engineering firm’s QRTC claim failed the substantial rights prong where engineering firm failed to address “the obvious question of how it could have substantial rights in the results of the research, if it needed the government’s ‘authorization’ to use those results.”
How later courts described this case
- engineering firm’s QRTC claim failed the substantial rights prong where engineering firm failed to address “the obvious question of how it could have substantial rights in the results of the research, if it needed the government’s ‘authorization’ to use those results.”
- engineering firm lacked substantial rights under “work for hire” contract that transferred “all rights, title, and interest” to the results of its work
- engineering firm lacked substantial rights under contract that required contractor to seek approval prior to using or releasing any “materials” or information acquired under the contract
- “Dynetics bears the burden of showing it had substantial rights in the results of the research.”
Written by the judges who cited it.
The opinion
UNITED STATES DISTRICT COURT
MIDDLE DISTRICT OF LOUISIANA
UNITED STATES OF AMERICA CIVIL ACTION
VERSUS
LEONARD L. GRIGSBY, ET AL. NO. 19-00596-BAJ-SDJ
RULING AND ORDER
The United States seeks to recover a $576,756 tax refund (plus interest) paid
to Defendants Leonard and Barbara Grigsby, which, allegedly, resulted from the
Internal Revenue Service erroneously granting a $1.3 million research expenses tax
credit to Defendants’ S-Corporation, Cajun Industries, LLC (“Cajun”).
Now the Government moves for summary judgment (Doc. 64, the “Motion”),
arguing that undisputed evidence establishes that Cajun, a construction company,
did not conduct any qualified research activities during the tax year in question, and,
by extension, Defendants are not entitled to the resulting refund. Defendants oppose
the Government’s Motion. (Doc. 71). For reasons to follow, the Government’s Motion
will be granted, and judgment will be entered in the United States’ favor.
I. BACKGROUND
A. Summary Judgment Evidence
The following facts are undisputed, as set forth in the parties’ statements of
undisputed facts supporting their respective memoranda (Doc. 64-2 (“USA SOF”),
Doc. 71-1 (“Defendants SOF”), Doc. 79-1 (“USA Reply SOF”)), the parties’ Joint
Statement Of Undisputed Facts submitted with their proposed joint Pretrial Order
(Doc. 82-1, “Joint PTO”), and the record evidence submitted in support of these
pleadings.
i. Relevant Tax History
Cajun is a civil construction company headquartered in Baton Rouge,
Louisiana. Cajun contracts with hundreds of private and public clients throughout
the Gulf South to provide a wide-range of construction services in various markets,
including oil and gas; chemical processing; power and utilities; infrastructure;
communications; and water quality.
Cajun is organized as a Subchapter S Corporation (“S-Corp”) for federal income
tax purposes, which means that Cajun’s income, losses, deductions, and credits pass
through to its shareholders on a pro rata basis. Cajun’s tax year runs from October
1st through September 30th. At all relevant times, Defendant Leonard Grigsby
owned a 73 percent interest in Cajun. (Joint PTO ¶¶ 2-4, 15, 17).
In 2015, Cajun hired alliantgroup LP [sic], a consulting firm, to analyze
whether Cajun was entitled to amend its prior tax returns to claim additional credits
for the 2011 through 2016 tax years. Specifically, alliantgroup reviewed whether (and
to what extent) Cajun was entitled to a tax credit “for increasing research activities”
under 26 U.S.C. § 41 (the “qualified research tax credit” or “QRTC”). Based on a
sampling of 105 projects from Cajun’s 2012 tax year, alliantgroup determined that
Cajun was entitled to claim additional research credits exceeding $1.3 million.
Thereafter, Cajun amended its tax return for the year ending September 30, 2013,
claiming a QRTC in the amount of $1,341,420. Cajun had never before claimed the
QRTC. (Joint PTO ¶¶ 5-6, 9, 19).
In conjunction with its amended return, Cajun issued an amended Form K-1
to its shareholders, including Mr. Grigsby. Mr. Grigsby’s amended K-1 reported a pro
rata allocation of Cajun’s QRTC in the amount of $979,237. (Joint PTO ¶¶ 7-8).
Upon receiving the amended Form K-1, Defendants filed an amended federal
income tax return for the 2013 tax year on which they reported Cajun’s QRTC.
Defendants’ QRTC claim generated a tax credit in the amount of $954,527 and, after
the credit was applied to reduce Defendants’ 2013 tax liability, an overpayment in
the amount of $576,756 plus statutory overpayment interest in the amount of
$73,663.38 (collectively, the “Contested Refund”). (Joint PTO ¶¶ 10-11).
On September 15, 2017, the IRS issued a tax refund check to the Defendants
for the 2013 tax year, which included the Contested Refund.1 (Joint PTO ¶¶ 12-14).
ii. Relevant Activities Resulting in Cajun’s Claimed QRTC
The parties agree that a sampling of four of Cajun’s projects during the tax
year ending September 2013 is determinative of the outcome of this dispute: Project
12-001 (the “Claiborne Project”); Project 12-023 (the “East Bank Project”); Project 12-
051 (the “Chevron Project”); and Project 13-020 (the “Methanex Project”) (collectively,
the “Representative Projects”). (Joint PTO ¶ 20; see also (Doc. 52 at p. 5 (“Pursuant
to an agreement between the parties, Defendants’ discovery responses are limited to
a sample of four projects from Cajun’s tax year ending September 30, 2013.”)).
To follow is a brief description of each Representative Project, with particular
1 The IRS issued Defendants a refund check in the amount of $671,071.38, comprised of the
Contested Refund ($576,756.00 principal plus $73,663.38 interest), plus an additional refund
of $20,652.00 that is not at issue in this case. (Joint PTO ¶¶ 12-14).
attention to the terms of the underlying contracts.2 See Tangel v. Comm’r of Internal
Revenue, 121 T.C.M. (CCH) 1001, 2021 WL 81731 at *4 (T.C. 2021) (instructing that
“the parties’ contract” determines who is entitled to the QRTC (citing authorities));
Populous Holdings, Inc. v. Comm’r of Internal Revenue, No. 405-17, 2019 WL
13032526, at *2 (T.C. Dec. 6, 2019) (instructing that courts consider “payment
procedures, quality and performance standards, termination clauses, and warranty
and default provisions” when determining entitlement to the QRTC).
a. The Methanex Project
In 2012, Cajun executed a construction services subcontract (Doc. 64-1, the
“Methanex Subcontract” or “Mx Subcontract”) with Jacobs Field Services (“Jacobs”)
to perform site preparation for the relocation of Methanex USA, LLC’s methanol
plant from Chile to Geismar, Louisiana. Cajun’s original scope of work was broadly
defined, and subject to a “capped”3 (not-to-exceed) price of $6,485,000. (Mx
2 The parties have each submitted excerpts of the underlying contracts, focusing on the
contractual terms most relevant to the instant dispute. There is substantial overlap among
the parties’ excerpts, though, in all instances, the Government’s excerpts are more inclusive
than Defendants’ excerpts. For simplicity, the Court cites to the Government’s excerpts only,
except to the extent that a critical contract term is included only in the excerpts provided by
Defendants.
3 A “capped” contract is a contract under which the contractor is paid for labor and other
expenses, plus a mark-up, subject to an agreed upon maximum price. Under a capped
contract, the contractor typically bills the client for labor and other expenses incurred up
until the maximum amount is reached. By contrast, a “fixed-price” contract is a contract
under which the contractor agrees to perform contracted work for a fixed total price that is
specified at contract formation. Typically, under a fixed-price contract, the contractor submits
invoices based upon completing particular milestones or percentages of work. A third type of
contract is an uncapped “cost-plus” contract, under which the contractor is paid for all time
and material costs incurred for the project. See Geosyntec Consultants, Inc. v. United States,
No. 12-cv-80334, 2013 WL 5328479, at *5 (S.D. Fla. Apr. 17, 2013), aff’d, 776 F.3d 1330 (11th
Cir. 2015). As set forth below, this case involves capped and fixed-price contracts only.
