Opinion

Ross Dress For Less, Inc. v. Makarios-Oregon, LLC

Court
District Court, D. Oregon
Filed
Jan 8, 2021
Cited by
0 cases
Authority
More cited than 28.7%

“Oregon treats a commercial lease as a contract and, in the absence of a provision in the lease to the contrary, ordinary contract principles apply.”

How later courts described this case

  • “Oregon treats a commercial lease as a contract and, in the absence of a provision in the lease to the contrary, ordinary contract principles apply.”
  • “This being a diversity case, jurisdiction is grounded on that fact and the [insurance] policy must be interpreted and construed in accordance with the Laws of Oregon, the place where the contract was made.”
  • noting that by accepting rent payment after giving commercial tenant notice of default and intent to terminate lease, landlord waived right to terminate lease
  • “The case is in federal court by diversity of citizenship only. The law of the state in which the court sits must apply.”

Written by the judges who cited it.

The opinion

IN THE UNITED STATES DISTRICT COURT

FOR THE DISTRICT OF OREGON

ROSS DRESS FOR LESS, INC., Case No. 3:14-cv-1971-SI

Plaintiff and FINDINGS OF FACT AND

Counterclaim-Defendant, CONCLUSIONS OF LAW

A T PHASE II

v.

MAKARIOS-OREGON, LLC;

WALKER PLACE, LLC;

CHARLES W. CALOMIRIS;

KATHERINE CALOMIRIS TOMPROS;

and JENNIFER CALOMIRIS,

Defendants and

Counterclaim-Plaintiffs.

Gregory D. Call and Tracy E. Reichmuth, CROWELL & MORING LLP, 3 Embarcadero Center, 26th

Floor, San Francisco, CA 94111; Joel A. Parker, Rebecca A. Boyette, and Jessica Schuh,

SCHWABE WILLIAMSON & WYATT PC, 1211 SW Fifth Avenue, Suite 1600, Portland, OR 97204.

Of Attorneys for Plaintiff.

Jeffrey M. Edelson, Molly K. Honoré, Paul S. Bierly, and Vivek A. Kothari, MARKOWITZ

HERBOLD PC, 1455 SW Broadway, Suite 1900, Portland, OR 97201. Of Attorneys for Defendant.

Michael H. Simon, District Judge.

This lawsuit involves a dispute over the contractual obligations of a commercial tenant

upon the expiration of two leases, each spanning more than 50 years, with two landlords for two

adjacent and partially conjoined buildings in downtown Portland, Oregon. Before the leases

expired, the tenant (or lessee) filed this action, seeking declaratory relief regarding its end-of-

lease obligations. After bifurcating the case, the Court held a bench trial on the lessee’s request

for declaratory relief and issued a ruling. That was Phase I. After the leases expired, the lessee

surrendered the premises. The two landlords (or lessors) filed supplemental counterclaims for

damages, alleging that the lessee failed to comply with its end-of-lease obligations. This is

Phase II. The lessee (Ross Dress for Less, Inc.) eventually settled with one of the lessors (Walker

Place, LLC) but not with the other (Makarios-Oregon, LLC).

A nonbreaching party to a contract typically is entitled to the benefit of its bargain (also

known as its “expectation” interest).1 Upon the expiration of a lease, a lessor generally may

recover damages caused by a commercial lessee’s breach of an express covenant to return the

premises in good order, condition, and repair, reasonable wear and tear excepted. In most cases,

the cost of repair is a convenient and appropriate way to measure the damages that a lessor

suffers in these circumstances. When the facts of a specific case, however, indicate that the cost

of repair is unrelated to a lessor’s actual damage, the general rule might not fully apply. Instead,

when the cost of repair substantially and disproportionately exceeds any diminution in market

value of the relevant property caused by the lessee’s nonperformance of its express obligations,

the diminution in market value may be a better measure of damages.

The pending dispute focuses on whether the lessee (Ross Dress for Less, Inc.)

surrendered the premises of the non-settling lessor (Makarios-Oregon, LLC) in the condition

required under the parties’ relevant lease and, if not, whether that lessor is entitled to the full cost

1 See Restatement (Second) of Contracts § 344 (defining “expectation interest” as a

party’s “interest in having the benefit of his bargain by being put in as good a position as he

would have been in had the contract been performed”); see also Brian H. Bix, Contract Law:

Rules, Theory, and Context 99 (2012) (“expectation damages are meant to put the nonbreaching

party in the same position it would have been in had the agreement been performed”).

of remediating all deficiencies in performance without regard to whether a specific deficiency (or

all deficiencies collectively) caused any loss in market value to the leased premises. Stated

another way, this case concerns the application of the “economic waste doctrine” in the context

of a commercial building with a lease spanning more than 50 years.

Oregon contract law applies to the commercial lease in this case. As discussed more fully

below, Oregon’s version of the economic waste doctrine provides that when the cost of repair is

not the “prudent” remedy to apply because that remedy would create “economic waste,” the

diminution in market value is the better measure of damages. As also discussed more fully

below, to avoid the risk of denying a contracting party the benefit of its bargain, this alternative

remedy must be applied carefully and cautiously. When a commercially leased building is

vacated, or surrendered, in a condition that materially breaches the lessee’s express covenant in

multiple respects, especially when the costs to repair some items are disproportionately high in

relation to any effect the condition of those specific items might have on the market value of the

premises, this caution militates in favor of evaluating the appropriate measure of damages on an

item-by-item basis.

In December 2019, the Court held a four-day bench trial on the supplemental

counterclaims asserted by the non-settling lessor (Makarios-Oregon, LLC) against the lessee

(Ross Dress for Less, Inc.). Afterward, the Court allowed the parties to file post-trial briefs and

responses. The Court then weighed and evaluated all evidence in the same manner that it would

instruct a jury to do and has fully considered the legal arguments of counsel. The Court now

makes the findings of fact and conclusions of law stated below. Any finding of fact that

constitutes a conclusion of law also is adopted as a conclusion of law, and any conclusion of law

that constitutes a finding of fact similarly is adopted as a finding of fact.

In the opinion of the Court, the facts found are all supported by the record, even though

the Court might not provide specific record citations. Also, unless otherwise noted, when

evidence is subject to an objection and the Court has relied on that evidence, the Court has

overruled the objection for the reason or reasons identified either by the Court or, if the Court is

silent, by the party offering the evidence in response to the other side’s objection. When the

Court has declined to consider evidence subject to an objection, the Court may state its basis for

sustaining the evidentiary objection; alternatively, the Court simply may have found that the

evidence subject to objection was not persuasive, thus making the objection moot. All objections

to evidence that the Court has not relied on and all procedural objections not expressly addressed

are denied as moot.

For the reasons stated below, the Court finds that Ross Dress for Less, Inc. materially

breached its end-of-lease and rent-payment obligations owed to Makarios-Oregon, LLC. The

Court separately will enter a judgment in favor of Makarios-Oregon, LLC in the total amount of

$2,931,829, which include prejudgment interest through January 8, 2021.

PROCEDURAL BACKGROUND

Plaintiff and Counterclaim-Defendant Ross Dress for Less, Inc. (Ross) filed this lawsuit

in December 2014. At that time, Ross leased portions of two buildings from Defendants and

Counterclaim-Plaintiffs Makarios-Oregon, LLC (Makarios) and Walker Place, LLC (Walker

Place). Both leases expired on September 30, 2016. Before their expiration, Ross sought a

judicial declaration that, among other things, Ross’s proposed end-of-lease plans would satisfy

its contractual obligations under the two leases. Makarios and Walker Place asserted that Ross’s

plans were inadequate; they also asserted counterclaims, seeking both a judicial declaration

clarifying the extent of Ross’s end-of-lease obligations and money damages for breach of

contract.

All parties moved for partial summary judgment, which the Court granted in part and

denied in part in March 2016. Ross Dress for Less, Inc. v. Makarios-Oregon, LLC, 180 F. Supp.

3d 745 (D. Or. 2016). The parties then agreed to bifurcate this lawsuit and waive their right to

have a jury resolve all factual disputes. In Phase I, the Court held a bench trial to determine the

extent of Ross’s end-of-lease obligations. In June 2016, the Court issued Phase I Findings of Fact

and Conclusions of Law. Ross Dress for Less, Inc. v. Makarios-Oregon, LLC, 191 F.

Supp. 3d 1189 (D. Or. 2016).

On September 6, 2016, Ross moved for an order determining whether, over the

objections of Makarios and Walker Place, Ross could remain on the premises of the two

buildings after the leases expired to complete any work that still needed to be done to surrender

the premises in the condition required under the leases. On September 27, 2016, the Court ruled

that after the two leases expired on September 30, 2016, neither Ross nor its agents could enter

or remain on the premises of either building over the objection of the respective lessor. Ross

Dress for Less, Inc. v. Makarios-Oregon, LLC, 210 F. Supp. 3d 1259 (D. Or. 2016). In April

2017, both Makarios and Walker Place filed supplemental counterclaims for money damages

against Ross, to be resolved in Phase II. Several months later, Walker Place settled its dispute

with Ross. In December 2018, Makarios amended its supplemental counterclaims. ECF 306.

As its first supplemental counterclaim, Makarios alleged that when Ross’s lease expired

on September 30, 2016, and Ross vacated the building leased from Makarios (the Richmond

Building), Ross failed to return the premises in the condition contractually required under the

relevant lease (the Richmond Lease). Makarios sought money damages for “costs of the required

work and repairs, architectural, engineering, and other professional fees, legal fees, permit fees,

inspection fees, and fees and costs associated with bringing the Richmond Building to the

condition required by the Richmond Lease.” ECF 306, ¶ 13. As its second supplemental

counterclaim, Makarios alleged breach of the implied covenant of good faith and fair dealing and

sought “damages in an amount to be proved at trial.” ECF 306, ¶ 24.2 As its third supplemental

counterclaim, Makarios alleged that Ross breached its obligation under the Richmond Lease to

pay rent and now owes Makarios unpaid rent through the end of the lease period. ECF 306, ¶33.

