Opinion

Northwest Environmental Defense Center v. U.S. Army Corps of Engineers

Court
District Court, D. Oregon
Filed
Sep 1, 2021
Cited by
0 cases
Authority
More cited than 28.7%

no deference owed where agency’s interpretation advanced in a legal brief is a “nothing more than a convenient litigating position” or a “post hoc rationalization . . . to defend past agency action against attack.”

How later courts described this case

  • no deference owed where agency’s interpretation advanced in a legal brief is a “nothing more than a convenient litigating position” or a “post hoc rationalization . . . to defend past agency action against attack.”
  • holding ESA “§ 7(a)(2)’s no-jeopardy duty covers only discretionary agency actions and does not attach to actions . . . that an agency is required by statute to undertake[.]”
  • finding irreparable harm where the highly precarious status and low abundance of the species made them vulnerable to extinction and operation of the dams caused substantial harm to the salmonids and accounted for most mortality of juveniles migrating downriver
  • where fish species had low abundance, declining productivity, and low spatial distribution, and dam operations harmed the species, injunction was warranted pending a new biological opinion

Written by the judges who cited it.

The opinion

IN THE UNITED STATES DISTRICT COURT

FOR THE DISTRICT OF OREGON

NORTHWEST ENVIRONMENTAL No. 3:18-cv-00437-HZ

DEFENSE CENTER, WILDEARTH

GUARDIANS, and NATIVE FISH OPINION & ORDER

SOCIETY,

Plaintiffs,

v.

UNITED STATES ARMY CORPS OF

ENGINEERS and NATIONAL MARINE

FISHERIES SERVICE,

Defendants.

CITY OF SALEM and MARION COUNTY,

Intervenor-Defendants.

HERNÁNDEZ, District Judge:

Before the Court is Plaintiffs Northwest Environmental Defense Center, WildEarth

Guardians, and Native Fish Society’s motion for injunctive relief. The Court GRANTS in part

and DENIES in part Plaintiffs’ motion.

BACKGROUND

The history of this case is well known to the parties and was thoroughly discussed in the

Court’s Opinion and Order on Defendants’ liability. See Nw. Env’t Def. Ctr. v. U.S. Army Corps

of Eng’rs (“NEDC”), 479 F. Supp. 3d 1003 (D. Or. 2020). Relevant here, Upper Willamette

River (“UWR”) Chinook salmon and UWR steelhead (collectively “salmonids”) were listed as

“threatened” under the Endangered Species Act (“ESA”) in 1999. 50 C.F.R. § 223.102. The

salmonids’ status remains threatened; however, Defendant National Marine Fisheries Service

(“NMFS”), the federal agency responsible for administration of the ESA with respect to the

listed salmonids, has recently been considering downgrading their status to “endangered.”

USACE 049439. Defendant U.S. Army Corps of Engineers (“Corps”) operates the Willamette

Valley Project (“WVP”)—a network of 13 federally owned dams and related facilities located in

the Willamette River Basin.

In 2008, NMFS, in consultation with the Corps, issued a Biological Opinion (“BiOp”)

analyzing the impacts the WVP has on the listed salmonids. NMFS found that “lack of passage is

one of the single most significant adverse effects on both the fish and their habitat,” and “[w]ater

quality problems are one of the major limiting factors in [downstream] habitat[.]” BiOp 9-33, 9-

52, 9-61.1 NMFS set forth a suite of Reasonable and Prudent Alternatives (“RPAs”) necessary to

avoid jeopardizing the existence and recovery of the listed salmonids and destroying or adversely

modifying the salmonids’ critical habitat. Under the relevant RPAs, the Corps is required to:

(1) Outplant adult salmonids above Green Peter Dam (South Santiam subbasin) if

deemed necessary by NMFS.

1 The 2008 BiOp begins at NMFS 0001. See Notice of Lodging of the Admin. Record, ECF 88.

For ease of reference, the Court refers to the BiOp’s original page numbers rather than the Bates

numbers.

(2) By May 2011 and until permanent downstream passage facilities are constructed,

carry out and study interim operational measures to pass juvenile salmonids as safely

and efficiently as possible downstream through WVP reservoirs and dams, including

such measures as reservoir drawdowns, pulsing flow releases, use of non-turbine

passage routes, and spill operations.

(3) Beginning in 2008, conduct a deep drawdown at Fall Creek Reservoir (Middle Fork

Willamette subbasin) to pass juvenile fish more safely through the regulating outlet.

(4) Build and begin operating permanent downstream fish passage facilities at:

(a) Cougar Dam (McKenzie subbasin) by 2015;

(b) Lookout Point Dam and Dexter Dam (Middle Fork Willamette subbasin) by

March 2022; and

(c) Detroit Dam and Big Cliff Dam (North Santiam subbasin) by March 2024.

(5) Study and plan a fourth downstream passage facility that can be built and operated

shortly after the BiOp’s term ends in 2023.

(6) Carry out and study interim water quality measures (operational and minor physical

modifications) to achieve temperature control and reduce exceedances of total

dissolved gas (“TDG”) limits until permanent water quality control facilities can be

constructed.

(7) By March 2019, build and begin operating a water temperature control tower at

Detroit Reservoir (North Santiam subbasin).

(8) Develop and implement protocols to protect water quality during emergency and

unusual events.

BiOp 9-33–36, 9-42, 9-48–58, 9-61–9-67.

The Corps has not begun operating any of the permanent downstream passage structures

required by the BiOp’s RPAs and will not meet any of the future deadlines for doing so; has

essentially abandoned plans to build a facility at Lookout Point Dam; and has not begun studying

or planning to construct the fourth fish passage facility discussed in the BiOp. NEDC, 479 F.

Supp. 3d at 1014. Except for the annual deep drawdown at Fall Creek Reservoir, the Corps has

not consistently carried out downstream fish passage measures in the WVP. Id. at 1015. The

Corps also has not constructed the water temperature control tower at Detroit Dam. Id. at 1014.

As early as 2017, NMFS determined it was necessary and, as provided in the RPA, requested the

Corps begin outplanting adult UWR Chinook salmon above Green Peter Dam. Pl. Ex. 85, ECF

118-23. The Corps has refused to do so. Id.

Shortly after Plaintiffs filed this action, the Corps and NMFS reinitiated formal ESA

consultation in April 2018. Initially, Defendants estimated that they would complete consultation

and issue a new biological opinion in 2022; they now estimate they will finish consultation by

the end of 2023. Def. Resp. 5, ECF 130. It took Defendants eight years to complete the 2008

BiOp. The status of the species has continued to decline since the 2008 BiOp was issued, and the

Corps’ operation of the WVP is a cause of that decline. NEDC, 479 F. Supp. 3d at 1017; Fourth

Schroeder Decl. ¶¶ 10, 12, 17-23, ECF 119; Fifth Schroeder Decl. ¶¶ 8-11, ECF 144.

On August 17, 2020, the Court concluded that the Corps is violating the ESA because its

operation of the WVP is jeopardizing the survival and recovery of the listed salmonids and is

“taking” the species in excess of the BiOp’s Incidental Take Statement (“ITS”). NEDC, 479 F.

Supp. 3d at 1018, 1023. The Court also determined that the Corps’ and NMFS’ multi-year delay

in reinitiating ESA consultation after it became clear that the Corps was not carrying out the

critical RPA measures was a substantial procedural violation of the ESA, as to the Corps, and the

Administrative Procedure Act, as to NMFS. Id. at 1027. Now in the remedial phase of this case,

Plaintiffs move for injunctive relief to remedy Defendants’ substantive and procedural ESA

violations. The state of Oregon, as amicus curiae, largely supports Plaintiffs’ proposed remedial

measures.

