE for disagreeing with the City about

the contract with Memphis Basketball, obtaining EDGE and the

County’s conditional approvals of the Supplemental Plan, suing

the City twice in Chancery Court, and commenting publicly about

those matters. (Id. ¶ 82.) The second reason is coercive. The

City wanted to deter EPE from maintaining its latest suit against

the City and from pursuing similar conduct designed to protect

EPE’s rights and interests. (Id. ¶ 91.)

On November 6, 2018, the City filed a motion to dismiss for

failure to state a claim. (D.E. No. 8.) The motion to dismiss

was granted on EPE’s state law claims of interference with

contractual relationships and interference with business

relationships and denied on EPE’s § 1983 claim. (D.E. No. 63.)

II. Jurisdiction

The Court has federal question jurisdiction. Under 28

U.S.C. § 1331, district courts have original jurisdiction “of

all civil actions arising under the Constitution, laws, or

treaties of the United States.” EPE asserts a right to relief

against the City under § 1983. That claim arises under the laws

of the United States.

III. Standard of Review

Under Federal Rule of Civil Procedure 56, on motion of a

party, the court “shall grant summary judgment if the movant

shows that there is no genuine dispute as to any material fact

and the movant is entitled to judgment as a matter of law.” Fed.

R. Civ. P. 56(a). “[T]he moving party is entitled to summary

judgment when the nonmoving party ‘fails to make a showing

sufficient to establish the existence of an element essential to

that party’s case, and on which that party will bear the burden

of proof at trial.’” George v. Youngstown State University, 966

F.3d 446, 458 (6th Cir. 2020) (quoting Celotex Corp. v. Catrett,

477 U.S. 317, 322–23 (1986)).

The non-moving party has the duty to point out specific

evidence in the record sufficient to justify a jury decision in

its favor. See Fed. R. Civ. P. 56(c)(1); InterRoyal Corp. v.

Sponseller, 889 F.2d 108, 111 (6th Cir. 1989). When confronted

with a properly supported motion for summary judgment, the non-

moving party must set forth specific facts showing that there is

a genuine dispute for trial. See Fed. R. Civ. P. 56(c). A

genuine dispute for trial exists if the evidence is “‘such that

a reasonable jury could return a verdict for the nonmoving

party.’” See Wasek v. Arrow Energy Servs., 682 F.3d 463, 467

(6th Cir. 2012) (quoting Anderson v. Liberty Lobby, Inc., 477

U.S. 242, 248 (1986)). “[I]n order to survive a summary

judgement motion, the non-moving party ‘must do more than simply

show that there is some metaphysical doubt as to the material

facts.’” Lossia v. Flagstar Bancorp, Inc., 895 F.3d 423, 428

(6th Cir. 2018) (quoting Matsushita Elec. Indus. Co. v. Zenith

Radio Corp., 475 U.S. 574, 586 (1986)).

Although summary judgment must be used carefully, it “is an

integral part of the Federal Rules as a whole, which are designed

to secure the just, speedy, and inexpensive determination of

every action[,] rather than a disfavored procedural shortcut.”

FDIC v. Jeff Miller Stables, 573 F.3d 289, 294 (6th Cir. 2009)

(internal quotation marks and citations omitted).

IV. Analysis

A. Ripeness

The City argues that EPE’s retaliation claim is not ripe

because there has not been a final decision on the Development

Application. (D.E. No. 310.) The Court rejected the City’s

ripeness claim at the motion to dismiss stage because the Court

necessarily accepted two assertions made by EPE as true. See

Elvis Presley Enterprises, Inc. v. City of Memphis, Tenn., No.

2:18-cv-2718, 2019 WL 3804265, at *6 (W.D. Tenn. Aug. 13, 2019)

(“EPE I”). At this stage, those assertions no longer need be

accepted. First, the Court accepted that the Development

Application did not include the Arena. See id. at *6 n.9. This

meant that EPE had no way to resubmit the Development Application

without the inclusion of the Arena because the Development

Application purportedly already did not include the Arena. See

id. It is now clear that the Development Application did include

the Arena. EPE would be able to resubmit the Development

Application without the inclusion of the Arena to determine

whether the Development Application could be approved. Second,

the Court accepted as true that EPE had no right to appeal from

the indefinite delay of the Development Application. See id. at

*6 n.10. It is now clear that EPE could appeal the decision to

delay the Development Application indefinitely. The Court must

consider the City’s ripeness argument again at this stage of the

litigation.