FINDINGS OF FACT

The Court finds the following facts by a preponderance of the evidence:

A. Background

1. From 1907 through 1976, members of the Failing family and related entities

(collectively, the Failings) owned a building located at 620 SW Fifth Avenue, in Portland,

Oregon (the Failing Building). It was originally constructed in 1907 as a six-story building. In

1913, an additional six floors were added. The Failing Building currently consists of twelve

floors and is listed on the National Register of Historic Buildings. In 1976, the Failings sold the

Failing Building to Henry Miller. In 1997, Miller sold the Failing Building to 620 Associates. In

2006, 620 Associates sold the Failing Building to Walker Place.

2. The Richmond Building is located at 600 SW Fifth Avenue, Portland, Oregon. It

is next to (and partially conjoined with) the Failing Building. Constructed in 1953, the Richmond

Building consists of five floors and a mezzanine. The predecessor building to the Richmond

Building (the Original Richmond Building) also was owned by the Failings.

3. J.J. Newberry Company (Newberry) was a national retail chain operating variety

stores across the United States. Newberry operated a retail store in downtown Portland, Oregon

from 1927 to 1996.

2 Makarios’s second supplemental counterclaim is based on the same operative facts that

underlie its first supplemental counterclaim, and the Court will treat these two claims together.

4. In 1946, when the Failings owned both the Original Richmond Building and the

Failing Building, the Failings leased both the Original Richmond Building and a portion of the

Failing Building to Newberry (the 1946 Lease). The 1946 Lease envisioned that Newberry

would raze the Original Richmond Building and construct a new Richmond Building, consistent

with various design mandates. Newberry razed the Original Richmond Building sometime before

1951 and oversaw construction of the new Richmond Building, which was completed in 1953.

Upon completion of the new construction, the basement, first, and second floors of the Failing

Building connected openly and seamlessly with the basement, first, and second floors of the

adjacent, newly built Richmond Building. These combined floors, spanning the two buildings,

created Newberry’s new retail space in downtown Portland. Newberry also used a portion of the

upper floors in the Richmond Building for storage.

5. In 1956, the Failings sold the Richmond Building to Newberry. Almost

contemporaneously, Newberry entered a sale-lease back transaction for the Richmond Building

with the New York Life Insurance Company (New York Life). From 1956 through 1986, New

York Life owned the Richmond Building.

6. When New York Life bought the Richmond Building from Newberry, New York

Life leased the Richmond Building back to Newberry for a term of 30 years, with rights of

renewal (the 1956 Richmond Lease or, simply, the Richmond Lease).

7. At approximately the same time in 1956, the Failings restated and amended the

1946 Lease with Newberry, specifically relating to the Failing Building (the 1956 Failing Lease).

8. After several extensions and amendments, both the 1956 Richmond Lease and the

1956 Failing Lease were set to expire on September 30, 2016.

9. In 1986, New York Life sold the Richmond Building to William Calomiris, who

died in approximately 2000. After several estate-related and intrafamily transactions, Charles W.

Calomiris, Katherine Calomiris Tompros, and Jennifer Calomiris (collectively, the Calomiris

Family) became the owners of the Richmond Building. In 2011, Makarios-Oregon, LLC (an

entity affiliated with the Calomiris Family) received an assignment of all rights under the 1956

Richmond Lease.

10. In 1992, Newberry’s parent corporation filed for Chapter 11 bankruptcy. This

resulted in Newberry closing its downtown Portland store in 1996.

11. Ross is a Virginia corporation that operates discount retail department stores

across the United States.

12. In 1996, Newberry and Ross negotiated the terms of an assignment and submitted

that assignment to the bankruptcy court for approval. The assignment stated that Ross would

assume from Newberry all of assignor’s leasehold estate and right, title, interest, and obligations

in, to, and under both the 1956 Failing Lease and the 1956 Richmond Lease (and the Failing and

Richmond Buildings) in their respective and existing “as is” physical conditions. Later in 1996,

the bankruptcy court approved the assignment.

13. The 1956 Failing Lease and the 1956 Richmond Lease required the tenant

(originally Newberry, and later Ross) to pay $34,000 annually in rent for the last 30 years of the

two leases. Ross paid $34,000 annually in rent for its 20-year tenancy. This rental obligation is

substantially below fair market value.

14. Ross spent more than $2 million to renovate the leased premises in both the

Richmond and Failing Buildings before opening its retail store at that location in 1996. Ross

operated a “Ross Dress for Less” store at that site from 1996 until 2014. Ross operated a “dd’s

Discounts” store there from 2014 until it vacated and surrendered the premises on approximately

September 30, 2016.

15. Before vacating the Richmond Building, Ross engaged Craig Stockbridge of

GBD Architects in Portland (GBD) to prepare three sets of plans related to the Richmond and

Failing Buildings: Non-Permit Plans; Permit Plans #1 (including structural work); and Permit

Plans #2 (involving utility separation; mechanical, electrical, and plumbing work; equipment

removal, and elevator modernization). Permit Plans #1 and #2 ultimately were combined for

review by the City of Portland. Ross submitted Permit Plans #1 to the City on August 10, 2016.

16. In 2017, the Calomiris Family sold the Richmond Building to MDI Alder Street,

LLC (MDI) for $4.5 million. Even before title was formally transferred by the Calomiris Family,

MDI entered into an agreement to resell the Richmond Building for $5.25 million to an entity

owned by Brandon Anderson, a principal of Walker Place. Shortly after the Calomiris Family

transferred ownership of the Richmond Building to MDI, MDI deeded the Richmond Building to

an affiliate of Walker Place. At that point, both the Richmond Building and the Failing Building

once again came under common control and essentially common ownership.

B. Article 16 of the Richmond Lease (“Surrender of Premises”)

1. Article 16 of the Richmond Lease is captioned “Surrender of Premises.”

Section 16.01 under that article provides:

The Tenant shall, upon the expiration or termination of this

lease for any reason whatsoever, surrender to the Landlord the

buildings, structures and building equipment then upon the

demised premises, together with all alterations and replacements

thereof then on the demised premises, in good order, condition

and repair, except for reasonable wear and tear; provided,

however, that if the Tenant shall have made any alteration or

alterations adapting the buildings, structures and building

equipment upon the demised premises for multiple occupancy,

then, in such event, prior to the expiration or termination of this

lease, the Tenant, at the Landlord’s request, shall restore said

buildings, structures and building equipment to the order and

condition which existed prior to such alteration or alterations.

(Emphasis added.)

2. Section 16.02 of the Richmond Lease provides:

The Tenant agrees that, prior to the expiration of this lease or, in

the event of termination of this lease for any reason whatsoever,

promptly after such termination, the Tenant, at the Tenant’s sole

cost and expense, shall make such alterations to the building

then erected on the demised premises as shall be necessary to

constitute such building an entirely independent and self-

sufficient structure. Such alterations shall include, without in any

way limiting the generality of the foregoing, the removal of

escalators, the construction of footings and a masonry curtain wall

along the westerly boundary line of the demised premises, the

removal of any facing encroaching upon adjoining premises, the

removal of signs, the relocation of plumbing, drain pipes,

sprinklers, electrical wiring, lighting fixtures and exhaust ducts, the

installation of a new soil connection to the city sewer, a new steam

connection and new electrical service conduits and equipment and

provision for a new toilet and rest room. The provisions of this

Section 16.02 shall survive the expiration or any termination of

this lease.

(Emphasis added.)

C. Condition of the Richmond Building upon Surrender; Remediation Costs

Overview

1. Upon the expiration of the Richmond Lease on September 30, 2016, Ross was

obligated under § 16.01 to surrender the Richmond Building “in good order, condition, and

repair, except for reasonable wear and tear.”

2. In addition, upon the expiration of the Richmond Lease, Ross was obligated under

§ 16.02 to make alterations to the Richmond Building “as shall be necessary to constitute such

building an entirely independent and self-sufficient structure.” In other words, upon expiration of

the Richmond Lease, Ross was obligated to make the Richmond Building a self-sufficient

structure that was entirely independent of the Failing Building.

3. At trial, the Court heard testimony from, among others, William S. Bailey, AIA, a

certified architect. Mr. Bailey is the managing partner of Waterleaf Architecture. The Court finds

Mr. Bailey credible and his testimony generally persuasive. Mr. Bailey described the condition

of the Richmond Building as of the date of its surrender by Ross, September 30, 2016. He also

testified about the reasonable costs needed to repair or restore the deficiencies and conditions in

the Richmond Building that he identified and described.

Hard Costs Sought by Makarios under § 16.01

4. As of the date of surrender, many aspects of the Richmond Building had been

repaired satisfactorily and were left in reasonably good order and condition. Several important

features in that building, however, had not been repaired satisfactorily, resulting in a material

breach of § 16.01 of the Richmond Lease.

5. The deficient conditions, features, or aspects of the Richmond Building and the

remediation work and related hard costs for that work, not including general contractor costs or

other soft costs needed to bring the Richmond Building into compliance with § 16.01 are as

follows:

a. Window Repair

Ross did not return the exterior windows on the upper floors in good order, condition,

and repair. The windows had significant dry rot, worn away paint, and missing caulking. The

damage to the windows at the end of the lease was not the result of reasonable wear and tear.

Had the windows been conscientiously and reasonably maintained, they would have been in

good order, condition, and repair at the end of the Richmond Lease. Ross’s work on the windows

before the end of the lease did not sufficiently repair the windows to good order, condition, and

repair. Ross painted over dry rot, installed plastic shopping bags as backer, and did not replace

caulk where needed. The hard cost to repair these windows is $122,500.

b. Roof Parapet Repair

Ross did not return the roof in good order, condition, and repair. The parapet coping that

Ross installed in 2015 did not meet industry standards. The hard cost to fix the sheet metal

flashing and coping on the roof is $7,128.

c. Terra Cotta Repair

Ross did not surrender the terra cotta exterior tile in good order, condition, and repair.