Subcontract at Recitals ¶¶ 3, 10; id. at Ex. “A” (Scope of Work)). Through dozens of
written change orders, Cajun’s scope of work gradually expanded to include site
establishment, construction of temporary facilities, earthwork, underground piping,
and concrete foundations, for which Cajun was ultimately paid $90 million. Cajun
performed its work according to plans provided by Jacobs, (see USA SOF ¶ 40;
Defendants SOF ¶ 40), and completed the Methanex Project in December 2014. (Joint
PTO ¶¶ 36-38, 51, 62-63).
The Methanex Subcontract is composed of a Construction Services Agreement
(“CSA”) and 10 Exhibits (“Ex.”). Most relevant here, the Exhibits include a detailed
scope of work (Ex. A); terms of monthly payment (including additional payment for
changes to Cajun’s original scope of work) (Ex. C); line-item pricing for Cajun’s labor
costs (including “Project Cost Engineer” wages), services and materials (Ex. D); and
quality control standards, including standards for Jacobs’ review and approval of
Cajun’s work (Ex. G).
As stated, Jacobs originally agreed to pay Cajun a “NOT TO EXCEED PRICE
[of] $6,485,000” to perform “the Scope of Work as outlined in Ex. A,” with
compensation “based on billed actual manhours and actual cost of other cost
reimbursable items in accordance with the agreed … rates as included in this Ex. D.”
(Mx Subcontract at Ex. D §§ 2.1-2.2; see also id. at Recitals ¶ 10). However, the
Methanex Subcontract makes additional compensation available to Cajun in stated
circumstances. Specifically, General Conditions (“GC”) § 8 (“Changes”) provides that
if Jacobs demands an adjustment to Cajun’s scope of work, Cajun is entitled to submit
a “prior written change order” negotiating a new contract price. (Mx Subcontract GC
§ 8A). In such instances, “[a]dditional compensation for changes shall, at [Jacob’s]
sole discretion, be determined by … (i) negotiated lump sum; (ii) time and materials;
(iii) unit price; or (iv) any combination of the foregoing.” (Id.).
The Methanex Subcontract requires Cajun to submit “an application for
payment … on or before the tenth day of each month, for Work completed during the
preceding month.” (Mx Subcontract GC § 9(A)). Cajun’s monthly applications are
subject to Jacobs’ “approval,” and Jacobs is entitled to demand “supporting
documentation … reasonably require[d] to evidence … [Cajun’s] entitlement to the
amounts claimed.” (Id. at §§ 9(A), (E)). Upon approval, Jacobs must pay Cajun within
10 days of Jacobs’ “receipt of the corresponding payment from [Methanex USA],” less
a 10 percent retainage. (Id. at § 9(A)). Payment of the retainage is due after Jacobs’
final acceptance of Cajun’s work. (Id.). Jacobs’ final acceptance is conditioned on
Cajun’s delivery of a lien waiver showing that Cajun performed its work “completely
… and that there are no unsatisfied or undischarged claims, demands, losses, liens,
attachments or encumbrances arising out of the Subcontract.” (Id.).
Cajun’s work under the Methanex Subcontract is subject to quality assurances
and controls set forth in Exhibit G. Among these assurances, Cajun is required to
bear the cost of remediating any work that fails to conform to “Project requirements”:
Subcontractor [Cajun] shall remain totally responsible for the quality
and accuracy of its Work which shall at all times conform to Project
requirements. In the event that the results of tests performed are not in
accordance with Project requirements, Subcontractor shall be
responsible for any repair, rework, re-testing and/or additional testing
required as a result of the Work not being compliant with Project
requirements. The costs associated with any repair, rework, re-testing,
and/or additional testing required as a result of the Work not being
compliant with Project requirements shall be to Subcontractor’s
account.
(Mx Subcontract Ex. G at § 1.9). Essentially the same term is repeated at Exhibit A
(Scope of Work) Section 23.6.
Finally, and importantly, the Methanex Subcontract sets forth detailed terms
regarding Cajun’s right (or lack thereof) to its “Work Product,” stating that all Cajun’s
Work Product under the Methanex Contract is “work made for hire” owned by
Methanex USA:
26. OWNERSHIP OF WORK PRODUCT, DRAWING AND
TECHNICAL DOCUMENTATION BY OWNER.
A. All Work Product prepared by Subcontractor [Cajun] shall be "works
made for hire," and all rights, title and interest to the Work Product,
including any and all copyrights in the Work Product, shall be owned by
Owner [Methanex USA, LLC] irrespective of any copyright notices or
confidentiality legends to the contrary which may have been placed in
or on such Work Product by Subcontractor. If, for any reason, any part
of or all of the Work Product is not considered a work made for hire for
Owner or if ownership of all right, title and interest in the Work Product
shall not otherwise vest in Owner, then Subcontractor agrees that such
ownership and copyrights in the Work Product, whether or not such
Work Product is fully or partially complete, shall be automatically
assigned from Subcontractor to Owner without further consideration,
and Owner shall thereafter own all right, title and interest in the Work
Product, including all copyright interests.
(Mx Subcontract GC § 26(A)).
“Work Product” is defined expansively, and means:
all documents, data, analyses, reports, plans, procedures, manuals,
drawings, specifications, calculations, or other technical tangible
manifestations of Subcontractor’s [Cajun’s] efforts (whether written or
electronic) created by Subcontractor in the performance of the Work,
including but not limited to all Documents.
(Mx Subcontract GC § 1). This definition incorporates two additional expansively-
defined terms, “Documents” and “Work”:
“Documents” means any or all tracings, designs, drawings, field notes,
requisitions, purchase orders, specifications, electronic information
(including but not limited to data files, operating codes, executable
computer programs, output therefrom, and other software in any form),
and other documents or records developed or acquired by Subcontractor
and its suppliers or sub-subcontractors in performing the Work.
…
“Work” means the work, services, deliverables, duties and activities to
be performed or provided by, or on behalf of, Subcontractor under this
Subcontract as more fully described in the Scope of Work [Ex. A].
(Mx Subcontract GC § 1).
b. The Chevron Project
In 2011, Cajun contracted with Chevron (Doc. 64-24 and Doc. 77-25,
collectively the “Chevron Contract”) to perform construction services as part of
Chevron’s expansion of its refinery in Pascagoula, Mississippi. The Chevron Project
was multi-phase, and Cajun’s scope of work included backfill, concrete, excavation,
earthwork, piling installation and testing, concrete foundations, underground piping
and utilities, road work, soil remediation, and tank testing. (Joint PTO ¶¶ 71, 90-91).
Cajun performed its work according to plans provided by Chevron, and completed the
Chevron Project in April 2013. (Joint PTO ¶¶ 97, 112).
The Chevron Contract includes of 44 pages of Terms and Conditions (“T&C”),
and 11 Exhibits. Relevant here, Exhibit A provides a detailed Scope of Work, and
Exhibit B provides an expansive Schedule of Compensation.
Like the Methanex Subcontract, the Chevron Contract is “capped,” setting a
not-to-exceed amount4 that Chevron agrees to pay Cajun “in accordance with Exhibit
B – Schedule of Compensation for Work conforming to Contract requirements.” (USA
SOF ¶ 86; Defendants SOF ¶ 86; Chevron Contract T&C § 7.1). In turn, Exhibit B
sets forth a table specifically allocating certain costs among the parties (Chevron
Contract Ex. B-1 (Allocation of Cost)), and line-item pricing for Cajun’s labor,
services, and materials (Chevron Contract Exhibits B-2 through B-8). Exhibit B
provides that Cajun shall be reimbursed for wages of all Cajun employees (including
“Project Engineers”) “performing … Work” on the Chevron Project (see Chevron
Contract Ex. B-1 §3.1(A), Ex. B-2 Item # 11), and that Cajun shall also be reimbursed
“the cost of testing the completed Facility or parts thereof, if necessary” (see Chevron
Contract Ex. B-1 §7.6).
