holding that plaintiff’s work inspecting and adjusting air conditioner units throughout office building were alterations that fell within the purview of NYLL § 240(1)
How later courts described this case
- holding that plaintiff’s work inspecting and adjusting air conditioner units throughout office building were alterations that fell within the purview of NYLL § 240(1)
- denying plaintiff’s motion to amend complaint to add NYLL § 240(1) claim based on injury caused by a collapsed “stack of boxes” because “plaintiff was not engaged in a covered activity at the time of the accident”
- granting summary judgment in favor of building owner on plaintiff’s Section 200 and common law negligence claims
- affirming summary judgment dismissing plaintiff’s claims to the extent they were based on Industrial Code Section 23-2.1(a)(1)
Written by the judges who cited it.
The opinion
UNITED STATES DISTRICT COURT
EASTERN DISTRICT OF NEW YORK
STEPHEN LOGERFO,
MEMORANDUM & ORDER
Plaintiff, 19-CV-02019 (HG) (AYS)
v.
JPMORGAN CHASE BANK, NATIONAL
ASSOCIATION, JPMORGAN CHASE
BANK, N.A., and THE CHASE
MANHATTAN BANK, N.A.,
Defendants.
JPMORGAN CHASE BANK, NATIONAL
ASSOCIATION, JPMORGAN CHASE
BANK, N.A., and THE CHASE
MANHATTAN BANK, N.A.,
Third-Party Plaintiffs,
v.
UNITY ELECTRIC CO., INC., UNI-DATA
COMMUNICATIONS, INC., UNITY
ELECTRIC LLC, UNITY INTERNATIONAL
GROUP, INC., ENGIE NORTH AMERICA
INC., ENGIE NYC LLC, and JONES LANG
LASALLE AMERICAS, INC.,
Third-Party Defendants.
HECTOR GONZALEZ, United States District Judge:
Plaintiff was injured while working at a building owned by JPMorgan Chase Bank, N.A.
(“JPM”) and has asserted claims against JPM for violations of the New York Labor Law
(“NYLL”) and for common law negligence. JPM has moved for summary judgment dismissing
those claims. JPM has also asserted claims for indemnification against Third-Party Defendants
Jones Lang Lasalle, the property manager for the building where Plaintiff was injured, and Unity
Electric Co., Inc., the subcontractor that employed Plaintiff. JPM seeks summary judgment on
those indemnification claims, and Jones Lang Lasalle has filed its own motion for summary
judgment seeking to dismiss JPM’s indemnification claims. For the reasons set forth below, the
Court grants JPM’s motion for summary judgment dismissing Plaintiff’s claims. Since the Court
has concluded that JPM is not liable to Plaintiff, and the parties have invoked only the Court’s
supplemental jurisdiction over the indemnification claims in the third-party action, the Court
declines to exercise supplemental jurisdiction over those claims and dismisses them without
prejudice.
FACTUAL BACKGROUND
Plaintiff was injured while working in a building owned by JPM. ECF No. 68 ¶¶ 2–3.
Plaintiff is an electrical foreman who was not employed by JPM but was instead employed by
Unity. Id. ¶ 1. Jones Lang Lasalle was responsible for providing “facilities management and
property services” at the building where Plaintiff was injured pursuant to a Master Services
Agreement between JPM and Jones Lang Lasalle. ECF No. 66-14 at 10. Jones Lang Lasalle
hired Unity as a subcontractor to perform some of that work and entered into a Service
Contractor Agreement with Unity governing their relationship. ECF No. 65-16. Pursuant to that
contract, Unity was responsible for ordinary repairs and preventative maintenance. Id. at 12.
However, Unity was also working on a specific project at the same building, in addition
to these general maintenance duties, which JPM refers to as a “Security Uplift,” and which
Plaintiff referred to as the “TR room card reader upgrade.” ECF No. 66-19 ¶ 16; Pls. Dep. at
21:10–20.1 That project involved making changes to various card readers necessary to access
certain rooms throughout JPM’s building and replacing them with different card readers. Pls.
Dep. at 23:2–17. JPM had hired a separate general contractor to work on that project, non-party
Structure Tone, Inc., not Jones Lang Lasalle. ECF No. 66-17. Structure Tone hired Unity as a
subcontractor for the security card reader project and entered into an agreement with Unity that
was separate from Unity’s Service Contractor Agreement with Jones Lang Lasalle. Id.
