transferring case where only party that satisfied venue failed to provide evidence establishing standing
How later courts described this case
- transferring case where only party that satisfied venue failed to provide evidence establishing standing
- rejecting standing argument where court found plaintiffs brought the action “based on costs they incurred in response to a speculative threat”
- “Having found that the Institute lacks standing to bring this action and has failed to state a claim upon which relief can be granted, plaintiff cannot manufacture venue by adding the Institute as a party.”
- finding no “injury in fact” where Plaintiffs’ alleged harms “rel[y] on a highly attenuated chain of possibilities”
Written by the judges who cited it.
The opinion
UNITED STATES DISTRICT COURT
WESTERN DISTRICT OF LOUISIANA
LAFAYETTE DIVISION
ASSOCIATED GENERAL CIVIL DOCKET NO. 6:24-cv-00037
CONTRACTORS OF AMERICA, INC.,
ET AL
VERSUS JUDGE DAVID C. JOSEPH
FEDERAL ACQUISITION MAGISTRATE JUDGE DAVID J.
REGULATORY COUNCIL, ET AL AYO
MEMORANDUM RULING
Before the Court is the RENEWED CIVIL RULE 12 MOTION (the “Motion”) [Doc.
33] filed by Defendants, in which Defendants challenge the standing of the Plaintiffs
under Article III and seek to transfer this matter on the grounds of improper venue.1
The Motion is opposed by the Plaintiffs.2 [Doc. 35]. For the following reasons,
1 The Defendants in the instant lawsuit are: Joseph R. Biden, Jr. (“President Biden”),
in his official capacity as President of the United States; the Federal Acquisition Regulatory
Council (the “FAR Council”); the four federal agencies that are members of the FAR Council,
including the Office of Federal Procurement Policy (“OFPP”), the Department of Defense
(“DOD”), the General Services Administration (“GSA”), and the National Aeronautics &
Space Administration (“NASA”), as well as the officials appointed to head those agencies,
including Christine J. Harada in her official capacity as FAR Council Chair & Senior Advisor
to Deputy Director for Management, OFPP; Jeffrey A. Koses, in his official capacity as
Administrator of GSA; John Tenaglia, in his official capacity as Principal Director Defense
Pricing & Contracting Office of Secretary of Defense; and Karla S. Jackson, Senior
Procurement Executive, Deputy Chief Acquisition Officer, and Assistant Administrator for
the Office of Procurement at NASA.
2 Plaintiffs in this matter are Associated General Contractors of America, Inc. (“AGC of
America”) and Louisiana Associated General Contractors, Inc. (“Louisiana AGC”)
(hereinafter, the “Association Plaintiffs”), as well as Boggs & Poole Contracting Group, Inc.;
Don M. Barron Contractor, Inc.; J.B. Mouton, LLC; Lincoln Builders, Inc.; Progressive
Construction Company, LLC; Bulliard Construction Company, Inc.; Rigid Constructors, LLC;
and Pat Williams Construction, LLC (hereinafter, collectively, the “Individual Plaintiffs”).
Defendants’ Motion is GRANTED IN PART, and this matter will be TRANSFERRED
to a district of proper venue.
FACTUAL BACKGROUND AND PROCEDURAL HISTORY
The instant lawsuit arises out of the issuance of a Presidential Executive Order
favoring Project Labor Agreements (“PLAs”) in the procurement of certain federal
construction projects. A PLA is a multi-employer, multi-union pre-hire agreement
designed to systemize labor relations at a construction site. It typically requires that
all contractors and subcontractors who will work on a project subscribe to the
agreement; that all contractors and subcontractors agree in advance to abide by a
master collective bargaining agreement for all work on the project; and that wages,
hours, and other terms of employment be coordinated or standardized pursuant to
the PLA across the many different unions and companies working on the project. The
implementation of a PLA on a project underwritten by the Government almost always
is accomplished by making agreement to the PLA a bid specification, thereby allowing
the contracting authority to ensure that firms at every level — from the general
contractor to the lowest level of subcontractor — comply with the terms of the PLA.
See generally Bldg. & Const. Trades Dep't, AFL-CIO v. Allbaugh, 295 F.3d 28, 30
(D.C. Cir. 2002).
On February 4, 2022, President Biden issued Executive Order 14,063 (“EO
14,063”), which creates a rebuttable presumption in favor of PLAs on all government
construction projects with a total estimated construction cost of $35 million or more.