The damage to the tile was not the result of reasonable wear and tear. Had the tiles been

conscientiously and reasonably maintained, they would have been in good order, condition, and

repair at the end of the Richmond Lease. Ross’s repair to shallow spalls in the terra cotta tile was

deficient, causing those patches to fail shortly after they were applied. The hard cost to repair the

terra cotta tile is $44,760.

d. Fire Escape Doors Repair

Ross did not surrender the fire escape doors in good order, condition, and repair. The

hard cost to remediate the rust that Ross allowed to accumulate on the fire escape doors during

Ross’s tenancy is $18,000.

e. Exterior Stucco Repair

Ross did not surrender the Richmond Building with its exterior stucco finishes in good

order, condition, and repair. The damage to the stucco was not the result of reasonable wear and

tear. Had the stucco been conscientiously and reasonably maintained, it would have been in good

order, condition, and repair. The hard cost to repair and repaint the exterior stucco is $26,387.

f. Basement and Third Floor Finish Repair

Ross did not surrender the Richmond Building with its finishes in the basement and third

floor in good order, condition, and repair. The damage to those finishes was not the result of

reasonable wear and tear. Conscientious and reasonable maintenance would have included

patching and repairing damaged walls, floors, and ceilings. The hard cost to repair these finishes

is $47,200.

g. Elevators 2 and 3 Repair

What the parties refer to as “Elevators 2 and 3” in the Richmond Building are a working

freight elevator and a working passenger elevator, respectively. Ross did not surrender these two

elevators in good order, condition, and repair, although they are both operable. The deteriorated

condition of these two elevators was not the result of reasonable wear and tear. Ross had a

maintenance contract in place that would have provided ongoing maintenance to the elevators if

Ross had used it. Ross terminated the maintenance contract in August 2016 without doing the

necessary work to repair these two elevators. The hard cost needed to bring these two elevators

into good order, condition, and repair is $175,000.

6. Makarios also is seeking other costs under § 16.01 that the Court is not allowing

for the reasons described below. Specifically, Makarios seeks to recover repair costs for the

following:

a. Unused Freight Elevator (Elevator 1)

Makarios seeks $450,000 to bring a third elevator (i.e., a second freight elevator), which

the parties refer to as “Elevator 1,” into good order, condition, and repair. Ross decommissioned

and abandoned this second freight elevator after Ross took over the Richmond Lease in 1996.

Ross “cannibalized” Elevator 1 by taking its parts to make repairs to the other two elevators

(Elevators 2 and 3). Ross never installed a new elevator to replace Elevator 1, nor did Ross

remove the abandoned elevator equipment. The hard cost to replace Elevator 1, including the

cost to demolish and remove the abandoned equipment, is $450,000. Makarios, however, did not

meet its burden of showing that a prudent lessor, upon the expiration of the Richmond Lease,

would have spent $450,000 to replace Elevator 1.3 The Court is not persuaded that Makarios has

met its burden of showing that a prudent lessor of the Richmond Building would have spent

$450,000 to install a third elevator (which would have been a second freight elevator) in that

five-story building.4 To reach any other conclusion would require unreasonable speculation by

the factfinder. Moreover, although a prudent lessor might have removed the abandoned

equipment from Elevator 1, Makarios did not separately provide any evidence of that specific

and more limited cost. See Ex. 785, at 2. The Court will not speculate on that cost.

b. Plumbing for Floors Three through Five

The boiler that had provided hot water to the upper floors (floors three through five) was

abandoned and left in place at the end of the Richmond Lease. Ross did not install any

replacement system to provide hot water to the upper floors. Also, the existing pipes were

unused and corroded. The sanitary sewer drain line was damaged and caused flooding in toilets

3 As mentioned earlier and discussed more fully below, Oregon’s version of the economic

waste doctrine provides that when the cost of repair is not the prudent remedy to apply because

that remedy would create economic waste, the diminution in market value is the better measure

of damages, and economic waste occurs when the defect is one that cannot be remedied without

an expenditure disproportionate to the end to be attained. The Court interprets this standard as

consistent with requiring the factfinder to consider what a prudent (or reasonable) person would

do under the relevant circumstances.

4 As discussed more fully below, the Court places the burden of showing that diminution

of value is the appropriate measure of damages when that amount is substantially (and grossly)

lower than the cost of repair. This is different, however, from requiring a plaintiff (or a

counterclaim-plaintiff) landlord to bear the burden of proving what a prudent (i.e., reasonable)

landlord would do or expect in making certain repairs.

in the upper floors. Makarios seeks $340,000 in hard costs to repair the plumbing for floors three

through five. At some point, a lessee (or lessees) who occupied any of floors three through five

would have needed plumbing, including hot water, on the occupied floors. Thus, at some point, a

prudent lessor likely would have installed such plumbing. But precisely where and in what

configuration (and thus at what cost) would depend on the specific use or uses of those spaces.

To reach any specific conclusions would require unreasonable speculation by the factfinder.

Makarios did not meet its burden of showing that a prudent lessor upon the expiration of the

Richmond Lease would have spent $340,000 to repair the plumbing on floors three through five.

c. Air Conditioning for Third Floor

When Ross took over the Richmond Lease in 1996, Ross did not use the third-floor air

conditioning system. Instead, Ross installed a freeze protection system that did not provide the

same zone heating and cooling as the air conditioning system that was originally installed in the

building. Makarios seeks $274,420 in hard costs to repair the air conditioning system on the third

floor. At some point, a lessee (or lessees) who occupied the third floor would have needed air

conditioning on that floor. Thus, at some point, a prudent lessor likely would have installed air

conditioning on that floor. But precisely where and in what configuration and whether in

conjunction with air conditioning for the other floors in the Richard Building (and thus at what

cost) would depend on the use or uses of that floor or those floors. To reach any specific

conclusion would require unreasonable speculation by the factfinder. Makarios did not meet its

burden of showing that a prudent lessor upon the expiration of the Richmond Lease would have

spent $274,420 to install air conditioning on the third floor.

Hard Costs Sought by Makarios under § 16.02

7. Ross did not perform two important obligations necessary for the Richmond

Building to be in compliance with § 16.02. First, Ross did not adequately erect a wall between

the Richmond Building and the Failing Building. Second, Ross did not adequately separate the

utilities in those two buildings. Further, Ross’s proposed plans, even if undertaken and

completed, were insufficient to achieve compliance.

8. To separate the Richmond Building from the Failing Building, as required under

§ 16.02, would Ross to construct a concrete masonry unit (CMU) or brick wall on or near the

property line between the Richmond Building and the Failing Building. In addition, separation of

the Richmond and Failing Buildings required the installation of proper footings and severance of

the beams that spanned the property line with separate footings installed for the Richmond

Building that were not interconnected with the Failing Building.

9. Further, to make the Richmond Building self-sufficient would require Ross to

install functioning HVAC, electrical, gas, and plumbing systems for the Richmond Building that

do not rely on the systems for those utilities located in the Failing Building. Separation and self-

sufficiency also would require compliance with applicable code provisions for separate

buildings. Not counting general contractor costs or other soft costs, a reasonable estimate for the

hard costs associated with the appropriate work needed to separate the Richmond Building and

make it self-sufficient is $927,079.

General Contractor Costs and Soft Costs

10. In addition to hard costs (or trade costs), there are general contractor costs that

must be incurred in making repairs of the scope required here. These include estimating and

design contingencies, market interest, general conditions and insurance bonds, and general

contractor overhead and reasonable profit. The Court finds that a total of 31.5 percent of total

hard costs (or trade costs) is a reasonable estimate of these general contractor costs.

11. Beyond the hard costs and general contractor costs, the following estimated

additional soft costs also are reasonable, necessary, and appropriate:

a. Architectural and engineering design fees: 12 percent of hard costs

b. Reimbursable expenses: 2 percent of hard costs

c. Construction materials testing: 2 percent of hard costs

Sub-total: 16 percent of hard costs

d. Permits: $58,934

Summary of Makarios’s Recoverable Costs under Article 16

12. The following is a summary of Makarios’s recoverable costs, not including

unpaid rent:

a. Window repair: 122,500

b. Roof parapet repair: 7,128

c. Terra cotta repair 44,760

d. Fire escape doors repair 18,000

e. Exterior stucco repair 26,387

f. Basement and third floor finish repair 47,200

g. Elevators 2 and 3 repair 175,000

h. Separation costs 927,079

Sub-total: 1,368,054

i. General contractor costs (31.5 percent) 430,937

j. Soft costs (other than permits) (16 percent) 218,889

k. Permits 58,934

Total: $2,076,814

D. Ross’s Unpaid Rent on the Richmond Building

1. In May 2015, Makarios brought a forcible entry and detainer (FED) action against

Ross in state court. In that lawsuit, Makarios alleged that Ross had allowed the Richmond

Building to fall into gross disrepair in violation of Ross’s obligations under the Richmond Lease.

A judge of the Multnomah County Circuit Court conducted a trial and ruled against Makarios,

based on the equitable doctrine of laches, among other things. The state trial court also awarded

Ross its attorney’s fees.5 Makarios appealed, and the Oregon Court of Appeals affirmed in part

and vacated and remanded in part. The court of appeals held that Makarios failed to preserve for

appellate review its claim that the trial court erred in concluding that laches barred the

Makarios’s claim. See Makarios-Oregon, LLC v. Ross Dress-for-Less, Inc., 293 Or. App. 732,

734 (2018). The court of appeals, however, vacated and remanded the award of attorney’s fees.

Id. Ross sought reconsideration of the designation of Makarios as the prevailing party for

purposes of costs on appeal. Makarios did not oppose that request, which the court of appeals

granted on December 12, 2018. See Makarios-Oregon, LLC v. Ross Dress-for-Less, Inc., 295 Or.

App. 1125 (2018). The state court judgment on Makarios’s FED action became final and

unappealable on March 6, 2019.