Whether a claim is ripe for decision is governed by federal

law. See Brown v. Ferro Corp., 763 F.2d 798, 801 (6th Cir. 1985)

(“The ripeness doctrine not only depends on the finding of a

case and controversy and hence jurisdiction under Article III,

but it also requires that the court exercise its discretion to

determine if judicial resolution would be desirable under all of

the circumstances.”); see also Leonard v. Planning Bd. of the

Town of Union Vale, 154 F. Supp. 3d 59, 65 n.5 (S.D.N.Y. 2016)

(“[W]here, as here, the basis for the court's federal

jurisdiction is the existence of a federal question, federal law

governs. Therefore, the Court will analyze the ripeness of

Plaintiffs’ claims under federal law.”). The City relies on the

“finality” requirement, a ripeness doctrine particular to land

use cases. See Miles Christi Religious Order v. Twp. of

Northville, 629 F.3d 533, 537 (6th Cir. 2010). Finality requires

that the relevant regulatory body issue a final decision before

claims arising from land disputes ripen. See id.; see also

Bannum, Inc. v. City of Louisville, Ky., 958 F.2d 1354, 1362-63

(6th Cir. 1992) (“By finality we mean that the actions of the

city were such that further administrative action by [the

plaintiff] would not be productive.”).

1. The finality requirement applies to EPE’s claim.

Although the finality requirement originated in the context

of takings claims, see Williamson Cty. Reg'l Planning Comm'n v.

Hamilton Bank of Johnson City, 473 U.S. 172, 186 (1985),

overruled on other grounds by Knick v. Twp. of Scott, 139 S. Ct.

2162 (2019), two Sixth Circuit cases have extended the finality

requirement to First Amendment retaliation claims, see Dubuc v.

Twp. of Green Oak, 406 F. App'x 983, 990-91 (6th Cir. 2011);

Insomnia, Inc. v. City of Memphis, 278 F. App'x 609, 616 (6th

Cir. 2008). The Insomnia court adopted the following two-prong

test for determining whether the finality requirement should

preclude a First Amendment retaliation claim: “‘(1) whether the

[plaintiffs] experienced an immediate injury as a result of [the

defendant's] actions and (2) whether requiring the [plaintiffs]

to pursue additional administrative remedies would further

define their alleged injuries.’” Insomnia, 278 F. App’x at 615

(quoting Murphy v. New Milford Zoning Comm'n, 402 F.3d 342, 351

(2d Cir. 2005)).

In Insomnia, plaintiffs claimed their application to

subdivide two parcels of land into three was denied because of

animus against adult businesses. Id. at 610-11. The Land Use

Control Board, which had denied the application, required

plaintiffs to resubmit it as a planned development, rather than

a subdivision. Id. at 611. Plaintiffs instead appealed to the

City Council, which rejected the appeal. Id. Plaintiffs then

filed suit in federal court. Id.

The finality requirement applied in Insomnia based on the

two-prong Murphy test. Insomnia, 278 F. App’x at 615-16; see

Murphy, 402 F.3d at 351. Under the first prong, plaintiffs had

not suffered an immediate injury because if they had resubmitted

their application as a planned development “there [was] a chance

that their proposal [would] be approved” and “under such

circumstances, Plaintiffs [would] be entitled to proceed with

the subdivision of their land,” which would “obviate the need

for federal review.” Id. at 615. Under the second prong,

requiring resubmission of the application as a planned

development would, if the plan were rejected, “further define

the contours of Plaintiffs’ claim of First Amendment

retaliation.” Id. at 616.

EPE has experienced no immediate injury.

EPE contends not only that it has suffered an immediate

injury, but that, because its injury arises outside the land use

context altogether, the finality requirement should not apply.

EPE claims that the retaliatory act was not the OPD’s decision

to delay indefinitely, but the city attorney’s interference with

the OPD’s decision.

EPE’s injury arises in the context of land use.

Interference by the city attorney, on its own, would not be an

injury. In Dubuc, the city attorney advised the Building Zoning

Administrator to issue no more permits for construction work on

a parcel because plaintiffs had filed a lawsuit against the city.