See Exec. Order No. 14,063, Use of Project Labor Agreements for Federal Construction
Projects, 87 Fed. Reg. 7363 (Feb. 4, 2022). Under EO 14,063, unless an exception is
granted, contractors bidding for work on federal constructions projects with an
estimated construction cost of $35 million or more will be required to: (i) bind all
contractors and subcontractors on the construction project through the inclusion of
appropriate specifications in all relevant solicitation provisions and contract
documents; (ii) allow all contractors and subcontractors on the construction project to
compete for contracts and subcontracts without regard to whether they are otherwise
parties to collective bargaining agreements; (iii) contain guarantees against strikes,
lockouts, and similar job disruptions; (iv) set forth effective, prompt, and mutually
binding procedures for resolving labor disputes arising during the term of the project
labor agreement; (v) provide other mechanisms for labor-management cooperation on
matters of mutual interest and concern, including productivity, quality of work,
safety, and health; and (vi) fully conform to all statutes, regulations, Executive
Orders, and Presidential Memoranda. EO No. 14,063, 87 FR 7363.
The presumption in favor of requiring a PLA can be rebutted if a senior agency
official determines that a PLA requirement “would not advance the Federal
Government’s interests in achieving economy and efficiency in Federal procurement;”
“would substantially reduce the number of potential bidders so as to frustrate full
and open competition;” or would otherwise be inconsistent with law. Id. A
determination that requiring a PLA would not advance economy and efficiency must
be based on one of the following factors: (i) the project “is of short duration and lacks
operational complexity;” (ii) “will involve only one craft or trade;” (iii) “will involve
specialized construction work that is available from only a limited number of
contractors or subcontractors;” or (iv) addresses an agency need “of such an unusual
and compelling urgency that a project labor agreement would be impracticable.” Id.
The FAR Council assists in the direction and coordination of Government-wide
procurement policy and Government-wide procurement regulatory activities within
the federal government. At President Biden’s direction, the agencies that make up
the FAR Council—GSA, DOD, and NASA—proposed amendments to the Federal
Acquisition Regulation (“FAR”) to implement EO 14,063. See DOD, GSA, NASA,
Federal Acquisition Regulation: Use of Project Labor Agreements for Federal
Construction Projects, 87 Fed. Reg. 51,044 (Aug. 19, 2022). The FAR Council agencies
promulgated a final rule in December 2023 after reviewing over 8,000 public
comments, 88 Fed. Reg. 88,708, 88,709 (Dec. 22, 2023) (the “Final Rule”),3 and the
Final Rule took effect on January 22, 2024. Id. at 88,708. The Final Rule, together
with EO 14,063, constitute the PLA Rule.
On January 10, 2024, the Association Plaintiffs—a nationwide organization of
contractors and its regional affiliate in Louisiana—filed this action against President
Biden, the FAR Council, the Office of Federal Procurement Policy and its acting
Administrator, GSA, DOD, NASA, and the FAR Council members from each agency.
See Complaint, [Doc. 1]. In the original Complaint, the Association Plaintiffs allege
that the PLA Rule exceeds the scope of the President’s statutory and constitutional
3 Additionally, on December 18, 2023, the Office of Management and Budget (“OMB”)
issued Memorandum M-24-06, Use of Project Labor Agreements on Federal Construction
Budgets, which provides guidance and other information to federal agencies and the
contracting workforce responsible for executing large-scale federal construction projects.
authority and is contrary to law, in violation of 5 U.S.C. § 706(2)(A). [Id. at ¶¶ 128-
144]. On the same day, the Association Plaintiffs filed a Motion for Preliminary
Injunction pursuant to FRCP 65(a) and for a stay of agency action pursuant to 5
U.S.C. § 705. [Doc. 2]. Following a status conference with counsel, the Court set
briefing deadlines on the Motion for Preliminary Injunction and a trial date of March
19, 2024. [Doc. 18].
On February 9, 2024, Defendants filed a Motion to Transfer Case and Motion
to Dismiss for Lack of Jurisdiction. [Doc. 19]. In their Motion, Defendants argued
that the Association Plaintiffs lack standing to bring the instant lawsuit and that
venue is improper in this district. Rather than oppose Defendants’ Motion to Transfer
and Dismiss, the Association Plaintiffs amended their Complaint on February 23,
2024 [Doc. 27] to add eight individual construction company plaintiffs (the
“Individual Plaintiffs”),4 arguing that each one has a principal place of business in
cities within the Western District of Louisiana, thereby curing any potential defects
with respect to venue. Recognizing that the addition of the Individual Plaintiffs
would impact the Defendants’ arguments concerning venue and standing in their
pending Motion, the Court denied Defendants’ Motion to Transfer and Motion to
Dismiss as moot and allowed Defendants to re-file their Rule 12 motion in light of the
4 The following Individual Plaintiffs were added: Boggs & Poole Contracting Group, Inc.
of Bossier City; Don M. Barron Contractor, Inc. of Farmerville; J.B. Moulton, LLC of
Lafayette; Lincoln Builders, Inc. of Ruston; Progressive Construction Co., LLC of Boyce;
Bulliard Construction Co., Inc. of St. Martinville; Rigid Constructors, LLC of Lafayette; and
Pat Williams Construction, Inc. of Lake Charles.