STANDARDS

Interim injunctions, such as those sought by Plaintiffs here, are not preliminary in the

conventional sense because the Court has already decided the merits of this case. The relief

sought, however, is also not permanent in the conventional sense because it may be lifted after

Defendants issue a new biological opinion. See Nat’l Wildlife Fed’n v. Nat’l Marine Fisheries

Serv. (“NWF VII”), No. 3:01-CV-0640-SI, 2017 WL 1829588, at *2 (D. Or. Apr. 3, 2017), aff’d

in part, appeal dismissed in part, 886 F.3d 803 (9th Cir. 2018) (“NWF VIII”). “Thus, the first

prong of the [permanent] injunction test should be modified to match the analogous prong in the

preliminary injunction test, such that “[P]laintiffs must show that they are ‘likely to suffer

irreparable harm in the absence of preliminary relief.’” NWF VIII, 886 F.3d at 817 (quoting

Winter v. Nat. Res. Def. Council, Inc., 555 U.S. 7, 20 (2008)).

To obtain such “interim injunctive measures,” Plaintiffs must therefore demonstrate: (1)

they are likely to suffer irreparable harm in the absence of the requested relief; (2) remedies

available at law, such as monetary damages, are inadequate to compensate Plaintiffs’ injury; (3)

the balance of hardships between Plaintiffs and Defendants warrants a remedy in equity; and (4)

the public interest would not be disserved by an injunction. Id. If the Court determines that

injunctive relief is warranted, such relief must be tailored to remedy the specific harm.

Melendres v. Arpaio, 784 F.3d 1254, 1265 (9th Cir. 2015) (“We have long held that injunctive

relief must be tailored to remedy the specific harm alleged.”) (quotation marks omitted)). “[T]he

district court has broad discretion in fashioning a remedy.” Id.

DISCUSSION

The Court has jurisdiction to enforce the ESA’s mandates, 16 U.S.C. § 1540(g)(1), and

“has many remedial tools at its disposal, including declaratory relief or an injunction[.]” Winter,

555 U.S. at 33. Plaintiffs seek a suite of interim injunction measures, including deadlines for key

analyses; operational measures and structural improvements to address fish passage and water

quality issues; and research and monitoring, adaptive management, and other miscellaneous

relief.

First, Plaintiffs request a deadline of December 2024 for the Corps and NMFS to

complete reinitiated ESA consultation and issue a new biological opinion on the WVP. Plaintiffs

also seek a December 2021 deadline for the Corps to complete a study of alternatives to

downstream passage options at Cougar Dam under a “no power” scenario (“Cougar 2.0 Study”).

Second, Plaintiffs propose interim operational measures, including deep reservoir

drawdowns in late fall to pass juvenile fish through the dams’ regulating outlets instead of the

hydropower turbines; spill operations to move juvenile fish more quickly through the reservoirs

and avoid passage through the turbines; collecting and planting adult salmonids above Green

Peter Dam so the fish can access prime spawning habitat and downstream juvenile fish passage

can be studied; using lower regulating outlets to better meet fall water temperature targets; and

spreading spill to reduce TDG levels below the dams.

Third, Plaintiffs seek an order requiring the Corps to design and build a structural

solution to reduce TDG levels below Big Cliff Dam; construct permanent adult fish release sites

in the South Santiam subbasin; repair the failed fish weir or build a new structural downstream

passage solution at Foster Dam; apply a fish friendly coating to the regulating outlets and install

a structural solution to reduce vertical plunge at Cougar Dam; and improve the Dexter Dam adult

fish facility.

Finally, Plaintiffs request an order directing the Corps to fund studies monitoring

downstream passage survival, migration timing, and water quality parameters during the interim

operations. Plaintiffs move the Court to assign a Technical Advisory Team comprised of fish

biologists that will direct the Corps on how to carry out the interim measures. Plaintiffs also

request an injunction requiring the Corps to strictly follow maintenance outage schedules; seek a

rule change to Oregon’s water quality standards for TDG levels; update the 2012 Operational

Measures Evaluation Team (“OMET”) Report; provide biannual status reports on the Corps’

implementation of the interim measures; and post all completed studies on a publicly accessible

website.

I. Irreparable Harm

A plaintiff “must show irreparable injury to justify injunctive relief.” Cottonwood Env’t

L. Ctr. v. U.S. Forest Serv., 789 F.3d 1075, 1091 (9th Cir. 2015). “In light of the stated purposes

of the ESA in conserving endangered and threatened species and the ecosystems that support

them, establishing irreparable injury should not be an onerous task[.]” Id. (citing 16 U.S.C.

§ 1531).

Plaintiffs argue that, absent their requested relief, they will likely suffer irreparable harm

to their recreational and aesthetic interests in the UWR salmonids during the time it takes

Defendants to complete reinitiated ESA consultation. Plaintiffs contend the Court’s ruling on

summary judgment makes clear that, without significant changes to improve juvenile fish

passage and water quality, the Corps’ operations will continue to kill and injure, i.e., “take,” an

unlawful amount of juvenile salmonids and will continue to jeopardize the species’ survival and

recovery. Therefore, argue Plaintiffs, the Court must order the Corps to carry out Plaintiffs’

proposed injunction measures to prevent this irreparable harm.

In a familiar line of reasoning already rejected by the Court and again rejected here, the

Corps contends that Plaintiffs cannot demonstrate irreparable harm because the salmonids’

status, although declining, has not been downgraded from “threatened” to “endangered”; the

species’ decline is largely due to other causes that have recently started improving, such as sea

lion predation, non-native hatchery fish, and poor ocean conditions; 2 and the harm to the

salmonids is caused by the existence of the dams, not the Corps’ operations. NEDC, 479 F. Supp.

3d at 1017-18 (finding the Corps’ assertion that it was not jeopardizing the species because their

ESA-listing has not been elevated from “threatened” to “endangered” revealed a “fundamental

misunderstanding of the ESA on the Corps’ part”); see also Alaska v. Lubchenco, 723 F.3d 1043,

1054 (9th Cir. 2013), as amended on denial of reh’g and reh’g en banc (Oct. 16, 2013) (“The

goal of the ESA is not just to ensure survival, but to ensure that the species recovers to the point

that it can be delisted.”).

The Corps also argues that carrying out actions that “take” individual juvenile fish or that

are not necessarily in furtherance of the salmonids’ recovery do not constitute irreparable harm.

Rather, Plaintiffs must show irreparable harm to the species as a whole. The Corps further asserts

that Plaintiffs’ requested relief should be denied because the Corps has adopted its own package

2 Notwithstanding Mr. Piaskowski’s assertion to the contrary, a one-year bump in the number of

returning fish is not a dependable measure of the status of the species; rather, several years of

data are necessary to reliably determine any trend in species abundance. Second Piaskowski

Decl. ¶¶ 9, 12, ECF 134; Fourth Schroeder Decl. ¶¶ 10, 12, 17-23; Fifth Schroeder Decl. ¶¶ 8-11

(noting “a couple of errors” in Mr. Piaskowski’s count of the 2020 winter steelhead and Chinook

salmon return and that “regardless of these errors, comparing a single year’s return to previous

averages is a meaningless measure for assessing the status of a population, much less a trend”).

of interim measures that will avoid irreparably harming the salmonids. See ECF 130-1, 178-2.

The Court disagrees.

As evinced by the listed species’ continuing decline, the Corps’ failure to provide

adequate fish passage and mitigate water quality issues is causing substantial, irreparable harm to

the salmonids. NEDC, 479 F. Supp. 3d at 1017 (D. Or. 2020) (“Far short of moving towards

recovery, the Corps is pushing the UWR Chinook and steelhead even closer to the brink of

extinction.”); see also Nat’l Wildlife Fed’n v. Burlington N. R.R., 23 F.3d 1508, 1512 n.8 (9th

Cir. 1994) (“We are not saying that a threat of extinction to the species is required before an

injunction may issue under the ESA. This would be contrary to the spirit of the statute, whose

goal of preserving threatened and endangered species can also be achieved through incremental

steps.”). Furthermore, Defendants’ failure to timely reinitiate ESA-consultation, which the Court

found to be a substantial procedural violation, is causing continuing harms and adverse effects to

the listed species. NEDC, 479 F. Supp. 3d. at 1025. Consistent with the opinions of NMFS,

Plaintiffs’ experts, and the Oregon Department of Fish and Wildlife, the Court finds that the

Corps’ interim measures do not adequately address the lack of volitional fish passage and water

quality issues in the WVP. See, e.g., Pl. Exs. 63-64, 66, 70-75, ECF 118; Fifth Schroeder Decl.;

Fourth Domingue Decl.

