Opinion

O'Reilly v. U.S. Army Corps of Engineers

Court
District Court, E.D. Louisiana
Filed
Aug 15, 2022
Cited by
0 cases
Authority
More cited than 22.3%

The opinion

UNITED STATES DISTRICT COURT

EASTERN DISTRICT OF LOUISIANA

LORETTO O’REILLY, JR., ET AL. CIVIL ACTION

VERSUS NO: 21-1027

UNITED STATES ARMY CORPS OF SECTION: "A" (5)

ENGINEERS, ET AL.

ORDER AND REASONS

The following motions are before the Court: Motion for Summary Judgment

(Rec. Doc. 41) filed by the plaintiffs, Loretto O’Reilly, Healthy Gulf, Coalition for

Responsible Zoning, and the Sierra Club and its Delta Chapter (“Plaintiffs”); Cross

Motion for Summary Judgment (Rec. Doc. 89) filed by All State Financial Co. (“All

State”); Cross Motion for Summary Judgment (Rec. Doc. 91) filed by the United

States Army Corps of Engineers and Lt. General Scott A. Spellmon (collectively and

singularly “the Corps”). All motions are opposed. The motions, submitted for

consideration on May 11, 2022, are before the Court on the briefs without oral

argument.

This civil action is a challenge to the Corps’ approval of two dredge and fill

permits issued under Section 404 of the Clean Water Act, for the destruction and

paving-in of a total of 40 acres of forested wetlands near Covington, St. Tammany

Parish, Louisiana. (Rec. Doc. 1, Complaint at 1).

Judicial review of final agency action is conducted under the auspices of the

Administrative Procedure Act (“APA”), 5 U.S.C. §§ 701-706. Plaintiffs allege that the

Corps violated both the National Environmental Policy Act (“NEPA”), 42 U.S.C. § 4321,

et seq., and the Clean Water Act (“CWA”), 33 U.S.C. § 1251, et seq., when it issued the

permits.

The two permits at issue in this action are the Timber Branch II permit (MVN-

2018-0215-EPP), which was obtained by All State, and the Ochsner Blvd. Extension

Road permit (MVN-2017-00075-EPP) (“the Ochsner permit”), which was obtained by St.

Tammany Parish (“the Parish”). Plaintiffs seek to have both permits enjoined for

violations of both the CWA and NEPA and remanded to the Corps for compliance with

those governing laws.1

Thus far in the litigation the Court has addressed emergency and preliminary

injunctive relief pertaining to the Ochsner permit only. (Rec. Doc. 63, Order and

Reasons denying TRO); (Rec. Doc. 84, Order and Reasons denying PI). Work pursuant

to that permit was underway and progressing when this action was filed. Construction

under the Timber Branch II permit issued to All State was not imminent when the case

was filed.

I. BACKGROUND

On February 6, 2018, Bruce Wainer of All State applied to the Corps for a

Section 404 wetlands fill permit to create the Timber Branch II subdivision, a proposed

multi-use commercial and residential development in unincorporated St. Tammany

Parish southwest of Covington, Louisiana. (Complaint ¶ 80); (TB-AR0942, 0956). The

total project acreage of Timber Branch II as described in the application is 69.19

1 All State was allowed to join the litigation as an intervenor. Plaintiffs argued that All State’s

intervention should be limited to the Timber Branch II permit, (Rec. Doc. 17, Opposition), but the

magistrate judge allowed the intervention as to both permits. (Rec. Doc. 26, Order). The Parish

was allowed to intervene without opposition. (Rec. Doc. 32, Order).

forested acres; wetlands comprise 24.58 of those acres. Wainer owns the entire 200-

acre tract within which Timber Branch II would be sited. (Complaint ¶ 96).

The (Little) Tchefuncte River runs to the immediate east of the Timber Branch II

tract. (Id. ¶ 85). The Timber Branch, which is a tributary to the Tchefuncte, runs

immediately south of the proposed Timber Branch II site. (Id. ¶ 88). The 24.58 acres of

wetlands at issue in the Timber Branch II project are adjacent to the Tchefuncte River

and its tributary, the Timber Branch. (Id. ¶ 89).

On November 3, 2020, the Corps approved the Section 404 permit for the Timber

Branch II development. (Id. ¶ 116); (TB-AR0002). Along with the permit, the Corps

issued a Memorandum for Record (“MOR”), which is the decision document supporting

the Corps’ decision to issue the permit. (TB-AR0021). The Corps determined that a full

Environmental Impact Statement was not required. Plaintiffs contend that this permit is

substantially similar to the fill project called Timber Branch I whose 404 permit the Court

enjoined in 2003, involving the same tract of land. See O’Reilly v. United States Army

Corps of Engr’s, No. 04-940, 2004 WL 1794531 (E.D. La. Aug. 10, 2004), affirmed in

part and reversed in part, 477 F.3d 225 (5th Cir. 2007).

Plaintiffs allege that the Timber Branch II site’s wetlands help to absorb runoff

during storm events and replacing those wetlands with impermeable concrete is going

to exacerbate the already serious flooding problem in the area. (Id. ¶¶ 91-104).

Moreover, development of the Timber Branch II site would result in habitat loss for a

litany of local wildlife. (Id. ¶¶ 107-08). But even beyond Timber Branch II, Plaintiffs

allege that the owner of the tract has plans to develop the entire 200-acre site because

he has recently requested a rezoning approval from the Parish for portions of the site;

and a large percentage of the remainder of the 200-acre Timber Branch II site is

wetlands. (Id. ¶¶ 113-115).

On November 10, 2016, the Parish applied for a permit to fill 31.5 forested acres

of land to build a two-mile extension road between Highway 1077 and Ochsner

Boulevard in order to alleviate local traffic congestion. (AR0146). Wetlands comprise

15.8 of the 31.5 acres to be filled. (Complaint ¶ 148).

During the public notice period, Plaintiffs did not comment upon or object to the

requested permit. Representatives of the plaintiff organizations did meet, however, with

the Corps to voice their concerns about the proposed road. In fact, no one formally

opposed the Ochsner permit. Both the Environmental Protection Agency (EPA) and the

Louisiana Department of Wildlife and Fisheries commented on the project, expressing

their concerns. (AR0124; AR0127). But it would be a mischaracterization of their

submissions to call them “opposition” to the project. Those agencies’ recommendations

were essentially what federal law would require the Corps to consider anyway. The

Louisiana Department of Environmental Quality later issued a Water Quality

Certification for the project. (AR0121).

The Supplemental Administrative Record demonstrates that the Corps

questioned the Parish about various aspects of the Ochsner permit application and the

decision to locate the extension in the chosen area. (Rec. Doc. 59).

On November 17, 2020, the Corps approved the Section 404 permit for the

Ochsner Blvd. Extension project. (AR0001). Along with the permit, the Corps issued a

Memorandum for Record (“MOR”), which is the decision document supporting the

Corps’ decision to issue the permit. (AR0014). The Corps determined that a full

Environmental Impact Statement was not required.

The Parish began the public bid process for the construction of the Ochsner

extension road in May and June 2021. The contract was awarded to Magee Excavation

& Development, LLC on October 13, 2021, and Magee received its notice to proceed

from the Parish on November 4, 2021. (Rec. Doc. 61-2, Affidavit). The preparatory work

on the site of the project began not long after.