Plaintiff testified that, on the day he was injured, he came to work to find that Unity had
received in his office a stack of invoices for “materials” that had been delivered the night before.
Pls. Dep. at 27:13–24. The boxes of materials had been delivered to a storage room that JPM
had made available for Unity in JPM’s building, which was next to Plaintiff’s office. Id. at
27:13–24, 79:6–80:10. Plaintiff went to the storage room to inspect an approximately six-foot
high stack of boxes, so that he could check them against the materials described in the invoices.
Id. at 28:5–13, 28:22–29:1. Plaintiff attempted to pull a box from the top of the stack, but the
“heavy” box fell onto his right shoulder before falling to the floor. Id. Although Plaintiff felt
“hurt” because of the incident, he continued to attempt to inspect the contents of the box, which
had gotten “wedged between [a] big wire reel” and another “stack of boxes.” Id. at 28:5–18.
Plaintiff tried to “yank” the wire reel “out of the way,” so that he could inspect the contents of
the box. Id. at 28:14–21. But while Plaintiff was pulling the wire reel, he felt “a pop sensation”
in the same shoulder on which the box had previously fallen. Id. Nobody other than Plaintiff
1 Since the parties have filed three different motions for summary judgment, there are
various filings on the Court’s docket that contain excerpts of Plaintiff’s deposition. See, e.g.,
ECF Nos. 64-8, 68-3, 75-1, 76-1. For ease of reference, the Court will cite Plaintiff’s deposition
transcript as “Pls. Dep.” and identify specific testimony using the page numbers from the
deposition transcript, rather than the pagination that the Court’s electronic filing system
imprinted on the parties’ excerpts of that transcript.
was in the room to witness the incident. Id. at 37:19–21. Plaintiff was later diagnosed with a
tear in a muscle in his right shoulder. Id. at 40:3–22.
Plaintiff testified that all of the materials that had been sent in the boxes that he
inventoried were related to the security card reader project even though the room where the
boxes were stored also contained “years of material[s]” that were used for other projects on
which Unity worked. Pls. Dep. at 27:13–24, 73:11–23. Specifically, the box that fell on Plaintiff
contained “transformers,” “door contacts,” “computer cards,” and “panel boxes.” Id. at 72:11–
18. JPM contends that the wire reel that Plaintiff was pulling when he heard his shoulder “pop”
was kept in the storage room for Unity’s general maintenance work and not for the card reader
project. ECF No. 66-20 at 2. But the deposition testimony that JPM cites to as purported
support for that assertion does not say anything about the purpose of the wire reel, and neither
JPM nor any other party has presented the Court with testimony or other evidence identifying the
purpose of the wire reel. See, e.g., Pls. Dep. at 27:13–28:21, 34:1–21.
Plaintiff testified that he did not have any stepladders available to access tall stacks of
boxes, but that he did have six- and eight-foot ladders available. Pls. Dep. at 29:5–22. However,
he said that the storage room was too cluttered with boxes and other materials to unfold a ladder.
Id. Plaintiff conceded that he had never, before his accident, raised concerns about the storage
room being too cluttered or in need of clearing out with JPM, Jones Lang Lasalle, or anyone else.
Id. at 78:21–79:5. He also could not recall another accident ever occurring in the storage room.
Id. at 91:19–22. But Plaintiff said that Unity employees had “asked a lot,” in connection with
other projects, about getting additional storage rooms in the building, and that JPM sometimes
provided additional rooms. Id. at 83:5–12. Plaintiff further testified that the clutter was caused,
at least in part, by JPM because whenever Unity completed a project in the building, JPM
insisted that Unity move all of the project materials out of the areas where work was being
performed, and that the storage room where Plaintiff was injured was the only place to store
them. Id. at 82:17–83:4. Plaintiff also insisted that JPM employees had the authority to enter
and clean out the storage room if they wanted to. Id. at 79:6–9. Although Unity had placed a
padlock on the storage room, building engineers employed by JPM had the combination
necessary to open the lock and could enter the room. Id. at 79:10–16.
Plaintiff commenced this action by asserting claims against only JPM for common law
negligence and violations of Sections 200, 240(1), and 241(6) of the NYLL. ECF No. 1. JPM
filed a third-party complaint asserting claims for indemnification and contribution against Jones
Lang Lasalle, Unity, and several companies affiliated with Unity, asserting claims for
indemnification and contribution. ECF No. 36. Jones Lang Lasalle and Unity each responded
by asserting counterclaims for indemnification and contribution against JPM. ECF Nos. 38, 45.