The evidence demonstrates that volitional fish passage is biologically necessary, and spill

operations and deep drawdown measures represent the most effective means for providing safe

fish passage under current dam configurations. Fourth Schroeder Decl. ¶¶ 38-39; Third

Domingue Decl. ¶¶ 5, 11. The biological justification for these operational measures is relatively

straightforward. Juvenile salmonids must pass through the dams to successfully outmigrate to the

marine environment. The salmonids typically navigate downstream by following the flow of the

river;3 however, the large, slow-moving reservoirs behind the dams disrupt these natural

outmigration cues, making it difficult for the fish to find their way downstream to the dam and

lengthening their exposure to predators and pathogens in the reservoirs. Increasing flow via

drawdowns and spill operations reduces the size of the reservoir and accelerates the salmonids’

navigation to the dam, thereby decreasing their exposure to pathogens and predators. But once

the juvenile salmonids reach the dams, they can only pass downstream through the hydropower

turbines, regulating outlets (“ROs”), or spillways. For likely obvious reasons, significantly

higher fish mortality occurs when the juvenile salmonids pass through the turbines instead of the

ROs or spillways, making non-turbine fish passage the safest available option. And, concerning

drawdowns specifically, juvenile salmonids are surface-oriented fish, meaning they cannot sound

very deep and are unlikely to find the ROs unless the reservoir surface elevation is drawn down

within 20 to 25 feet of the outlet opening. Fourth Schroeder Decl. ¶¶ 38-39; Third Domingue

Decl. ¶ 11; Pl. Ex. 19, at 76, ECF 36-19; Pl. Exs. 24, 29, ECF 36.

In formulating its interim measures, the Corps did not consider conducting deep

drawdowns at Cougar or Lookout Point reservoirs on the basis that it does not have authority

under the Flood Control Act of 1950 (“1950 FCA”), Pub. L. No. 81-516, § 204, 64 Stat. 163

(1950), and House Document 531 (“HD 531”) to draw the reservoirs below the “power pool”

during the “critical power production period, October through March.” H.R. Doc. No. 81-531,

App. J at 2054. As discussed infra, the Corps has discretion under the 1950 FCA and HD 531 to

conduct deep drawdowns and water quality measures that preclude hydropower generation for

the benefit of the listed salmonids. In addition, water temperatures below Detroit, Green Peter,

3 “The smolts, apparently, prefer not to swim. They face upstream, open their mouths, and permit

the current to carry them downstream.” Idaho ex rel. Evans v. Oregon, 462 U.S. 1017, 1020 n.1

(1983).

and Lookout Point dams continue to be too cold in the summer and too warm in the fall, and

TDG exceedances repeatedly occur below Big Cliff Dam. Pl. Ex. 76 at 23-25, 32, 37-40, 67-70,

ECF 118-14; Pl. Ex. 77 at 25-27, 34, 40-42, 69-72, ECF 118-15; Pl. Ex. 78 at 4, ECF 118-16.

Because the Corps’ interim measures do not adequately address these adverse impacts to

the listed salmonids, the Court finds that “continuation of the status quo could result in

irreparable harm to [the] threatened species” absent interim measures that improve fish passage

and water quality in the WVP. NWF VIII, 886 F.3d at 820-22 (finding irreparable harm where

the highly precarious status and low abundance of the species made them vulnerable to

extinction and operation of the dams caused substantial harm to the salmonids and accounted for

most mortality of juveniles migrating downriver); see also Marbled Murrelet v. Babbitt, 83 F.3d

1060, 1066 (9th Cir. 1996), as amended on denial of reh’g (June 26, 1996) (“A reasonably

certain threat of imminent harm to a protected species is sufficient for issuance of an injunction

under section 9 of the ESA.”); S. Yuba River Citizens League v. Nat’l Marine Fisheries Serv.,

804 F. Supp. 2d 1045, 1054-55 (E.D. Cal. 2011) (where fish species had low abundance,

declining productivity, and low spatial distribution, and dam operations harmed the species,

injunction was warranted pending a new biological opinion); Hoopa Valley Tribe v. Nat’l Marine

Fisheries Serv., 230 F. Supp. 3d 1106, 1134, 1137-39 (N.D. Cal. 2017) (finding injunctive relief

appropriate for a substantial procedural violation of the ESA and irreparable harm likely where

operations threatened listed salmon’s abundance, fitness, and resilience, making future protective

measures particularly important, and the defendant was unlikely to provide those measures

without a court order). And, because the Corps’ operation of the WVP threatens the continued

existence and recovery of the listed salmonids, Plaintiffs’ members will suffer irreparable harm

to their recreational and aesthetic interests in the salmonids. NWF VIII, 886 F.3d at 822.

Accordingly, Plaintiffs have established they will likely suffer irreparable harm absent injunctive

relief.

II. Remaining Injunction Factors

Because the ESA “afford[s] first priority to the declared national policy of saving

endangered species” and establishes that the value of endangered species is “incalculable,”

Tennessee Valley Auth. v. Hill, 437 U.S. 153, 185, 187-88 (1978), “[t]he ESA removes the latter

three factors in the four-factor injunctive relief test from [the court’s] equitable discretion.” NWF

VIII, 886 F.3d at 817; see also Marbled Murrelet, 83 F.3d at 1073 (9th Cir. 1996) (“Congress has

determined that under the ESA the balance of hardships always tips sharply in favor of

endangered or threatened species.”). The court must “presume that remedies at law are

inadequate, that the balance of interests weighs in favor of protecting endangered species, and

that the public interest would not be disserved by an injunction.” NWF VIII, 886 F.3d at 817

(citation omitted).

Contrary to the Corps’ argument, limited agency resources and impacts to power

production, recreation, and local economies do not overcome the presumption that the balance of

harms and public interest factors tip in Plaintiffs’ favor. NWF VII, 2017 WL 1829588, at *6

(“[T]he Court does not weigh the public interest or balance the equities, for example by weighing

any potential implications on the power system or costs to the Federal Defendants.”).

Furthermore, Plaintiffs’ requested relief does not, as the Corps asserts, frustrate the purposes of

the ESA. The bulk of Plaintiffs’ requested remedies are simply RPA measures that the Corps has

failed to carry out, have already undergone environmental consultation, and were deemed

necessary by NMFS to avoid jeopardy to the listed salmonids under the ESA. The Court

therefore concludes that Plaintiffs have established the latter three factors in the four-factor

injunctive relief test. Accordingly, Plaintiffs have demonstrated that they are entitled to interim

injunctive measures that will improve fish passage and water quality in the WVP.

III. The Corps’ Authority Under the 1950 FCA

The Corps argues that the Court cannot grant Plaintiffs’ request for deep drawdown

measures at Cougar and Lookout Point dams because it does not have authority to do so under

the 1950 FCA. A court may not issue an injunction enforcing the ESA if doing so would cause

an agency to violate other statutory requirements. San Luis & Delta-Mendota Water Auth. v.

Jewell, 747 F.3d 581, 645 n.49 (9th Cir. 2014); see also Nat’l Ass’n of Home Builders v. Defs. of

Wildlife, 551 U.S. 644, 669 (2007) (holding ESA “§ 7(a)(2)’s no-jeopardy duty covers only

discretionary agency actions and does not attach to actions . . . that an agency is required by

statute to undertake[.]”) (emphasis original).