Plaintiffs complain that the Timber Branch II and Ochsner Blvd. Extension Road

permits are only two of dozens of Section 404 permits that the Corps has issued in

rapidly-developing west St. Tammany Parish, which have collectively eliminated

hundreds of acres of flood-absorbing wetlands and replaced them with impermeable

concrete. (Complaint ¶ 2). Primary among Plaintiffs’ concerns (which include loss of

wildlife habitat, traffic and noise problems, and diminution of water quality) is that one of

the most critical functions of wetlands is their capacity to absorb floodwaters, and

according to Plaintiffs, flooding has reached epic proportions in the region. (Id. at 1). At

the risk of oversimplifying Plaintiffs’ challenge to the Corps’ decision to issue the Timber

Branch II and Ochsner permits—because Plaintiffs do challenge the permits on

numerous grounds—the crux of Plaintiffs’ complaint is that the Corps took a myopic

view with respect to each permit without considering the detrimental cumulative impacts

that these two additional permits would contribute to in light of all of the other permits

issued in that region.

Plaintiffs filed their complaint for declaratory and injunctive relief on May 27,

2021. The administrative record was lodged on November 15, 2021, (Rec. Doc. 36),

and supplemented on January 10, 2022, (Rec. Doc. 59). On November 22, 2021,

Plaintiffs moved for leave to file a motion for summary judgment pertaining to both

permits that exceeded the page limits imposed by the Local Rules. (Rec. Doc. 38). The

Court granted that motion but rather than have the motion for summary judgment

submitted on the December 8, 2021 date requested by Plaintiffs, a date which would

have required the oppositions to be filed immediately after the Thanksgiving holiday

weekend, the Court set the motion for submission on January 19, 2022. (Rec. Doc. 40,

Order).

The Corps and the intervenors sought to adjust the briefing schedule which then

prompted Plaintiffs’ to file their first motion for a temporary restraining order (“TRO”).2

(Rec. Doc. 48, Motion). On the same day that they moved for a TRO, Plaintiffs filed a

motion for preliminary injunctive relief. (Rec. Doc. 49, Motion for Preliminary Injunction).

In light of the flurry of motions being filed, including those for emergency relief, the Court

held a telephone status conference on December 15, 2021. (Rec. Doc. 54, Minute

Entry). The parties proposed various approaches to structuring the motion practice in

this case and the Court urged all parties to reach an agreement. The parties reached

much common ground as to scheduling but days later Plaintiffs filed their amended

motion for a temporary restraining order. (Rec. Doc. 55, Motion). The Court then issued

its own briefing schedule. (Rec. Doc. 57, Order).

2 The first motion for a temporary restraining order was filed as an ex parte/consent motion with

no notice of submission but the Court instructed the Clerk to accept the deficient motion. The

Court dismissed that motion as moot (Rec. Doc. 57, Order), after Plaintiffs filed their amended

motion for a TRO.

On January 13, 2022, the Court denied the motion for a temporary restraining

order as to the Ochsner permit, explaining that the question whether the work at issue

should be enjoined pending a decision on the merits should be decided on Plaintiffs’

motion for a preliminary injunction. (Rec. Doc. 63, Order and Reasons at 6). Because

the motion for a preliminary injunction would be submitted relatively soon and

expeditiously addressed, and because the work taking place at the time pursuant to the

Ochsner permit was preparatory in nature, a TRO was not necessary.3 (Id.).

On February 18, 2022, the Court entered its Order and Reasons denying the

motion for a preliminary injunction as to the Ochsner permit. (Rec. Doc. 84, Order and

Reasons). As of the time that the briefing was complete as to that permit, the Parish had

already spent over $4,000,000.00 in public funds on the Ochsner Blvd. Extension Road

project. (Rec. Doc. 61-1, Long affidavit). The Court explained why Plaintiffs had not

demonstrated a substantial likelihood of success on the merits as to the Ochsner permit

claim.4 (Rec. Doc. 84, Order and Reasons at 12-14).

The parties’ respective motions for summary judgment on the merits as to both

the Ochsner permit and the Timber Branch II permit are now ripe for decision.

3 In their motion for a temporary restraining order, the Plaintiffs had limited their arguments to a

single issue, the alternatives analysis, i.e., that the Corps failed to adequately address

alternatives that avoid the destruction of wetlands. The Court did not address whether Plaintiffs

had satisfied the substantial likelihood of success on the merits prong as to alternatives

because the Court was persuaded that other aspects of the case militated against issuing a

TRO pending the preliminary injunction hearing.

4 Plaintiffs point out that during the proceedings for emergency and preliminary injunctive relief

regarding the Ochsner permit, they presented to the Court only a portion of their case and the

applicable law. (Rec. Doc. 93, Opposition at 4 n.2). Therefore, the denial of preliminary relief

does not mean that they cannot prevail nonetheless on the merits.

II. DISCUSSION

Governing Law

The Court’s review of the Corps’ decision to issue the challenged permits is

subject to the APA’s “arbitrary, capricious, an abuse of discretion, or otherwise not in

accordance with law” standard. City of Shoreacres v. Waterworth, 420 F.3d 440, 445

(5th Cir. 2005) (quoting 5 U.S.C. § 706(2)(A); Shell Offshore v. Babbitt, 238 F.3d 622,

627 (5th Cir. 2001)). This is a demanding standard. Atchafalaya Basinkeeper v. United

States Army Corps of Eng’rs, 894 F.3d 692, 697 (5th Cir. 2018). The standard of review

is a deferential one, regardless of whether the Corps’ decision is challenged under the

CWA or NEPA or both. Id. at 445. The Court is not permitted to conduct a de novo

review of the permitting decision and ultimately substitute its own determination for that

of the Corps’. Town of Abita Springs v. United States Army Corps of Engr’s, 153 F.

Supp. 3d 894, 921 (E.D. La. 2015) (citing Avoyelles Sportsmen’s League, Inc. v. Marsh,

715 F.2d 897, 904 (5th Cir. 1983)). The Court must simply review the Corps’ decision,

as supported by the administrative record, and affirm it (even if the Court disagrees)

unless it is arbitrary or capricious. Id. (citing Ethyl Corp. v. EPA, 541 F.2d 1, 36 (D.C.

Cir. 1976)).

Nevertheless, the agency must examine the relevant data and articulate a

satisfactory explanation for its action including a “rational connection between the facts

found and the choice made.” Atchafalaya Basinkeeper, 894 F.3d at 697 (quoting Motor

Vehicle Mfrs. Ass’n v. State Farm Mut. Auto Ins. Co., 463 U.S. 29, 43 (1983)). In

reviewing that explanation, the court must “consider whether the decision was based on

a consideration of the relevant factors and whether there has been a clear error of

judgment.” Id.

Ordinarily, an arbitrary and capricious decision is one in which the agency has

relied on factors which Congress had not intended it to consider, or one in which the

agency entirely failed to consider an important aspect of the problem, or one in which

the agency offered an explanation that runs counter to the evidence before the agency,

or is so implausible that it could not be ascribed to a difference in view or the product of

agency expertise.5 Fath v. Tex. Dept. of Trans., 924 F.3d 132, 136 (5th Cir. 2018)

(quoting Motor Vehicle Mfrs. Ass’n, 463 U.S. 29 at 43).

