Opinion

Skipton v. RevHoney, Inc.

Court
District Court, W.D. Missouri
Filed
May 6, 2021
Cited by
0 cases
Authority
More cited than 24.3%

held a contract for construction validly incorporated by reference general condition requiring arbitration of disputes

How later courts described this case

  • held a contract for construction validly incorporated by reference general condition requiring arbitration of disputes

Written by the judges who cited it.

The opinion

IN THE UNITED STATES DISTRICT COURT FOR THE

WESTERN DISTRICT OF MISSOURI

SOUTHERN DIVISION

DES DEVELOPMENT, LLC, )

)

Plaintiff, )

)

v. ) Case No. 6:19-cv-03379-MDH

)

REVHONEY, INC., )

)

Defendant. )

ORDER

Before the Court is Plaintiff DES Development, LLC’s (“DES”) Motion for Summary

Judgment (Doc. 89). For the reasons set for herein, the Motion is GRANTED IN PART AND

DENIED IN PART.

BACKGROUND

DES brought suit to enforce an Equipment Rental Agreement (“ERA”) against RevHoney,

Inc. (Doc. 73, 1). DES also claims that RevHoney and owners Jerry and Debra Brown breached

the November 2019 Mediated Settlement Agreement (“MSA”). Id.

1. Equipment Rental Agreement

In September 2018, DES entered into the ERA with RevHoney, through which it leased all

the equipment covered by DES’s leases with North Star Leasing Company to RevHoney for use

in its beverage manufacture, bottling, and distribution operations. Id. For the benefit of RevHoney,

DES entered into three leases for beverage production and bottling equipment. (Doc. 89 Ex. B-D).

On September 18, 2018, DES Development and RevHoney entered into the ERA. DES purchased

the equipment at issue in February 2020.

Pursuant to the ERA: “Rent and terms will be Passed through at DES Development LLC

cost from NorthStar[sic] Leasing.” (Doc. 82 Ex. A, at 1). The ERA further specifies “[i]tems will

be added during this lease agreement and again passed through at cost.” Id.

The September 13, 2018 North Star lease, which was incorporated into the ERA by

reference, specified the monthly rental payment for that equipment was $3,711.00 for a period of

fifty-eight (58) months. (Doc. 82 Ex. B, at 9). The October 11, 2018, North Star lease, which was

incorporated into the ERA by reference, specified the monthly rental payment for that equipment

was $2,440.00 for a period of forty-six (46) months. (Doc. 82 Ex. C, at 8). The December 21, 2018,

North Star lease, which was incorporated into the ERA by reference, specified the monthly rental

payment for that equipment was $1,639.00 for a period of fifty-eight (58) months. (Doc. 82 Ex. D,

at 9).

Once the Equipment Rental Agreement was executed, each month RevHoney consistently

sent DES Development a check for the payment due on the outstanding North Star leases. (Doc.

89 Ex. A). As the two subsequent North Star Leases were executed—in October 2019 and

December 2019, respectively—RevHoney increased its monthly payment accordingly to represent

the additional payment obligation. Id. RevHoney’s monthly obligation to DES for the sub-leased

production and bottling equipment was approximately $7,079.00. Without notice to DES,

RevHoney ceased making its contractually obligated monthly payments in June 2019. (Doc. 89

Ex. F). According to DES, RevHoney rectified its payment delinquency in November 2019 but

otherwise RevHoney has made no payments since. (Doc. 89 Ex. E).

2. Mediated Settlement Agreement

In November 2019, DES demanded payment of $55,000.00 from RevHoney for unpaid

lease payments and attorney’s fees. RevHoney ultimately did deliver a $55,000.00 check to DES,

but before the Mediated Settlement Agreement (“MSA”). (Doc. 89 Ex. E). In November 12, 2019,

the parties held an in-person, informal mediation in Springfield, Missouri and reached the

resolution described in the Mediated Settlement Agreement dated November 12, 2019. (Doc. 89

Ex. J).