Despite being “capped,” the Chevron Contract also provides that additional
compensation is available to Cajun in stated circumstances. Specifically, Terms and
Conditions § 4 (“Changes”) states that if Chevron demands an increase “in the
quantity, character, kind or execution of the Work,” Cajun may respond with “a
written estimate … based upon the rates established in Exhibit B … for the cost of
performing the [additional] Work.” (Chevron Contract T&C §§ 4.1-4.2). The parties
will then execute a written change order allowing Cajun to proceed with the
additional work at the new price. (Id. at § 4.2). Additionally, if Chevron demands an
adjustment to Cajun’s scope of work, Cajun may respond with a “written notice”
4 The parties agree that the Chevron Contract is capped, but do not specify the Contract’s
not-to-exceed amount here. (See USA SOF ¶ 86; Defendants SOF ¶ 86).
seeking “price adjustment” for labor, services, and materials. (Chevron Contract
T&C § 4.3).
The Chevron Contract requires Cajun to submit weekly invoices to Chevron
for “craft labor,” and monthly invoices for “all other reimbursable costs,” supported
by “evidence [of] receipted bills, expense accounts …, third party invoices, releases
and waivers of lien rights, or other specific and detailed documentation.” (Chevron
Contract T&C §§ 8.2-8.3). Thereafter, within 30 days, Chevron must pay Cajun “the
[undisputed] compensation provided under a Work Authorization,” subject to a 5
percent retainage. (Id. at §§ 8.3, 8.5). Chevron is only allowed to withhold payment
to the extent that Chevron disputes Cajun’s supporting documentation, and even
then only until such time that Cajun “amends the invoice in satisfaction of the dispute
or provides the required documentation to substantiate invoice details.” (Id. at §
8.5.2). Cajun is entitled to payment of the retainage “after 90 days from Mechanical
Completion, provided that there are no undischarged or unsecured liens, attachments
or claims in connection with the Work.” (Id. at §8.3).
Cajun’s work under the Chevron Contract is subject to Chevron’s “provisional”
and “final” acceptance. “Provisional Acceptance” is conditioned on three factors: “(i)
actual, Contract-compliant completion of the Subject system or Work authorization;
(ii) the subject Work is tight, internally, and externally clean, and (as applicable) has
been properly precommissioned [sic], adjusted, and tested; and (iii) all of [Cajun’s]
Construction Equipment, other supplies, personnel and debris has been removed
from the Work Areas.” (Chevron Contract T&C § 6.1). “Final Acceptance” is
conditioned on Chevron’s receipt of: “all Technical Information” (discussed below);
releases; materials audits/reconciliations; and documentation supporting
government permits. (Id. at § 6.5)
Additionally, the Chevron Contract states that Cajun’s work is subject to
Cajun’s guarantee(s) that it will perform “in a safe, diligent, skillful and workmanlike
manner, in accordance with generally accepted industry practices and sound
engineering principles,” and, further that Cajun’s “services … Materials or processes”
will not “violate or otherwise infringe upon any third party’s intellectual property
rights.” (Id. at § 13.1).
Finally, like the Methanex Contract, the Chevron Contract sets forth detailed
terms regarding Cajun’s right (or lack thereof) to its “Work Product”—and,
specifically its “Technical Information”—stating, in relevant part:
18. CONFIDENTIALITY AND WORK PRODUCT
18.1. CONTRACTOR [Cajun] agrees that Technical Information will be
used only for performance of the Services for COMPANY [Chevron].
18.2. Technical Information shall not be disclosed to any third party
without COMPANYs express written consent, … [excluding Technical
Information that is “[a]vailable generally to the public through no act or
omission of CONTRACTOR.”]
…
18.3. Article 18 shall remain in force and effect and binding on
CONTRACTOR notwithstanding the termination of this Contract in all
other respects. …
18.4. All inventions, discoveries and improvements (patentable and
unpatentable) that are made or conceived by CONTRACTOR or
CONTRACTOR’s employees in performing the Services and all domestic
and foreign patent rights based thereon shall belong to COMPANY or
an Affiliate designated by COMPANY. CONTRACTOR shall promptly
and fully disclose all such inventions, discoveries and improvements to
COMPANY or the designated Affiliate. CONTRACTOR shall cooperate
as may reasonably be required in order to obtain patent protection
therefore, including the signing of any proper affidavits, patent
applications and the like. Furthermore. CONTRACTOR and employees
of CONTRACTOR shall assign any and all patent applications resulting
therefrom to the designated Affiliate. The cost of obtaining patent
protection shall be borne by COMPANY. …
18.5. Equitable Relief. CONTRACTOR acknowledges and agrees that
due to the unique nature of the Technical Information there may be no
adequate remedy at law for any breach of the obligations set out in this
Article 18, and that any breach of these obligations may allow
CONTRACTOR or another person to compete unfairly with COMPANY
resulting in irreparable harm to COMPANY. Accordingly,
CONTRACTOR agrees that upon a breach (or threat of a breach),
COMPANY is entitled to immediate equitable relief, including a
restraining order and preliminary injunction, and COMPANY may seek
indemnification from CONTRACTOR for any loss or harm in connection
with any breach or enforcement of CONTRACTOR’s obligations
provided in this Article 18 or for the unauthorized use or release of
Technical Information. CONTRACTOR shall notify COMPANY
immediately upon the occurrence of any unauthorized release of
Technical Information or other breach of this Article 18.
(Chevron Contract T&C § 18).
“Technical Information” is defined expansively, and means:
any and all information, data and knowledge which is either made
available to CONTRACTOR by COMPANY relating to the performance
of the Work, or developed by CONTRACTOR as a consequence or arising
out of this Contract. Technical Information includes all inventions,
discoveries or improvements (patentable or otherwise) that are made or
conceived by CONTRACTOR in performing the Work and all patent
rights associated with these inventions, discoveries or improvements.”
(Chevron Contract T&C § 1.1.31). This definition incorporates one additional
expansively-defined term, “Work”:
“Work” and “Services” are interchangeable and mean (unless the
context requires otherwise) all work, services, operations or activities
identified as Contractor’s scope of work under this Contract and in each
relevant Work Authorization and all other activities that are required
for Contractor’s full performance of its obligations under this Contract.
(Chevron Contract T&C § 1.1.36).
c. The Claiborne Project
In September 2011, the United States Army Corps of Engineers (the “Corps”)
awarded Cajun a federal public-bid contract (Doc. 64-18, the “Claiborne Contract”) to
construct a box culvert (underground canal), as part of a flood control system at South
Claiborne Avenue in New Orleans, Louisiana. (Joint PTO ¶ 156). The Claiborne
Contract described Cajun’s work as “construction of a pile founded concrete box
culvert, clearing and grubbing, excavation, construction, dewatering, driving sheet
piles, driving timber piles, utility relocations, maintenance and diversions of storm
water, box culvert construction, asphalt road work, fertilizing and seeding,
backfilling, and other incidental work as specified in the specifications and as
indicated on the drawings.” (Claiborne Contract Solicitation, Offer, and Award
(“SOA”) § 10). Cajun performed its work according to plans provided by the Corps;
the Corps accepted Cajun’s work on the Claiborne Project in September 2017. (Joint
PTO ¶¶ 160-161, 172, 188).
The Claiborne Contract was a “firm fixed price contract” (Joint PTO ¶ 158), bid
by Cajun for a total amount of $25,971,694.50. (Claiborne Contract SOA § 22). The
Claiborne Contract sets forth Cajun’s line-item deliverables, and anticipated costs for
each deliverable priced by unit or by lump sum. (Joint PTO ¶ 158; (Claiborne Contract
Bidding Schedule – Alternate 1)).
Importantly, the Claiborne Contract incorporates numerous provisions of the
Federal Acquisition Regulations (FAR)—both “by reference” and “by full text.”
(Claiborne Contract pp. 25-30).