Amended Complaint. [Doc. 28]. On February 28, 2024, Defendants filed the instant
motion [Doc. 33]; Plaintiffs opposed the Motion on March 4, 2024 [Doc. 35].5
Thus, all issues before the Court, including venue, standing, and injunctive
relief, have been fully briefed, and the issues are now ripe for review.
LEGAL STANDARDS
I. Standing
“A preliminary injunction is an extraordinary and drastic remedy” that is
“never awarded as of right.” Munaf v. Geren, 553 U.S. 674, 689–90, 128 S. Ct. 2207,
171 L.Ed.2d 1 (2008) (citation omitted).6 Nor can a preliminary injunction properly
be requested by a plaintiff who lacks standing to sue. Speech First, Inc. v. Fenves,
979 F.3d 319, 329 (5th Cir. 2020), citing Lujan, 504 U.S. at 561. Article III of the
Constitution limits federal courts’ jurisdiction to certain “Cases” and “Controversies.”
Clapper v. Amnesty Int'l USA, 568 U.S. 398, 408, 133 S. Ct. 1138, 1146, 185 L.Ed.2d
264 (2013). The Supreme Court has explained that “[n]o principle is more
fundamental to the judiciary’s proper role in our system of government than the
5 All briefing on the Motion for Preliminary Injunction and Motion to Stay [Doc. 2] has
been completed as well. Defendants filed an opposition to the Plaintiffs’ Motion for
Preliminary Injunction and Motion to Stay [Doc. 25]; Plaintiffs filed a Reply Brief [Doc. 32];
and Defendants filed a Sur-Reply Brief on March 7, 2024 [Doc. 38].
6 To demonstrate eligibility for such relief, a plaintiff must clearly show: (1) “a
substantial threat of irreparable injury,” (2) “a substantial likelihood of success on the
merits,” (3) “that the threatened injury if the injunction is denied outweighs any harm that
will result if the injunction is granted,” and (4) “that the grant of an injunction will not
disserve the public interest.” Lujan v. Defs. of Wildlife, 504 U.S. 555, 560, 112 S. Ct. 2130,
2136, 119 L.Ed.2d 351 (1992); Jordan v. Fisher, 823 F.3d 805, 809 (5th Cir. 2016) (citation
omitted). Whether to grant preliminary injunctive relief is committed to the district court’s
sound discretion. Miss. Power & Light Co. v. United Gas Pipe Line, 760 F.2d 618, 621 (5th
Cir. 1985).
constitutional limitation of federal-court jurisdiction to actual cases or controversies.”
DaimlerChrysler Corp. v. Cuno, 547 U.S. 332, 341, 126 S. Ct. 1854, 164 L.Ed.2d 589
(2006) (internal quotation marks omitted); Raines v. Byrd, 521 U.S. 811, 818, 117 S.
Ct. 2312, 138 L.Ed.2d 849 (1997) (internal quotation marks omitted); see, e.g.,
Summers v. Earth Island Institute, 555 U.S. 488, 492–93, 129 S. Ct. 1142, 173 L.Ed.2d
1 (2009). “One element of the case-or-controversy requirement” is that plaintiffs
“must establish that they have standing to sue.” Lujan, 504 U.S. at 560.
To establish Article III standing, an injury must be “concrete, particularized,
and actual or imminent; fairly traceable to the challenged action; and redressable by
a favorable ruling.” Clapper, 568 U.S. at 409, citing Monsanto Co. v. Geertson Seed
Farms, 561 U.S. 139, 149, 130 S. Ct. 2743, 2752, 177 L.Ed.2d 461 (2010). See also
Louisiana v. Biden, 575 F. Supp. 3d 680, 689 (W.D. La. Dec. 16, 2021) (Drell, J), aff'd,
55 F.4th 1017 (5th Cir. 2022). It is well-established that a court’s standing review is
“especially rigorous when reaching the merits of the dispute would force us to decide
whether an action taken by one of the other two branches of the Federal Government
was unconstitutional,” as Plaintiffs request here. Clapper, 568 U.S. at 408, citing
Raines, supra, at 819–820, 117 S. Ct. 2312. See also Louisiana by & through Landry
v. Biden, 64 F.4th 674, 680 (5th Cir. 2023); Valley Forge Christian College v.
Americans United for Separation of Church and State, Inc., 454 U.S. 464, 473–74, 102
S. Ct. 752, 70 L.Ed.2d 700 (1982); Schlesinger v. Reservists Comm. to Stop the War,
418 U.S. 208, 221–22, 94 S. Ct. 2925, 41 L.Ed.2d 706 (1974). Indeed, “[r]elaxation of
standing requirements is directly related to the expansion of judicial power.”
Clapper, 568 U.S. at 408-09. See also United States v. Richardson, 418 U.S. 166, 188,
94 S. Ct. 2940, 41 L.Ed.2d 678 (1974) (Powell, J., concurring). Whether a plaintiff
has standing is determined at the time of filing, Lujan, 504 U.S. at 570 n.5, (noting
that “standing is to be determined as of the commencement of suit”), and the party
invoking federal jurisdiction bears the burden to show standing. Lujan, 504 U.S. at
561.