On June 2, 2020, this Court granted RevHoney’s Motion to Enforce Settlement Agreement

and held that the portion of the parties’ MSA relating to the production and bottling equipment—

the subject of the ERA—to be enforceable. (Doc. 49). As it relates to the ERA, the MSA contains

the following terms:

1. CONSIDERATION; As full consideration for the Parties’ agreements and the releases,

the Parties agree as follows.

a. Equipment Rental Agreement:

i. The Equipment Rental Agreement dated September 18, 2018 shall be

amended to include a purchase option by RevHoney for $1.00 at the end

of the rental term as contemplated by the North Star Leasing lease

agreements;

ii. The parties shall cooperate to facilitate future rental payments being

funded direct to North Star from RevHoney, Inc.’s business bank account,

subject to approval by North Star;

ili. Debra and Jerry Brown shall execute personal guaranties for the

indebtedness contemplated in the Equipment Rental Agreement;

iv. Pending negotiation of the check received from RevHoney on November

11, 2019, the lawsuit styled Skipton et al v. RevHoney, Inc. in the Western

District of Missouri shall be dismissed with prejudice.

v. For clarity, North Star retains ownership of the Equipment

There is no dispute that the ERA has not been amended as required by the MSA, despite at

least two attempts by DES. (See Doc. 89 Ex. T, U, W, X). RevHoney apparently intends to only

amend the ERA in a way that would give it the right to immediately purchase all leased equipment

for the $1.00 purchase option noted in the MSA, expressly rejecting the rental terms contemplated

in the North Star leases. (See Doc. 94, 40-41). It is also not disputed that the Browns have not

executed the personal guarantees required by the MSA.

STANDARD

Summary judgment is proper where, viewing the evidence in the light most favorable to

the non-moving party, there are no genuine issues of material fact and the moving party is entitled

to judgment as a matter of law. Fed. R. Civ. P. 56(a); Reich v. ConAgra, Inc., 987 F.2d 1357, 1359

(8th Cir. 1993). “Where there is no dispute of material fact and reasonable fact finders could not

find in favor of the nonmoving party, summary judgment is appropriate.” Quinn v. St. Louis

County, 653 F.3d 745, 750 (8th Cir. 2011). Initially, the moving party bears the burden of

demonstrating the absence of a genuine issue of material fact. Celotex Corp. v. Catrett, 477 U.S.

317, 323 (1986). If the movant meets the initial step, the burden shifts to the nonmoving party to

“set forth specific facts showing that there is a genuine issue for trial.” Anderson v. Liberty Lobby,

Inc., 477 U.S. 242, 248 (1986). To satisfy this burden, the nonmoving party must “do more than

simply show there is some metaphysical doubt as to the material facts.” Matsushita Elec. Indus.

Co. v. Zenith Radio Corp., 475 U.S. 574, 586 (1986).

A question of material fact is not required to be resolved conclusively in favor of the party

asserting its existence. Rather, all that is required is sufficient evidence supporting the factual

dispute that would require a jury to resolve the differing versions of truth at trial. Anderson v.

Liberty Lobby, Inc., 477 U.S. at 248-249. Further, determinations of credibility and the weight to

give evidence are the functions of the jury, not the judge. Wierman v. Casey’s General Stores, et

al., 638 F.3d 984, 993 (8th Cir. 2011).

DISCUSSION

1. Equipment Rental Agreement

RevHoney argues that the ERA was not a “formal” agreement (Doc. 94, beginning at 38),

and further argues that its intent was simply to reimburse DES for its payments to North Star. Id.

at 39. However, despite the repeated language that the ERA was not a “formal” agreement, at no

point does RevHoney argue that the ERA is unenforceable, void, or voidable. Therefore, because

the argument is waived, the Court concludes that the ERA is a binding contract.

DES argues that the North Star leases are incorporated into the ERA. Contract

interpretation is a question of law for the Court to decide. WireCo WorldGroup, Inc. v. Liberty

Mut. Fire Ins. Co., 231 F. Supp. 3d 313, 320 (W.D. Mo. 2017), aff’d on other grounds, 897 F.3d

987 (8th Cir. 2018) (citing Barkley, Inc. v. Gabriel Bros., 829 F.3d 1030, 1038 (8th Cir. 2016)). In

guiding that decision, it is well established that “[i]t is possible for a contract to incorporate the

terms of a separate ... document by reference.” Liberty Mut. Fire Ins. Co. v. Centimark Corp., No.