Jones Lang Lasalle and Unity each also asserted cross-claims for contribution and
indemnification against each other. Id.
JPM has moved for summary judgment dismissing all of Plaintiff’s claims and has also
moved for summary judgment on its own claims for indemnification against Jones Lang Lasalle
and Unity. ECF Nos. 65, 66. Plaintiff, Jones Lang Lasalle, and Unity have each opposed the
respective motions for summary judgment against them. ECF Nos. 68, 70, 71. However, only
Jones Lang Lasalle has filed its own motion for summary judgment seeking the dismissal of the
indemnification claims against it, including JPM’s indemnification claim. ECF No. 64. Plaintiff
has not moved for summary judgment on his claims against JPM, and Unity has not moved for
summary judgment either to dismiss JPM’s claims or to seek a finding that it has prevailed on its
own indemnification-related cross-claims or counterclaims.
LEGAL STANDARD
Summary judgment is appropriate “if the movant shows that there is no genuine dispute
as to any material fact and the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P.
56(a). In other words, a court should grant summary judgment “if the pleadings, depositions,
answers to interrogatories, and admissions on file, together with the affidavits, if any, show that
there is no genuine issue as to any material fact and that the moving party is entitled to a
judgment as a matter of law.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247 (1986).2 The
moving party has the burden of demonstrating that there is no genuine issue of material fact.
Celotex Corp. v. Catrett, 477 U.S. 317, 323 (1986). “Where the moving party demonstrates the
absence of a genuine issue of material fact, the opposing party must come forward with specific
evidence demonstrating the existence of a genuine dispute of material fact.” Brown v. Eli Lilly &
Co., 654 F.3d 347, 358 (2d Cir. 2011).
When deciding a summary judgment motion, any ambiguities and inferences drawn from
the facts must be viewed in the light most favorable to the nonmoving party. LaFond v. Gen.
Physics Servs. Corp., 50 F.3d 165, 171 (2d Cir. 1995). Although “courts must refrain from
assessing competing evidence in the summary judgment record and avoid making credibility
judgments,” a party must defeat summary judgment by putting forth “evidence on which the jury
could reasonably find for the non-moving party.” Saeli v. Chautauqua Cty., 36 F.4th 445, 456
(2d Cir. 2022) (emphasis in original) (affirming summary judgment dismissing claims).
2 Unless noted, case law quotations in this order accept all alterations and omit internal
quotation marks, citations, and footnotes.
DISCUSSION
The Court grants JPM’s motion for summary judgment in full and dismisses all of
Plaintiff’s claims against it. The Court therefore does not need to reach JPM’s, Jones Lang
Lasalle’s, and Unity’s claims for indemnification against each other, and it declines to exercise
supplemental jurisdiction over those claims.
I. Each of Plaintiff’s Claims Against JPM Fails as a Matter of Law
Plaintiff has asserted claims against JPM pursuant to three different provisions of the
NYLL: Sections 200, 240(1), and 241(6). Plaintiff’s claim pursuant to Section 240(1) fails
because his injury was not caused by an elevation-related risk to which that section applies.
Plaintiff’s claim pursuant to Section 241(6) fails because it must be premised on a violation of
New York’s Industrial Code, and Plaintiff cannot prove as a matter of law that JPM violated any
provision of the industrial code. Finally, Plaintiff’s claim pursuant to Section 200 and his
common law negligence claim fail because Plaintiff cannot demonstrate that JPM was on notice
of the allegedly unsafe working conditions and, therefore, cannot prove that JPM was negligent.
A. Plaintiff’s NYLL § 240(1) Claim
Section 240(1) of the NYLL requires property “owners” who contract for work related to
“altering . . . a building or structure” to “furnish or erect, or cause to be furnished or erected for
the performance of such labor, scaffolding, hoists, stays, ladders, slings, hangers, blocks, pulleys,
braces, irons, ropes, and other devices which shall be so constructed, placed and operated as to
give proper protection to a person so employed.” NYLL § 240(1). “New York Labor Law §
240(1) imposes a nondelegable duty upon owners and general contractors and their agents to
provide safety devices necessary to protect workers from risks inherent in elevated work sites.”