Because Defendants challenge the standing of all Plaintiffs under Rule
12(b)(1), and because they have submitted materials outside the pleadings, they have
asserted a factual attack on the subject matter jurisdiction of the court. Paterson v.
Weinberger, 644 F.2d 521, 523 (5th Cir. 1981). Under these circumstances, the
Plaintiffs are required to submit facts through some evidentiary method, and they
have the burden of proving by a preponderance of the evidence that the trial court
has subject matter jurisdiction. Id. at 523. The “court is free to weigh the evidence
and satisfy itself as to the existence of its power to hear the case.” Williamson v.
Tucker, 645 F.2d 404, 413 (5th Cir. May 1981). “[N]o presumptive truthfulness
attaches to plaintiff’s allegations, and the existence of disputed material facts will not
preclude the trial court from evaluating for itself the merits of jurisdictional claims.”
Williamson, 645 F.2d at 413.
A. Imminent Injury
Plaintiffs allege, generally, that they and their members, all contractors, face
certain and imminent injury from the PLA Rule in multiple ways. In being forced to
make what they deem a Hobson’s choice, the Plaintiffs argue that they will either
walk away from large-scale federal projects because of the requirement to use a PLA,
or they will continue to bid on federal contracts to their detriment. Under either
scenario, Plaintiffs allege they will incur increased costs and lower profit margins
because of the requirement to use a PLA. Specifically, the Plaintiffs allege that the
PLA Rule poses imminent harm because it causes business uncertainty and an
inability to plan for future projects; will change their business models; and will cause
them to expend resources on PLA-related actions which, but for the PLA Rule, they
would not need to expend. Plaintiffs allege that for those contractors who decide to
abandon the federal market, they will incur additional cost related to developing bids
in the private and local sectors in order to continue to provide their employees with
steady employment. If they decide to continue competing for large scale federal
contracts, they allege they will incur additional compliance costs stemming from the
collective bargaining agreements required by the PLA Rule.
“Although imminence is concededly a somewhat elastic concept, it cannot be
stretched beyond its purpose, which is to ensure that the alleged injury is not too
speculative for Article III purposes—that the injury is certainly impending.” Lujan,
504 U.S. at 565, n.2 (internal quotation marks omitted). Accordingly, “threatened
injury must be certainly impending to constitute injury in fact,” and “[a]llegations of
possible future injury” are not sufficient. Clapper, 568 U.S. at 1147. See also
Whitmore v. Arkansas, 495 U.S. 149, 158, 110 S. Ct. 1717, 109 L.Ed.2d 135 (1990);
Friends of the Earth, Inc. v. Laidlaw Environmental Services (TOC), Inc., 528 U.S.
167, 190, 120 S. Ct. 693, 145 L.Ed.2d 610 (2000); Babbitt v. Farm Workers, 442 U.S.
289, 298, 99 S. Ct. 2301, 60 L.Ed.2d 895 (1979). Mere probability of a disfavored
outcome does not suffice to create a legally cognizable injury. Ctr. for Biological
Diversity v. EPA, 937 F.3d 533, 538–39 (5th Cir. 2019). See Texas v. United States,
787 F.3d 733, 747–48 (5th Cir. 2015), citing Clapper, 568 U.S. at 409. See also US
Inventor Inc. v. Vidal, 2022 WL 4595001, at *3 (5th Cir. Sept. 30, 2022) (unpublished)
(the injury itself must be certainly impending, not speculative).
To support their arguments of imminent harm to all Plaintiffs, the eight
Individual Plaintiffs, added as parties after venue was challenged, filed largely
identical declarations explaining the impact of the PLA Rule on their construction
companies. With one exception, each declarant states that his company has
experience performing federal work funded 100 percent by federal dollars and
requiring compliance with the FAR; that part of the business plan of his company is
to continue bidding on and performing federal construction projects; and that his
company is not now and never has been a union contractor.7 Each declarant also
avers the following:
I am aware that certain federal projects are already being discussed for
possible bidding, indicating they will be let in accordance with the PLA
Rule. [Contractor] has no intention of bidding any new federal work that
would require our company to sign a Project Labor Agreement. We
prefer, and our subcontractors historically prefer, to be open shop.8
7 See Barron Decl., [Doc. 32-1]; Billeaud Decl., [Doc. 32-2]; Boggs Decl., [Doc. 32-3];
Bulliard Decl., [Doc. 32-4]; Cavys Decl., [Doc. 32-5]; Comeaux Decl., [Doc. 32-6]; Graham
Decl., [Doc. 32-7] Urbina Decl., [Doc. 32-8].