A. Overview of the 1950 FCA and HD 531

In the 1950 FCA, Congress authorized the Corps to build, operate, and maintain the

Willamette Valley Project (“WVP”) “substantially in accordance with the plans recommended in

the report of the Chief of Engineers . . . contained in House Document 531[.]” § 204, 64 Stat. at

179. As a roadmap, HD 531 contains the Chief of Engineers’ Report, which in turn recommends

adopting the Board of Engineers for Rivers and Harbors’ (“Board”) Report, which in turn

recommends adopting the Division Engineer’s Report, which in turn recommends adopting the

Portland District’s Report. Contained in Appendix J to HD 531, the Portland District’s Report is

specific to the WVP and contains the power storage allocations that the Corps asserts preclude it

from conducting deep drawdowns at the WVP’s hydropower dams.

The Chief of Engineers’ Report is a “comprehensive plan for development of the

Columbia River and its tributaries for flood control, navigation, power development, irrigation,

and other purposes, including fish and wildlife conservation and recreation.” H.R. Doc. No. 81-

531 (“HD 531”) at 1. The Chief of Engineers recommended “[t]hat the comprehensive plan

outlined in the report of the division engineer, with modifications as outlined herein and in the

report of the Board of Engineers for Rivers and Harbors, be approved as the basis for long-range

development of the Columbia River Basin” and that the Willamette Basin plan described in the

Board’s Report be authorized “generally in accordance with the plans outlined in the report of

the division engineer and with such modification as the Chief of Engineers may find advisable.”

Id. at 5 (emphasis added).

The Board’s Report presents “a comprehensive plan coordinating existing and potential

developments in the Columbia River Basin to perfect a balanced system of project works for the

control of floods and the ultimate development for optimum beneficial use of the water resources

of the basin.” Id. at 8. The Board found that, “[a]fter full consideration of the division engineer’s

report and of the additional information presented by local interests at the public hearings and in

correspondence, the Board . . . concurs generally in the view of the division engineer.” Id. at 18.

The Board recommended “[t]hat the comprehensive plan described in the report of the division

engineer, be approved as the general guide for the further development of the water resources of

the basin and that the work listed in the [Willamette Basin Plan] be authorized at this time . . .

generally in accordance with the plans of the division engineer and with such modifications

thereof as in the discretion of the Chief of Engineers may deem advisable[.]” Id. at 21 (emphasis

added).

The Division Engineer’s Report recommended “the comprehensive plan of water

resource development . . . be adopted as a general guide for the further development of the water

resources of the Columbia River Basin . . . and that future plans for water use development give

due consideration to the comprehensive plan outlined herein.” Id. at 342 (emphasis added). The

Division Engineer provided that the WVP “will be operated in a coordinated manner in the

combined interest of flood control, navigation, irrigation, power, drainage, fish and wildlife,

recreation, domestic water supply, and stream-polution [sic] abatement.” Id. at 248. The Division

Engineer’s Report recommended allocating storage capacity in the WVP’s reservoirs for

purposes of flood control, hydropower, and joint use. Id. at 244. In discussing the need for

hydropower development in the WVP, the Division Engineer noted:

[D]uring the winter months when Columbia River and its tributaries east of Cascade

Range experience low-water flows, high flows prevail in Willamette Valley

streams. These conditions favor development of generating plants in Willamette

River sub-basin which could be operated on a low load-factor to supply a part of

the peak-power requirements of that area and to supplement Columbia River Basin

power during the low-flow season on Columbia River.

Id. at 239.

The Division Engineer provided that, “[i]n general, this report does not outline the final

plan of operation, but rather the basic criteria for such a plan and the results which can be

obtained from the system.” Id. at 324 (emphasis added). The Division Engineer references the

Portland District’s Report in Appendix J for a more detailed discussion of the Willamette River

subbasin plan. Id. at 244.

The Portland District’s Report includes an analysis of data applicable to the Willamette

subbasin, proposed projects that were considered, and various special studies regarding

precipitation, meteorology, hydrology, hydropower, and the rule curves for reservoir regulation.

Appendix J describes a system of reservoirs wherein space at each storage project would be

allocated for flood storage, power storage (if the dam provided hydropower), and dead storage.

Id. at 1787, 1921, 2039, 2040 (Detroit); 1757, 1908, 2039, 2040 (Lookout Point); 1763, 1911,

2039, 2040 (Cougar); 1752-53, 1907, 2039, 2040 (Hills Creek); 1780, 1918, 2039, 2040 (Green

Peter). The projected storage allocations for the hydropower projects discussed in the Portland

District’s Report are consistent with the allocations outlined in the Division Engineer’s Report.

Id. at 244.

The Portland District’s Report provides that during the flood season (November 15 to

February 1), reservoir storage space would be evacuated to allow for flood storage. Id. at 1816.

Power storage is described as “that increment of storage which lies directly above dead storage

[and directly below flood control storage], and which is reserved exclusively for power

generation. This storage would be drawn out for power production only if all flood-control were

evacuated and inflow to the reservoir were inadequate to maintain firm power output.” Jd. at

2239 (emphasis added). The following diagram illustrates a typical rule curve and storage

allocation for the WVP dams that generate hydropower:

= A Le YL TY PY A MO

2.) eee

The exclusive power storage is considered necessary only “in the critical power

production period, October through March” which 1s “when the flows in Columbia River are

low.” Id. at 2054, 2057. For the remainder of the year, “power production would be incidental to

reservoir releases made in the interest of other conservation uses.” at 2057. During the power

16 — OPINION & ORDER

production period, “releases and storage (within the confining limits of flood control) are

determined by the power requirements,” and power storage “would be drawn out for power

production only if all flood-control storage were evacuated and inflow to the reservoir were

inadequate to maintain firm power output,” which was forecasted to “happen on the average in

about 1 year out of 10.” Id. at 2058, 2239.

Power storage is intended “to insure that Willamette River plants would contribute, in all

years, a maximum amount of continuous power to the Columbia River power system during the

6-month critical power production period on Columbia River.” Id. at 2239. The WVP power

storage allocations are based on: (1) “the maximum amount of prime power that could have been

generated at Willamette River plants during” the “1937 critical period, the worst of record on

Columbia River,” and (2) “[t]he amount of storage that would be required to produce this same

amount of 6-month prime power under the worst Willamette River flow conditions, which

occurred in 1941.” Id. In other words, the power storage allocations represent the amount of

impounded water that would be needed to produce enough hydropower to meet regional demand

under a worst-case scenario in both the Willamette River and Columbia River. Id. at 2058

(noting the “rule curves were prepared for each power site to show the maximum amount of

storage required on any date to assure production of prime power for the remainder of the power

season”); see also id. at 1726 (“[G]enerating plants in the Willamette Basin[] could be operated

. . . to supply a part of the peak power requirements of that load area and to supplement

Columbia Basin power during the low flow season on Columbia River.”).

After the flood season, the storage space reserved for flood control would be filled and

used for conservation releases during the “low-water season,” May 1 to November 15, for

purposes such as navigation, irrigation, power, fish, municipal and industrial water supply,

pollution abatement, and recreation. Id. at 1817, 1831, 2053, 2058. “[T]he general plan of

reservoir regulation was to obtain a maximum degree of flood protection and at the same time

provide stored water for conservation uses during low-water seasons.” Id. at 2053.

The Portland District’s Report notes that the reservoir regulation study discussed in

Appendix J was “based upon the best information presently available as to conservation

requirements and reservoir regulation policy,” and that “the schedules and rule curves developed

should not be considered final if future development in the basin should alter the concept of any

of the conservation requirements, or should research indicate that a change in reservoir

regulation policy would be beneficial.” Id. at 2064 (emphasis added). The District’s Report

specifically noted that “[a]dditional investigations and studies are required in order satisfactorily

to solve the problem of maintaining fish life within Willamette River Basin,” and that “[m]any

problems are so complex that additional studies will have to be made to in order to find

satisfactory solutions.” Id. at 2284.