Quishpe v. Urban Atelier Grp., LLC, No. 21-cv-2723, 2023 WL 5625307, at *5 (E.D.N.Y. Aug.
31, 2023). Since the duty is nondelegable, a plaintiff need not prove a defendant’s negligence,
and a plaintiff’s own comparative negligence “does not furnish a defense” unless the defendant
can prove that the “plaintiff [wa]s the sole proximate cause of his or her own injuries.” Id.
JPM unsuccessfully argues that Plaintiff was not engaged in construction work that
brings him within the purview of NYLL Section 240(1) because Plaintiff was merely unloading
boxes and not installing security card readers in JPM’s building when he was injured. ECF No.
66-20 at 10–11, 12–13, 15–16. However, when considering whether a plaintiff was altering a
structure in a manner that brings his work within the scope of Section 240(1), New York courts
do not “limit [their] analysis of [a] plaintiff’s activity to the moment of his injury.” Saint v.
Syracuse Supply Co., 30 N.E.3d 872, 876 (N.Y. 2015). In other words, courts do not “isolate the
moment of injury and ignore the general context of the work.” Id. at 877. Section 240(1) applies
to a plaintiff’s work if the plaintiff is “performing duties ancillary” to activities that fall within
the scope of the statute—meaning duties that are “an integral part of” a construction project. Id.
Whether Plaintiff was performing construction work at the time of his injury, therefore, depends
on whether Unity’s broader security card reader project is considered construction work.
The card reader project entailed a sufficiently significant alteration to JPM’s building to
bring Plaintiff’s work within the scope of Section 240(1). The New York Court of Appeals has
held that “allowing every change in a structure to qualify as an alteration gives the statute [i.e.,
NYLL § 240(1)] too broad a reach.” Joblon v. Solow, 695 N.E.2d 237, 241 (N.Y. 1998).
Accordingly, “the term ‘altering’ in section 240(1) requires making a significant physical change
to the configuration or composition of the building or structure.” Saint, 30 N.E.3d at 877
(emphasis in original). “[W]ork being performed that affects a crucial building system” qualifies
as an alteration even if the system does not “affect[] the building’s structural integrity.”
Mananghaya v. Bronx-Lebanon Hosp. Ctr., 83 N.Y.S.3d 444, 451 (1st Dep’t 2018) (holding that
“significant change to . . . hospital’s air conditioning system” fell within scope of the statute).
The upgrade of the security system in JPM’s building was significant enough to bring Plaintiff’s
work within the scope of Section 240(1) because the New York Court of Appeals has held that a
similar electrical upgrade fell within the statute’s scope. Weininger v. Hagedorn & Co., 695
N.E.2d 709, 710 (N.Y. 1998) (holding that “running computer and telephone cable” throughout
office building was considered sufficiently signification alteration to building); see also Prats v.
Port Auth. of N.Y. & N.J., 800 N.E.2d 351, 353–54 (N.Y. 2003) (holding that plaintiff’s work
inspecting and adjusting air conditioner units throughout office building were alterations that fell
within the purview of NYLL § 240(1)).
Plaintiff’s Section 240(1) claim nevertheless fails because he cannot show that his injury
resulted from the type of elevation-related risk that Section 240(1) was designed to protect
against. “Not every worker who falls at a construction site, and not every object that falls on a
worker, gives rise to the extraordinary protections of Labor Law § 240(1).” Narducci v.
Manhasset Bay Assocs., 750 N.E.2d 1085, 1089 (N.Y. 2001). A plaintiff must show that he
“suffered an injury as the direct consequence of a failure to provide adequate protection against a
risk arising from a physically significant elevation differential.” Soto v. J. Crew Inc., 998 N.E.2d
1045, 1047 (N.Y. 2013). Accordingly, even if a plaintiff has been “injured by the operation of
gravity,” a claim based on Section 240(1) will still fail if the gravity-related injury did not
involve “a physically significant elevation differential or an extraordinary elevation risk
encompassed by the statute.” Buono v. AvalonBay Cmty., No. 19-cv-5413, 2021 WL 51524, at
*3 (S.D.N.Y. Jan. 6, 2021) (granting summary judgment dismissing Section 240(1) claim based
on six-foot ladder that tipped over and fell on plaintiff).