FAR 52.232-5 (Sept. 2002)5—incorporated by reference (Claiborne Contract at
p. 27)—governs “Payment Under Fixed-Price Construction Contracts,” and requires
the Corps to pay Cajun “the contract price as provided in this contract” pursuant to
monthly progress payments. FAR 52.232-5(a), (b). Cajun is required to support its
monthly payment requests with “[a]n itemization of the amounts requested, related
to the various elements of work required by the contract covered by the payment
requested”—including detailed information related to any subcontractor retained by
Cajun—as well as a certification stating that “[t]he amounts requested are only for
performance in accordance with the specifications, terms, and conditions of the
contract.” Id. at §§ (b)(1), (c). Upon receipt, the Corps determines whether Cajun has
made “satisfactory progress,” and, if so, pays Cajun “in full.” Id. at § (e). If, however,
“satisfactory progress has not been made,” the Corps may withhold a 10 percent
retainage “until satisfactory progress is achieved.” (Id.).
Despite being “fixed price,” the Claiborne Contract allows for additional
compensation to Cajun in stated circumstances. Specifically, FAR 52.243-4 (June
2007)6—incorporated in “full text” (Claiborne Contract at p. 41)—governs “Changes”
and requires the Corps to “make an equitable adjustment and modify [the price of]
the contract in writing” in the event the Corps changes the “specifications,” the
“method or manner of performance of the work,” or other factors that result in
5 All citations and references herein to FAR 52.232-5 are to the September 2002 version.
6 All citations and references herein to FAR 52.243-4 are to the June 2007 version.
increased cost or time required for the Claiborne Project. FAR 52.243-4(a), (d).
Additionally, the Claiborne Contract allows Cajun to recover ownership and
operating costs for “construction and marine plant [sic] and equipment in sound
workable condition,” as well as “[e]quipment rental costs.” (Claiborne Contract at p.
39). The Corps also agrees to reimburse Cajun “the amount of premiums paid for
performance and payment bonds (including coinsurance and reinsurance
agreements, when applicable) after [Cajun] has furnished evidence of full payment to
the surety.” FAR 52.232-5(g).
The Claiborne Contract conditions final payment on Cajun’s satisfaction of
three requirements: “(1) Completion and acceptance of all work; (2) Presentation of a
properly executed voucher; and (3) Presentation of release of all claims against the
Government arising by virtue of this contract.” FAR 52.232-5(h).
Finally, the Claiborne Contract sets forth terms regarding Cajun’s right (or
lack thereof) to its “material and work,” stating, in relevant part:
(f) Title, liability, and reservation of rights. All material and work
covered by progress payments made shall, at the time of payment,
become the sole property of the Government[.]
FAR 52.232-5(f). This provision incorporates the term “work,” which, under the
applicable (2011) FAR 2.101,7 is defined as follows (in relevant part):
Building or work means construction activity as distinguished from
7 The Claiborne Contract incorporates by reference FAR 52.202-1 Definitions (July 2004),
(Doc. 64-18 at p. 25), which states that “[w]hen a … contract clause uses a word or term that
is defined in the [FAR], the word or term has the same meaning as the definition in FAR
2.101 in effect at the time the solicitation was issued.” FAR 52.202-1 (July 2004). The Corps
solicited the Claiborne Contract in August 2011. (Claiborne Contract SOA § 3). Accordingly,
the 2011 version of FAR 2.101 applies, and all references herein to FAR 2.101 are to the 2011
version.
manufacturing, furnishing of materials, or servicing and maintenance
work. The terms include, without limitation, buildings, structures, and
improvements of all types, such as bridges, dams, plants, highways,
parkways, streets, subways, tunnels, sewers, mains, power lines,
pumping stations, heavy generators, railways, airports, terminals,
docks, piers, wharves, ways, lighthouses, buoys, jetties, breakwaters,
levees, canals, dredging, shoring, rehabilitation and reactivation of
plants, scaffolding, drilling, blasting, excavating, clearing, and
landscaping.”
FAR 2.101 Definitions (2011).
d. The East Bank Project
In January 2012, the Sewerage and Water Board of New Orleans (“SWBNO”)
awarded Cajun a state public-bid construction contract (Doc. 64-29, the “East Bank
Contract”) as part of SWBNO’s improvements to the flood protection system at the
East Bank Wastewater Treatment Plant in New Orleans. (See East Bank Contract §
1-03(A) (Scope And Extent Of Contract)). Cajun’s work under the East Bank Contract
consisted of installing/repaving an access road; relocating pipelines and utilities;
excavation; demolition; driving piles; constructing “concrete footing and T-wall”; and
installing three metal floodgates, drainage, and “entrance stairs and emergency exit
stairs.” (See id.). Cajun performed its work according to plans provided by SWBNO
(see East Bank Contract ¶ 30 (Drawings and Specifications); see also § 1-02 (Scope
And Extent Of Contract)); SWBNO accepted Cajun’s work on the East Bank Project
in October 2015. (Joint PTO ¶ 150).
The East Bank Contract is also a “fixed price contract,” (Joint PTO ¶ 126), bid
by Cajun for the “full sum” of $24,391,466.00. (See East Bank Contract p. 3; Joint
PTO ¶ 126). Nonetheless, the East Bank Contract provides that additional
compensation is available to Cajun when “clearly shown that such special
construction is beyond the scope and intent of the original plans and specifications.”
(East Bank Contract ¶ 31 (Drawings and Specifications)). The parties agree that
through various change orders, the East Bank Contract “increased by more than $5
million for a total value of $29.4 million.” (Joint PTO ¶ 127).
The East Bank Contract provides that Cajun will be paid on a monthly basis
for “work actually performed, at the prices bid in [Cajun’s] proposal, plus whatever
payments for extra work may be approved … as full compensation for furnishing all
the labor, materials, tools. equipment, etc., needed to complete the whole work of the
contract, well and faithfully done, in accordance with the drawings and specifications,
and meeting the requirements of the Engineer.” (See East Bank Contract ¶ 52
(Monthly Payments)). Critically, Cajun’s monthly payments expressly include “full
compensation for all loss, damages or risks of every description, connected with or
resulting from the nature of the work, or from any obstructions or difficulties
encountered, of any sort or nature whatsoever, or from the action of the elements;
also for all expenses in consequence of the suspension or discontinuance of the work
as provided for in the contract.” (Id.).
Additionally, the East Bank Contract makes express allowances for payment
of “laboratory inspection and testing,” stating that if SWBNO’s Engineer determines
that such inspection or testing is required, SWBNO pays the cost, and Cajun will “not
bear any part of the cost of the inspection and testing service.” (East Bank Contract
¶ 29 (Laboratory Inspection)).
The Claiborne Contract conditions final payment for Cajun’s work on
SWBNO’s inspection and verification. (East Bank Contract ¶ 56 (Completion Of
Contract And Final Payment)). “If no defects are discovered, or when any defects
found to exist have been repaired by the Contractor at his own expense, so that all
the structures built by him, under this contract, and all the paved or unpaved
surfaces disturbed by the work of this contract, are in acceptable conditions … the
Engineer will recommend that the contract be accepted by [SWBNO].” (Id.).
The East Bank Project Contract does not contain any terms restricting Cajun’s
right to its research or work product developed in the course of the East Bank Project.
B. Procedural History
On September 11, 2019, the United States initiated this action seeking to
recover the Contested Refund pursuant to 26 U.S.C. § 7405. (Doc. 1; see also Doc. 14).
On April 21, 2022, the Court granted the parties’ joint motion to bifurcate this
matter, allowing the parties to proceed first with a determination of whether
Defendants are entitled to the disputed QRTC and, in turn, the Contested Refund
(the “Qualification Phase”), and leaving for later (as necessary) the amount of any
such QRTC/Refund (the “Quantification Phase”). (Doc. 55). Thereafter, again at the
parties’ invitation (Doc. 59), the Court issued a revised scheduling order governing
the Qualification Phase, setting a fact discovery deadline of August 1, 2022, an expert
discovery deadline of October 7, 2022, a dispositive motion deadline of August 15,
2022, and a ten-day trial commencing November 14, 2022. (Doc. 69).