The Corps’ permitting decision must comply with both the CWA and NEPA.6

O’Reilly, 477 F.3d at 229 n.1 (citing Sierra Club v. Sigler, 695 F.2d 957, 967 (5th Cir.

1983)). Unlike the CWA, which has substantive environmental goals, NEPA imposes

procedural requirements on federal agencies requiring them to consider and analyze

the environmental impact of their actions. City of Shoreacres, 420 F.3d at 450 (citing

Robertson v. Methow Valley Citizens Council, 109 S. Ct. 1835, 1846 (1989)); O’Reilly,

477 F.3d at 228 (quoting Coliseum Square Ass’n, Inc. v. Jackson, 455 F.3d 215, 224

(5th Cir. 2006)). Most notably, it is NEPA that directs federal agencies to prepare an

Environmental Impact Statement (“EIS”) for “major Federal actions significantly affecting

5 Importantly, review within the proper administrative framework is based on the agency’s

administrative record as a whole and not just the four corners of the EA. See Atchafalaya Basin

Keeper, 894 F.3d at 700.

6 No one has questioned the applicability of both bodies of law to the permit at issue—the CWA,

because the permits will involve the discharge of dredged or fill material into wetlands, see City

of Shoreacres, 420 F.3d at 446 n.2 (citing 33 U.S.C.§ 1344(a); 33 C.F.R. § 328.3(a)(2)), the

regulation of which has been delegated by Congress to the Corps, Avoyelles Sportsmen’s

League, 715 F.2d at 911 (citing 33 U.S.C. §§ 1344, 419), and NEPA, because permitting the

Ochsner extension road and the Timber Branch II development constitutes “major Federal

actions significantly affecting the quality of the human environment,” 42 U.S.C. § 4332(C).

the quality of the human environment,” except in certain qualifying situations.7 O’Reilly,

477 F.3d at 228 (citing 42 U.S.C. § 4332(2) (emphasis added); Sabine River Auth. v.

U.S. Dept. of Interior, 951 F.2d 669, 676 (5th Cir. 1992)). An Environmental Assessment

(“EA”) is a “concise” public document prepared by the federal agency to “briefly” provide

sufficient evidence and analysis for determining whether to prepare an EIS or issue a

Finding of No Significant Impact (“FONSI”). 40 C.F.R. § 1508.9(a)(1). An EA shall

include brief discussions of the anticipated environmental impacts of the proposed

action and alternatives. Id. § 1508.9(b). An EA is intended to be a brief and concise

document, normally not exceeding 15 pages. 33 C.F.R. § 230.10(a)-(c). But while the

EA’s discussion of the required permitting factors can and should be brief, it must also

be sufficient to demonstrate “reasoned decision making” and cannot omit “a significant

environmental concern.” Fritiofson v. Alexander, 772 F.2d 1225, 1236 (5th Cir. 1985)

(citing Foundation on Econ. Trends v. Heckler, 756 F.2d 143, 154 (D.C. Cir. 1985)). But

NEPA plays no role in requiring the agency to favor an environmentally preferable

course of action. Sabine River Auth., 951 F.2d at 676.

To assist federal agencies in determining whether an EIS is required pursuant to

NEPA, the Council on Environmental Quality (“CEQ”) has been authorized to

promulgate guidelines in the form of regulations.8 O’Reilly, 477 F.3d at 228 (citing 40

C.F.R. § 1500.3; Coliseum Square, 465 F.3d at 224). Federal agencies must consider

7 The Council on Environmental Quality regulations applicable to the NEPA EIS determination

define “significantly” as requiring considerations of both context and intensity. 40 C.F.R. §

1508.27. The regulation lists ten factors for an agency to consider when assessing intensity. Id.

§ 1508.27(b).

8 As a courtesy to the Court, Plaintiffs have included as Appendix 1 to their motion for summary

judgment a copy of the CEQ’s NEPA regulations that were applicable to the permitting decisions

at issue. (Rec. Doc. 41-14). The regulations have since been revised.

the cumulative or incremental environmental impacts of their actions. “Cumulative

impact” is the impact on the environment which results from the incremental impact of

the action when added to other past, present, and reasonably foreseeable future actions

regardless of what agency or person undertakes such other actions. 40 C.F.R. §

1508.7. Cumulative impacts can result from individually minor but collectively significant

actions taking place over a period of time. Id. Federal agencies must take a “hard look”

at the consequences of their actions in preparing detailed studies for projects that will

significantly impact the environment and in deciding how much study is required. Fath,

924 F.3d at 136 (citing Robertson v. Methow Valley Citizens Council, 490 U.S. 332,

349-50 (1989)). The Corps’ NEPA obligation is limited to discussing relevant factors and

explaining its decision, not to reaching conclusions in which the court concurs. O’Reilly,

477 F.3d at 228 (citing Robertson v. Methow Valley Citiz. Council, 490 U.S. 332, 350

(1989)).

The Corps issues § 404 (of the CWA) permits under the guidance and

requirements imposed by its own regulations as well as the CWA’s § 404(b)(1)

guidelines developed by the EPA. See 33 C.F.R. Pt. 320; 40 C.F.R. Pt. 230. The

404(b)(1) guidelines provide that the Corps must ensure that the proposed fill material

will not cause any significantly adverse effects on human health or welfare, aquatic life,

aquatic ecosystems, or recreational, aesthetic, or economic values. 40 C.F.R. §

230.10(c)(1)-(4). The 404(b)(1) guidelines prohibit a dredge and fill permit if there is a

“practicable alternative” to the proposed discharge which would have less adverse

impact on the aquatic ecosystem, so long as the alternative does not have other

significant adverse environmental consequences. 40 C.F.R. § 230.10(a). Consideration

of practicable alternatives must include the option of “not discharging into the waters of

the U.S.” Id. § 230.5(c). In cases where the proposed project is not water dependent,

the 404(b)(1) guidelines mandate a presumption that practicable alternatives “that do

not involve special aquatic sites” like wetlands are available “unless clearly

demonstrated otherwise.” Id. § 230.10(a)(3).

The 404(b)(1) guidelines also require examination of the cumulative effects on

the aquatic ecosystem of the permitting decision. Id. § 230.11(g). Cumulative impacts

are the changes in an aquatic ecosystem that are attributable to the collective effect of a

number of individual discharges of dredged or fill material. Id. § 230.11(g)(1). Although

the impact of a particular discharge may constitute a minor change in itself, the

cumulative effect of numerous such piecemeal changes can result in a major

impairment of the water resources and interfere with the productivity and water quality

of existing aquatic ecosystems. Id. The Corps’ own permitting regulations provide for a

“public interest” review that includes consideration of cumulative impacts. 33 C.F.R. §

320.4(a)(1).