8 This language appears in Paragraph 9 of each of the Declarations.
Despite stating that there are current federal projects being discussed for
bidding, none of the Individual Plaintiffs specify what those projects are, where the
projects would take place, or the basis for their certainty that such projects will
require a PLA. Furthermore, the Individual Plaintiffs’ declarations are belied by
their histories of actual federal contracting practices. To support their argument that
it is unlikely the PLA Rule poses imminent harm to any of the Plaintiffs—but
particularly to the Individual Plaintiffs—Defendants proffered records kept by the
Federal Procurement Data System (FPDS), a GSA website, which shows no evidence
that any Individual Plaintiff has ever been a signatory to a federal contract that
reached the $35 million threshold that would trigger application of the portions of
the PLA Rule Plaintiffs challenge here. As the Defendants point out, one Individual
Plaintiff, Rigid Construction, has entered into a handful of contracts with the federal
government worth tens of millions of dollars, but the highest cost contract on the
public record is $22,387,000. [Doc. 33-8]. Individual Plaintiff, Bulliard Construction
Co., Inc., has no record of having entered a federal government contract for nearly
thirty years. [Doc. 33-3]. The Court’s own review of the GSA records shows that, of
the eight Individual Plaintiffs, only three have contracted with the federal
government in the last ten years. [Boggs and Poole, Doc. 33-2]; [Progressive, [Doc.
33-7]; [Rigid Construction, Doc. 33-8]. Of those three, only Progressive and Rigid
have ever had federal government contracts that exceeded $10 million in contract
costs.9 Thus, importantly, none of the Individual Plaintiffs have ever been signatory
to a federal construction project with costs exceeding $35 million.
This factual scenario significantly compromises the Individual Plaintiffs’
argument that the PLA Rule is an imminent threat to their business interests. If
none of the Individual Plaintiffs have ever been a party to a federal contract worth
$35 million or more in the past, any likelihood that they would be signatories to such
a contract in the future is wholly speculative. And without such a showing, there is
no basis to believe the PLA Rule would impact their businesses. Indeed, if any of the
Individual Plaintiffs were to successfully bid on a federal government contract that
could, potentially, trigger application of the PLA Rule, it would be the first time.
The Individual Plaintiffs’ argument of imminent harm is further undercut by
the existence of enumerated exceptions to the presumption of PLA requirements. The
Plaintiffs argue that the possibility of exceptions to the PLA Rule is “illusory.” In
other words, the Individual Plaintiffs urge this Court to accept—with no supporting
evidence—that the exceptions outlined in the PLA Rule are pretextual and will never
be granted. The FAR Regulations themselves, however, require that, in addition to
the market research that must be conducted under FAR Part 10, the Final Rule
requires contracting officers to conduct an “inclusive market analysis” to evaluate
whether a PLA requirement for any particular project would advance the
Government’s interests in accordance with EO 14,063. This inclusive market
9 The Individual Plaintiff with the highest contract amount is Rigid Construction, with
a contract valued at $22,387,000, well shy of the $35 million amount to trigger application of
the PLA Rule. [Doc. 33-8 at p. 6].
analysis must consider the market conditions in the project area and the availability
of unions and unionized and non-unionized contractors. Federal Acquisition
Regulation: Use of Project Labor Agreements for Federal Construction Projects, 88 FR
88708-02.10 Thus, in determining whether it is appropriate to require a PLA in a
federal construction contract, agency officials must conduct market research. There
is, therefore, a built-in mechanism for determining whether the project at issue is one
that is aligned with the purposes and benefits of the PLA Rule. See also FAR
22.504(d) and 36.104(c).
Furthermore, the challenged regulations themselves enumerate several
exceptions to the PLA Rule, including projects that are of short duration and are not
operationally complex, projects that are not heavily dependent on crafts or trades or
will involve specialized construction work that is available from only a limited
number of contractors or subcontractors, and projects where a PLA is impracticable.
The Individual Plaintiffs have presented no evidence that these exceptions would not
apply or be considered by the agencies with respect to future projects. And while the
Individual Plaintiffs argue that only a small percentage of contracts will qualify for
10 This practice is already in place, as demonstrated by the Supplemental Declaration of
George Rogers, CEO and President of RQ Construction, LLC (“RQ”), a California-based
construction firm, which has responded to numerous requests for information made by the
government about PLA requirements, including one for a forthcoming project to build a child-
care center at Barksdale Air Force Base that does not fall under the challenged portion of the
PLA Rule because the value of the contract is less than $35 million. [Rogers Supp. Decl., Doc.
32-9, ¶¶ 6–9]; [Rogers Letter to Bourgault, Doc. 32-15]. The Court notes that neither Mr.
Rogers nor RQ are parties to this lawsuit. To the extent that the claims of RQ may be
represented by the Association Plaintiffs, that matter is for another day and another court,
as venue is not proper in this district as discussed below.
an exception, such conjecture is both highly speculative and, without any statistical
data given the newness of the Rule, completely unsupported.