B. Analysis

Plaintiffs seek an injunction requiring the Corps to conduct deep drawdowns between

November 15 and December 15 at Cougar and Lookout Point reservoirs. Due to the amount of

time it takes to draft and refill the reservoirs, the drawdowns would eliminate the ability to

generate hydropower during the six-month power production period for approximately six weeks

at Cougar Dam and approximately ten weeks at Lookout Point Dam. Wells Decl. ¶¶ 60, 83, ECF

69. Plaintiffs argue the 1950 FCA and HD 531 imposes broad goals on the Corps and gives the

agency discretion to modify WVP operations based on changed circumstances.

The crux of the Corps’ position is that the 1950 FCA grants it some discretion to dip into

the power pool to meet downstream flow requirements for the listed salmonids, but it does not

have the authority to conduct deep drawdowns that would preclude hydropower generation

during the power production period. The 2008 BiOp’s RPA Measure 4.8 required the Corps to

conduct downstream fish passage measures until it completed the permanent passage structures

called for by the BiOp. Consistent with RPA 4.8, the Corps conducted a deep drawdown at

Cougar Reservoir in 2012 and began planning to conduct a drawdown at Lookout Point

Reservoir, but then decided in March 2018 that it did not have the authority to do so under the

1950 FCA. In support of its about-face on the authority issue, the Corps submits a November

2020 opinion drafted by its legal department, and adopted by the Corps, explaining its lack of

authority under the 1950 FCA. Corps’ Legal Opinion, ECF 131-1.4

The Corps’ Legal Opinion concludes that deep drawdowns are a type of project

modification that the Chief of Engineers must obtain congressional approval of before

conducting. In Env’t Def. Fund, Inc. v. Alexander (“EDF”), the district court held that the Corps

had the authority to make several construction modifications to a water development project that

significantly deviated from the plan of improvement contained in the authorizing legislation and

associated Corps’ reports. 467 F. Supp. 885 (N.D. Miss. 1979), aff’d, 614 F.2d 474 (5th Cir.

1980). In determining the limits of the Corps’ authority to make “such modifications as in the

4 The Corps argues its legal opinion is entitled to deference and cites a case where Chevron

deference was applied to uphold an agency’s interpretation of the Fair Labor Standards Act,

Long Island Care at Home, Ltd. v. Coke, 551 U.S. 158, 165 (2007). However, the Corps’ Legal

Opinion was not subject to notice-and-comment procedures and is therefore not entitled to

Chevron deference. Christensen v. Harris Cty., 529 U.S. 576, 587 (2000). At most, the Corps’

opinion is entitled to non-binding Skidmore deference, id., and more likely deserves no deference

at all, Christopher v. SmithKline Beecham Corp., 567 U.S. 142, 155 (2012) (no deference owed

where agency’s interpretation advanced in a legal brief is a “nothing more than a convenient

litigating position” or a “post hoc rationalization . . . to defend past agency action against

attack.”) (internal citations and quotation marks omitted); see also Corps’ Legal Opinion 1

(noting the opinion was drafted “[a]s a result of [ESA] consultations and associated litigation”).

Even assuming Skidmore deference applies, the Corps’ Legal Opinion is not persuasive for the

reasons explained herein.

discretion of the Secretary of War (Army) may be advisable,” the district court looked to the

Corps’ “general principles” for determining when a project modification exceeded its discretion

and needed congressional authorization. Id. at 900-01, 908-09.

Under those principles, the Corps would seek congressional approval where a

modification would materially change the scope of the project (i.e., the territorial area to be

served), the purpose or function of the project (i.e., navigation, flood control, etc.), or the plan of

improvement as originally authorized by Congress. Id. at 909. The Corps would not, however,

seek approval for construction modifications that were: (1) necessary for engineering reasons to

produce the degree or extent of navigation improvement intended by Congress, such as the

shifting of a dam to a nearby, better location; or (2) moderate extensions of project scope to

account for developments occurring after the project was authorized and avoid the construction

of obsolete projects. Id.

The Corps contends that deep drawdowns constitute a material change to the purpose and

function of the WVP and, therefore, cannot be implemented absent congressional authorization.

The EDF court, however, deferred to the Corps’ “general principles” for seeking congressional

authorization because the act authorizing the project “contained no extraordinary or unusual

language which would vary the authority of the Corps officials to make changes in design over

and beyond the [Corps’ ‘general principles’] without seeking additional authorization from

Congress.” Id. Here, the Court need not defer to these “general principles” because HD 531

contains much more than a general grant of discretionary authority and expressly provides that

“the schedules and rule curves developed should not be considered final if future development in

the basin should alter the concept of any of the conservation requirements, or should research

indicate that a change in reservoir regulation policy would be beneficial.” HD 531 at 2064. Not

only is the Corps’ authority to adjust WVP operations under the 1950 FCA much broader than it

was in EDF, but HD 531 also contemplates prioritizing the needs of the salmonids over power

production when necessary. Id. at 2058 (providing an “exception” to the power storage

requirement and detailing that the Corps should use power storage to support fish life “when a

shortage of water existed” because “under this condition . . . fish life . . . would have priority

over power”). Thus, the Corps’ “general principles” are irrelevant here.

In Britt v. U.S. Army Corps of Eng’rs, the Second Circuit held that the Corps had lawfully

approved a new location for a bridge even though it would be built one-and-one-half miles south

from the location approved by Congress. 769 F.2d 84, 90 (2d Cir. 1985). Like here, Congress

enacted legislation authorizing the Corps to build a project “in accordance with the plans”

outlined in a preliminary report contained in a House Document, which in turn recommended the

project be built “with such modifications thereof as in the discretion of the Chief of Engineers

may be advisable.” Id. at 88-89 (emphasis omitted). The court found that language alone

indicated that “Congress gave the Chief of Engineers considerable discretion to approve

modifications of the project.” Id. at 89. The Second Circuit explained:

Particularly in a situation such as is presented here, where more than twenty-five

years have elapsed between the Congressional authorization and the actual

implementation of the project, it would be unreasonable to impute to Congress the

intent to preclude the Chief of Engineers from making reasonable modifications in

the project to accommodate intervening developments in the economic, social,

ecological, or political climate. . . . [M]odifications by the Chief of Engineers in a

project such as this are within the scope of his authority unless they are so foreign

to the original purpose of the project as to be arbitrary and capricious.

Id. The court concluded that changing the location of the bridge was within the Corps’ authority

because it “appears generally to serve the purpose of facilitating automobile traffic across the

northern end of the Bay” and, therefore, did “not appear to be foreign to the original purpose of

the project.” Id. at 90.

Similarly, in United States v. 2,606.84 Acres of Land in Tarrant County, Texas, the Fifth

Circuit determined that the Corps acted within its authority when it built a dam that was

significantly larger, more expensive, and approximately three miles away from the location

authorized by Congress. 432 F.2d 1286, 1293 (5th Cir. 1970), cert denied, 402 U.S. 916 (1971).

In reversing the lower court, the Fifth Circuit found that “[t]he source of the trial court’s

misconception [that the dam exceeded congressional authority] is found in the finality and

binding effect which it gave H.D. 403.” Id. at 1292. The court determined that Congress could

not have intended HD 403 to be the final plan for the project because the “cover letter of the

document itself states that it is a ‘preliminary examination and survey’” and the Chief of

Engineers recommended the project be carried out “‘generally in accordance’ with the plans

contained in the report ‘as modified herein, and with such future modifications thereof as in the

discretion of the Secretary of War and the Chief of Engineers may be advisable.’” Id. The Fifth

Circuit concluded that the Corps was authorized to deviate from the plans in HD 403: “It is

undisputed that the Congressional authorization was for a flood control project on the Clear Fork

of the Trinity River. This is what the Corps of Engineers built. The area served and the project

purposes were not changed.” Id. at 1293.