Dubuc, 406 F. App’x 983, 985 (6th Cir. 2011). Despite the

retaliatory action by the city attorney, the ripeness issue was

“tied to [the] finality of the underlying land use decision.”

EPE I, 2019 WL 3804265, at *6 n.11; see Dubuc, 406 F. App’x at

990-91. In this case, despite the alleged retaliation by the

city attorney, the injury stems from the land use decision. EPE

I, 2019 WL 3804265, at *10 n.14 (“The source of EPE's harm is

the OPD's decision, allegedly instructed by the city attorney,

to defer consideration of the Development Application

indefinitely.”).

EPE also alleges immediate injury stemming from the OPD’s

decision to delay the Development Plan indefinitely. EPE claims

that it is now subject to a “Kafkaesque nightmare” of bureaucracy

requiring it to resubmit the Development Plan without the Arena

or to appeal the OPD’s decision. Resubmitting an altered plan

(Insomnia) and appealing from an adverse land use decision

(Dubuc), EPE’s available administrative remedies, are exactly

the administrative remedies that were available in the Sixth

Circuit cases applying the finality requirement to retaliation

claims. See Insomnia, 278 F. App’x at 615 (“If Plaintiffs file

a renewed plan as a proposed development . . . .”); Dubuc, 406

F. App’x at 991 (“Pursuing this ability to appeal . . . .”).

Implicit in those decisions is that pursuit of the administrative

remedies themselves cannot be the immediate injury. See Dubuc,

406 F. App’x at 991; Insomnia, 278 F. App’x at 615.

EPE alleges that it faces the costs of its inability to

move forward with development because of the OPD decision to

delay the Development Application indefinitely. That is exactly

the type of non-immediate injury that plaintiffs in Dubuc and

Insomnia faced. See Dubuc, 406 F. App’x at 990-91; Insomnia,

278 F. App’x at 615.

EPE has experienced no immediate injury.

Requiring finality would “further define the

contours” of the retaliation claim.

The alleged injuries could be further defined by pursuit of

administrative remedies. That demonstrates the finality

requirement should be applied to EPE’s claim. As in Insomnia,

if a resubmission of the Development Plan that did not include

the Arena were denied, or an appeal were denied, those denials

would “further define the contours” of EPE’s retaliation claim

because denial could be evidence of further retaliation.

Insomnia, 278 F. App’x at 616.

Because EPE has experienced no immediate injury and any

injury would be further defined by EPE’s pursuit of its

administrative remedies, the finality requirement applies to

EPE’s claims.

2. EPE has not received a final decision, and so its

claim fails to satisfy the finality requirement.

The finality requirement can be satisfied by exhaustion of

administrative remedies or futility. See Bannum, 958 F.2d at

1363 (“This test, of course, can be met by the exhaustion of

remedies. It can also be met by other evidence and can be

satisfied prior to compliance with all the required procedures.

. . . The ‘futility exception’ to the threshold requirement of

finality . . . is but another way of articulating the analysis

explained above.”). The City asserts that EPE has not exhausted

its administrative remedies. EPE has not claimed that it would

be futile to do so.

The undisputed evidence shows that EPE had two

administrative options. (See D.E. No. 312-1 at 8515-16.) EPE

could revise its application such that the Arena was not included

as part of the Development Application and resubmit the

Development Application for consideration. (Id.) EPE could

appeal the decision to the Memphis and Shelby County Board of

Adjustment. (Id.)

Failure to pursue either of its remedies

renders EPE’s claim unripe.

It is not apparent that an appeal would not resolve EPE’s

harm. For example, in Dubuc, the city attorney directed the

Building Zoning Administrator to stop issuing construction

permits for plaintiffs’ parcel. The issue was not that the

permits had yet to be decided. Even if the delayed permits had

been constructively denied, the First Amendment retaliation

claim would not have been ripe because plaintiffs had not

appealed that denial. Dubuc, 406 F. App’x at 990-91. The claim

was not ripe because it was “not apparent that [plaintiffs’]

issues could not be resolved with further administrative action.”

Id. at 991.

EPE’s claim could also be resolved by resubmitting the

Development Plan without inclusion of the Arena. In Insomnia,

resubmission of the subdivision plan as a planned development

was required to give the city more control. Insomnia, 278 F.