Section 404 permits are also subject to mitigation requirements. No discharge of

dredged or fill material shall be permitted unless appropriate and practicable steps have

been taken which will minimize potential adverse impacts of the discharge on the

aquatic ecosystem. 40 C.F.R. § 230.10(d). The Corps’ regulations (developed in

cooperation with the EPA) provide standards and criteria for the use of all types of

compensatory mitigation. 33 C.F.R. § 332.1(a)(1). Compensatory mitigation for

unavoidable impacts may be required to ensure that an activity requiring a § 404 permit

complies with the 404(b)(1) guidelines. Id. § 332.1(c)(3). Compensatory mitigation

means the restoration (re-establishment or rehabilitation), establishment (creation),

enhancement, and/or in certain circumstances preservation of aquatic resources for the

purposes of offsetting unavoidable adverse impacts which remain after all appropriate

and practicable avoidance and minimization has been achieved. Id. § 332.2. It includes

the use of a mitigation bank or an in-lieu fee program. Id. Mitigation bank means a site,

or suite of sites, where resources (e.g., wetlands, streams, riparian areas) are restored,

established, enhanced, and/or preserved for the purpose of providing compensatory

mitigation for impacts authorized by DA permits. Id.

In general, a mitigation bank sells compensatory mitigation credits to permittees

whose obligation to provide compensatory mitigation is then transferred to the mitigation

bank sponsor. Id. In general, the required compensatory mitigation should be located

within the same watershed as the impact site, and should be located where it is most

likely to successfully replace lost functions and services, taking into account such

watershed scale features as aquatic habitat diversity, habitat connectivity, relationships

to hydrologic sources (including the availability of water rights), trends in land use,

ecological benefits, and compatibility with adjacent land uses. Id. § 332.3(b)(1).

Plaintiffs’ Standing

A preliminary issue in every case such as this one is whether the party bringing

the lawsuit has standing. Sabine River Auth., 951 F.2d at 673.

Plaintiffs contend that they have standing to challenge the permits at issue and

they have provided a significant amount of briefing and evidentiary support for this

contention. No party has questioned the plaintiffs’ standing to challenge the permits at

issue.

But standing has both constitutional and prudential limitations, Optimus Steel,

LLC v. United States Army Corps of Engr’s, 492 F. Supp. 3d 701, 715 (E.D. Tex. 2020)

(citing Bennett v. Spear, 520 U.S. 154, 162 (1997)), the former of which enforces the

Constitution’s non-waivable case-or-controversy requirement, and the latter of which

embodies judicially self-imposed limits on the exercise of federal jurisdiction, Cibolo

Waste, Inc. v. City of San Antonio, 718 F.3d 469, 473 (5th Cir. 2013) (citing Elk Grove

Unified Sch. Dist. v. Newdow, 542 U.S. 1, 11 (2004)). Although challenges to prudential

standing are waivable if not raised, Board of Miss. Levee Comm’rs v. EPA, 674 F.3d

409, 417-18 (5th Cir. 2012), constitutional standing implicates subject matter jurisdiction

and therefore is not waivable, cannot be conferred by consent, and must be considered

by the Court even if not questioned by the opposing party. See Ford v. NYLCare Health

Plans, 301 F.3d 329, 331-32 (5th Cir. 2002) (citing SEC v. Forex Asset Mgmt., LLC, 242

F.3d 325, 328 (5th Cir. 2001)).

Article III standing requires a plaintiff to show: “(1) an injury in fact (2) that is fairly

traceable to the actions of the defendant and (3) that likely will be redressed by a

favorable decision.” Cibolo Waste, 718 F.3d at 473 (citing Procter & Gamble Co. v.

Amway Corp., 242 F.3d 539, 560 (5th Cir.2001). An injury in fact is “an invasion of a

legally protected interest which is (a) concrete and particularized and (b) actual or

imminent, not conjectural or hypothetical.” Id. (citing Lujan v. Defenders of Wildlife, 504

U.S. 555, 560 (1992)). Additionally, in the context of NEPA, beyond constitutional

standing requirements the plaintiff must establish that the injury he complains of “falls

within the ‘zone of interests’ sought to be protected by the statutory provision whose

violation forms the legal basis for his complaint.” Sabine River Auth., 951 F.2d at 675

(quoting Lujan v. Nat’l Wildlife Feder., 497 U.S. 871, 883 (1990)).

The plaintiffs in this case are Loretto O’Reilly, Jr. (an individual), Healthy Gulf (a

Louisiana non-profit corporation), Coalition for Responsible Zoning (a Louisiana

corporation), and Sierra Club (Delta Chapter) (a non-profit organization throughout the

United States with a chapter in Louisiana).

Associational standing for an organization may be established if at least one

member of the organization would have standing to sue in his or her own right. Nat’l

Rifle Ass’n of Am., Inc. v. Bureau of Alcohol, Tobacco, Firearms, & Explosives, 700 F.3d

185, 191 (5th Cir. 2012), abrogated on other grounds by New York State Rifle & Pistol

Ass'n, Inc. v. Bruen, 142 S. Ct. 2111 (2022) (citing Tex. Demo. Party v. Benkiser, 459

F.3d 582, 587-88 (5th Cir. 2006)). An individual plaintiff must show an injury in fact

(concrete and particularized and actual or imminent), that is fairly traceable to the

challenged action of the defendant, that is likely to be redressed by a favorable

decision. Friends of the Earth, Inc. v. Laidlaw Env't Servs. (TOC), Inc., 528 U.S. 167,

180 (2000) (citing Lujan v. Defenders of Wildlife, 504 U.S. 555, 560–561 (1992)).

Mr. O’Reilly has submitted a declaration that focuses exclusively on the Timber

Branch II proposal. (Rec. Doc. 41-11). The Ochsner Extension Road is mentioned twice

in passing. (Id. ¶¶ 5, 25). This declaration does not establish that O’Reilly has suffered

or will suffer an injury in fact from the Corps’ granting of the Ochsner permit. O’Reilly

has established, however, injury in fact and the other elements of standing as to the

Timber Branch II permit.

Healthy Gulf has the burden of showing that at least one of its members has

standing to challenge the permits. Healthy Gulf’s executive director has submitted a

declaration, but the only member identified out of the otherwise generic statements

made in the declaration is Ms. Hazel Piazza. (Rec. Doc. 41-9 ¶ 8). Ms. Piazza did not

submit a declaration of her own and like O’Reilly her injuries pertain to the Timber

Branch II permit. Thus, Healthy Gulf has failed to establish associational standing to

challenge the Ochsner permit. Healthy Gulf has established, however, injury in fact and

the other elements of standing as to the Timber Branch II permit through its member

Ms. Piazza.

Coalition for Responsible Zoning (“CFRZ”) has the burden of showing that at

least one of its members has standing to challenge the permits. The Court is persuaded

that the declaration of Dr. Ryan Green, a CFRZ member whose property is

approximately 30 yards from the proposed extension road, (Rec. Doc. 41-3 ¶ 8),

establishes the elements of standing necessary for CFRZ to challenge the Ochsner

permit. The declarations of Nancy Wagner (Rec. Doc. 41-7), Elise Read (Rec. Doc. 41-

6), William J. Spatz (Rec. Doc. 41-5), and Dr. Green establish CFRZ’s standing to

challenge the Timber Branch II permit.