4:08-CV-230-DJS, 2009 WL 1588454 at *3 (E.D. Mo. June 5, 2009); see also State ex rel. Hewitt

v. Kerr, 461 S.W.3d 798, 810–11 (Mo. 2015).

In Missouri, “matters incorporated into a contract by reference are as much a part of the

contract as if they had been set out in the contract in haec verba.” Metro Demolition & Excavating

Co. v. H.B.D. Contracting, Inc., 37 S.W.3d 843, 846 (Mo. Ct. App. 2001) (citing Trantham v. Old

Republic Ins. Co., 797 S.W.2d 771, 774 (Mo. App. E.D. 1990); Jim Carlson Const., Inc. v. Bailey,

769 S.W.2d 480 (Mo. App. W.D. 1989) (held a contract for construction validly incorporated by

reference general condition requiring arbitration of disputes)).

To incorporate terms into a contract by reference under Missouri law, “the intent to

incorporate must be clear, and the contract must make [ ] clear reference to the document and

describe [ ] it in such terms that its identity may be ascertained beyond a doubt.” See Hardwood

Lumber, Inc. v. Brewco Inc., No. 3:18-05088-CV-RK, 2019 WL 1672295, at *3 (W.D. Mo. Apr.

17, 2019) (quoting Morgantown Mach. & Hydraulics of Ohio, Inc. v. Am. Piping Products, Inc.,

887 F.3d 413, 415 (8th Cir. 2018)). “[M]atters incorporated into a contract by reference are as

much a part of the contract as if they had been set out in the contract in haec verba.” 5 Am. Piping

Products, Inc., 887 F.3d at 415—16 (internal citations and quotations omitted). Further, “[t]here is

no requirement that an incorporated document be attached to the contract or provided to the parties

prior to the execution of the contract.” State ex rel. Pinkerton v. Fahnestock, 531 S.W. 3d 36, 15

(Mo. banc 2017).

DES contends that the North Star leases have been incorporated into the ERA. Specifically,

the ERA states:

Rental Rate:

Rent and terms will be Passed through at DES Development LLC cost from NorthStar Leasing. Items will be

added during this lease agreement and again passed through at cost.

Here, there were three leases entered into between DES and North Star Leasing. (Doc. 89 Ex. E).

There is little argument as to which leases and which terms the ERA was referring to. RevHoney’s

directors, Jerry and Debra Brown, executed personal guarantees for two of the three leases, so

RevHoney had actual knowledge of the North Star leases, the monthly rents owed, and the terms

of the same. Similarly, RevHoney executed a corporate guarantee for the liabilities contemplated

by the December 21, 2018 North Star lease. (Doc. 89 Ex. D). RevHoney does not dispute that the

North Star leases were incorporated into the ERA.

RevHoney’s principle argument is that once DES purchased the equipment in February

2020, RevHoney no longer had any obligation to make lease payments. Specifically, RevHoney

believes that once there was no longer a pass-through lease, the ERA did not apply. (See Doc. 94,

generally). The Court finds no merit in that argument. As noted above, the rental terms were

clearly laid out in the North Star leases. The September 13, 2018 North Star lease which was

incorporated into the ERA by reference specified the monthly rental payment on for the that

equipment was $3,711.00 for a period of fifty-eight (58) months. (Doc. 89 Ex. B, at 9). The October

11, 2018, North Star lease which was incorporated into the Equipment Rental Agreement by

reference specified the monthly rental payment on for that equipment was $2,440.00 for a period

of forty-six (46) months. (Doc. 82 Ex. C, at 8). The December 21, 2018, North Star lease which

was incorporated into the Equipment Rental Agreement by reference specified the monthly rental

payment on for the that equipment was $1,639.00 for a period of fifty-eight (58) months. (Doc. 82

Ex. D, at 9).

There is no authority to support the contention that once DES purchased the equipment the

North Star lease terms became inactive. Both DES and RevHoney were parties to the North Star

lease, and DES is entitled to act as the sole lessor particularly in light of the personal and corporate

guarantees provided in the original leases. In the ERA itself, DES is already defined as “OWNER”

as the term is used throughout the document. (Doc. 89 Ex. A).

Furthermore, “[w]hen interpreting contracts, [courts attempt] to avoid absurd results.” TNT

Amusements, Inc. v. BFC Enterprises, Inc., No. ED-108209, 2020 WL 2529525, at *5 (Mo. App.