5 Section 6.02 of the Richmond Lease stated that the “Tenant” shall pay and indemnify

the “Landlord” for all legal costs and charges, including counsel fees, reasonably incurred in

obtaining possession of the demised premises after default of the Tenant or in enforcing any

covenant or agreement of the Tenant. This provision, as written, would only allow the Landlord

(Makarios) to recover attorney’s fees from the Tenant (Ross). Oregon law, however, makes such

contractual provisions reciprocal by statute. See Or. Rev. Stat. § 20.096(1). On this basis, the

state trial court awarded Ross, as the prevailing party, its attorney’s fees.

2. In May 2015, when Makarios filed its FED action to evict Ross from the

premises, it returned rent to Ross for the remainder of the Lease. Makarios returned the rent

pending the final resolution of the state court action. Makarios did so because it was required by

law to refuse any further rent payments from Ross if Makarios wanted to sue for breach of the

lease. C & K Mkt., Inc. v. Roccasalva, 246 Or. App. 277, 282 (2011) (stating that landlord’s

acceptance of rent payments waived landlord’s right to terminate lease; acceptance of rent after

landlord sent notice of default to tenant “was legally incompatible with [landlord’s] purported

termination of the lease”); KMT Enters., Inc. v. Nyssen, 154 Or. App. 477, 482 (1998) (noting

that by accepting rent payment after giving commercial tenant notice of default and intent to

terminate lease, landlord waived right to terminate lease). Makarios, however, did not intend to

waive its right eventually to collect rent if it were unsuccessful in its FED action.6

3. From time to time, Ross continued to attempt to pay its rent, but while the FED

action was pending, Makarios either returned or refunded Ross’s payments. On January 6, 2017,

Ross wrote to Makarios’s property manager to advise that it was canceling all outstanding and

undeposited checks to avoid escheatment and stating Ross’s position that Makarios’s voluntary

return of the rent checks demonstrates Makarios’s waiver of its right to collect rent.

4. When Ross vacated the Richmond Building on September 30, 2016, the total

unpaid rent for Ross’s possession of the Richmond Building from May 2015 through September

2016 was $48,161.

6 Oregon law provides that when a lessee remains in possession of premises pending

litigation over breach of the lease—as Ross did—the lessee remains obligated to pay rent. See

Hendrickson v. Carson, 69 Or. App. 482, 485 (1984); KMT, 154 Or. App. at 483-84 (explaining

Hendrickson).

5. It was not ascertainable, however, that Ross owed this rent until the Oregon Court

of Appeals issued it final decision on Makarios’s FED action on December 12, 2018 and that

decision became final and unappealable on March 6, 2019.

E. Additional Findings Relevant to Ross’s Affirmative Defenses

1. Makarios did not fail to mitigate its damages.

2. Makarios did not interfere with Ross’s performance.

3. Makarios did not voluntarily waive its right to receive rent or otherwise relinquish

any rights in connection with Ross’s rent obligation or end-of-lease obligations for surrender and

separation.

4. Makarios did not take any action that would have reasonably led Ross to act

inconsistently with Ross’s rent obligation or Ross’s end-of-lease separation and surrender

obligations.

5. Ross did not reasonably rely on any action or inaction by Makarios that resulted

in Ross’s failure to fulfill its rent obligation or its end-of-lease surrender and separation

obligations.

6. Makarios did not act inequitably in connection with Ross’s tenancy or surrender.

7. Makarios did not delay in taking action to enforce its right to receive rent or

obtain the benefit of Ross’s end-of-lease separation and surrender obligations.

8. Makarios asserted its claims against Ross promptly upon the expiration of the

Richmond Lease.

9. Makarios did not cause Ross to fail to pay rent or otherwise fail to fulfill Ross’s

end-of-lease surrender and separation obligations.

F. Additional Findings Relating to the Testimony of Messrs. Anderson and Calomiris

1. At trial, the Court also heard testimony from, among others, Brandon Anderson.

The Court finds Mr. Anderson credible. Mr. Anderson is a real estate developer and owns,

through affiliated entities, several commercial buildings in Portland. As noted earlier,

Mr. Anderson is affiliated with Walker Place, which owns the Failing Building. Further, an

affiliate of Walker Place now owns the Richmond Building. Thus, the Richmond and Failing

Buildings, essentially, are currently under common ownership and, through Mr. Anderson and

his affiliates, common control. At trial, Mr. Anderson stated that the Richmond and Failing

Buildings are more valuable connected to each other, assuming common ownership and control,

than they would be if fully separated. Mr. Anderson explained that if a common owner owed both

buildings, it would not make economic sense to separate the two buildings. No one testified,

however, that the Richmond Building standing alone would have no value; nor would such a

conclusion be reasonable under the facts presented. Thus, all that can be reasonably concluded is

that the two buildings, if there were common ownership, would be worth more together than

would be the sum of their independent, stand-alone values. That says nothing, however, about

the situation when the two buildings are not under common ownership.

2 At trial, the Court also heard testimony from, among others, Charles W.

Calomiris. The Court finds Mr. Calomiris credible.7 Among other things, Mr. Calomiris testified

on direct examination that he (and Makarios) wanted Ross to perform its end-of-lease obligations

by making appropriate repairs to the Richmond Building and by separating the Richmond

Building from the Failing Building. Mr. Calomiris explained that the Richmond Building needed

to be separated from the Failing Building so that he (and Makarios) could be able to operate and

7 Other witnesses also testified at trial, whom the Court has not expressly mentioned. The

Court generally finds these witnesses to be credible as well.

lease the Richmond Building and obtain bank financing for that building. On cross-examination,

Mr. Calomiris confirmed that during his deposition previously taken in this case he explained

that a commercial lease gives a landlord certain rights by defining the obligations of a tenant,

that these rights have value, and that this has “nothing to do” with a landlord making its own

decisions about how to spend the landlord’s own money on a building.

CONCLUSIONS OF LAW

A. Applicable Law

In this case based on diversity jurisdiction, Oregon’s substantive law governs. See Getlin

v. Md. Cas. Co., 196 F.2d 249, 250 (9th Cir. 1952) (“The case is in federal court by diversity of

citizenship only. The law of the state in which the court sits must apply.”); see also Snook v. St.

Paul Fire & Marine Ins. Co., 220 F. Supp. 314, 316-17 (D. Or. 1963) (“This being a diversity

case, jurisdiction is grounded on that fact and the [insurance] policy must be interpreted and

construed in accordance with the Laws of Oregon, the place where the contract was made.”).

Because resolution of the parties’ dispute turns upon the interpretation and application of

their commercial lease agreement, ordinary principles of contract law apply. See Harold

Schnitzer Props. v. Tradewell Grp., Inc., 104 Or. App. 19, 23 (1990) (“Oregon treats a

commercial lease as a contract and, in the absence of a provision in the lease to the contrary,

ordinary contract principles apply.”). Under Oregon law, the “central issue” in interpreting a

lease is “the intent of the parties at the time of the execution of the lease.” Stark St. Props., Inc. v.

Teufel, 277 Or. 649, 658 (1977). In addition, the Ninth Circuit has confirmed that the

“‘fundamental goal of contract interpretation is to give effect to the mutual intent of the parties

as it existed at the time of contracting.’ This fundamental axiom is widely accepted and

uncontested.” Pauma Band of Luiseno Mission Indians of Pauma & Yuima Reservation v.

California, 813 F.3d 1155, 1165 (9th Cir. 2015) (citation omitted) (emphasis in original).

B. History of the Economic Waste Doctrine

The origin of the economic waste doctrine is generally considered to be Justice Cardozo’s

opinion for the New York Court of Appeals in Jacob & Youngs v. Kent, 230 N.Y. 239, 129 N.E.

889 (1921), although the term “economic waste” does not appear anywhere in that decision. In

that case, a residential construction contract expressly called for the use of a specific brand of

plumbing pipe, known as “Reading pipe.” After the owner discovered that the builder used an

alternative, but fully satisfactory, brand of pipe (known as “Cohoes pipe”), the owner refused to

pay for any of the work performed. The builder sued. The trial court ruled for the owner, and the

intermediate appellate court reversed. Affirming the appellate court and ruling for the builder,

Justice Cardozo wrote:

The evidence sustains a finding that the omission of the prescribed

brand of pipe was neither fraudulent nor willful. It was the result

of the oversight and inattention of the plaintiff’s subcontractor.

Reading pipe is distinguished from Cohoes pipe and other brands

only by the name of the manufacturer stamped upon it at intervals

of between six and seven feet. Even the defendant’s architect,

though he inspected the pipe upon arrival, failed to notice the

discrepancy. The plaintiff tried to show that the brands installed,

though made by other manufacturers, were the same in quality, in

appearance, in market value and in cost as the brand stated in the

contract—that they were, indeed, the same thing, though

manufactured in another place. The evidence was excluded, and a

verdict directed for the defendant. The Appellate Division reversed

and granted a new trial.

We think the evidence, if admitted, would have supplied some

basis for the inference that the defect was insignificant in its

relation to the project. The courts never say that one who makes a

contract fills the measure of his duty by less than full performance.

They do say, however, that an omission, both trivial and innocent,

will sometimes be atoned for by allowance of the resulting

damage, and will not always be the breach of a condition to be

followed by a forfeiture. . . . Considerations partly of justice and

partly of presumable intention are to tell us whether this or that

promise shall be placed in one class or in another. . . .

In the circumstances of this case, we think the measure of the

allowance is not the cost of replacement, which would be great, but

the difference in value, which would be either nominal or

nothing. . . . It is true that in most cases the cost of replacement is

the measure. . . . The owner is entitled to the money which will

permit him to complete, unless the cost of completion is grossly

and unfairly out of proportion to the good to be attained. When

that is true, the measure is the difference in value. The rule that

gives a remedy in cases of substantial performance with

compensation for defects of trivial or inappreciable importance,

has been developed by the courts as an instrument of justice. The

measure of the allowance must be shaped to the same end.

Id., 230 N.Y. at 244-45 (emphasis added).