Historically, the Supreme Court is “reluctant to endorse standing theories that
require guesswork as to how independent decisionmakers will exercise their
judgment.” Clapper, 568 U.S. at 413. Thus, a prospective injury that is contingent
on the choices of a third party is less likely to establish standing. Id. See also US
Inventor Inc. v. Vidal, 2022 WL 4595001, at *4 (5th Cir. Sept. 30, 2022) (unpublished)
(“[T]o clearly connect Plaintiff-Appellants’ procedural harm to their injury, we must
engage in conjecture about how independent third parties, i.e., the PTAB and a
district court, would act. Clapper rejected such conjectures as speculation insufficient
to support a redressable injury.”).
In Clapper, the Supreme Court rejected standing premised on a “speculative
chain of possibilities.” 568 U.S. at 414. There, the plaintiffs challenged a new
Government surveillance program and alleged injury from the Government’s
interception of plaintiffs’ communications with foreign contacts. Id. at 404–07. The
Court held that plaintiffs lacked standing because connecting the injury (the
interception of communications) with the proffered cause (the new program) required
speculation as to how the Government and Article III judges would act in a “chain of
possibilities,” namely the complex series of events needed for the Government to
actually surveil plaintiffs. Id. at 410. Such speculation meant that the resulting
injury to plaintiffs was not “certainly impending” to constitute an injury in fact
despite an “objectively reasonable likelihood” of plaintiffs’ communications being
intercepted. Id. See also Biden, 64 F.4th at 674 (finding no “injury in fact” where
Plaintiffs’ alleged harms “rel[y] on a highly attenuated chain of possibilities”). Here,
the Individual Plaintiffs’ argument that exceptions will not be granted is a theory
that requires guesswork as to how senior agency officials will navigate the complex
issues associated with solicitation of large-scale federal construction projects. How
these independent decisionmakers will exercise their judgment is, at this juncture,
unknown. But the agencies’ solicitations for market data evaluations, which are
already occurring, suggest that GSA, DOD, and NASA are following the procedures
implemented by the FAR Council; therefore, the Individual Plaintiffs’ argument that
senior agency officials will not consider, and grant, exceptions is unpersuasive.
Finally, to the extent that “some” of the Individual Plaintiffs argue, generally,
that they are experiencing ongoing, immediate injury because they are actively
assessing whether they can afford to write off the expense they have incurred to
procure equipment necessary to bid for federal contracts and comply with various
certification requirements, this argument is unpersuasive, and a similar argument
was rejected in Clapper. 568 U.S. at 415-16 (internal citations omitted) (“In other
words, respondents cannot manufacture standing merely by inflicting harm on
themselves based on their fears of hypothetical future harm that is not certainly
impending. Any ongoing injuries that respondents are suffering are not fairly
traceable to § 1881a.”). Again, given that the Individual Plaintiffs have never been
signatories to the type of contract that will trigger application of the PLA Rule,
planning, spending, and general uncertainty about the outcomes of contracts a
business is not likely to engage in does not create immediate harm for the purposes
of Article III standing. See Clapper, 568 U.S. at 416 (rejecting standing argument
where court found plaintiffs brought the action “based on costs they incurred in
response to a speculative threat”).
Thus, the Court concludes that the Individual Plaintiffs have not carried their
burden of showing that the PLA Rule poses the threat of concrete, particularized, or
imminent injury to their business interests.
B. Traceability
Traceability requires a causal connection between the injury and the conduct
complained of—the injury has to be “fairly ... trace[able] to the challenged action of
the defendant, and not ... th[e] result [of] the independent action of some third party
not before the court.” Lujan, 504 U.S. at 560–61, citing Simon v. Eastern Ky. Welfare
Rights Organization, 426 U.S. 26, 41–42, 96 S. Ct. 1917, 1926, 48 L.Ed.2d 450 (1976).
Furthermore, it must be “likely,” as opposed to merely “speculative,” that the injury
will be “redressed by a favorable decision.” Lujan, 504 U.S. at 561. Because the Court
finds no imminent injury, the Associated Plaintiffs cannot meet the traceability
threshold.
For all of these reasons, the Court concludes that the Individual Plaintiffs’
standing theory rests on a speculative chain of possibilities that does not establish
that their potential injury is certainly impending. Accordingly, the Court concludes
that the Individual Plaintiffs do not have standing under Article III to seek injunctive
relief against the Defendants for promulgation and enforcement of the PLA Rule, and
they will be dismissed from this lawsuit without prejudice.
II. Venue
Under Rule 12(b)(3) and 28 U.S.C. § 1406(a),11 a party may move to dismiss,
or in the alternative transfer, a case filed in an improper venue. Atl. Marine Constr.