E.D. 2020) (mem. op.) (quoting Guller v. Waks, 550 S.W.3d 505, 510 (Mo. App. E.D. 2017)).

“[Courts] interpret contracts to reach fair, reasonable, and practical results, for it is to be presumed

that the parties contracted to that end.” See TNT Amusements, Inc., 2020 WL 2529525, at *5

(quoting Patterson v. Rough Road Rescue, Inc., 529 S.W.3d 887, 894 (Mo. App. E.D. 2017)).

Courts will reject interpretation of a contract that yields unreasonable results when a probable and

reasonable construction can be adopted. See id.; Belton Chopper 58, LLC v. North Cass Dev., LLC,

496 S.W.3d 529, 532 (Mo. App. W.D. 2016). To allow RevHoney to maintain the equipment that

it has not fully paid for under the terms provided by the North Star leases and incorporated into

the ERA would yield an absurd result, which the Court seeks to avoid.

It is undisputed that RevHoney has not paid the entirety of its obligation for the leases of

the equipment. RevHoney ultimately made payments through at least November 2019 (about

twelve months in rent) but has not made all payments which are due under the leases.1 Accordingly,

RevHoney is in breach of the ERA, and the damages are calculated below.

2. Mediated Settlement Agreement

RevHoney argues that DES was the first party to breach the MSA because this suit

allegedly should have been dismissed pending the negotiation of the $55,000.00 paid to DES by

RevHoney, which is reflected by element (iv) of the MSA as shown above. However, this was just

one requirement of the MSA and the other elements remain unmet. Further, the payment was made

before the MSA was actually executed. (Doc. 89 ¶ 10). This $55,000.00 was tendered as

consideration for Plaintiff passing the then-scheduled hearing on its requested temporary

restraining order. See id. ¶¶ 8–10. The general rule is that past or moral consideration is not

sufficient to support a promise. See Garrett v. American Family Mutual Ins. Co., 520 S.W.2d 102,

111, n. 2 (Mo. App. 1975). Therefore, contrary to Defendants’ repeated assertion, the $55,000.00

check from November 2019 is not legally competent consideration to support the MSA.

Regardless, the obligation of DES to dismiss the litigation is found to be dependent upon

1 It is disputed whether any further rent payments have been made.

RevHoney’s and the Browns’ compliance with the terms of the Mediated Settlement Agreement.

If they had done so, DES might well have been obligated to dismiss this action.

a. RevHoney

RevHoney was required to, with DES, amend the ERA to include a purchase option of

$1.00 at the end of the rental term as contemplated by the North Star lease agreements. It is

undisputed that the ERA has not been amended. RevHoney has refused to agree to any amendment

that does not allow them to immediately exercise the $1.00 purchase option, based on its invalid

assertion that the rental term ended once DES purchased the equipment. (See Doc. 94, 40). While

under the mediation agreement RevHoney is entitled to buy the equipment subject to the lease for

the sum of $1.00, that buyout right vests only when all lease payments have been made. The rental

terms, as discussed above, are dictated by the North Star leases, and RevHoney cannot exercise a

purchase option until those terms of length have expired. Therefore, RevHoney has breached the

MSA.

b. Jerry Brown and Debra Brown

Jerry and Debra Brown were required under the MSA to execute personal guarantees for

indebtedness as contemplated by the ERA. There is no dispute that they have failed to do so.

Defendants’ only stated reason for breaching the MSA by not executing personal guaranties is

their unsupported belief there are “no lease agreements” so there was nothing for them to

guarantee. (Doc. No. 94 § IV(C)(3)). As discussed above, there are valid lease agreements and a

valid settlement agreement. The Browns breached the terms of the MSA. Their breach of the MSA

makes them liable for any amounts RevHoney is ultimately found due to DES for the breach of

the ERA.

3. Damages

Upon finding RevHoney to be in breach of the ERA, the Court concludes that the

appropriate amount of damages owed by RevHoney is equal to the remaining lease payments for

the entirety of the three North Star leases as was contemplated by the pass-through lease agreement

in the ERA. DES alleges that RevHoney still owes 45 payments of $3,711.00 on the September

North Star Leasing Co. Lease, or $166,995.00; 34 payments of $2,440.00 on the October 2018

North Star Leasing Co. Lease, or $82,960.00; 47 payments of $1,639.00 on the December 2018

North Star Leasing Co. Lease, or $77,033.00. In total, DES asserts that RevHoney owes

$326,988.00 in contractually obligated payments under the ERA. RevHoney asserts that it has

made approximately $30,000 more in payments to DES than DES gives it credit for in its request

for damages.