The event that led to Plaintiff’s injury—a box falling from a height of approximately six
feet—does not satisfy this criterion. The New York Court of Appeals has, on multiple occasions,
rejected Section 240(1) claims based on plaintiffs or objects that fell from similarly modest
heights. Soto, 998 N.E.2d at 1049 (holding that plaintiff’s “dusting of a six-foot-high display
shelf” was not a task that fell within the scope of NYLL § 240(1)); Broggy v. Rockefeller Grp.,
Inc., 870 N.E.2d 1144, 1147–48 (N.Y. 2007) (affirming grant of summary judgment in favor of
defendant “because the evidence in this record demonstrates as a matter of law that” plaintiff
who stood on, and fell from, desk while cleaning interior windows “did not . . . need protection
from the effects of gravity”); Toefer v. Long Island R.R., 828 N.E.2d 614, 618 (N.Y. 2005)
(holding that “[a] four-to-five-foot descent from a flatbed trailer or similar surface does not
present the sort of elevation-related risk that triggers Labor Law § 240(1)’s coverage”). Other
courts have followed suit and held that NYLL § 240(1) does not apply to falls from heights
similar to the stack of boxes that Plaintiff was working with. Walter v. CSX Transp., Inc., No.
22-1254-cv, 2023 WL 4044113, at *2 (2d Cir. June 16, 2023) (affirming summary judgment
dismissing NYLL § 240(1) claim because “[t]he task of unloading a truck is not an elevation-
related risk simply because there is a difference in elevation between the ground and the truck
bed”); Decker v. C&S Wholesale Grocers, Inc., 786 N.Y.S.2d 328, 329 (2d Dep’t 2004) (denying
plaintiff’s motion to amend complaint to add NYLL § 240(1) claim based on injury caused by a
collapsed “stack of boxes” because “plaintiff was not engaged in a covered activity at the time of
the accident”).
In reaching the conclusion that Plaintiff’s injury did not occur because of a significant
elevation differential, the Court is not relying on JPM’s argument that Plaintiff was injured
because of his attempt to pull a wire reel located at ground level and not because of the falling
box. ECF No. 66-20 at 12–13. Whether Plaintiff’s injury was caused solely by pulling on the
wire reel or prompted by the falling box and then completed by Plaintiff’s efforts to pull the wire
reel is an issue of fact that the Court cannot resolve at the summary judgment stage. Resolving
this dispute would be particularly inappropriate because the parties have not submitted medical
opinion evidence addressing the cause of Plaintiff’s injury. However, even if Plaintiff’s injury
was caused solely by the falling box, Plaintiff’s Section 240(1) claim fails for the reasons
explained above.
B. Plaintiff’s NYLL § 241(6) Claim
Section 241(6) of the NYLL requires property owners to ensure that “all areas in which . .
. work is being performed” are “so constructed, shored, equipped, guarded, arranged, operated
and conducted as to provide reasonable and adequate protection and safety to the persons
employed therein or lawfully frequenting such places.” NYLL § 241(6). Although the text of
Section 241(6) addresses only work related to “construction, excavation or demolition,” see id.,
the New York Court of Appeals has interpreted the statute’s definition of the term “construction”
to include “alteration[s]” that would fall within the scope of Section 240(1), see Joblon, 695
N.E.2d at 242.
As with a claim under Section 240(1), Section 241(6) imposes a “nondelegable” duty on
a building’s owner, so a plaintiff need not demonstrate the owner’s negligence or even show that
the owner “exercised supervision or control over [his] worksite.” Quishpe, 2023 WL 5625307,
at *4. However, since Section 241(6) does not define an applicable standard for “reasonable and
adequate protection and safety,” “[t]o establish liability under NYLL section 241(6), a plaintiff
must demonstrate that his injuries were proximately caused by a violation of an applicable New
York Industrial Code provision.” Buono, 2021 WL 51524, at *3; see also Quishpe, 2023 WL
5625307, at *4 (“To establish liability under § 241(6), a plaintiff must specifically plead and
prove the violation of an applicable Industrial Code regulation.”). Here, Plaintiff has relied on
Industrial Code Section 23-2.1(a)(1). ECF No. 68-1 at 13–15.
Plaintiff cannot demonstrate that Industrial Code Section 23-2.1(a)(1) applies to the
course of events that led to his injury. That provision requires: “All building materials shall be
stored in a safe and orderly manner. Material piles shall be stable under all conditions and so
located that they do not obstruct any passageway, walkway, stairway or other thoroughfare.” 12
N.Y.C.R.R. § 23-2.1(a)(1). The first sentence of this provision is a general statement about the
storage of materials that does not specify the specific locations to which the provision applies.