Sierra Club (Delta Chapter) has the burden of showing that at least one of its

members has standing to challenge the permits. Sierra Club has submitted the

declaration of its chapter chair, Mr. David Stets. (Rec. Doc. 41-10). The member

identified in his declaration is Ms. Piazza, whose injuries pertain to the Timber Branch II

permit not to the Ochsner permit. Mr. Matthew Allen is a member of the Sierra Club’s

Delta Chapter but his declaration, which refers to concerns with his elderly parents’

property, does not demonstrate that he would have standing to challenge either permit.

Thus, Sierra Club has failed to establish associational standing to challenge the

Ochsner permit. Sierra Club has established, however, injury in fact and the other

elements of standing as to the Timber Branch II permit through its member Ms. Piazza.9

The Ochsner Permit

Plaintiffs contend that the Corps’ decision to issue the Ochsner permit was

arbitrary and capricious or otherwise not in accordance with the law because the Corps

violated various mandates of the CWA and NEPA when it issued the permit. Plaintiffs

accuse the Corps of simply checking off boxes in the document, reciting boilerplate

language, providing no real analysis or detail, and giving cursory or summary treatment

to significant issues that federal law required the Corps to consider.

Before proceeding to whether Plaintiffs have shown that the Corps’ issuance of

the Ochsner permit was arbitrary and capricious, two points must be stressed at the

outset. First, as mentioned above, during the public notice period when the Parish’s

application for the Ochsner permit was under consideration, Plaintiffs did not comment

upon or object to the requested permit even though representatives of the plaintiff

organizations did meet with the Corps to voice their concerns about the proposed road.

9 Plaintiffs did not break out the standing analysis by substantive claim and by permit, which is

what should have been done in this case. Plaintiffs have barely shown standing as to the

Ochsner permit and on appeal the Fifth Circuit may conclude that they have completely failed in

that showing. As the Court explains later in this opinion, Plaintiffs’ decision to join the two

separate permits in one lawsuit does not reduce their burden as to each permit, whether the

issue is standing or a decision on the merits. The Court notes that a central part of the “injury”

that Plaintiffs repeatedly refer to in their briefing, particularly where cumulative impacts are

concerned, is catastrophic flooding in homes and businesses, including what occurred in St.

Tammany in 2016. But the Court hesitates to conclude that Plaintiffs have shown a concrete or

actual or imminent threat of flooding in their own properties. It is not enough that many of the

residents in St. Tammany Parish oppose overdevelopment in the area because of concerns

about flooding.

In fact, Plaintiffs were very engaged and vocal in getting their concerns about the

connector road raised to the Parish’s elected officials and the Corps. The decision to

proceed with the road both by the Parish and the Corps was not made in ignorance of

any of the issues that Plaintiffs now raise. The Court has already explained that it does

not agree with the opponents’ suggestion that Plaintiffs’ failure to object during the

public notice period necessarily forecloses the relief that Plaintiffs now seek, (Rec. Doc.

84, Order and Reasons at 3 n.4), but because Plaintiffs did not submit anything during

the public notice period, the administrative record upon which the Court’s agency-

deferential review is based lacks support for many of the contentions that Plaintiffs have

raised. One specific example is the argument that the proposed extension road will be

ineffective for relieving local traffic congestion in the area or that the road would present

safety concerns for motorists. Further, because Plaintiffs did not formally present their

concerns and objections to the Corps so as to make them part of the administrative

record, the failure of the Corps to affirmatively address those concerns and objections in

the EA is not a basis to fault the Corps’ decision unless the failure to do so is otherwise

violative of federal law.

Second, the fact that Plaintiffs chose to challenge the Ochsner permit and the

Timber Branch II permit in the same complaint does not combine into one the two

separate administrative records upon which the Corps’ permitting decisions were based.

The Corps and the intervenors have stressed that this case involves two separate

permits—one obtained by a municipality and the other by a private party—that resulted

from separate applications, for completely separate projects. Plaintiffs’ own declarants

cast doubt on the suggestion that the proposed Ochsner connector road would be of

use to residents of the proposed Timber Branch II development providing further

support for the distinctness of the two projects.10 (Rec. Doc. 49-10 Spatz declaration ¶

7; Rec. Doc. 49-11 Read declaration ¶ 29). Yet Plaintiffs’ approach in their briefing

tends to obfuscate the distinctness of the permits. Notwithstanding Plaintiffs’ valid

concern regarding the cumulative impacts analysis for each permit in reference to the

other—the projects do share geographical and temporal similarities because they are

located only one mile apart and the permits were approved within days of each other—it

remains that the validity of each permit must be judged on the administrative record

supporting it. The more sparse Ochsner administrative record cannot be bolstered by

the litigation decision to join the challenge to the Ochsner permit with the challenge to

the Timber Branch II permit.

Turning now to the merits of Plaintiffs’ challenge to the Ochsner permit, the

Corps issued a FONSI and determined that a full EIS was not required for the Ochsner

permit. The MOR is the Corps’ decision document issued in support of the Ochsner

permit. (AR0014-AR0035). “Having reviewed the information provided by the applicant

and all interested parties and an assessment of the environmental impacts, [the Corps

finds] that this permit action will not have a significant impact on the quality of the

human environment.” (AR0034).

The Corps made a factual finding that the anticipated environmental

consequences and impacts attributed by “this project” would not be significant.

10 Of course, All State has vehemently opposed Plaintiffs’ efforts to enjoin the Parish’s permit for

the Ochsner Blvd. Extension Road. All State explains that it has a vested interest in the

Extension Road project because it will benefit the areas surrounding the project. (Rec. Doc. 60,

All State TRO opposition at 3). The Parish has not filed a cross motion for summary judgment

as to the Ochsner permit, but All State has included such relief as part of its cross motion for

summary judgment.

(AR0029). But both NEPA and the CWA require consideration of cumulative impacts,

and this is where Plaintiffs focus their challenge to the Ochsner permit. Plaintiffs claim

that the failure to properly consider cumulative impacts as required by NEPA rendered

the FONSI determination arbitrary and capricious, and then beyond that it violated the

CWA.11 The cumulative impacts requirements for NEPA and the CWA are substantively

similar.

Plaintiffs contend that the Corps’ cumulative impacts determination for the

Ochsner permit lacks any analysis of the cumulative impacts of the extension road in

relation to the Timber Branch II development, and the dozens of other § 404 permits

that the Corps has issued in conjunction with other wetland fill projects in the same

area.12 The primary cumulative impact that concerns Plaintiffs is how the risk of flooding

would be increased from the wetlands authorized to be destroyed in conjunction with

the road and with the other projects already permitted in the area. Essentially, Plaintiffs’

are contending that insofar as cumulative impacts are concerned, the Corps “entirely

failed to consider an important aspect of the problem.” Fath, 924 F.3d at 136 (quoting

Motor Vehicle Mfrs. Ass’n, 463 U.S. at 43).

11 One of the intensity factors contained in NEPA’s CEQ regulations is “[w]hether the action is

related to other actions with individually insignificant but cumulatively significant impacts.” 40

C.F.R. § 1508.27(b)(7). Of course another of those intensity factors is the “unique

characteristics of the geographic area,” such as proximity to wetlands, id. § 1508.27(b)(3). But

as the Corps points out the presence of wetlands alone cannot foreclose a FONSI because

otherwise an EIS would be required every time someone applied for a § 404 permit affecting

wetlands, which as a matter of law is not the case.