In 1932, the American Law Institute (ALI) published its Restatement (First) of Contracts.

The Restatement refocused the terminology away from Jacob & Youngs’ direction that

courts avoid damages that are “grossly and unfairly out of proportion to the good to be attained”

and instead advised courts to avoid “economic waste.” The Restatement, however, did not define

“economic waste.” Also, the Restatement made no mention of the nonperformance needing to be

trivial and innocent (i.e, unintentional), as stated by Justice Cardozo in Jacob & Youngs.

Section 346 addressed damages for breach of a construction contract. Subsection 1(a) provided:

(1) For a breach by one who has contracted to construct a

specified product, the other party, can get judgment for

compensatory damages for all unavoidable harm that the builder

had reason to foresee when the contract was made, less such part

of the contract price as has not been paid and is not still payable,

determined as follows:

(a) For defective or unfinished construction[,] he can

get judgment for either

(i) the reasonable cost of construction and

completion in accordance with the contract, if this is possible and

does not involve unreasonable economic waste; or

(ii) the difference between the value that the

product contracted for would have had and the value of the

performance that has been received by the plaintiff; if construction

and completion in accordance with the contract would involve

unreasonable economic waste.

Restatement (First) of Contracts, § 346(1)(a) (emphasis added).

Further, as explained, in relevant part, in comment (b):

Sometimes defects in a completed structure cannot be physically

remedied without tearing down and rebuilding, at a cost that would

be imprudent and unreasonable. The law does not require damages

to be measured by a method requiring such economic waste. If no

such waste is involved, the cost of remedying the defect is the

amount awarded as compensation for failure to render the

promised performance.

Id. § 346, cmt. b (emphasis added).

The next significant development occurred in 1962, in a decision from the Supreme Court

of Oklahoma in the case of Peevyhouse v. Garland Coal & Mining Co., 1962 OK 267, 382

P.2d 109 (1962). In that case, the plaintiffs owned a farm containing coal deposits. They leased

their land to the defendant for five years for coal mining, specifically strip-mining. The contract

contemplated that coal would be taken from pits on the surface of the ground, instead of from

underground mine shafts, and the defendant expressly agreed to perform certain restorative and

remedial work on the land at the end of the lease period. This included needing to move many

thousands of cubic yards of dirt, at a cost estimated at about $25,000. Upon the expiration of the

lease, the defendant refused to perform that work, arguing that the damages should be limited to

the diminution in value of plaintiffs’ farm resulting from the failure of the defendant to render

performance as agreed, i.e., the difference between the present value of the farm and what its

value would have been if the defendant had done what it agreed to do.

The trial court instructed the jury that it must return a verdict for plaintiffs but left the

amount to be decided by the jury. On the measure of damages, the trial court instructed the jury

that it may consider the cost of performance of the work the defendant agreed to do, together

with all the evidence offered on behalf of either party. The jury returned a verdict for the

plaintiffs in the amount of $5,000, which was a fraction of the cost of performance, but much

more than the total value of the farm, even if the remedial work had been done. On appeal, the

plaintiff sought the full cost of performance (about $25,000), and the defendant argued that the

damages must be limited to the difference in the market value of the property, which was only

about several hundred dollars. After discussing § 346 of the Restatement (First) of Contracts and

its concept of “economic waste,” the Supreme Court of Oklahoma stated:

We therefore hold that where, in a coal mining lease, lessee agrees

to perform certain remedial work on the premises concerned at the

end of the lease period, and thereafter the contract is fully

performed by both parties except that the remedial work is not

done, the measure of damages in an action by lessor against lessee

for damages for breach of contract is ordinarily the reasonable cost

of performance of the work; however, where the contract provision

breached was merely incidental to the main purpose in view, and

where the economic benefit which would result to lessor by full

performance of the work is grossly disproportionate to the cost of

performance, the damages which lessor may recover are limited to

the diminution in value resulting to the premises because of the

non-performance.

Peevyhouse, 382 P.2d at 113 (emphasis added). The court concluded that “[u]nder the most

liberal view of the evidence herein, the diminution in value resulting to the premises because of

non-performance of the remedial work was $300.00.” Id. at 114. The Peevyhouse court did not

explain why the breach by the lessee was held to be “merely incidental to the main purpose” of

the contract. Nor did the court attach any significance to the fact that the breach was willful or

intentional, rather than innocent.

The next step in the evolution of the “modern” doctrine of economic waste occurred in

1981, when the ALI published the Restatement (Second) of Contracts. Here, the Restatement

explained that an injured party has a right to damages based on expectation interests as measured

by “(a) the loss in the value to him of the other party’s performance caused by its failure or

deficiency, plus (b) any other loss, including incidental or consequential loss, caused by the

breach, less (c) any cost or other loss that he has avoided by not having to perform.” Restatement

(Second) of Contracts § 347. Comment (b) explains this concept of “loss in value,” in relevant

part, as follows:

If defective or partial performance is rendered, the loss in value

caused by the breach is equal to the difference between the value

that the performance would have had if there had been no breach

and the value of such performance as was actually rendered. In

principle, this requires a determination of the values of those

performances to the injured party himself and not their values to

some hypothetical reasonable person or on some market.

Id. at § 347, cmt. b.

The next section (§ 348) is captioned, “Alternatives to Loss in Value Performance.” It

provides the current articulation of the economic waste doctrine, although it does not use term

“economic waste.” Instead, § 348 discusses costs that are “disproportional” to the “probable loss

in value.” Subsection (2) of § 348 provides:

(2) If a breach results in defective or unfinished construction

and the loss in value to the injured party is not proved with

sufficient certainty, he may recover damages based on.

(a) the diminution in the market price of the property

caused by the breach, or

(b) the reasonable cost of completing performance or of

remedying the defects if that cost is not clearly disproportionate to

the probable loss in value to him.

Id. at § 348(2) (emphasis added). Comment (c) explains this rule and its relationship to economic

waste, stating:

Sometimes, especially if the performance is defective as

distinguished from incomplete, it may not be possible to prove the

loss in value to the injured party with reasonable certainty. In that

case he can usually recover damages based on the cost to remedy

the defects. Even if this gives him a recovery somewhat in excess of

the loss in value to him, it is better that he receive a small windfall

than that he be undercompensated by being limited to the resulting

diminution in the market price of his property.

Sometimes, however, such a large part of the cost to remedy the

defects consists of the cost to undo what has been improperly done

that the cost to remedy the defects will be clearly disproportionate

to the probable loss in value to the injured party. Damages based

on the cost to remedy the defects would then give the injured party

a recovery greatly in excess of the loss in value to him and result in

a substantial windfall. Such an award will not be made. It is

sometimes said that the award would involve “economic waste,”

but this is a misleading expression since an injured party will not,

even if awarded an excessive amount of damages, usually pay to

have the defects remedied if to do so will cost him more than the

resulting increase in value to him. If an award based on the cost to

remedy the defects would clearly be excessive and the injured

party does not prove the actual loss in value to him, damages will

be based instead on the difference between the market price that

the property would have had without the defects and the market

price of the property with the defects. This diminution in market

price is the least possible loss in value to the injured party, since he

could always sell the property on the market even if it had no

special value to him.

Id. at § 348, cmt. c (emphasis added).

More recently, the doctrine of economic waste has come under a fair amount of criticism,

especially from the “law and economics” school of legal theory. See, e.g., Juanda Lowder Daniel

& Kevin Scott Marshall, Avoiding Economic Waste in Contract Damages: Myths,

Misunderstandings, and Malcontent, 85 Neb. L. Rev. 875, 906-11 (2007); see also Alan

Schwartz and Robert E. Scott, Market Damages, Efficient Contracting, and the Economic Waste

Fallacy, 108 Colum. L. Rev. 1610 (2008). In addition, many states have their own articulation of

the doctrine, some with their own nuances. In the pending case, Oregon law applies, so it is to

Oregon law that the Court turns next.

C. The Economic Waste Doctrine as Applied in Oregon

The most recent case from the Oregon Supreme Court to address the economic waste

doctrine is Montara Owners Ass’n v. La Noue Dev., LLC, 357 Or. 333 (2015), written by then-

Chief Justice Balmer. In that case, a homeowners’ association sued its general contractor for

townhouse development. The association sought damages allegedly caused by defective design

and construction. The general contractor asserted third party claims against its subcontractors

and settled with the homeowners’ association. During the jury trial between the general

contractor and several subcontractors, the trial court instructed the jury about economic waste,

telling the jury that, as to damages, it could choose between the cost of repair and the diminished

value of the properties, depending on whether the jury found undue, or gross, economic waste.8

The jury returned a verdict in favor of the general contractor but for substantially less than the

general contractor sought. The general contractor appealed, arguing that the instruction misstated

the law and that the instruction should not have been given (even if it did correctly state the law)

because there was no evidence in the record to support the instruction.

The Oregon Court of Appeals affirmed in part and reversed in part. On the economic

waste issue, the court of appeals rejected the general contractor’s suggestion that the court create

an exception to the economic waste doctrine for disputes between a general contractor and a

subcontractor. 259 Or. App. at 264-65. The court of appeals, however, agreed with the general

contractor that, in this case, there was no evidence at trial from which the jury could determine

8 The trial court instructed the jury as follows:

The cost of replacement or repair is the correct measure of damage

for defects in construction work unless that remedy generates

undue economic waste. If you find that, except for technical,

nonsubstantial, or immaterial departures by the defendants from

the plans and specifications, the [framing] [siding] work is

satisfactory, and that an award to La Noue for claimed repair costs

would result in gross economic waste, the proper measure of

damages is not the cost of repair but rather the difference in the

value of Montara as built and what its value would be if it had been

built according to the contracts.

Montara Owners Ass'n v. La Noue Dev., LLC, 259 Or. App. 657, 663-64 (2013), aff’d in part,

rev’d in part, 357 Or. 333 (2015) (emphasis added) (brackets in original).

economic waste, or diminished value. Id. at 265. The court of appeals further held that the error

was not harmless, noting that because the subcontractor was arguing for an instruction on a

different measure of damages (i.e., diminished value), the subcontractor had the burden to

present sufficient evidence under that measure. Id.