Co. v. U.S. Dist. Ct. for W. Dist. of Tex., 571 U.S. 49, 55, 134 S. Ct. 568, 187 L.Ed.2d
487 (2013). In determining whether venue is proper, “the court must accept as true
all allegations in the complaint and resolve all conflicts in favor of the plaintiff.”
Braspetro Oil Servs. v. Modec (USA), Inc., 240 F. App'x 612, 615 (5th Cir. 2007).
However, the Court may consider evidence in the record beyond the facts alleged in
the complaint and its attachments, including affidavits or evidence submitted by
defendants in support of a motion to dismiss, or by a plaintiff in response to the
motion. Ginter ex rel. Ballard v. Belcher, Prendergast & Laporte, 536 F.3d 439, 449
(5th Cir. 2008). When it is determined that a case is filed in a division or district of
improper venue, the district court may either dismiss the case or transfer it to any
district or division of proper venue. See 28 U.S.C. § 1406(a). See also Texas v. United
States Dep't of Health & Hum. Servs., 2023 WL 4629168, at *3 (W.D. Tex. July 12,
2023; Umphress v. Hall, 2020 WL 4731980, at *2 (N.D. Tex. Aug. 14, 2020).
The applicable venue statute, 28 U.S.C. § 1391(e), provides that a civil action
in which the defendant is the federal government may be brought in any judicial
11 28 U.S.C. § 1406(a) provides that “[t]he district court of a district in which is filed a
case laying venue in the wrong division or district shall dismiss, or if it be in the interest of
justice, transfer such case to any district or division in which it could have been brought.”
district: (1) where the defendant resides, (2) where a “substantial part of the events
or omissions giving rise to the claim occurred, or a substantial part of the property
that is the subject of the action is situated,” or (3) where the plaintiff resides if no real
property is involved in the action. Because the Individual Plaintiffs will be dismissed
from the lawsuit for lack of standing, the Court must determine whether venue is
proper in this district in their absence. See, e.g., Miller v. Albright, 523 U.S. 420, 426-
27, 118 S. Ct. 1428, 140 L.Ed.2d 575 (1998); Ga. Republican Party v. SEC, 888 F.3d
1198, 1202-05 (11th Cir. 2018) (transferring case where only party that satisfied
venue failed to provide evidence establishing standing); Immigrant Assistance Project
v. INS, 306 F.3d 842, 867 n.20 (9th Cir. 2002) (holding that the standing of one
plaintiff was “important because it is the only plaintiff ... who is a resident of
Washington and on whom, therefore, venue in the Western District of Washington
could be based”); Nat’l Infusion Ctr. Ass’n v. Becerra, — F. Supp. 3d. —, 2024 WL
561860, at *5 (W.D. Tex. Feb. 12, 2024) (ordering transfer because, after dismissal of
lead plaintiff, “no defendant would reside in this district, no plaintiff resides in this
district, and nothing suggests that a substantial part of the events or omissions giving
rise to the claim occurred in this district”); A.J. Taft Coal Co. v. Barnhart, 291 F.
Supp. 2d 1290, 1304 (N.D. Ala. 2003) (“Venue is proper in this court because at least
one Alabama plaintiff had standing.”); Inst. of Certified Pracs., Inc. v. Bentsen, 874 F.
Supp. 1370, 1372 (N.D. Ga. 1994) (“Having found that the Institute lacks standing to
bring this action and has failed to state a claim upon which relief can be granted,
plaintiff cannot manufacture venue by adding the Institute as a party.”); see also 14D
Charles Alan Wright & Arthur R. Miller, Federal Practice & Procedure § 3815 (4th
ed.) (“[V]enue cannot be based on the joinder of a plaintiff” that has been added “for
the purpose of creating venue in the district.”).
The Association Plaintiffs do not reside in the Western District of Louisiana,
as neither maintains a principal place of business here. The Defendants reside, for
the purposes of venue, in the district where they perform their official duties, which
in this case is Washington, D.C. Fla. Nursing Home Ass'n v. Page, 616 F.2d 1355,
1360 (5th Cir. 1980), rev'd sub nom. Fla. Dep't of Health & Rehab. Servs. v. Fla.
Nursing Home Ass'n, 450 U.S. 147, 101 S. Ct. 1032, 67 L.Ed.2d 132 (1981). Thus, for
venue to be proper in this district, it must be proper under § 1391(e)(1)(B), which
allows suit to be brought “in any judicial district where … a substantial part of the
events or omissions giving rise to the claim occurred.” Plaintiffs argue that venue is
proper in Louisiana because “decisions applying” the PLA Rule “are and will be made
in this district,” and because “actions that this Complaint challenges have been taken,
in material part, in this judicial district.” [Amended Complaint, Doc. 27, at ¶ 25].
In assessing venue under § 1391(e)(1)(B), the Court must examine which
alleged acts or omissions by [the defendant] ‘gave rise’ to [the plaintiff]’s claim[.]”