On August 15, 2022, the United States timely submitted the instant Motion
for Summary Judgment (Doc. 64). Defendants timely submitted their opposition (Doc.
71), to which the United States timely submitted a reply (Doc. 79).
For reasons set forth below, the United States’ Motion will be granted and
judgment will be entered in the United States’ favor on the issue of Defendants’
qualification for the QRTC, obviating the need to proceed to the Quantification Phase.
II. ANALYSIS
A. Standard
Federal Rule of Civil Procedure (“Rule”) 56(a) provides that the Court may
grant summary judgment only “if the movant shows that there is no genuine dispute
as to any material fact and the movant is entitled to judgment as a matter of law.”
Fed. R. Civ. P. 56(a). If the movant bears its burden, the nonmoving party “must do
more than simply show that there is some metaphysical doubt as to the material
facts.” Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 586 (1986).
“Where the record taken as a whole could not lead a rational trier of fact to find for
the non-moving party, there is no ‘genuine issue for trial.’” Id. at 587. Stated
differently, “[i]f the party with the burden of proof cannot produce any summary
judgment evidence on an essential element of [its] claim, summary judgment is
required.” Geiserman v. MacDonald, 893 F.2d 787, 793 (5th Cir. 1990).
B. Applicable Law
The issue presently before the Court is a narrow one: whether Cajun is entitled
to the QRTC for the tax year ending September 2013, which, in turn, resulted in the
Contested Refund to Defendants. If Cajun is not entitled to the disputed QRTC,
Defendants are not entitled to the Contested Refund, and the matter is resolved.
The U.S. Court of Appeals for the Fifth Circuit instructs that “[i]n an action to
recover an improperly paid refund, the United States, as plaintiff, bears the ultimate
burden of proof to show … that some amount has been erroneously refunded.” United
States v. McFerrin, 570 F.3d 672, 675 (5th Cir. 2009) (hereinafter McFerrin II)
(quotation marks and alterations omitted). To carry its burden, the Government must
“prove either that the [taxpayers] were not entitled to any refund … or prove how
much of the refund was paid in error.” United States v. McFerrin, 492 F. Supp. 2d
695, 701 (S.D. Tex. 2007) (hereinafter McFerrin I) (citing authorities).
When a disputed refund derives from a claimed tax credit, the Circuit instructs
that the taxpayer must produce evidence “to substantiate [the] claimed credit”:
Tax credits are a matter of legislative grace, are only allowed as clearly
provided for by statute, and are narrowly construed. Taxpayers are
required to retain records necessary to substantiate a claimed credit.
McFerrin II, 570 F.3d at 675 (citations omitted); see also Bubble Room, Inc. v. United
States, 159 F.3d 553, 561 (Fed. Cir. 1998) (“In a tax refund case, the ruling of the
Commissioner of Internal Revenue is presumed correct. To rebut this presumption of
correctness, the taxpayer must come forward with enough evidence to support a
finding contrary to the Commissioner's determination. In addition, the taxpayer has
the burden of establishing entitlement to the specific refund amount claimed.”
(citations omitted)); 26 C.F.R. § 1.41-4(d) (providing substantiation requirement to
claim the qualified research credit).
C. Discussion
i. Defendants fail to offer competent evidence or
argument establishing that Cajun performed “qualified
research”
The QRTC provides a credit for increasing research activities. 26 U.S.C. § 41.
“Qualified research” has four separate and independent requirements:
(1) the expenses must be of the type deductible under [26 U.S.C.] § 174;
(2) the research must be undertaken “for the purpose of discovering
information ... which is technological in nature;” (3) the application of
that information must be “intended to be useful in the development of a
new or improved business component of the taxpayer;” and (4)
substantially all of the research activities must “constitute elements of
a process of experimentation.”
McFerrin II, 570 F.3d at 676 (quoting 26 U.S.C. § 41(d)(1)).
Most relevant here, the third element—“development of a new or improved
business component”—requires proof of a “product, process, computer software,
technique, formula, or invention which is to be … (i) held for sale, lease, or license, or
(ii) used by the taxpayer in a trade or business of the taxpayer.” 26 U.S.C. §
41(d)(2)(B).
Defendants contend that a dispute exists regarding the “business component
element” because for each of the Representative Projects, Cajun “develop[ed]
construction processes which Cajun used to construct items for its clients.” (Doc. 71
at p. 3). This argument fails for two reasons.
First, as noted in the Government’s reply memorandum, Defendants’
invocation of new “processes” flies in the face of their November 17, 2021 verified
supplemental interrogatory responses, which unequivocally state that, as to each
Representative Project, Cajun developed a “product.” (See Doc. 64-15 at pp. 1-2
(Defendants’ Supplement To The United States’ First Set Of Interrogatories For
Interrogatories One And Two)). A “product” is plainly not a “process”—under any
common understanding8 or the Tax Code9—and the Government was entitled to rely
on Defendants’ interrogatory responses when preparing its case—and, more
specifically, its motion for summary judgment. Cf. Bradley v. Allstate Ins. Co., 620
F.3d 509, 527 (5th Cir. 2010) (“Although interrogatory responses are not binding
judicial admissions, they may be used as evidence for assessing summary judgment.”
(citations omitted)).
Rule 26(e) obliged Defendants to supplement their interrogatory responses to
“correct” their earlier disclosure, and to inform the Government that they intended
to prove the business component element through evidence of a “process.” No such
supplementation occurred. The question that follows is whether Defendants’
undisputed failure to supplement their discovery responses bars them from relying
on evidence of Cajun’s purported new or improved “construction processes” to
8 A “product” is “[s]omething produced by human or mechanical effort,” or “[a] direct result;
a consequence.” PRODUCT, AMERICAN HERITAGE COLLEGE DICTIONARY (3d ed. 1997)
Conversely, a “process” is “[a] series of actions, changes, or functions bringing about a result,”
or “[a] series of operations performed in the making or treatment of a product.” PROCESS,
id. Put simply, a “process” is the means, whereas a “product” is the end.
9 The QRTC defines the “business component” to include both a “product” and a “process.” 26
U.S.C. § 41(d)(2)(B). The Treasury Regulations advise that a “product” and a “production
process for the product” are separate business components. See 26 C.F.R. § 1.41-4(b)(1).
Additionally, canons of construction require that “different words within the same statute
should, if possible, be given different meanings.” BNSF Ry. Co. v. United States, 775 F.3d
743, 755 n.86 (5th Cir. 2015) (quoting Firstar Bank, N.A. v. Faul, 253 F.3d 982, 991 (7th
Cir.2001)). To depart from this rule here—that is, to equate “product” with “process” for the
purposes of the QRTC—would violate “the rule against superfluities,” which holds that “a
statute should be interpreted so as not to render one part inoperative.” See id. at 759 & n.120
(quoting Colautti v. Franklin, 439 U.S. 379, 392 (1979)).
establish a contested issue of fact as to the business component element. See Fed. R.
Civ. P. 37(c)(1) (“If a party fails to provide information or identify a witness as
required by Rule 26(a) or (e), the party is not allowed to use that information or
witness to supply evidence on a motion, at a hearing, or at a trial, unless the failure
was substantially justified or is harmless.”).
The answer to this question is determined by the balance of four factors: “(1)
the importance of the evidence; (2) the prejudice to the opposing party; (3) the
possibility of curing such prejudice by granting a continuance; and (4) the explanation
for the party’s failure to disclose.” Frey v. Bd. of Supervisors of Louisiana State
University, No. 16-cv-00489, 2018 WL 4089356, at *3 (M.D. La. Aug. 27, 2018)
(Jackson, J.) (quoting Texas A&M Research Foundation v. Magna Transp. Inc., 338
F.3d 394, at 402 (5th Cir. 2003)). Here, the balance of these factors heavily favors
rejecting Defendants’ late-game substitution.