12 Plaintiffs clarify that while they argue that the Corps should have considered the impacts of

the Ochsner permit and the Timber Branch II permit as part of the cumulative impacts analysis

of the other project, their contention is not that the Corps piecemealed the two applications by

not considering them together. (Rec. Doc. 41-14 at 15 n.9).

Plaintiffs also point out that the area where the extension road will be built is

largely undeveloped right now. But once the road is built there will be an incentive to

develop further. So additional development in the area should be considered a

reasonably foreseeable future impact when considering cumulative impacts.

The Corps acknowledged that “[cumulatively, similar projects as well as new

development off of the new roadway could have a long-term impact on the aquatic

ecosystem.” (AR0024). But Plaintiffs accuse the Corps of providing no analysis of this

long-term impact or apparently failing to take into account the numerous other 404 fill

projects that have been permitted and allowed to destroy hundreds of acres of wetlands

in the vicinity. The Corps did not expressly list those other permits in the MOR. As

Plaintiffs point out the Corps has in its records all projects it has permitted within three

miles of the site and certainly all permits issued for this same watershed. (Rec. Doc. 30,

Answer ¶ 124).

The Corps was required to consider the cumulative impacts of the Ochsner

extension road under NEPA, the CWA, and implementing regulations. The Corps

determined that the geographic scope for the cumulative effects assessment is the

Liberty Bayou-Tchefuncte area, which is not disputed. (AR0029). The Corps determined

that the direct effects of the proposed project “would be but not limited to” habitat loss,

water and air quality, noise, and energy consumption. (AR0029). Indirect effects of the

proposed project “would be but not limited to” traffic, noise, and continued impacts to

the ecosystem within the region. (Id. § 9.1). But the Corps determined that the

environmental impacts attributable to the project would not be significant. (Id. § 9.5).

Section 9.7 of the MOR contains the Corps’ conclusions regarding cumulative impacts.

That section reads:

When considering the overall impacts that will result from the proposed

activity, in relation to the overall impacts from past, present, and reasonably

foreseeable future activities, the incremental contribution of the proposed

activity to cumulative impacts in the [Liberty Bayou-Tchefuncte area], are

not considered to be significant. Compensatory mitigation will be required

to help offset the impacts to eliminate or minimize the proposed activity’s

incremental contribution to cumulative effects within the [Liberty Bayou-

Tchefuncte area]. Mitigation required for the proposed activity is discussed

in Section 8.0.

(AR0029-AR0030).

Plaintiffs correctly point out that the MOR does not discuss any of the past § 404

permits issued for the Liberty Bayou-Tchefuncte area and it does not mention the

Timber Branch II permit. The Court has previously observed that Plaintiffs’ criticisms of

the cumulative impacts section of the MOR are not exaggerated. (Rec. Doc. 84, Order

and Reasons at 12). Of course, the Corps correctly points out that lack of detail does

not necessarily render any of the determinations contained in the MOR to be arbitrary

and capricious. The Court remains persuaded (as it explained when denying preliminary

relief) that the administrative record does not demonstrate that the Corps failed to

consider the collective impacts of other § 404 permits in the area, including the Timber

Branch II permit, when it issued the Ochsner permit. Even though Plaintiffs did not

comment during the public notice period, representatives of the plaintiffs’ interests met

with personnel from the Corps to explain the potential problems with the extension road.

Plaintiffs’ concerns are legitimate but this is not a case where the Corps has issued a

decision counter to the evidence in the record, and it is not a case where there was only

one permissible decision to be made.

Further, the Court is persuaded that the possibility that the extension road might

prove an attractive lure to further development at some point in the future, while

plausible (the Corps did acknowledge this possibility), is too speculative to constitute a

reasonably foreseeable impact and issuing the permit for the connector road.

The Corps did not reach the decision urged by Plaintiffs but the Court is not

persuaded that the concise nature of the MOR renders the Corps’ FONSI determination

or the permitting decision arbitrary and capricious for failure to consider what the CWA

and NEPA required as to cumulative impacts. The fact that the MOR does not expressly

list the past § 404 permits issued for the Liberty Bayou-Tchefuncte area or the Timber

Branch II permit does not ipso facto mean that the Corps did not consider the

cumulative impacts of those permitting decisions when issuing the FONSI and then

ultimately the permit itself.

Next, Plaintiffs argue that the Corps violated the CWA’s 404(b)(1) guidelines

because the MOR does not explain how the mitigation measures employed—the

purchase of mitigation bank credits—compensates for the environmental impacts of the

project. Plaintiffs complain that the Corps failed to articulate how the mitigation

measures are related to the FONSI, which may implicate NEPA if the mitigation was

relied upon to reduce the project’s significance level before the threshold required for a

full-blown EIS.

The Corps determined that compensatory mitigation would be required to offset

environmental losses resulting from proposed unavoidable impacts to waters of the

United States. (AR0027). Because the proposed project would directly impact

approximately 16 acres of pine flatwood/savanna, the Parish purchased 40.6 acres of

pine flatwood/savanna. (AR0028). The LRAM method was used to determine the

mitigation amount.13 (Id. § 8.4). The Corps made a factual determination that

compensatory mitigation for the Ochsner proposal would help alleviate the loss of

wetland habitat functions realized by the construction activities. (AR0024). The Corps

also indicated that the impact was in the service area of an approved mitigation bank.

(AR0027).

The Corps did not rely on mitigation to arrive at the FONSI when it issued the

Ochsner permit so the Ochsner permit was not issued based on a mitigated FONSI. In

Atchafalaya Basinkeeper, the Fifth Circuit stressed the difference between a FONSI

with accompanying compensatory mitigation and a mitigated FONSI. 894 F.3d at 698.

In this case the Corps’ failure to relate the mitigation measures to the FONSI was not

arbitrary and capricious because the FONSI was not based on mitigation.

As Plaintiffs point out the MOR does not contain a narrative explanation as to

how the mitigation bank credits would compensate for any cumulative impacts, such as

the loss of the flood-absorbing capacity of the wetlands being destroyed by the project.

But the Corps had already concluded that the unmitigated impacts anticipated from the

Ochsner project would not be significant. (AR0029). This factual finding is not arbitrary

and capricious based on the administrative record, which contains no evidence as to

how the wetlands directly impacted by the project contribute to flood control in the

watershed. The Corps’ conclusion that the purchase of 40.6 acres of pine

13 The Fifth Circuit gave in depth consideration to the Louisiana Wetland Rapid Assessment

Method, or LRAM, in its Atchafalaya Basinkeeper v. United States Army Corps of Engineers

decision, 894 F.3d 692, 699-700 (5th Cir. 2018). The LRAM is a type of “functional assessment”

tool that the CWA regulation advises “should be used” to “determine how much compensatory

mitigation is required.” Id. at 700 (quoting 33 C.F.R. § 332.3(f)(1)).

flatwood/savanna would be sufficient compensatory mitigation for the loss of the

wetlands necessary to complete the extension road is not arbitrary and capricious.