The Oregon Supreme Court affirmed in part and reversed in part. Regarding the issue of

the jury instruction on economic waste, the Supreme Court agreed with the court of appeals that

the instruction should not have been given because no evidence was presented at trial regarding

diminution in value but disagreed with the appellate court’s conclusion that the error

substantially affected the general contractor’s right; that is, the Oregon Supreme Court held that

the error was harmless.9 Montara, 357 Or. at 350-51. For purposes of the pending dispute, the

principal teaching of the Oregon Supreme Court’s decision in Montara concerns the general

application of the economic waste doctrine under Oregon law, including its application to lessors

and lessees. Although much of this teaching comes from dicta, the Oregon Supreme Court’s

comments provide a generally reliable guide for a federal court to use in predicting how the

Oregon Supreme Court would likely resolve the issues in the pending case.10

9 In Montara, the subcontractor’s expert testified that the entire cost of repair would be

about $1 million, with only five percent of that amount attributable to this specific subcontractor.

The general contractor sought $2 million from this subcontractor. The jury awarded $43,711 in

damages, which was very close to the damages figure presented by the subcontractor’s expert.

Under these circumstances, because no party presented any evidence of diminution of value and

the Oregon Supreme Court presumed that the jury followed the instructions, the Supreme Court

concluded that any error in giving an instruction about diminution in value when no such

evidence was presented was harmless. Montara, 357 Or. at 351-52.

10 “When interpreting state law, federal courts are bound by decisions of the state’s

highest court.” Arizona Elec. Power Co-op., Inc. v. Berkeley, 59 F.3d 988, 991 (9th Cir.1995). In

the absence of a decision from the state’s highest court, “a federal court must predict how the

highest state court would decide the issue using intermediate appellate court decisions, decisions

from other jurisdictions, statutes, treatises, and restatements as guidance.” In re Kirkland, 915

F.2d 1236, 1239 (9th Cir. 1990).

In Montara, the Oregon Supreme Court, under the heading “The Economic Waste

Doctrine in Oregon,” explained that when a “contractor fails to keep an agreement, the measure

of damages is always the sum which will put the injured party in as good a position as if the

contract had been performed.” Montara, 357 Or. at 346 (simplified). The Supreme Court next

said: “In Oregon construction defect cases, that sum is the amount of money equal to the cost of

curing the defects, provided repair is the prudent remedy to apply.” Id. (simplified) (emphasis

added). The Supreme Court added that the injured plaintiff “usually” recovers such amount as he

has reasonably expended, or will reasonably have to spend, to remedy the defect and that the cost

of repair calculation is “ordinarily” the measure of damages in a construction defect case. Id.

The Oregon Supreme Court continued:

However, Oregon courts use an alternative measure of damages—

the diminution in the market value of the property—when the cost

of repair is not “the prudent remedy to apply” because that

remedy would create “economic waste.” See Turner [v. Jackson],

139 Or. 539[,] 560 [(1932)]. In the case of economic waste,

“damages will be measured not by the cost of remedying the

defect, but by the difference between the value of the building as it

is and what it would have been worth if it had been built in

conformity with the contract”—in other words, the diminution in

value. . . .

Economic waste occurs where “the defect in material or

construction is one that cannot be remedied without an

expenditure for reconstruction disproportionate to the end to be

attained, or without endangering unduly other parts of the

building.” Id.; see also Restatement (Second) of Contracts

§ 348(2)(b) (1979) (courts award “the reasonable cost of

completing performance or of remedying the defects if that cost is

not clearly disproportionate to the probable loss in value to” the

injured party). Stated differently, “[d]iminution in value is the

proper measure of damages only when the cost of repair is

disproportionate to the diminution in value.” Hanset v. General

Construction Company, 285 Or. 101, 106 (1979) (emphasis in

original).

Montara, 357 Or. at 346-47 (footnotes omitted).11

In Montara, the Oregon Supreme Court also rejected the general contractor’s argument

that for the economic waste doctrine to apply, the party injured by the defective work must be a

homeowner. Id. at 348-49. The Supreme Court explained:

One of the leading cases on economic waste arose from the breach

of a lease contract requiring a lessee to regrade a family farm at the

conclusion of a mining lease term. Peevyhouse v. Garland Coal &

Min. Co., 1962 OK 267, ¶ 14, 382 P.2d 109, 114 (1962) (where the

cost of regrading was $29,000 and the market value was

diminished only $300, court measured property owners’ lost

expectancy by the lesser amount). [The general contractor] cites no

authority that limits the application of Oregon’s economic waste

doctrine to cases where one party is a homeowner or landowner,

and we see no principled reason to adopt that limitation.

Id. at 349.12

In Montara, the general contractor also argued that even if the economic waste doctrine

applies to this type of case, the subcontractor failed to meet his burden of proof to show

economic waste. Id. at 349. The subcontractor responded, first, by arguing that the burden was

not his and, alternatively, to the extent it was, then he met it. Id. Second, the subcontractor

argued that after he made some showing of economic waste, the subsequent burden to prove

damages—the amount of the diminution in value—shifted back to the party seeking damages (in

this case, the general contractor) because the party seeking damages always has the burden of

proof on damages. Id.

11 The economic waste doctrine has long been part of the rule in Oregon. See, e.g., Beik v.

Am. Plaza Co., 280 Or. 547, 555 (1977) (“The rule in Oregon is that the cost of replacement or

repair is the correct measure of damage for defects in work unless that remedy generates undue

economic waste.”) (citing Schmauch v. Johnston, 274 Or. 441 (1976), and Turner v. Jackson,

139 Or. 539, 560 (1932)).

12 The Oregon Supreme Court’s reference in Montara to Peevyhouse also confirms that

Oregon law applies the economic waste doctrine to commercial lease restoration cases and does

not limit that doctrine to lawsuits involving defective construction.

The Oregon Supreme Court in Montara declined to resolve the issues of burden of

production and burden of proof, explaining:

Regardless of which party ultimately bore the burden of production

or proof on economic waste, if there was no evidence in the record

to support that part of the instruction, the instruction was

erroneous.

As discussed above, the proper determination of whether economic

waste would result from an award of cost of repair damages

requires a comparison of the cost of repair and the diminution in

value. Thus, it was error to give the part of the instruction that

dealt with economic waste unless there was some evidence in the

record of both measures of damage. Here, there was no evidence in

the record regarding diminution in value. [The subcontractor]

points only to evidence that some (but not all) of his breaches of

contract were merely “technical” deviations from the plans and to

evidence of the cost to build the townhouses. Neither party put on

evidence of the value of the townhouses or of any reduction in

value as a result of [the subcontractor’s] breach of contract. And

neither party sought to tie that breach to any particular reduction in

value or in market price. At least some evidence of diminution in

value was required to support an instruction that would have

allowed the jury to base its verdict on that theory. Because there

was no such evidence, the trial court erred in giving that part of the

instruction.

Id. at 573.13

13 Arguing that Makarios, and not Ross, bears the burden of showing no economic waste,

Ross cites San Nicolas v. United States, 617 F.2d 246 (Ct. Cl. 1980). In that case, the court stated

that “Plaintiff has the burden to establish by a preponderance of the evidence that the fair market

value of the property in the condition which the defendant had covenanted to restore it was

greater than the property’s fair market value in an unrestored state at the termination of the

lease.” Id. at 249. San Nicolas, however, brought that lawsuit against the United States, as lessee.

The Court of Claims in San Nicolas cited another case against the United States in support of this

proposition, Dodge St. Bldg. Corp. v. United States, 341 F.2d 641, 645 (Ct. Cl. 1965), which

itself cited an even earlier case against the United States, Realty Assocs. v. United States, 138 F.

Supp. 875, 878 (Ct. Cl. 1956). Headnote 3 in Realty Assocs. reads: “In proceeding on claim

against government for breach of agreement to restore property leased to government by

plaintiff’s predecessor in title, plaintiff failed to sustain burden of showing actual damage by

virtue of breach of contract.” (emphasis added). Thus, in contractual restoration claims brought

against the United States, the Court of Claims consistently required that the plaintiff bear the

burden of showing no economic waste. Ross, however, is not the United States and this is not the

Court of Claims.

Although the Oregon Supreme Court did not resolve that specific question in Montara,

the Washington Supreme Court has done so in a persuasive opinion. In a decision applying

Washington law in the context of the economic waste doctrine in a case involving a breach of

commercial lease by a lessee, the Washington Supreme Court described the relevant burdens of

proof and production as follows:

Damages for breach of lease are determined by two methods: the

cost of restoration of the premises to a prescribed condition or the

diminution in market value of the property as a result of the failure

to comply with the lease. The appropriate measure of damages is

the method which yields the lesser amount. Fisher [Props., Inc. v.

Arden-Mayfair, Inc.], 106 Wash. 2d [826,] 843-44, [(1986)]; 2 M.

Friedman, Leases § 18.1 (2d ed. 1983). The plaintiff must come

forward with evidence on only one of the measures of damages

and then the burden of production shifts to the defendant to present

evidence that the other measure of damages is less.

Fisher Props., Inc. v. Arden-Mayfair, Inc., 115 Wash. 2d 364, 368 (1990). This is a reasonable

allocation of the burdens of production and proof that likely would be followed by the Oregon

Supreme Court.14

Makarios also argues that the economic waste doctrine does not apply when the party

asserting the doctrine willfuly or intentionally breached its contractual duties. No Oregon case,

however, expresses that proposition. Further, such a rule would be inconsistent with Peevyhouse,

which the Oregon Supreme Court recognized as “[o]ne of the leading cases on economic waste.”