First, evidence of Cajun’s new construction processes is plainly important to
Defendants, insofar as it is the only evidence (and argument) offered to establish the
business component element of their QRTC claim.10 At the same time, however, the
significance of such evidence is substantially minimized by Defendants’ failure to
specifically identify even one new or improved “construction process” that Cajun
10 Notably, Defendants’ opposition memorandum fails to cite any evidence or offer any
argument establishing that Cajun’s work on the Representative Projects resulted in new
“products.” Under this Court’s Local Civil Rules, Defendants’ failure to address the issue of
whether Cajun’s work resulted in a new or improved products acts as a waiver. See Johnson
v. Cooper T. Smith Stevedoring Co., Inc., No. 20-cv-00749, 2022 WL 2679436, at *3 n.7 (M.D.
La. July 11, 2022) (Jackson, J.) (citing authorities).
developed while working on the Representative Projects (an independent basis for
granting the Government’s Motion, as set forth below).
Second, the Government is obviously prejudiced by Defendants’ about-face.
Relying on Defendants’ prior interrogatory responses, the Government focused its
summary judgment evidence and argument exclusively on whether Cajun developed
new or improved “products” (arguing, in each instance, that Cajun did not develop
any such products). (See Doc. 64-1 at pp. 12-13). Now Defendants have effectively
pulled the rug from under the Government’s case, depriving the Government of an
opportunity to develop evidence contradicting Defendants’ re-stated position.
Third, an eleventh hour continuance to re-open discovery would obviously
mitigate prejudice to the Government. Any such continuance, however, would disturb
the November 2022 trial date. Additionally, a continuance would necessarily include
yet another round of summary judgment briefing—to allow the Government a fair
chance to address Defendants’ new arguments prior to trial—delaying trial for
months, at minimum. This case is already more than three years old, and all sides
deserve a resolution.
Finally, Defendants have offered no explanation whatsoever for their change
of tack. Even now—weeks after the Government raised the issue of Defendants’
surprise substitution in its reply brief (Doc. 79 at p. 3)—Defendants have not
addressed the issue, much less sought leave to supplement their discovery responses.
Balancing these factors, the Court easily determines that the proper sanction
for Defendants’ failure to supplement their discovery responses is to preclude
Defendants from relying on evidence (and related argument) that Cajun developed
“processes” capable of satisfying the business component element of the QRTC. Fed.
R. Civ. P. 37(c)(1); see Alldread v. City of Grenada, 988 F.2d 1425, 1436 (5th Cir. 1993)
(district court properly excluded evidence based on offering party’s failure to
supplement interrogatory responses (citing authorities)); Guidry v. Aventis Pharms.,
Inc., No. 03-cv-493, 2005 WL 8155425, at *2 (M.D. La. Dec. 20, 2005) (excluding
evidence offered in opposition to summary judgment based on offering party’s failure
to supplement its Rule 26 disclosures). As a result, Defendants have failed to produce
any competent evidence supporting an essential element of their QRTC claim, and
summary judgment is required. Geiserman, 893 F.2d at 793.
But even if the Court looks past Defendants’ dilatory tactics, their belated
reliance on “construction processes” fails for yet another reason: lack of specificity. As
indicated above, Defendants vaguely reference new “construction processes”
throughout their opposition memorandum, yet fail to specifically identify even one
new or improved process that resulted from Cajun’s work on the Representative
Projects. Instead, as to each Project, Defendants equate new or improved “processes”
with Cajun’s “methods of construction,” stating without elaboration that “Cajun
performed engineering analyses that fundamentally relied on engineering principles,
which allowed Cajun to determine the proper method of construction.” (See Doc. 71
at pp. 19-21). As a result, the Court is left to guess what “construction processes” (if
any) Defendants contend are new or improved.
Vague and conclusory statements cannot create an issue of fact capable of
withstanding summary judgment. E.g., Allen v. Our Lady of the Lake Hosp., Inc., No.
19-cv-00575, 2022 WL 2921001, at *5 n.9 (M.D. La. July 25, 2022) (Jackson, J.) (“As
a rule, summary judgment evidence ‘must be particularized, not vague or
conclusory.’” (quoting Guzman v. Allstate Assurance Co., 18 F.4th 157, 161 (5th Cir.
2021)). Moreover, this Court has repeatedly admonished that that it “will not
speculate on arguments that have not been advanced, or attempt to develop
arguments on a party’s behalf.” Johnson, 2022 WL 2679436, at *3 n.7. Defendants’
obfuscation deprives the Court of any meaningful criteria by which to measure
whether Cajun’s alleged “construction processes” were, in fact, new or improved, as
required to establish the business component element. For present purposes, the
result is the same: Defendants fail to create a contest as to a material element of their
QRTC claim, and summary judgment is required. Geiserman, 893 F.2d at 793.
ii. Any “qualified research” that Cajun performed fails the
“funded research” exclusion
Defendants’ QRTC claim fails for another reason: Cajun’s alleged research was
“funded” within the meaning of the Tax Code, and thus expressly excluded from
eligibility for the QRTC.
“Funded research” is one of eight express exclusions to the QRTC, and means
“[a]ny research to the extent funded by any grant, contract, or otherwise by another
person (or governmental entity).” 26 U.S.C. § 41(d)(4)(H). The U.S. Tax Court recently
explained that the rationale for the “funded research” exception is to prevent two
parties from claiming the same QRTC:
Section 41 allows a credit to taxpayers who increase their research
expenses above a base amount. Sec. 41(a), (c). “Qualified research
expenses” include in-house research expenses and contract research
expenses. Sec. 41(b)(1). “In-house research expenses” include wages paid
to employees who engage in (or directly supervise) qualified research
and amounts paid or incurred for supplies used in the conduct of
qualified research. Sec. 41(b)(2). “Contract research expenses” are
amounts paid by a taxpayer to a person other than an employee to
perform qualified research. See sec. 41(b)(3).
When a contractor … performs research in fulfilling a contract with its
customer, each party may have a possible claim to the research credit:
[the contractor’s] credit would be based on its in-house research
expenses and [the customer’s] would be based on its contract research
expenses. To prevent double claiming of the credit and to determine
which contracting party is entitled to the credit, the statute provides
that qualified research does not include “funded research.” Sec.
41(d)(4)(H).
Tangel, 2021 WL 81731 at *3.
To determine whether research is “funded,” the Tax Regulations direct the
Court to focus on the underlying contract(s). 26 C.F.R. § 1.41-4A(d)(1) (“All
agreements (not only research contracts) entered into between the taxpayer
performing the research and other persons shall be considered in determining the
extent to which the research is funded.”); see Tangel, 2021 WL 81731 at *4; Fairchild
Indus., Inc. v. United States, 71 F.3d 868, 870 (Fed. Cir. 1995) (“In an accordance with
Treasury Regulation § 1.41–2(e)(2) the contractual arrangement is the factor that
determines who is entitled to the tax benefit[.]”), modified (Feb. 23, 1996).
When it is not obvious from the underlying contract(s) whether the claimed
research was “funded,” the Regulations instruct the Court to consider two main
factors: First, “[a]mounts payable under any agreement that are contingent on the
success of the research … are not treated as funding.” Id. In such circumstances the
party performing the research is entitled to the QRTC because it bears the risk of
failure. See 26 C.F.R. § 1.41-2(e)(2); see also Fairchild Indus., 71 F.3d at 870.
Second, a taxpayer is entitled to the QRTC only if it “retains substantial rights
in the research.” 26 C.F.R. § 1.41-4A(d)(3)(i). “If a taxpayer performing research for
another person retains no substantial rights in research under the agreement
providing for the research, the research is treated as fully funded…, and no expenses
paid or incurred by the taxpayer in performing the research are qualified research
expenses.” Id. at § 1.41-4A(d)(2). The Regulations further advise that a contractor
does not maintain substantial rights where the underlying contract “confers on
another person the exclusive right to exploit the results of the [contractor’] research.”