Next, Plaintiffs argue that the Corps violated NEPA and the CWA because the

Corps did not conduct an alternatives analysis in accordance with the governing

regulations. In cases where the proposed project is not water dependent, the 404(b)(1)

guidelines mandate a presumption that practicable alternatives “that do not involve

special aquatic sites” are available “unless clearly demonstrated otherwise.” Id. §

230.10(a)(3). The Ochsner extension road is not water-dependent. (AR0015). Plaintiffs

complain that the Corps did not require the Parish to rebut the practicable alternatives

presumption even though the 404(b)(1) guidelines required it. Plaintiffs complain that

alternatives were addressed in a one-page letter from the Parish engineer to the Corps

(AR108), which gave no clear or reasoned explanation for why the road location was

the least environmentally damaging alternative.

The Corps discussed the no action alternative, and two off-site alternatives were

submitted. (AR0018). The two off-site alternatives were not practicable due to significant

right-of-way problems, construction costs, and major traffic disruptions during

construction. (Id.). The no action alternative was rejected because even though there

would be no adverse environmental consequences in doing nothing, the local traffic

conditions (and safety) would not be improved and the other potential benefits

associated with the project would be lost. (Id.).

The Parish submitted to the Corps on-site alternatives with eight different

alignments. (Id.). The Corps was satisfied that the alignment preferred by the Parish

provided the shortest route/length between Ochsner Boulevard and LA Highway 1077

and required less acreage and wetlands to be impacted. (AR0019). The chosen site

addressed the Parish’s needs while minimizing and avoiding adverse impacts to

wetlands. (Id.). The Corps was persuaded that the project was designed to the minimum

width necessary to meet the desired goal. (AR0014). All work shall be conducted within

the right of way and hauled in fill shall come from a clean site chosen by the contractor.

(AR0014).

The MOR provides sufficient explanation as to why certain alternatives were not

chosen and why the Parish’s preferred alternative was actually the most

environmentally friendly. That the MOR does not include an express analysis of the

non-water dependent presumption imposed by the 404(b)(1) guidelines does not render

the Corps’ decision arbitrary or capricious. The record establishes that the Corps was

aware of the presumption and the record contains evidence sufficient to rebut it. Town

of Abita Springs, 153 F. Supp. 3d at 921. Further, the Court finds nothing problematic in

the fact that the Corps did not require the Parish to submit the Lambert Consultants

study underlying the letter that the Lambert consultant submitted in support of the

project, (AR0109), or that the Parish did not submit a traffic study in support of the

connector road. The Corps, whose business is to evaluate/issue dredge and fill permits

consistent with the CWA not to design effective traffic control measures, was entitled to

rely on the Parish’s plausible conclusion (supported by its consultant) that the proposed

road would be effective in alleviating traffic problems in the area. The administrative

record does not contradict this conclusion.

In sum, Plaintiffs have not demonstrated that the Corps’ decision to issue the

Ochsner permit MVN-2017-00075-EPP was arbitrary and capricious. Plaintiffs’ motion

for summary judgment is therefore granted as to the issue of CFRZ’s standing to

challenge the Ochsner permit and denied in all other respects as to the Ochsner permit.

The Corps’ and All State’s cross motions for summary judgment are granted as to the

Ochsner permit.

The Timber Branch II Permit

As with the Ochsner permit, Plaintiffs contend that the Corps’ decision to issue

the Timber Branch II permit was arbitrary and capricious or otherwise not in accordance

with the law because the Corps violated various mandates of the CWA and NEPA when

it issued the permit.

Before proceeding to whether Plaintiffs have shown that the Corps’ issuance of

the Timber Branch II permit was arbitrary and capricious, the Court first considers the

role of the Fifth Circuit’s 2007 decision in O’Reilly, supra. O’Reilly was an appeal of this

Court’s ruling enjoining the § 404 permit issued by the Corps in 2003 for Phase I of a

project called Timber Branch involving the same tract of land at issue herein. No. 04-

940, 2004 WL 1794531. That permit was issued to the prior owner of the land—not to

All State—and it was based on a different development/design plan for Timber Branch

II.

This Court had determined that the Corps’ FONSI was arbitrary and capricious

and that the Corps must prepare a full-blown EIS. Id. at *6. On appeal, the Fifth Circuit

agreed that the FONSI violated NEPA, but the panel was not persuaded that the permit

should be enjoined until the Corps prepared an EIS. O’Reilly, 477 F.3d at 234. Rather,

the appropriate remedy was to allow the Corps to correct the deficiencies in its EA

which could potentially cure the problems identified with the FONSI. Id. The Fifth Circuit

did not vacate the injunction against the 2003 permit but rather amended it “enjoin[ing]

the Corps from issuing a § 404 permit herein until further orders of the district court

consistent with this opinion,” and remand[ing] the case to the Corps for further

proceedings including the preparation of a new EA, a new FONSI, or an EIS or other

appropriate disposition, consistent with this opinion.” Id. at 240-41 (emphasis added).

It was over fifteen years ago when the court of appeals issued its opinion which

left in place the amended injunction and remanded the case to the Corps. Presumably,

the former owner of the tract abandoned the plans for the Timber Branch I project

because it appears that no further action was taken to correct the problems with the

2003 Timber Branch permit. At some point in time All State purchased the land and then

initiated the permit process anew in 2018. There is nothing in the administrative record

to suggest that All State or the Corps relied in any manner on the prior owner’s

application and permit. There has been no suggestion of collusion with the former

owner in order to circumvent the court of appeals’ amended injunction.

The Corps and All State stress that the instant case involves a different applicant,

a different project, a different decision document, and a different Corps permit than the

404 permit issued in 2003. (Rec. Doc. 91-1 at 11 n.3). All State argues that it cannot be

bound by anything in the prior litigation because it did not own the property at the time

and was not the permittee when the injunction was issued.

While Plaintiffs suggest that the prior O’Reilly case forms a “part of the history of

proceedings in this matter,” (Rec. Doc. 41-14 at 3 n.2), they do not argue that the

Timber Branch II permit currently at issue is void for having been issued in defiance of

an extant injunction. But what Plaintiffs point out is that the concerns with Timber

Branch I that were raised in 2003 are worse today due to the rapid and seemingly

unchecked permitting and development taking place in the area in recent years, making

the Corps’ decision to issue the Timber Branch II permit all the more egregious.

The Court is persuaded that the Corps’ issuance of the current Timber Branch II

permit did not violate the injunction left in place by the Fifth Circuit’s 2007 decision.

Thus, while the prior O’Reilly decision perhaps should not be ignored completely

because it did involve the same tract of land and a development similar in design,14 it

does not provide legally preclusive effect in this case.15 Nor does the administrative

record upon which that permit was based (amassed from 1999 when the former owner

began the application process to 2003 when the permit was issued) or the 2003

decision document form a part of the administrative record currently before the Court.