App’x at 615. If the Arena were removed from the Development

Plan and the Development Plan were resubmitted, giving the City

assurance that there would be no violation of the Arena Use

Agreement, “there is a chance [plaintiffs’] proposal will be

approved.” Insomnia, 278 F. App’x at 615.

Finding EPE’s claim unripe promotes policy

considerations.

As in Insomnia, three of four policy concerns promoted by

finality are furthered by finding that there has been no final

decision in this case. Insomnia, 278 F. App’x at 616.

First, “requiring a claimant to obtain a final decision

from a local land use authority aids in the development of a

full record.” Id. at 613 (quoting Murphy, 402 F.3d at 348). In

this case, a fuller record developing the contours of the injury

would help the Court make its determination about whether a

“person of ordinary firmness” would be deterred by that injury

from continuing protected First Amendment conduct. See Thaddeus-

X v. Blatter, 175 F.3d 378, 397 (6th Cir. 1999).

Second, finality “enforces the long-standing principle that

disputes should be decided on non-constitutional grounds

whenever possible.” Insomnia, 278 F. App’x at 613 (quoting

Murphy, 402 F.3d at 348). If relief can be had through the

administrative process in this case, which cannot be determined

without requiring finality, the Court can avoid “judicial

entanglement in [a] constitutional dispute[].” Id. (quoting

Murphy, 402 F.3d at 348).

Third, “federalism principles also buttress the finality

requirement.” Id. (quoting Murphy, 402 F.3d at 348). Requiring

a final decision about the land use issue in this case “evinces

the judiciary’s appreciation that land use disputes are uniquely

matters of local concern more aptly suited for local resolution.”

Id. (quoting Murphy, 402 F.3d at 348).

B. Attorney’s Fees

The City argues that it is entitled to an award of

attorneys’ fees pursuant to 42 U.S.C. § 1988(b). “[W]hile

prevailing plaintiffs are entitled to attorneys[’] fees under

that statute in all but special circumstances, prevailing

defendants are entitled to attorneys[’] fees much less

frequently.” Wolfe v. Perry, 412 F.3d 707, 720 (6th Cir. 2005).

“[A] prevailing defendant should only recover upon a finding by

the district court that ‘the plaintiff’s action was frivolous,

unreasonable, or without foundation, even though not brought in

subjective bad faith.’” Wayne v. Village of Sebring, 36 F.3d

517, 530 (6th Cir. 1994) (quoting Hughes v. Rowe, 449 U.S. 5, 14

(1980)) (emphasis in original). “Application of these standards

requires inquiry into the plaintiffs’ basis for bringing suit.”

Smith v. Smythe-Cramer Co., 754 F.2d 180, 183 (6th Cir. 1985).

“The Supreme Court has noted, however, that ‘[i]n applying these

criteria, it is important that a district court resist the

understandable temptation to engage in post hoc reasoning by

concluding that, because a plaintiff did not ultimately prevail,

his action must have been unreasonable or without foundation.’”

Wolfe, 412 F.3d at 720 (quoting Christiansburg Garment Co. v.

EEOC, 434 U.S. 412, 421-22 (1978)).

Although, as the City argues, EPE’s allegation that the

Arena was not included in the Development Application was

inaccurate, EPE’s suit is not frivolous, unreasonable, or without

foundation. The City relies on Owens v. Swan, 962 F. Supp. 1436

(D. Utah 1997) for the proposition that an inaccurate or

untruthful representation to the Court warrants an award of fees

to the prevailing defendant. However, in Owens, the inaccurate

representation formed the basis for a claim in the complaint.

Owens, 962 F. Supp. at 1442 (“[T]he record establishes that

plaintiffs’ amended complaint . . . was based on a factual

allegation which was untrue”). Here, the inaccurate

representation was important, but ancillary, to the alleged

retaliation that formed the basis for EPE’s claim. The Court

declines to award attorneys’ fees under 42 U.S.C. § 1988(b).

V. Conclusion

For the forgoing reasons, the Motion to Exclude is DENIED

as moot, the Motion for Fees is DENIED, and the Motion is GRANTED.

So ordered this _21st_ day of October, 2020.

/s/ Samuel H. Mays, Jr.

SAMUEL H. MAYS, JR.

UNITED STATES DISTRICT JUDGE

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.