Id. However, New York courts have determined, based on the second sentence, that the
provision does not apply in “an open work area,” and instead applies only “in a passageway,
hallway, stairway, or other thoroughfare.” Ormsbee v. Time Warner Realty Inc., 166 N.Y.S.3d
130, 131 (1st Dep’t 2022) (affirming summary judgment dismissing plaintiff’s claims to the
extent they were based on Industrial Code Section 23-2.1(a)(1)); Wiley v. Marjam Supply Co.,
Inc., 87 N.Y.S.3d 675, 679 (3d Dep’t 2018) (affirming summary judgment in favor of defendant
because falling piece of “sheetrock was stored in the corner of a second-floor room and did not
obstruct any passageway, walkway, stairway or other thoroughfare”); Desena v. N. Shore
Hebrew Academy, 989 N.Y.S.2d 505, 510 (2d Dep’t 2014) (granting summary judgment to
defendant because “12 NYCRR 23–2.1 [wa]s not applicable” to plaintiff’s claims since “[t]he
accident occurred in an open area at a worksite, not a passageway, walkway, stairway or other
thoroughfare”). As in these other cases, Plaintiff’s Section 241(6) claim fails because the storage
room in which he was injured is not the type of setting covered by Industrial Code Section 23-
2.1(a)(1). Buono, 2021 WL 51524, at *4 (granting summary judgment in favor of defendant
because Industrial Code Section 23-2.1(a)(1) “d[id] not apply to the site of [p]laintiff’s
accident”).
JPM said in its opening brief that Plaintiff had previously indicated that JPM can be held
liable for violating NYLL § 241(6) because of violations of New York Industrial Code Sections
23-1.7(e)(2) and 23-1.5, which relate to “general hazards” and the “[g]eneral responsibility of
employers,” respectively. ECF No. 66-20 at 13, 16; see 12 N.Y.C.R.R. §§ 23-1.5, 23-1.7. JPM
argued that Plaintiff cannot prove those violations as a matter of law, but in Plaintiff’s opposition
brief, he addressed only JPM’s arguments about Industrial Code Section 23-2.1(a)(1), without
making any arguments about the other sections addressed by JPM. ECF No. 66-20 at 13–16;
ECF No. 68-1 at 13–15. Plaintiff has, therefore, waived any claim based on a violation of
Industrial Code Sections 23-1.7(e)(2) and 23-1.5. When a party represented by counsel files an
opposition to a motion for summary judgment that addresses some claims but not others, as
Plaintiff has done here, a district court may “infer from [the] party’s partial opposition that
relevant claims or defenses that are not defended have been abandoned.” Jackson v. Fed. Exp.,
766 F.3d 189, 198 (2d Cir. 2014) (holding that district court properly treated plaintiff as having
waived certain claims).
Plaintiff’s Section 241(6) claims based on these Industrial Code provisions would fail
even if they were not waived. Industrial Code Section 23-1.7(e)(2) is plainly inapplicable
because it “applies where a plaintiff is injured because of a tripping hazard,” and Plaintiff was
indisputably not injured by a tripping hazard. Buono, 2021 WL 51524, at *3 (granting motion
for summary judgment dismissing Section 241(6) claim based on alleged violation of Industrial
Code Section 23-1.7(e)(2)). Industrial Code Section 23-1.5 describes the “[g]eneral
responsibility of employers.” 12 N.Y.C.R.R. § 23-1.5. But the New York Court of Appeals has
explained that “to state a claim under section 241(6), [a] plaintiff must allege that defendant
violated an Industrial Code regulation that sets forth a specific standard of conduct and [is] not
simply a recitation of common-law safety principles.” Toussaint v. Port Auth. of N.Y. & N.J.,
188 N.E.3d 571, 574 (N.Y. 2022); see also Ross v. Curtis-Palmer Hydro-Elec. Co., 618 N.E.2d
82, 87–88 (N.Y. 1993) (holding that a Section 241(6) violation cannot be premised on an
Industrial Code provision that contains “a reiteration of common-law standards”).
“[S]ubsections (a) and (b) of Industrial Code 23-1.5 are nothing more than general safety
provisions” and, therefore, “do not provide a basis for Plaintiff’s § 241(6) claim.” Csikos v. S.M.