Id. In other words, the contractor “does not retain substantial rights in the research
if the [contractor] must pay for the right to use the results of the research.” Id. at §
1.41-4A(d)(3)(i); see Tangel, 2021 WL 81731 at *4.
“Incidental benefits to the taxpayer from performance of the research (for
example, increased experience in a field of research) do not constitute substantial
rights in the research.” 26 C.F.R. §1.41-4A(d)(2).
In sum,
If the taxpayer does not have the right to use or exploit the results of the
research, its expenditures are not entitled to the tax credit regardless
whether there is an agreement that the research will be paid for only if
successful, and regardless whether the taxpayer receives some
“incidental benefit” such as increased experience.
Lockheed Martin Corp. v. United States, 210 F.3d 1366, 1374–75 (Fed. Cir. 2000).
Importantly, at summary judgment, Defendants must establish a plausible
contractual basis to conclude that Cajun retained substantial rights in its research.
Dynetics, Inc. & Subsidiaries v. United States, 121 Fed. Cl. 492, 523 (2015) (“Dynetics
bears the burden of showing it had substantial rights in the results of the research.”).
For each Representative Project, Defendants assert that payment was
contingent on the success of Cajun’s research and that Cajun retained substantial
rights in its research. (Doc. 71 at pp. 24-27). Defendants’ arguments, however, are
not convincing. For reasons explained below, the plain terms of the contracts
underlying the Representative Projects dictate either that Cajun relinquished its
right to any research or was paid for its research, such that if even if Cajun engaged
in qualified research, the resulting QRTC can be claimed only by Cajun’s contracting
counterpart. See Tangel, 2021 WL 81731 at *3,
a. Cajun relinquished all rights to its research
under the Methanex, Chevron, and Claiborne
Contracts
As stated, Defendants stake their QRTC claim solely on new or improved
“methods of construction”—“construction processes”—developed by Cajun while
working on the Representative Contracts. (See Doc. 71 at pp. 19-21). The Methanex,
Chevron, and Claiborne Projects each fail the “substantial rights” prong of the
“funded research” exclusion because in each instance Cajun transferred all rights to
any new or improved “construction processes” to its contracting counterpart.
Again, to retain “substantial rights” Cajun must, at minimum, maintain the
right to use or exploit its research without having to pay for it. 26 U.S.C. § 1.41-
4A(d)(2); Lockheed Martin, 210 F.3d at 1374–75. Cajun plainly retained no such right
under the Methanex contract, which states that Cajun’s “Work Product” is “work[]
made for hire,” and, further, expressly transfers ownership of all Cajun’s Work
Product to Methanex USA.
Cajun’s express consent to a “work for hire” contract is significant of itself,
because it strongly signals that Cajun relinquished ownership of any new or improved
methods of construction to Methanex USA. “Work for hire” is a term of art derived
from Copyright law; for 120 years it has meant “work … produced at the instance and
expense of [an] employer.” See Brattleboro Pub. Co. v. Winmill Pub. Corp., 369 F.2d
565, 567 (2d Cir. 1966) (discussing Bleistein v. Donaldson Lithography Co., 188 U.S.
239, 248 (1903)). Under the modern Copyright Act, “work for hire” means both work
produced by an employee within the scope of employment, and work produced by an
independent contractor under a written agreement. 17 U.S.C. § 101. Under a “work
for hire” contract, “the … person for whom the work was prepared is considered the
author …, and, unless the parties have expressly agreed otherwise in a written
instrument signed by them, owns all of the rights comprised in the copyright.” 17
U.S.C. § 201(b). Put simply, “work for hire” is work that is ordered, paid for, and
owned by the party that commissions it.
Cajun’s execution of a contract expressly stating that all Cajun’s “Work
Product”—defined expansively to include all “data, analyses, reports, plans,
procedures, manuals, drawings, specifications, calculations, or other technical
tangible manifestations of [Cajun’s] efforts … created by [Cajun] in the performance
of the [work, services, deliverables, duties and activities to be performed or provided
… under this Subcontract]” (Mx Subcontract GC § 1 (definition of “Work Product,”
incorporating the defined terms “Work” and “Documents”)—is “work[] made for hire”
substantially weakens any claim that Cajun can somehow avoid paying Methanex
USA for the right to use or exploit its new construction methods developed in the
course of the Methanex Project.11
The nail in the coffin is Cajun’s express transfer of all “rights, title and
interest” to its Work Product to Methanex USA. Together, the Methanex Contract’s
“work for hire” and transfer of title provisions eliminate any plausible reading under
which Cajun retains the right to use new or improved “methods of construction”
developed on the Methanex Project without paying for it. See Dynetics, 121 Fed. Cl.
at 517-519 (engineering firm lacked substantial rights under “work for hire” contract
that transferred “all rights, title, and interest” to the results of its work); Tangel,
2021 WL 81731 at *4 (engineering firm lacked “substantial rights” under contract
that transferred ownership of all “technical information” “supplied” or “designed”
under the contract).
The same conclusion obviously applies to the Chevron Project. Under the plain
terms of the Chevron Contract, Cajun agreed to use “Technical Information”—i.e.,
“all inventions, discoveries or improvements (patentable or otherwise) that are made
or conceived by [Cajun] in performing the Work”—only “for performance of the
11 Indeed, Cajun’s express acknowledgment that its Work Product under the Methanex
Contract is “work for hire” supports a determination that Cajun’s QRTC claim fails both
prongs of the “funded research” exclusion. For reasons stated above, Cajun’s claim fails the
“substantial rights” prong because it transferred all ownership of new or improved
(copyrightable) construction processes to Methanex. 17 U.S.C. § 201(b). Additionally, Cajun’s
agreement to a “work for hire” contract supports a finding that Cajun’s QRTC claim fails the
“payment contingent on success” prong because whatever new construction processes it
produced were “at the instance and expense of [Methanex],” Brattleboro, 369 F.2d at 567. In
any event, having determined that Cajun fails the “substantial rights prong” of the funded
research exclusion, the Court does not reach the issue of whether the Methanex Contract also
fails the “payment contingent on success” prong. See also infra n.12
Services for [Chevron]”; further, Cajun agreed not to disclose “Technical Information
… to any third party without [Chevron’s] express written consent.” (Chevron Contract
T&C §§ 18.1-18.2, incorporating the defined term “Technical Information”). If that
wasn’t enough, Cajun also expressly agreed: (1) to forfeit to Chevron any claim to any
“inventions, discoveries and improvements “(patentable and unpatentable) that are
made or conceived by [Cajun] … in performing the Services”; (2) to “promptly and
fully disclose all such inventions, discoveries and improvements to [Chevron]”; (3) to
“cooperate as may reasonably be required in order to obtain patent protection”; and
(4) to consent to “a restraining order and preliminary injunction” in the event of
Cajun’s “unauthorized use or release of Technical Information.” (Chevron Contract
T&C § 18). Again, there is no room for debate as to the meaning of these provisions:
Cajun retained no right to any new or improved methods of construction it may have
developed working on the Chevron Project. See, supra, Dynetics, 121 Fed. Cl. at 517-
519; see also id. at 519-523 (engineering firm lacked substantial rights under contract
that required contractor to seek approval prior to using or releasing any “materials”
or information acquired under the contract).12
12 A separate issue is whether the Methanex and Chevron Projects also fail the “payment
contingent on success” prong of the “funded research” analysis. See 26 C.F.R. § 1.41-2(e)(2).
As set forth above, the Methanex and Chevron Contracts are each “capped” contracts under
which Cajun agreed to an original not-to-exceed price for labor, material, and expenses. In
Geosyntec Consultants, Inc. v. United States, the U.S. Court of Appeals for the Eleventh
Circuit provided substantial guidance for determining when “capped” contracts fail the
“contingent on success” prong. 776 F.3d 1330, 1338 (11th Cir. 2015). Ultimately, the Eleventh
Circuit held that the capped contracts in dispute were “funded”—and rejected an engineering
firm’s claim to the QRTC—due to multiple contract terms, which, in sum, ultimately
conditioned payment on the engineering firm’s “performance … regardless of the success of
its research.” See id. at 1339. These contract terms included: (1) the engineering firm was
entitled to additional compensation in specified circumstances; (2) the underlying contracts
The Claiborne Project follows suit. Under the Claiborne Contract, “[a]ll
material and work covered by progress payments … [became] the sole property of the
Government” at the time of payment. FAR 52.232-5(f). Again, the term “work” is
defined broadly to mean all “construction activity.” FAR 2.101 (2011). Logically, any
new or improved “method of construction” is part of Cajun’s “construction activity.”