Montara, 357 Or. at 349. Peevyhouse involved a lessee of land that breached a provision in its

14 Indeed, this conclusion appears similar to the view held by then-Oregon Court of

Appeals Judge Nakamoto, now Oregon Supreme Court Justice Nakamoto, in her concurring

opinion in Montara. See 259 Or. App. at 686 (“Although the contours of the economic waste

doctrine in Oregon are not as specifically defined as in cases from other jurisdictions, . . . given

the present circumstances, where [the subcontractor] did not make it evident that he was going to

rely on the economic waste doctrine at trial, I concur that [the subcontractor] bore the burden to

produce evidence of the diminution in the value of the buildings before the jury was instructed

on his theory of damages.”) (Nakamoto, J., concurring).

coal mining lease by failing to perform the required end-of-lease restorative and remedial work

after completing its strip-mining operations.

Relatedly, in Bowes v. Saks & Co., 397 F.2d 113 (7th Cir. 1968), landlords brought an

action against a commercial tenant for damages caused by the tenant’s breach of a clause in the

lease requiring the tenant to restore the premises at the end of the lease. The trial court entered

judgment adverse to the landlords. The Seventh Circuit affirmed, holding that the landlords

suffered no damages caused by the commercial tenant’s failure to restore the premises at the end

of the lease because the landlords sold the premises before the expiration of the lease. The

Seventh Circuit, referring to several cases, including Peevyhouse, explained:

In an action for breach of contract, as opposed to a suit sounding in

specific performance, the lessor is entitled only to the damages that

were caused to the property by the failure to restore. Where the

expense of restoration exceeds the diminution in the market value

of the property caused by the lessee’s nonperformance, the

diminution in fair market value is the proper measure of

damages. . . . If the cost or repair rule will give lessors a greater

benefit from the breach than could be gained from full

performance, a different measure of damages must be applied to

avoid injustice.

Id. at 116-17. Nothing was said in Bowes about this doctrine not applying in cases of willful or

intentional breach. There are, however, cases from other jurisdictions that appear to support

Makarios’s assertion, at least in construction defect cases.15

15 See, e.g., Roudis v. Hubbard, 574 N.Y.S.2d 95, 96 (1991) (“The ‘diminution in value’

measure of damages which defendant insists is applicable herein may only be judicially applied

where the contractor’s breach was unintentional and constituted substantial performance in good

faith.” (emphasis added)); Shell v. Schmidt, 164 Cal. App. 2d 350, 355 (1958) (noting that when

a contractor intentionally deviated from the plans and specifications, notwithstanding a claimed

justification for the deviation, it was not entitled to the diminution in value damage measure, as

good faith compliance is one of the elements of substantial performance). These two cases, and

others that are similar, arise in the context of a contractor failing fully to perform under a

construction agreement and derive from Jacob & Youngs v. Kent. Other cases, however, in the

context of a lessee failing to comply with restoration obligations in a lease and deriving from

Peevyhouse, do not appear to contain any requirement of unintentional breach. The Court is

D. Application of Economic Waste Doctrine

Fundamentally, Ross argues that the repair, restoration, and separation work that

Makarios contends Ross was contractually obligated to perform under the Richmond Lease had

no economic value. In other words, Ross contends that there would be no diminution in value

caused by Ross’s failure to perform that work. From this, Ross concludes that the cost of

performing that work, estimated to be in the millions of dollars, is disproportionately greater than

any nonexistent diminution in value caused by Ross’s failure to perform. Thus, under the

doctrine of economic waste, Ross argues, Makarios should recover nothing. Stated in still

another way, Ross contends that Makarios already was in as good a position as it would have

been had Ross fully performed its contractual end-of-lease obligations. Thus, according to Ross,

Makarios merely is seeking a “windfall.”

At trial, Ross presented evidence that the highest and best use of the Richmond Building

was “adaptive reuse,” while the building remaining conjoined and open with the Failing

Building.16 Ross also presented evidence showing that MDI purchased the Richmond Building

without requiring any additional repair, restoration, or separation work, before promptly reselling

the Richmond Building to an affiliate of Walker Place. After that, the Richmond Building and

the Failing Building again came under common ownership and control.

unaware of any case law or secondary literature explaining this apparent divergence, and neither

Makarios nor Ross has provided any.

16 Adaptive reuse involves taking an older building, such as the Richmond Building, and

reusing it for a purpose other than the purpose for which it was originally designed. At trial, Ross

called Gregory Close as a witness. Mr. Close has experience in commercial real estate

development and real estate investment advice. Among other things, Mr. Close described the

concept of “adaptive reuse.” Similarly, Mr. Anderson described one potential adaptive reuse of

the Richmond Building and portions of the Failing Building as providing for creative space in a

high-density open floor plan.

Ross also argues that Makarios presented no evidence that the repair, restoration, and

separation work demanded by Makarios would have provided any increase in the economic

value of the Richmond Building. Instead, Ross maintains, Makarios merely wanted to

“monetize” Ross’s contractual obligations and exploit the economic “power” that the Richmond

Lease gave to the lessor, Makarios. Stated another way, according to Ross, Makarios did not

really want Ross to perform any of the required end-of-lease work on the Richmond Building.

Instead, Makarios, believing that the lease provided Makarios will the legal ability to require

Ross to incur significant end-of-lease expenses, wanted to exploit that economic power by

eventually “compromising” with Ross so that Ross would pay Makarios for a release of Ross’s

end-of-lease obligations. In that way, Makarios will have “monetized” the economic power and

leverage over Ross created by the terms of the Richmond Lease. According to Ross, however,

that is precisely what the economic waste doctrine is intended to prevent. That doctrine applies

when enforcement of a contractual obligation would require a party to incur repair costs that are

grossly disproportional to any economic benefit, as measured by the avoidance of a diminution

of value if the work were not performed. As the commentary to the Restatement (Second) of

Contracts notes:

It is sometimes said that the award would involve “economic

waste,” but this is a misleading expression since an injured party

will not, even if awarded an excessive amount of damages, usually

pay to have the defects remedied if to do so will cost him more

than the resulting increase in value to him.

Restatement (Second) of Contracts § 348, cmt. c. Instead, the “injured party,” if awarded

excessive damages (either by judgment or settlement), would thereby receive a windfall beyond

what was needed to make that party whole.

The Court agrees in part with Ross’s arguments. First, the Court is persuaded, for the

reasons described by Mr. Anderson, that the highest and best use of the Richmond Building is

adaptive reuse, with that building remaining conjoined and open with the Failing Building.

Second, the Court also agrees with Ross that it is not the purpose of judicial enforcement of

contracts to facilitate a nonbreaching party in monetizing the economic leverage that it has over a

breaching party by obtaining compensation above the amount of harm caused by a breach when

that harm is significantly less than the cost of performance by the breaching party. It is beyond

serious dispute that the objective of American contract law is to protect the nonbreaching party

in receiving the benefit of her bargain by being put in as good a position as she would have been

in had the contract been performed. See Montara, 357 Or. at 346 (“the measure of damages is

always the sum which will put the injured party in as good a position as if the contract had been

performed”); see also n.1, supra. Thus, if performance by Ross of its contractual obligations

under §§ 16.01 and 16.02 would have provided no economic benefit for the Richmond Building,

then Ross’s failure to perform would have caused no damages recoverable under contract law.

That does not mean, however, that Ross prevails.

Just because the highest and best use of the Richmond Building may be adaptive reuse by

remaining conjoined and open with the Failing Building, that does not show that performance by

Ross of its repair, restoration, and separation obligations would have provided no value for the

Richmond Building. But even if there was some increase in value that would have been provided

to the Richmond Building by Ross’s performance, that still is not the end of the analysis. For the

economic waste doctrine to apply, the Court must find that any increase in value to the

Richmond Building resulting from performance (or the avoidance of a diminution in value) is

“grossly disproportionate to the cost of performance.” Peevyhouse, 382 P.2d at 113. Or,

explained by the Oregon Supreme Court in Montara, “[i]n Oregon construction defect cases, that

sum is the amount of money equal to the cost of curing the defects, provided repair is the

prudent remedy to apply.” Montara, 357 Or. at 346 (simplified). The question then becomes

whether the Montara standard is functionally the same as the Peevyhouse standard.

The Court concludes that these two standards are functionally equivalent. As explained

by the Oregon Supreme, “Oregon courts use an alternative measure of damages—the diminution

in the market value of the property—when the cost of repair is not ‘the prudent remedy to apply’

because that remedy would create ‘economic waste.’” Montara, 357 Or. at 346. In the very next

paragraph, the Supreme Court explains the concept of “economic waste” by stating, in relevant

part: “Economic waste occurs where ‘the defect in material or construction is one that cannot be

remedied without an expenditure for reconstruction disproportionate to the end to be attained.’”

Montara, 357 Or. at 346 (quoting Schmauch v. Johnston, 274 Or. 441, 447 (1976)) (emphasis

added). The Oregon Supreme Court then adds: “Stated differently, ‘[d]iminution in value is the

proper measure of damages only when the cost of repair is disproportionate to the diminution in

value.’” Montara, 357 Or. at 346-47 (quoting Hanset v. General Constr. Co., 285 Or. 101, 106

(1979) (emphasis in original) (brackets in original)). This makes the central question whether the

costs of repair, restoration, and separation are disproportionate to the diminution in value.

Further, Montara explains that the diminution in value is just another way of saying “the

difference between the value of the building as it is and what it would have been worth if it had

been built in conformity with the contract.” Montara, 357 Or. at 346 (quoting Schmauch v.

Johnston, 274 Or. at 447).

Thus, the Court must compare the costs of repair, restoration, and separation, which

Makarios’s witness Mr. Bailey says totals more than several million dollars, with the difference

between the value of the Richard Building as it was on September 30, 2016 and what it would

have been worth if Ross had not materially breached its §§ 16.01 and 16.02 lease obligations.

That comparison, however, cannot be done given the record in this case because the Court rejects

Ross’s conclusory assertion that the repairs would have offered no value at all.