Constr. & Contracting, Inc., No. 18-cv-9598, 2021 WL 5771921, at *5 (S.D.N.Y. Dec. 3, 2021)
(granting summary judgment in favor of defendant on NYLL § 241(6) claim). To the extent
subsection (c) contains sufficiently specific requirements, it is “inapplicable” because “it governs
the condition of equipment and safeguards,” yet Plaintiff does not allege that his injury occurred
because any safety equipment, or any of the materials in the box that fell on him, were in poor
condition. Csikos, 2021 WL 5771921, at *5
C. Plaintiff’s NYLL § 200 and Negligence Claims
NYLL Section 200 requires that: (i) all areas of a workplace “be so constructed,
equipped, arranged, operated and conducted as to provide reasonable and adequate protection to
the lives, health and safety of all persons employed therein or lawfully frequenting such places”;
and (ii) “[a]ll machinery, equipment, and devices in such places shall be so placed, operated,
guarded, and lighted as to provide reasonable and adequate protection to all such persons.”
NYLL § 200(1). The statute is a “codification of the common-law duty of property owners and
general contractors to provide workers with a safe place to work,” and “liability under the statute
is governed by common-law negligence principles.” Quishpe, 2023 WL 5625307, at *3.
Therefore, “[c]ourts generally analyze claims brought under both § 200 and the common law
simultaneously.” Buono, 2021 WL 51524, at *4.
“Cases involving Labor Law § 200 fall into two broad categories: namely, those where
workers are injured as a result of dangerous or defective premises conditions at a worksite, and
those involving the manner in which the work is performed.” Ortega v. Puccia, 866 N.Y.S.2d
323, 329 (2d Dep’t 2008). Plaintiff’s claim is based on the former theory because he contends
that his injury was caused by the cluttered conditions in the storage room. ECF No. 68-1 at 17–
21. “Where a premises condition is at issue, property owners may be held liable for a violation
of Labor Law § 200 if the owner either created the dangerous condition that caused the accident
or had actual or constructive notice of the dangerous condition that caused the accident.”
Ortega, 866 N.Y.S.2d at 329.
Plaintiff’s Section 200 claim fails because he cannot demonstrate that JPM caused or had
notice of the cluttered conditions. JPM may have assigned Unity the specific storage space
where Plaintiff’s injury occurred and approved orders of project materials, but Plaintiff testified
that Unity employees unloaded the boxes of materials and arranged them in the manner that
caused Plaintiff’s injury. Pls. Dep. at 27:13–24, 70:13–71:10. Although Unity had previously
asked JPM for additional storage space, Plaintiff conceded that neither he, nor anyone else he
knew of, raised any complaints with JPM about the storage space being too cluttered. Id. at
78:21–79:5, 85:5–12. Based on these events, JPM cannot be held responsible for the conditions
that caused Plaintiff’s injury because it did not “have actual or constructive notice of the
allegedly dangerous condition.” See Dwyer v. Goldman Sachs Headquarters LLC, 819 F. Supp.
2d 320, 330 (S.D.N.Y. 2011) (granting summary judgment in favor of building owner on
plaintiff’s Section 200 and common law negligence claims).
II. The Court Declines to Exercise Supplemental Jurisdiction Over the Third-
Party Claims
The Court has diversity jurisdiction over the claims in the first-party action but merely
supplemental jurisdiction over the claims in the third-party action. JPM removed Plaintiff’s
claims against it from state court based on diversity jurisdiction. ECF No. 1. The parties in the
first-party action have diverse citizenship because Plaintiff is a citizen of New York, and JPM, as
a national banking association, is a citizen only of Ohio since its articles of association designate
an office in Ohio as its main office. See OneWest Bank, N.A. v. Melina, 827 F.3d 214, 219 (2d
Cir. 2016) (holding that “a national bank is a citizen only of the state listed in its articles of
association as its main office”). JPM has invoked only supplemental jurisdiction over its claims
for indemnification against Jones Lang Lasalle and Unity. ECF No. 36 ¶ 9. Additionally, JPM’s
third-party complaint does not plead facts sufficient to invoke the Court’s diversity jurisdiction
over its third-party claims because several of the third-party defendants are limited liability
companies affiliated with Unity, and JPM has not pled the states of citizenship of their members.