Defendants ignore the obvious question of how Cajun maintained substantial rights
to its new methods of construction if all Cajun’s construction activities became the
did not make payment contingent on the success of the firm’s research, but instead required
payment for the firm’s work product even if it did not produce the desired outcome; and (3)
the underlying contracts’ inspection, acceptance and approval terms were not mandatory
prerequisites to payment, instead the firm’s invoices were payable upon invoicing unless an
item on the invoice was disputed. See id. at 1339-43.
Notably, in conducting this analysis, the Eleventh Circuit expressly rejected the
engineering firm’s argument that its research was not funded because “under the capped
contracts … its compensation was fixed,” and thus “it ran the risk of not receiving the full
ceiling price or, conversely, of exceeding its own budget,” explaining:
these cost-of-performance arguments focus on the amount Geosyntec would be
paid and/or the likelihood that its contracts would be profitable, which is of no
matter here. Cost-of-performance is not the financial risk with which we are
concerned because “the only issue is whether payment was contingent on the
success of the research”—that is, the financial risk of failure.
Id. at 1339 (quoting Fairchild Indus., 71 F.3d at 872).
The capped Methanex and Chevron Contracts share many of the key characteristics
driving the analysis and result in Geosyntec. In its principal brief, the Government cites
repeatedly to Geosyntec, and relies on Geosyntec to argue that “[e]ven if Cajun had substantial
rights in the projects, the contracts are funded because Cajun’s right to payment was not
contingent on the success of any research.” (Doc. 64-1 at pp. 23-25). Significantly, Defendants
fail to even mention Geosyntec in their opposition, much less distinguish the case, begging
the question whether the same result should follow here as to the Methanex and Chevron
Projects. Defendants’ failure in this regard is conspicuous, because they elsewhere criticize
the Government for omitting authorities from its “funded research” exclusion argument.
(Doc. 71 at p. 23 n. 107 (“Given the limited number of decisions on the funded research issue,
it would be surprising if Plaintiff was unaware of the Lockheed rule – particularly since a
case Plaintiff cites to in its argument … cites to that case as well.”).
Regardless, the Court does not reach the issue of whether the Methanex and Chevron
Projects also fail the “payment contingent on success” prong, having already determined that
these Projects fail the “substantial rights” prong.
sole property of the Government. (See Doc. 71 at p. 27). Defendants’ failure in this
regard is a tacit admission that they cannot overcome the Claiborne Contract’s
transfer of title provision. See Johnson, 2022 WL 2679436, at *3 n.7 (a party’s failure
to address an issue acts as a waiver); e.g. Dynetics, 121 Fed. Cl. at 521 (engineering
firm’s QRTC claim failed the substantial rights prong where engineering firm failed
to address “the obvious question of how it could have substantial rights in the results
of the research, if it needed the government’s ‘authorization’ to use those results.”).13
In sum, Defendants have failed to show any plausible basis to conclude that
Cajun retained substantial rights to any research it may have performed on the
Methanex, Chevron, and Claiborne Projects. Rather, the plain terms of the
underlying contracts dictate the opposite conclusion: Cajun did not maintain
substantial rights to any research it may have performed under the Methanex,
Chevron, or Claiborne Contracts. Again, summary judgment is required. Geiserman,
893 F.2d at 793; e.g., Dynetics, 121 Fed. Cl. at 523.
b. Cajun was paid for its research under the East
Bank Contract
The East Bank Contract is silent as to Cajun’s ownership of construction
13 In Dynetics, Inc. & Subsidiaries v. United States, cited above, the U.S. Court of Federal
Claims provided extensive guidance regarding the contours of the “substantial rights” prong
of the “funded research” exclusion. 121 Fed. Cl. 492, 521 (2015). Not surprisingly, the
Government cites Dynetics in its opening memorandum, and relies on it to argue that “Cajun
did not retain substantial rights in the Methanex, Chevron, or Claiborne Projects.” (Doc. 64-
1 at pp. 22-23). Surprisingly, Defendants fail to meaningfully address Dynetics in their
opposition, choosing instead to deflect attention from the case in a footnote. (Doc. 71 at p. 23
n.107). And again, Defendants’ failure is particularly galling given their criticism that the
Government omitted certain authorities from its opening memorandum. See supra n. 12.
Going forward, Defendants would do well to avoid hoisting themselves with their own petard.
processes developed during the course of the East Bank Project. Still, the East Bank
Project fails the “payment contingent on success” prong of the “funded research”
exclusion. Why? Because SWBNO plainly paid Cajun for whatever alleged research
Cajun may have performed.
The East Bank Contract was a fixed price contract. Fixed priced contracts are
presumed to be “unfunded research, qualifying the contractor for the credit.” See
Populous Holdings, 2019 WL 13032526, at *2 (citing authorities). The rationale
behind this presumption is easily understood:
Fixed price contracts are inherently risky for the contractor if the
research is unsuccessful. Under fixed price contracts, the contractor
must remedy failed research at its own expense. Fixed price contracts
“generally place maximum economic risk on contractors who ultimately
bear responsibility for all costs and resulting profit or loss.”
Id. (citing authorities).
But whatever initial presumption may attach to the East Bank Contract, it is
definitively rebutted by the Contract’s express terms, which provide that Cajun’s
monthly payments include
full compensation for all loss, damages or risks of every description,
connected with or resulting from the nature of the work, or from any
obstructions or difficulties encountered, of any sort or nature
whatsoever, or from the action of the elements; also for all expenses in
consequence of the suspension or discontinuance of the work as provided
for in the contract.
(East Bank Contract ¶ 52 (Monthly Payments). Additionally, the East Bank Contract
obligated SWBNO and only SWBNO to pay the costs of unanticipated “laboratory
inspection and testing.” (East Bank Contract ¶ 29 (Laboratory Inspection)).
The upshot is that Cajun was compensated for any risk and attendant costs
“connected with or resulting from the nature of [its] work” on the East Bank Project,
and bore no risk that it would be required to pay the costs of additional research or
testing. Accordingly, any research Cajun may have performed was “funded” under a
plain reading of the “funded research” exclusion, and cannot qualify for the QRTC.
26 U.S.C. § 41(d)(4)(H) (“Funded Research” is “[a]ny research to the extent funded by
any grant, contract, or otherwise by another person (or governmental entity).”).
III. CONCLUSION
In sum, Defendants have failed to produce competent evidence or argument
creating a substantial issue of fact that Cajun performed qualified research on the
Representative Projects. Additionally, even assuming Cajun performed qualified
research on the Representative Projects, the underlying contracts dictate that all
such research falls within the “funded research” exclusion. Having now established
that Cajun is not entitled to the disputed QRTC, and, in turn, that Defendants are
not entitled to the Contested Refund, final judgment will be entered in favor of the
United States. See McFerrin I, 492 F. Supp. 2d at 701.
Accordingly,
IT IS ORDERED that United States’ Motion For Summary Judgment
(Doc. 64) be and is hereby GRANTED.
IT IS FURTHER ORDERED that the parties’ pending Motions In Limine
(Docs. 86, 87, 88, 89, 90, 91, 92, 93, and 94) be and are hereby TERMINATED AS
MOOT.
Final judgment in favor of the United States shall issue separately.
Baton Rouge, Louisiana, this 19th day of October, 2022
_____________________________________
JUDGE BRIAN A. JACKSON
UNITED STATES DISTRICT COURT
MIDDLE DISTRICT OF LOUISIANA