And in a more analogous case involving operational modifications, as opposed to

construction modifications, the Eighth Circuit held that, under the 1944 FCA, the Corps had

authority to make operational changes during drought years that reduced or eliminated

navigation on the river to hold water in reservoirs for the benefit of recreation. In re Operation of

Missouri River Sys. Litig., 421 F.3d 618, 629 (8th Cir. 2005). Under the 1944 FCA, navigation

and flood control are the “dominant” purposes of the Missouri River project, whereas irrigation,

recreation, and fish and wildlife are “secondary” purposes. Id. The 1944 FCA did “not set forth

what level of river flow or length of navigation season is required to make navigation ‘dominant’

over a ‘secondary’ interest such as recreation.” Id. The Eighth Circuit upheld the Corps’ drought

contingency plan because the Corps had considered all of the competing purposes before making

its decision. Id. The court cautioned, however, that “[i]f, due to extreme conditions, the Corps is

faced in the future with the unhappy choice of abandoning flood control or navigation on the one

hand or recreation, fish and wildlife on the other, the priorities established by the FCA would

forbid the abandonment of flood control or navigation.” Id. at n.7. Nonetheless, the Eighth

Circuit held that, even though the drought contingency plan required shortening, and even

eliminating, the navigation season in some years, the plan did not “abandon” navigation. Id.

Here, the Corps argues that Plaintiffs’ proposed drawdowns would “completely

eliminate” the purpose of the exclusive power storage during the critical power production

period and, thus, are “‘so foreign to the original purpose of the project’ that performing them

would violate the 1950 FCA[.]” Def. Resp. 17 (quoting Britt, 769 F.2d at 89): see also Corps’

Legal Opinion 18-19 (“[T]he deep drawdowns at issue here would completely eliminate the

reservoir storage that was specifically and exclusively reserved for the purpose of power

production in a critical power production period in the comprehensive plan adopted by

Congress.”). Problematically, the Corps’ argument treats the WVP’s power storage as a purpose

in and of itself; however, the power storage is simply a means of effectuating a purpose—

preventing regional power shortages in the winter when flows are lower in the Columbia River.

The Corps has not put forth any argument nor submitted any evidence indicating that the

drawdowns would lead to an abandonment of this purpose. Contrary to the Corps’ position, the

drawdowns will not eliminate hydropower production during the entire power production period.

Nor will the drawdowns at Cougar and Lookout Point reservoirs preclude power generation at

the other hydropower dams in the WVP—Hills Creek, Green Peter, and Detroit (to the extent

Detroit’s turbines are operated during the day under the interim drawdown measure).5 The

drawdowns do not constitute an abandonment of the power storage purpose in the same way that

the Corps’ drought contingency plan in Missouri River did not amount to an abandonment of that

project’s “dominant” navigation purpose.

Although HD 531 specifies that WVP power storage is “reserved exclusively for power

generation” and Missouri River found the 1944 FCA’s lack of specifics regarding the necessary

flows and length of the “dominant” navigation season established that the Corps had discretion to

adjust its operations on the Missouri River, the WVP plan Congress approved in the 1950 FCA is

5 The Portland District’s Report detailed that, due to the interconnectedness of the Pacific

Northwest power transmission system, power production “at individual [WVP] plants in all years

would not be essential.” HD 531 at 2240. The reservoir regulation study found that “[d]uring the

periods when firm power could not have been produced in Willamette Valley, Columbia River

flows were sufficiently high to enable other Columbia River system plants to make up the

deficiency, and the system firm power would have been maintained.” Id. at 2062. The

comprehensive plan noted that “[f]urther development of storage in Columbia River Basin within

the United States, as contemplated in present power studies in this report, would increase the

minimum dependable flow [during the critical power production months from 75,000 second-

feet] to approximately 125,000 second-feet. This increased flow would result from the regulation

of storage primarily in the interest of system power production.” Id. at 2573 (App. L) (emphasis

added). HD 531 also noted, but did not include in its plan of development, that future projects on

the Canadian portion of the Upper Columbia River would increase the ability to provide even

greater minimum dependable flows year-round in the Columbia River. Id. at 305. “The 1964

Columbia River Treaty between the United States and Canada provided for building four storage

reservoirs: three in Canada (Mica, Kennleyside, and Duncan) and one in the United States

(Libby). The reservoirs that were built and operated under the Treaty represent almost half the

water storage on the Columbia River System.” Nw. Env’t Def. Ctr. v. Bonneville Power Admin.,

117 F.3d 1520, 1525 (9th Cir. 1997). Currently, the WVP contributes less than 4% of the

federally generated power in the Pacific Northwest. Connolly Decl. ¶¶ 18-19, ECF 66. Thus, the

low winter flows in the Columbia River, and accompanying limits on power generation

capability that the WVP’s power storage allocations were designed to guard against, have been

alleviated by increased storage capacity in the Columbia River. The Court therefore finds that it

is highly unlikely that the amount of WVP power storage specified in HD 531 is still needed to

prevent regional power shortages caused by low winter flows on the Columbia River and, as

noted, no such argument has been made here.

“not [to] be considered final . . . should research indicate that a change in reservoir regulation

policy would be beneficial.” HD 531 at 2064, 2239; see also id. at 324 (“In general, this report

does not outline the final plan of operation, but rather the basic criteria for such a plan and the

results which can be obtained from the system.”). Like HD 403 in 2,606.84 Acres, the WVP plan

is preliminary in nature; the “cover letter of [HD 531] itself states that it is a ‘preliminary

examination and survey’” and the Chief of Engineers recommended the project be carried out

“generally in accordance with the plans outlined in the report” and “with such modification as

the Chief of Engineers may find advisable.” 2,606.84 Acres, 432 F.2d at 1292; HD 531 at 5. “It

has long been the custom of Congress to approve projects of this nature on the basis of such

preliminary plans and to authorize the Chief of Engineers to make such modifications as later

studies indicate are necessary.” Britt, 769 F.2d at 89 (quoting 2,606.84 Acres, 432 F.2d at 1292).

Given the highly imperiled status of the listed salmonids, the deep drawdown measures

constitute such necessary modifications.

Indeed, HD 531 itself makes clear that its plans are just a “general guide” for

management of the dams in the Columbia and Willamette basins, which could be adjusted later

as conditions changed or more information about the dams’ effects became known—expressly

including impacts to fish. HD 531 at 16, 21, 253, 324, 334, 342, 2284, 2885, 2924 (noting “the

safe downstream passage of migrating fingerlings at dams” required further study and solutions).

The Board Report specifically noted that the comprehensive plan was “sufficiently flexible to

permit equitable adjustments as the execution of the plan proceeds.” Id. at 20. Notwithstanding

the Corps’ assertion that its hands are tied, the “report does not outline the final plan of

operation, but rather the basic criteria for such a plan and the results which can be obtained from

the system.” Id. at 324.

Furthermore, many of HD 531’s fish-related assumptions have proven untrue over time.

For example, the Portland District’s Report found that during the critical power period,

hydropower generation could be prioritized because “[f]ish requirements are always less than

power requirements during this period.” Id. at 2239.6 The Corps even hypothesized that the

dams’ regulation of flows “would greatly improve conditions on the main streams below the

reservoirs and would aid fish migration materially.” Id. at 1866. Subsequent studies and the 2008

BiOp’s findings demonstrate, however, that the Corps’ operation of the WVP is materially

impeding fish migration. As the Second and Fifth Circuits have observed, “[i]t imparts both

stupidity and impracticality to Congress to conclude that the [authorizing] statute impliedly

forbids any change in a project once approved, and thus prevents the agency official from

providing for the unforeseen or the unforeseeable.” Britt, 769 F.2d at 89 (quoting Creppel v. U.S.