Jenkins Brick Co. v. Bremer, 321 F.3d 1366, 1372 (11th Cir. 2003); see also Turentine
v. FC Lebanon II LLC, 2022 WL 16951647, at *2 (N.D. Tex. Nov. 15, 2022) (“in
determining whether or not venue is proper, the Court looks to the defendant’s
conduct and where that conduct took place.”). As an initial matter, the Court notes
that the claims in the Amended Complaint concern the promulgation of the PLA Rule
and its enforcement nationwide. Thus, the claims and legal theories pled by the
Plaintiffs do not hinge on the application of the PLA Rule to any particular contract
solicitation; rather, they seek to enjoin the rule’s application to contract solicitations
across the board. See Experian Info. Sols., Inc. v. FTC, 2001 WL 257834, at *3 (N.D.
Tex. Mar. 8, 2001) (adopting findings and recommendation) (venue was not proper in
the Northern District of Texas where plaintiff’s claim involved a pure question of law
about an agency rule rather than any enforcement action taken within the district).
Thus, the events giving rise to the PLA Rule took place where EO 14,063 and the
Final Rule were both drafted and enacted, that is, in Washington, D.C.
With respect to their argument that venue is proper in the Western District of
Louisiana because the “decisions applying” the PLA Rule “are and will be made in
this district,” [Doc. 27 at ¶ 25], the Plaintiffs cite a federal construction contract at
Barksdale AFB in Bossier Parish, Louisiana, as one example of decision-making with
respect to the PLA Rule in Louisiana. In connection with this contract solicitation,
George Rogers, CEO and President of RQ Construction, submitted a Supplemental
Declaration, attesting that he has responded to numerous requests for information
made by the government about PLA requirements, including one for a forthcoming
project to build a child-care center at Barksdale AFB. [Rogers Supp. Decl., Doc. 32-
9, ¶¶ 6–9]; [Rogers Letter to Bourgault, Doc. 32-15]. But the record shows that
Commanding Officer Bourgault, the contracting officer for the Barksdale project, is
in Jacksonville, Florida, and all communication between George Rogers of RQ and
Officer Bourgault took place with Mr. Rogers in Carlsbad, California, and Officer
Bourgault in Jacksonville, Florida. [Doc. 32-15]. Thus, to the extent that the
Plaintiffs focus on this particular contract to establish venue in Louisiana, the
decision-making process appears to be taking place in Florida. Otherwise, they fail
to show that any decision-making process has taken place in Louisiana.
For these reasons, the Court finds that venue is not proper in the Western
District of Louisiana and the instant lawsuit will be transferred to a court having
proper venue. The Defendants seek transfer to the District Court for the District of
Columbia, but the Plaintiffs have not indicated an alternate preferred venue. The
Court will allow them to so indicate within seven (7) days.
Finally, because the Court has determined that venue is not proper in the
Western District of Louisiana without the Individual Plaintiffs as parties, the Court
need not consider the Article III standing of the Association Plaintiffs. See, e.g., Miller
v. Albright, 523 U.S. 420, 426-27, 118 S. Ct. 1428, 140 L.Ed.2d 575 (1998); Ga.
Republican Party v. SEC, 888 F.3d 1198, 1202-05 (11th Cir. 2018) (transferring case
where only party that satisfied venue failed to provide evidence establishing
standing).12
CONCLUSION
Considering the foregoing,
IT IS HEREBY ORDERED that Defendants’ RENEWED CIVIL RULE 12 MOTION
[Doc. 33] is GRANTED IN PART. Having concluded that the Individual Plaintiffs in
this case do not have Article III standing to challenge the PLA Rule, the claims of
12 The Court notes that the Individual Plaintiffs were added as parties only in response
to a well-founded Motion to Dismiss or Transfer for lack of venue.
Boggs & Poole Contracting Group, Inc; Don M. Barron Contractor, Inc.; J.B. Mouton,
LLC; Lincoln Builders, Inc.; Progressive Construction Company, LLC; Bulliard
Construction Company, Inc.; Rigid Constructors, LLC; and Pat Williams
Construction, LLC are DENIED AND DISMISSED WITHOUT PREJUDICE.
IT IS FURTHER ORDERED that, with venue being improper upon the
dismissal of the Individual Plaintiffs, this matter will be transferred to a court with
proper venue. Within seven (7) days, the Plaintiffs shall advise the Court whether
they wish this matter to be transferred to the residence of the Association Plaintiffs,
i.e., the Middle District of Louisiana or the Eastern District of Virginia, or to the
residence of the Defendants, the District Court for the District of Columbia.
IT IS FURTHER ORDERED that the status conference currently set for March
14, 2024, and the Bench Trial currently set for March 19, 2024, are CANCELLED.
THUS, DONE AND SIGNED in Chambers on this 12“ day of March 2024.
Chord C beats
DAVID C. JOSEPH
UNITED STATES DISTRICT JUDGE
Page 22 of 22