The Court agrees that RevHoney owes DES all payments that were due under the original

ERA if the leases between DES and North Star, which were incorporated into the ERA, had gone

to full term. However, the total amount of payments RevHoney has made to DES to date is

disputed. DES claims that RevHoney has paid $84,948.00 under the ERA whereas RevHoney

claims it has paid $115,770.01. The facts and materials provided by the parties in their briefings

on this Motion are inadequate to resolve this genuine dispute of material fact. The sole issue

remaining for trial is the issue of what sums paid by RevHoney should be credited to the amount

it owes DES against the lease obligation under the ERA if the parties cannot resolve this issue

themselves.

4. Attorney’s Fees

According to their terms, both the Equipment Rental Agreement and the MSA provide that

a prevailing party is entitled to recover its reasonable attorneys’ fees, costs, and expenses. If a

contract provides for the payment of attorney’s fees and expenses incurred in the enforcement of

a contract provision, the trial court must comply with the terms of the contract and award them to

the prevailing party. Clean Unif. Co. St. Louis v. Magic Touch Cleaning, Inc., 300 S.W.3d 602,

612 (Mo. Ct. App. 2009) (citing Sheppard v. East, 192 S.W.3d 518, 523 (Mo. App. 2006)).

Appellate courts consider the trial court to be an expert on the amount of attorney’s fees to be

awarded. Magic Touch Cleaning, Inc., 300 S.W.3d at 612. The court that ‘tries a case and is

acquainted with all the issues involved may fix the amount of attorneys’ fees without the aid of

evidence. See id. (citing Nelson v. Hotchkiss, 601 S.W.2d 14, 21 (Mo. banc 1980)) (internal

quotations removed). The determination of the amount of attorney’s fees is within the sound

discretion of the trial court, and we will not reverse unless the award is arbitrarily arrived at or is

so unreasonable that it indicates indifference and a lack of proper judicial discrimination. Magic

Touch Cleaning, Inc., 300 S.W.3d at 612.

The September 18, 2018, Equipment Rental Agreement specifically provides that

RevHoney, the “Renter,” shall pay:

[A]ll reasonable attorney and other fees, the expenses and costs incurred by [DES]

in protection [of] its rights under this [Equipment Rental Agreement] and for any

action taken [by DES] to collect any amounts due [DES] under this [Equipment

Rental Agreement].

(Doc. 89 Ex. A)

Similarly, the MSA contains an express provision entitling DES to recover its attorneys’

fees in this case. (Doc. 89 Ex. J) Specifically, the MSA provides that:

In the event that any action or proceeding is brought to interpret or enforce any of

the terms and conditions of this Agreement, the prevailing Party shall be entitled to

have and recover from the other Party all costs and reasonable attorneys’ fees

incurred in connection therewith.

The Court finds that DES is entitled to recover attorney’s fees, the amount of which will be

determined at the end of litigation in this case.

CONCLUSION

Wherefore, for the reasons stated herein, the Court GRANTS IN PART AND DENIES

IN PART Plaintiff’s Motion for Summary Judgment (Doc. 89). Summary judgment is granted

against RevHoney, Inc. for breach of contract under the Equipment Rental Agreement. Summary

judgment is granted against RevHoney, Inc. for breach of the Mediated Settlement Agreement.

Summary judgment is granted against Jerry Brown and Debra Brown for their failure to execute

personal guarantees in breach of the Mediated Settlement Agreement. The sole issue remaining

for trial is the issue of what sums paid by RevHoney, Inc. should be credited to the amount it owes

DES against the lease obligation under the Equipment Rental Agreement. The case remains

scheduled for jury trial on the remaining issue of the amount of payments previously made by

RevHoney, Inc. that should be credited toward the total lease payments due.

IT IS SO ORDERED.

Dated: May 6, 2021 /s/ Douglas Harpool______

DOUGLAS HARPOOL

United States District Judge

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.