Army Corps of Eng’rs, 670 F.2d 564, 572 (5th Cir. 1982)) (brackets original).

In sum, the 1950 FCA and HD 531 are intended to serve as a general guide for operating

the WVP, provide an “exception” to the power storage requirement when there is insufficient

water to support fish life, expressly recognize that further studies were needed to find solutions

for the dams’ impacts on salmonids, provide that the rule curves should not be considered final if

further research indicated changed operations were needed, and grant broad discretion to the

Chief of Engineers to make operational modifications he or she finds advisable. Because the

deep drawdowns Plaintiff seek do not appear to be foreign to the original purpose of the project,

are “substantially in accordance with the plans recommended in” HD 531, and do not equate to

an abandonment of the purpose of the WVP’s power storage, the Court will order this relief.

6 The Fish and Wildlife Coordination Act of 1958, 16 U.S.C. §§ 661-664, and the Pacific

Northwest Electric Power Planning and Conservation Act of 1980, 16 U.S.C. §§ 839-839h,

placed fish and wildlife on equal footing with power production.

IV. Narrowly Tailored

If a court determines that injunctive relief is warranted, such relief must be tailored to

remedy the specific harm. Melendres, 784 F.3d at 1265. With the exception of the proposed

injunction measures discussed below, the Court finds Plaintiffs’ requested remedies are narrowly

tailored to remedy the irreparable harm in this case.

A. Technical Advisory Team

Plaintiffs request an injunction delegating oversight authority and adaptive management

of the injunction actions to a Technical Advisory Team (“TAT”). Plaintiffs seek an order

requiring the Corps to follow the TAT’s direction unless doing so would be infeasible or present

a dam or human safety issue. For the TAT to work as Plaintiffs envision, however, the Court

would have to delegate its Article III injunction powers to the TAT. The Constitution prohibits

this abdication of judicial authority. Armstrong v. Brown, 768 F.3d 975, 987-88 (9th Cir. 2014)

(a court may not delegate its Article III powers to an expert advisor but may retain an expert to

monitor compliance and make recommendations to the court); Burlington N.R.R. Co. v. Dep’t of

Revenue of State of Wash., 934 F.2d 1064, 1072 (9th Cir. 1991).

Although the Corps often ignores the recommendations of the expert agencies and

improperly prioritizes other project purposes over the needs of the listed salmonids, the Court

has no basis to believe that the Corps will not follow the Court’s orders. At this juncture, the

Court declines to order expert oversight of the Corps’ implementation of the interim measures

because more narrowly tailored options, i.e., implementation plans created by an expert panel

and biannual status reports, are available to ensure the Corps complies with the mandates of the

ESA and the Court’s injunction during the reconsultation period.

///

B. Oregon Water Quality Standards

The Court will not order the Corps to exceed Oregon’s standards for TDG levels in

violation of the Clean Water Act. Although there is some evidence that brief periods of elevated

TDG levels up to 120-125% have a negligible effect on fish, NWF VII, 2017 WL 1829588 at *7,

a court may not command an agency to violate its other statutory obligations. San Luis, 747 F.3d

at 645 n.49. Nor will the Court order the Corps to seek a rule change allowing temporary TDG

exceedances. The State of Oregon does not believe it necessary to change its water quality

standards, and this Court will not order a futile act. Amicus Reply Br. 4, ECF 140.

C. Unrelated Studies and General Research

The Court declines to grant Plaintiffs’ request for a December 2021 deadline for the

Corps to complete the Cougar 2.0 Study, request for the Corps to fund and implement general

research needed for the new biological opinion, and request for the Corps to update the 2012

OMET Report. The Cougar 2.0 Study and Defendants’ record development during reinitiated

consultation are separate processes that are properly left to the agencies’ discretion. The

sufficiency of the 2012 OMET Report was never challenged in this action. Accordingly, those

requests are not narrowly tailored to remedy the specific harms at issue in this case.

V. Expert Panel

It is abundantly clear that changes to the Corps’ operation of the WVP are necessary to

avoid irreparable harm. It is also clear that such operational modifications necessitate

consideration of biological tradeoffs, involve many complex and sometimes imprecise variables,

require adaptive management in their implementation, and must be monitored to measure their

efficacy. Less clear is how some of the injunction measures can be implemented in a

comprehensive manner that balances the potential tradeoffs, accounts for the multifarious

variables, and provides the most benefit to the listed salmonids. Thus far, the Court has been

forced to glean NMFS’ expertise from the administrative record, as not one declaration from a

NMFS fish biologist has been submitted in this case. The Corps makes much-to-do about

developing its interim measures in coordination with NMFS; however, the measures were

created under the incorrect assumption that the Corps lacks statutory authority to conduct deep

drawdowns or other operational measures that reduce hydropower generation during the power

production period. Therefore, the Court finds it appropriate to fashion an Expert Panel, in which

the parties’ technical experts will confer and flesh out the implementation details of numerous

interim mitigation measures.

As detailed in the accompanying Interim Injunction, the Court is ordering Defendants to

carry out specific interim measures that the Court finds do not require further clarification, as

well as other measures that are biologically necessary but involve technical aspects requiring

further input from the parties’ experts. The Expert Panel “will be limited to eight members

comprised of two of Plaintiffs’ fish experts, two NMFS’ fish experts, two Corps’ dam-operations

experts, and two ‘ad hoc’ federal experts, such as the US Fish & Wildlife Service (‘USFWS’) or

US Geological Survey (‘USGS’), where necessary to advise on matters within their respective

areas of expertise.” Minute Order, ECF 196. The experts’ deliberations will not devolve into a

forum for further disagreement about the biological benefits of, or the Corps’ authority to carry

out, the interim measures. The Court has already determined that the Corps has discretionary

authority and must provide volitional downstream fish passage and water quality measures to

mitigate irreparable harm to the listed salmonids. Those issues are therefore beyond debate and

need not be taken into consideration during the expert panels’ deliberations. Simply put, the

Expert Panel’s task is to hammer out the details and propose implementation plans7 containing

the best means for effectuating the ends the Court has determined equity demands.

CONCLUSION

For the reasons discussed, the Court GRANTS in part and DENIES in part Plaintiffs’

Motion for Injunctive Relief [117].

IT IS SO ORDERED.

DATED:___S_e_p_t_e_m__b_e_r_ 1_,_ 2__0_2_1____.

______________________________

MARCO A. HERNÁNDEZ

United States District Judge

7 Due to the short timeframe provided for conducting the Cougar deep drawdown and Foster spill

operation (Injunction Measures 13 & 14), the Court directed the Expert Panel to submit

implementation plans for those measures prior to issuing this Opinion & Order. Plaintiffs’

experts agree with the Expert Panel’s implementation plan for the 2021 Cougar drawdown but

request an order directing the Corps to conduct a more robust PIT-tag study of the operation.

Defendants also support a PIT-tag study; however, they note that there is simply not enough time

to put such a study in place this year due to fiscal laws and regulations. Instead, Defendants

propose operating rotary screw traps below Cougar Dam and, if available by mid-October, using

marked juvenile spring Chinook to assess passage efficiency. Defendants also note that they will

conduct a PIT-tag study beginning next year. Given the short deadline for carrying out the

Cougar drawdown and Defendants’ assurances that they will implement more robust RM&E in

future years, the Court accepts the Cougar drawdown implementation plan as proposed.

INTERIM INJUNCTION

For the reasons discussed, Plaintiffs have demonstrated they are entitled to injunctive

relief. Accordingly, the Court ORDERS as follows:

(1) Defendants SHALL complete reinitiated ESA-consultation and issue a new biological

opinion by December 31, 2024.