It would have been easy enough to offer in evidence two appraisals, one appraising the

Richmond Building as it stood on September 30, 2016, and the other providing a hypothetical

appraisal of what that building would have been worth had the contractually obligated repairs,

restoration, and separation work been performed. Neither side offered this evidence, and thus the

party who bears the burden of proof (or at least of production) loses on this point. As previously

discussed, the Court believes that the Oregon Supreme Court would follow the approach of the

Washington Supreme Court here. See Fisher Props., 115 Wash. 2d at 368 (“The plaintiff must

come forward with evidence on only one of the measures of damages and then the burden of

production shifts to the defendant to present evidence that the other measure of damages is

less.”). Here, Makarios (as Counterclaim-Plaintiff) came forward with one of the measures of

damages, namely the cost of repair, restoration, and separation. The burden then shifted to Ross

to present evidence of the other measure of damages (diminution of value, i.e, the difference

between the value of the Richmond Building as it is and what it would have been worth if it had

Ross performed its end-of-lease obligations). Because Ross did not produce that evidence, Ross

cannot receive the benefit of the economic waste doctrine.

This analysis does not mean that Makarios is entitled to all the damages that it sought. As

previously discussed, the Court finds that Makarios has not met its burden of showing that a

reasonable landlord would have made the extensive and expensive repairs to the unused freight

elevator (Elevator 1), the plumbing for floors three through five, and the air conditioning for the

third floor. Although Mr. Bailey testified persuasively about the costs of repair for items those

items, Makarios did not present persuasive testimony from any witness that a prudent landlord

would have incurred those significant expenses, and the Court may not speculate.

The Court, however, did not find that all prudent landlords in the position of Makarios

necessarily would incur the significant costs associated with separating the Richmond Building

from the Failing Building, especially considering Mr. Anderson’s testimony that separation

would not achieve the highest and best use of the Richmond Building. A prudent landlord simply

might have decided to sell the Richmond Building to the owner of the Failing Building (or buy

the Failing Building) to obtain the benefits that Mr. Anderson described. It is not necessarily

imprudent, however, to fail to do something that achieves the highest and best use, especially

when legitimate reasons are offered. Here, Mr. Calomiris testified about why he and his family

wanted a standalone building, and the Court accepts that testimony.

Although the separation cost issue in this case presents a close question (indeed, probably

the most difficult question in this lawsuit), what tips the balance for the Court is the unequivocal

expression in the Richmond Lease that, at the conclusion of the lease, the tenant must separate

the Richmond Building from the Failing Building and make the Richmond Building into a

standard alone, self-sufficient building. See Richmond Lease, § 16.02. In 1956, the landlord for

the Richmond Building appears to have believed that separation would be prudent, and the then-

lessee (Newberry) contractually agreed to do that. The Court, applying a preponderance standard

to the record evidence in this case, concludes that such a decision still would be at least one of

several reasonable, or prudent, options in 2016.

As discussed previously, this decision might have been otherwise had Ross presented

persuasive evidence, probably in the form of two appraisals from qualified experts, comparing

the fair market value of the Richmond Building as it existed on September 30, 2016 with what its

fair market value would have been had it been separated from the Failing Building, as the leased

required, without assuming common ownership of the two buildings. Ross appears to argue that

the Court should find that the fair market value of the Richmond Building would have gone

down after separation, resulting in no diminution in value caused by Ross’s failure to separate the

buildings. According to Ross, that would have made the separation costs ($927,079) grossly

disproportionate to any diminution in value caused by nonperformance (none). This, according to

Ross, would support a conclusion of no damages resulting from the breach of § 16.02. Ross’s

argument, however, assumes common ownership. If there were common ownership of the two

buildings, then—based on Mr. Anderson’s testimony—Ross might be correct.

But as of September 30, 2016, there was not common ownership of the Richmond and

Failing Buildings. Thus, the data that is needed—but was not provided—is whether separating

the Richmond Building from the Failing Building would have added value (and in what amount),

subtracted value, or not have affected value for the Richmond Building as a standalone entity,

without making any assumptions about common ownership. Only then could a factfinder

correctly compare separation costs with the relevant diminution of value, if any.

In the absence of expert appraisals that do not assume common ownership, Ross is

simply asking the factfinder to speculate about the effect that separation might have on the value

of the Richmond Building without common ownership. Further, it is plausible that leaving the

Richmond Building connected to the Failing Building in violation of § 16.02 would substantially

diminish the fair market value of the Richmond Building, because it would leave only one

potential buyer for that building—the owner of the Failing Building. Any other potential buyer

would need to bear the costs of separation (or the even greater costs of purchasing the Failing

Building). Indeed, it looks likely that leaving the Richmond Building connected to the Failing

Building in violation of the lease would reduce the fair market value of the Richmond Building

by approximately the amount of the separation costs. To confirm (or refute) this, however,

appraisals would have been helpful, and perhaps even necessary. Finally, if the diminution in

value resulting from Ross’s breach of § 16.02 is approximately equal to the separation costs (or

at least not grossly disproportionate to them), that would show an absence of economic waste. In

any event, the Court must base its decision on evidence and not speculation.

E. Additional Conclusions of Law

1. Makarios did not fail to mitigate its damages. Makarios was not obligated to

perform Ross’s end-of-lease obligations to mitigate its damages.

Further, Makarios was not obligated to sell the Richmond Building to Brandon Anderson

(or to anyone else) to be entitled to recover damages for Ross’s breach of its end-of-lease

obligations. Ross did not meet its burden of showing the affirmative defense of failure to

mitigate.

2. Ross asserts that it wanted to complete its §§ 16.01 and 16.02 obligations after

September 30, 2016, but Makarios would not permit Ross to do so. Considering the long-running

disputes between the parties regarding the way in which Ross wanted to perform its repair,

restoration, and separation obligations, Makarios was not required to allow Ross perform work

on the Richmond Building after September 30, 2016, to be entitled to recover damages for

Ross’s breach of its end-of-lease obligations.

3. Makarios also did not interfere with any performance by Ross of its end-of-lease

obligations before September 30, 2016. The defense of interference requires the asserting party

to prove that the other party unjustifiably prevented the breaching party’s performance or that the

breaching party did not bear the risk, under the circumstances, that it would be prevented from

performing the obligations under the contract. Ross did not meet its burden of showing the

affirmative defense of interference.

4. Makarios did not waive its rights to seek damages for Ross’s breach of its end-of-

lease obligations. The defense of waiver requires the asserting party to prove that the other party

voluntarily relinquished a known right, manifested by clear and unequivocal action. Ross did not

meet its burden of showing the affirmative defense of waiver.

5. Ross also did not meet its burden of showing the affirmative defenses of estoppel,

unclean hands, or laches.

6. Ross breached its end-of-lease obligations under the Richmond Lease on or about

September 30, 2016. Makarios timely asserted its supplemental counterclaims alleging that Ross

breached its end-of-lease obligations within the applicable six-year statute of limitations. See Or.

Rev. Stat. § 12.080.

7. Ross’s failure to comply with its end-of-lease obligations under § 16.01

constitutes a material breach of the Richmond Lease.

8. Ross’s failure to comply with its end-of-lease obligations under § 16.02

constitutes a material breach of the Richmond Lease.

9. Ross is liable to Makarios for damages for breach of §§ 16.01 and 16.02 of the

Richmond Lease in the total amount of $2,076,814, not including prejudgment interest.

10. Ross’s failure to pay rent for the Richmond Building from May 2015 through

September 30, 2016 constitutes a material breach of the Richmond Lease. Ross owes unpaid rent

for that period in the total amount of $48,161, not including prejudgment interest.

11. A federal court sitting in diversity applies state law, not federal law, regarding the

issue of prejudgment interest. Atl. Richfield Co. v. Farm Credit Bank of Wichita, 226 F.3d 1138,

1156 (10th Cir. 2000). Unless the parties have agreed otherwise, “in diversity actions, state law

determines the rate of prejudgment interest, and postjudgment interest is governed by federal

law.” Citicorp Real Estate, Inc. v. Smith, 155 F.3d 1097, 1108 (9th Cir. 1998). In Oregon,

prejudgment interest is allowed at the rate of nine percent per year, unless the parties have agreed

otherwise, on all moneys after they become due. Or. Rev. Stat. § 82.010(1)(a). Further, “the fact

that the amount owed cannot be ascertained without resolving complex issues of fact does not

bar a determination that the defendant owed sums certain at a date certain.” Jones v. Dorsey, 193

Or. App. 688, 692-93 (2004). Thus, under Oregon law, “it is well settled that, even though

damages are not ascertainable until issues of fact have been decided by the jury, prejudgment

interest is proper.” Strader v. Grange Mut. Ins. Co., 179 Or. App. 329, 339 (2002) (simplified).

12. Ross owes Makarios prejudgment interest on the principal amount of $2,076,814

for its §§ 16.01 and 16.02 obligations, beginning October 1, 2016 through the date of judgment.

As of January 8, 2021, this prejudgment interest totals $798,862. Thus, Ross’s liability under

§§ 16.01 and 16.02, including prejudgment interest, totals $2,875,676.

13. As previously noted, it was not ascertainable that Ross owed unpaid rent in the

amount of $48,161 for the Richmond Building from May 2015 through September 30, 2016,

until the state court judgment on Makarios’s FED action became final and unappealable on

March 6, 2019. Accordingly, Ross owes Makarios prejudgment interest on the principal amount

of $48,161 for unpaid rent, beginning March 6, 201 through the date of judgment. As of

January 8, 2021, this prejudgment interest totals $7,992. Thus, Ross’s liability for unpaid rent,

including prejudgment interest, totals $56,153.

14. As of January 8, 2021, Ross owes Makarios the total amount of $2,931,829 under

the Richmond Lease.

CONCLUSION

The Court makes the findings of fact and conclusions of law stated here. The Court

separately will enter judgment in favor of Makarios-Oregon, LLC and against Ross Dress for

Less, Inc. in the total amount of $2,931,829, consistent with these findings and conclusions.

IT IS SO ORDERED.

DATED this 8th day of January, 2021.

/s/ Michael H. Simon

Michael H. Simon

United States District Judge

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.