Id. ¶¶ 3–8; see Platinum-Montaur Life Scis., LLC v. Navidea Biopharms., Inc., 943 F.3d 613, 615
(2d Cir. 2019) (holding that a limited liability company “takes the citizenship of all of its
members”). Neither Jones Lang Lasalle nor Unity have asserted in their answers to JPM’s third-
party complaint that diversity jurisdiction exists as a basis for exercising jurisdiction over their
counter-claims against JPM or their cross-claims against each other, and their answers do not
allege facts sufficient to invoke diversity jurisdiction. ECF Nos. 38, 45.
The Court could exercise supplemental jurisdiction over the claims in the third-party
action, and they were properly included in the case up until this point. Subject to certain
exceptions not applicable here, “in any civil action of which the district courts have original
jurisdiction, the district courts shall have supplemental jurisdiction over all other claims that are
so related to claims in the action within such original jurisdiction that they form part of the same
case or controversy under Article III of the United States Constitution.” 28 U.S.C. § 1367(a).
Since the third-party claims depend on an assessment of the events leading up to Plaintiff’s
injury, they satisfy this standard of relatedness. See Viacom Int’l, Inc. v. Kearny, 212 F.3d 721,
727–28 (2d Cir. 2000) (holding that district court had supplemental jurisdiction over third- and
fourth-party claims between non-diverse parties). The Court may, therefore, exercise
supplemental jurisdiction over the claims in the third-party action, so long as “the parties in the
first-party action[] are themselves diverse,” which they are for the reasons described above.
Genger v. Genger, 771 F. App’x 99, 100 (2d Cir. 2019).
But the Court is not required to exercise supplemental jurisdiction. A court “may decline
to exercise supplemental jurisdiction” under various different circumstances, including when it
“has dismissed all claims over which it has original jurisdiction.” 28 U.S.C. § 1367(c)(3).
Ordinarily, a court’s resolution of all the claims over which it has original jurisdiction before trial
“generally points to declining to exercise supplemental jurisdiction” over any remaining claims.
Catzin v. Thank You & Good Luck Corp., 899 F.3d 77, 86 (2d Cir. 2018). Applying that
principle favoring dismissal makes sense here. Since the Court has dismissed all of Plaintiff’s
claims against JPM, thereby eliminating JPM’s potential liability, there is little reason to exercise
supplemental jurisdiction over the indemnification claims in the third-party action. “Claims for
indemnification do not generally ripen until a judgment in the underlying action is paid.”
Cucchiara v. Hollingsworth, No. 15-cv-314, 2016 WL 6068193, at *8 (S.D.N.Y. Oct. 14, 2016)
(declining to exercise supplemental jurisdiction over defendant’s indemnification claim against
third party after granting summary judgment dismissing plaintiff’s claims); Choi v. Hoyt De
Leon Corp., No. 19-cv-4445, 2023 WL 5671993, at *6 (E.D.N.Y. Sept. 1, 2023) (reiterating
same ripeness principle and denying summary judgment on third-party indemnification claims).
The court therefore dismisses the third-party claims without prejudice because it declines to
exercise supplemental jurisdiction over them. Piotrowski v. Rocky Point Union Free Sch. Dist.,
No. 18-cv-6262, 2023 WL 2710341, at *14 (E.D.N.Y. Mar. 30, 2023) (declining to exercise
supplemental jurisdiction over indemnification claims between defendants after granting
summary judgment dismissing all of plaintiff’s claims).
CONCLUSION
For the reasons set forth above, the Court GRANTS in full JPM’s motion for summary
judgment against Plaintiff and dismisses all of Plaintiff’s claims against JPM with prejudice.
ECF No. 66. The Court declines to exercise supplemental jurisdiction over the indemnification
and contribution claims that JPM, Jones Lang Lasalle, and Unity have asserted against each other
in the third-party action and dismisses the claims in the third-party action without prejudice. The
Court therefore DENIES as moot JPM’s motion for summary judgment seeking indemnification
against Jones Lang Lasalle and Jones Lang Lasalle’s motion for summary judgment seeking to
dismiss on the merits JPM’s indemnification claims against it. ECF Nos. 64, 65. The Clerk of
Court is respectfully directed to enter judgment dismissing with prejudice Plaintiff’s claims
against JPM and dismissing without prejudice the claims asserted in the third-party action and to
close this case.
SO ORDERED.
/s/ Hector Gonzalez
HECTOR GONZALEZ
United States District Judge
Dated: Brooklyn, New York
December 27, 2023