(2) The Expert Panel SHALL confer and, no later than the deadlines set herein, submit

implementation plans fleshing out the parameters of the measures discussed in this

Interim Injunction. The Expert Panel’s proposed measures must be in accordance with

the best available science, technically feasible, incorporate principles of adaptive

management, and provide meaningful research, monitoring, and evaluation (“RM&E”) of

the interim measures.

(3) Until Defendants issue a new biological opinion, the Corps SHALL implement the

interim injunction measures to the greatest extent practicable under existing hydrologic

conditions and necessary flood control operations. In carrying out the interim measures,

the Corps must make every effort to comply with the various water quality standards

governing the WVP.1

(4) The Corps SHALL fund and/or carry out RM&E to evaluate the effects of the interim

measures on UWR Chinook salmon and UWR steelhead. The Expert Panel will propose

specific RM&E to accompany the interim measures in the implementation plan

submissions.

1Should Plaintiffs believe the Corps is not operating consistently with the implementation plans,

the parties SHALL meet and confer and make reasonable efforts to resolve the dispute. If the

parties are unable to resolve their dispute, Plaintiffs may file a motion with the Court to clarify

the Corps’ obligations under or address the Corps’ compliance with the Implementation Plan.

(5) The Corps SHALL follow its established maintenance outage schedules and emergency

protocols.

(6) Beginning February 28, 2022, Defendants SHALL provide status reports every six

months detailing their progress and compliance with the interim measures. The biannual

status reports must include the following information: (1) the interim measures that have

occurred at each dam; (2) any deviation from outage schedules, emergency protocols, and

water quality standards; (3) all RM&E that was conducted during the prior six months

and any available results of that research; (4) all RM&E planned for the next six months;

and (5) any proposed changes to the interim measures based on changed circumstances or

the results of RM&E.

(7) Defendants SHALL post the results of all RM&E on a publicly accessible website.

(8) Given the Corps’ track record of not following through on past interim measures and

repeatedly missing self-imposed deadlines, the Court finds it necessary to incorporate

into this Interim Injunction the Corps’ Interim Measures that sufficiently mitigate

irreparable harm. See Interim Measures Implementation Plan, ECF 130-1; Refinements to

Interim Measures, 178-2. The Court therefore ADOPTS by reference and ORDERS the

Corps to implement Interim Measure Nos. 5, 6, 7, and 20.

(9) “Deep drawdown” measures must: (1) be performed during peak juvenile migration

timing; (2) prioritize volitional fish passage; (3) draw down the reservoir elevation to

within 25' or less of the regulating outlets; and (4) prioritize use of the regulating outlets

during the drawdown, especially during the hours between sunset and sunrise.

///

///

North Santiam Subbasin

(10) The Corps SHALL carry out fish passage and water quality operations at Detroit and Big

Cliff reservoirs as detailed in the Corps’ Interim Measure Nos. 5-7.

(a) By September 8, 2021, the Expert Panel will make a recommendation to the Court

on whether the interim operation should be modified to incorporate use of the

lower regulating outlets at Detroit Dam for temperature control purposes.

(b) By February 10, 2022, the Expert Panel must determine whether operational

measures alone are sufficient to maintain acceptable TDG levels below Big Cliff

Dam. If the Expert Panel determines a structural solution is needed, Defendants

SHALL propose a reasonable timeline for designing and constructing a structural

solution for mitigating excess TDG levels during spill operations. Defendants’

proposed timeline for designing and constructing a structural solution for elevated

TDG levels below Big Cliff Dam is due no later than August 5, 2022.

South Santiam Subbasin

(11) Within one year of this Interim Injunction, the Corps SHALL begin outplanting adult

UWR Chinook salmon above Green Peter Dam.

(a) By November 5, 2021, the Expert Panel will submit an outplanting plan,

including any improvements and/or development of adult release sites necessary

to accomplish adult outplanting above Green Peter Dam.

(12) After adult outplanting above Green Peter Dam begins, the Corps SHALL carry out

juvenile downstream passage measures at Green Peter Dam.

(a) By November 5, 2021, the Expert Panel will submit an implementation plan for a

spring fish-passage operation at Green Peter Dam that prioritizes volitional fish

passage through non-turbine routes.

(b) By March 15, 2022, the Expert Panel will submit an implementation plan for a

fall fish-passage operation at Green Peter Dam that prioritizes volitional fish

passage through non-turbine routes.

(13) Beginning fall 2021, the Corps SHALL carry out fall and spring fish-passage operations

at Foster Dam.

(a) The Corps SHALL carry out the Foster fall spill operation specified in the Expert

Panel’s implementation plan included as Attachment 1 to this Interim Injunction.

(b) By October 15, 2021, the Expert Panel will submit an implementation plan for a

spring spill or delayed refill fish-passage operation at Foster Dam that prioritizes

volitional fish passage through non-turbine routes.

McKenzie Subbasin

(14) Beginning fall 2021, the Corps SHALL conduct the Cougar Dam deep drawdown

measure specified in the Expert Panel’s proposed implementation plan included as

Attachment 2 to this Interim Injunction.

(15) Beginning in 2022, the Corps SHALL conduct spring passage measures at Cougar Dam.

(a) By October 15, 2021, the Expert Panel will submit an implementation plan for

spring fish-passage operations at Cougar Dam, including delayed refill measures,

that prioritize volitional downstream fish passage through non-turbine routes.

(b) By March 15, 2022, the Expert Panel must determine whether structural

improvements/modifications need to be made to Cougar Dam’s regulating outlets

to ensure safer fish passage and reduce TDG levels.

Middle Fork Willamette Subbasin

(16) In coordination with the Expert Panel, the Corps SHALL conduct an analysis to

determine the degree of landslide risk associated with implementing a fall deep

drawdown at Lookout Point Reservoir. The deep drawdown(s) studied in the analysis

must prioritize volitional fish passage through Lookout Point Dam using non-turbine

routes and must include any corresponding operational changes required to provide fish

passage at Dexter Dam. The Corps’ risk-analysis and recommendation on the deep

drawdown operation at Lookout Point Dam is due by January 31, 2022.

(17) Beginning 2022, the Corps SHALL conduct spring spill operations at Lookout Point Dam

and Dexter Dam.

(a) By December 8, 2021, the Expert Panel will submit an implementation plan for a

Lookout Point/Dexter spring spill operation specifying what elevation at Lookout

Point Reservoir the Corps will begin spill operations to provide the most benefit

to the salmonids. The implementation plan must prioritize use of the spillway to

the maximum extent practicable and turbine use should be limited to only the

amount necessary to manage water temperatures and TDG levels. The Expert

Panel must also determine whether, in addition to the Corps’ plan of splitting

water between the spillway and powerhouse detailed in Interim Measure No. 21

(ECF 178-2), Lookout Point Dam’s regulating outlets should also be utilized for

temperature control in the late summer and early fall.

(18) As required by RPA 4.6, the Corps SHALL make improvements to and begin operating

the Dexter adult fish facility within two years of this Interim Injunction.

(19) Beginning in 2021, the Corps SHALL conduct the annual Fall Creek Reservoir deep

drawdown operation similar to prior years but extend the dates from December 1 through

January 15. The Corps must monitor for erosion to the earthen embankment that could

occasion the extended drawdown measure and may suspend the measure for dam safety

reasons. The Corps must notify the Court within three days of the suspension.

(20) Beginning in 2022, the Corps SHALL conduct winter and spring downstream passage

operations at Fall Creek Dam.

(a) By October 15, 2021, the Expert Panel will submit implementation plans for

winter and spring fish-passage operations that prioritize volitional passage over

trap-and-haul operations if hydrologic conditions allow and downstream water

quality requirements can be met.

IT IS SO ORDERED.

DATED:___S_e_p__te_m__b_e_r_ 1_,_ 2__0_2_1____.

______________________________

MARCO A. HERNÁNDEZ

United States District Judge