Turning then to the merits of Plaintiffs’ challenge to the Timber Branch II permit,

the Corps issued a FONSI and determined that a full EIS was not required for the

Timber Branch II permit. The MOR is the Corps’ decision document issued in support of

the permit. (TB-AR0021). “Having reviewed the information provided by the applicant

14 All State points out that the prior application was for 81.58 acres with 39.54 acres of wetlands

affected whereas All State’s Timber Branch II impacts less wetlands and is smaller in scope.

Also, the administrative record contains all new site analysis, hydraulic studies, and alternative

site analysis.

15 Besides the legitimate differences between the facts underlying the 2003 permit and the one

at issue here, the Court does not interpret the Fifth Circuit’s 2007 injunction as intending to

restrain use of the land itself in perpetuity. The problem with the 2003 permit was the

deficiencies in the decision document supporting it. Again, All State applied for the Timber

Branch II permit anew relying on nothing from the former owner’s application and the Corps

prepared a new decision document. The Court does not interpret the Fifth Circuit’s injunction to

preclude consideration of a new § 404 permit under those circumstances.

The Corps and All State also stress that unlike the instant case, O’Reilly dealt with a

mitigated FONSI which the Fifth Circuit in more recent jurisprudence has relied upon when

distinguishing O’Reilly. See, e.g., Atchafalaya Basinkeeper, 894 F.3d at 698-99.

and all interested parties and an assessment of the environmental impacts, [the Corps

finds] that this permit action will not have a significant impact on the quality of the

human environment.” (TB-AR0043). Therefore, the Corps concluded that an EIS would

not be required. Id.

The Corps identified direct effects of the proposed project as (but not limited to)

habitat loss, water and air quality, noise and energy consumption. Indirect effects of the

proposed project would be (but not limited to) increased traffic, noise, and continued

impact to the ecosystem within the region. (TB-AR0038). The Corps made a factual

finding that the anticipated environmental consequences and impacts attributed by “this

project” would not be significant. (TB-AR0038). The Corps considered the public interest

review factors when deciding to issue the permit and concluded that the majority of

them were beneficial. (TB-AR0034-0035).

As explained above, NEPA’s regulations required the Corps to consider both

context and intensity in determining whether a project’s effects are significant enough to

require a full EIS. See 40 C.F.R. § 1508.27. But the ten intensity factors listed in the

CEQ regulation are not categorical rules; rather, they guide the agency’s determination.

Spiller v. White, 352 F.3d 235, 243 (5th Cir. 2003). An agency’s decision document is

not deficient simply because the agency does not separately and directly address each

of the factors. Id. And a FONSI is not arbitrary and capricious simply because it

implicates one or more of the intensity factors. See id.

The intensity factors implicated herein are the unique characteristics factor of §

1508.27(b)(3) because wetlands are involved, the cumulative impacts factor of §

1508.27(b)(7), the latter of which Plaintiffs focus upon, and arguably the precedent

factor of § 1508.27(b)(6), in light of Plaintiffs’ concerns about future phases of the

Timber Branch development. Plaintiffs argue that the Corps failed to properly consider

cumulative impacts as required by NEPA rendering the FONSI determination arbitrary

and capricious, and then beyond that the Corps violated the CWA because that body of

law also requires consideration of cumulative impacts. As with the Ochsner permit,

Plaintiffs’ argument is that the Corps failed to consider the cumulative impacts of the

Timber Branch II permit both in relation to the Ochsner permit and to the numerous

other 404 permits issued in the Liberty Bayou-Tchefuncte area in recent years. The

specific adverse cumulative impact that Plaintiffs stress is the potential for flooding in

the area given that wetlands generally serve a valuable flood-absorbing function.

In the MOR the Corps acknowledged that “[c]umulatively, similar projects could

have a long-term impact on the aquatic ecosystem.” (TB-AR0032). But in its

conclusions regarding cumulative impacts, the Corps stated that “the incremental

contribution of the proposed activity to cumulative impacts in the area . . . are not

considered to be significant.” (TB-AR0038). The Corps determined that flood hazards

associated with the project would be “negligible.” (TB-AR0034). The Corps determined

that “[w]ater circulation will be altered at the project site due to the redirection of flow via

subsurface drainage towards the dry retention pond.” (TB-AR0032).

As with the Ochsner permit’s MOR, the Court is not persuaded that the Corps

simply failed to consider the cumulative impacts of the Timber Branch II permit when

concluding that the impacts would not trigger the need for an EIS under NEPA’s

regulations. The administrative record that accompanies the Timber Branch II permit is

robust and evinces significant involvement of Plaintiffs and other concerned citizens

during the thirty-three months that the permit application was pending. But in concluding

that the flooding impact of Timber Branch II itself would be negligible, the Corps

implicitly resolved against Plaintiffs the factual questions pertaining to Timber Branch

II’s flood zone designation, its potential to contribute to flooding in the area, and the

anticipated efficacy of the dry retention pond.

The Timber Branch II project appears to be located in FEMA flood zone X. (TB-

AR AR0123). To help allay flooding concerns raised during the public notice period, All

State modified its project design to include a dry retention pond to increase storm water

retention. Modeling concluded that the proposed drainage modifications and the dry

retention pond, with 91.1 acre-feet of storage, would decrease predevelopment peak

discharge of floodwater runoff by over 25 percent. (TB-AR0181-184). The hydrologic

analysis performed for the Timber Branch II project shows that it complies with the

Parish’s ordinances requiring 25% or more reduction in pre-development runoff. (TB-

AR0099, 178-249).

In reaching its significance findings, the Corps credited the McHugh hydrologic

analysis submitted by All State in support of the project, (TB-AR0176), which suggests

that Timber Branch II’s design will actually decrease floodwater runoff. (TB-AR0181-

184). The Corps chose not to rely upon the study submitted by Dr. Koob, which

supports Plaintiffs’ contentions regarding flooding in the area. (TB-AR0367).

Based on the administrative record, the Corps’ significance conclusions,

including with respect to the potential for flooding impacts attributable to Timber Branch

II, are not arbitrary and capricious. But Plaintiffs argue that the FONSI was arbitrary and

capricious because the Corps did not consider the cumulative flooding impacts

attributable to Timber Branch II. In support of this contention Plaintiffs point out that the

MOR does not discuss any of the other projects (including the Ochsner extension road)

that the Corps has permitted in the area (even though it has those records in its

archives), it does not reference the reasonably foreseeable future development of the

rest of the 200-acre tract of land surrounding the proposed Timber Branch II site, and it

fails to even mention St. Tammany’s catastrophic flooding event of 2016.

Of course, as the Corps points out, NEPA does not prescribe any specific

method of analyzing cumulative impacts. And mindful that consideration of cumulative

impacts under NEPA’s CEQ’s regulations constitutes just one of the ten non-categorial

factors to guide the agency’s permitting decision, the Court is not persuaded that the

Corps’ FONSI for Timber Branch II was arbitrary and capricious for failure to consider

cumulative flooding impacts in the region. The concerns regarding flooding in the area

due to overdevelopment were discussed at length in Dr. Koob’s study which is part of

the administrative record. (TB-AR0367). Even if the Corps had made a factual

determination that the destruction of wetlands in the Liberty Bayou-Tchefuncte area is

contributing to destructive flooding property in the area, and assuming that this is

factually correct, the Corps’ FONSI would not ipso facto have been arbitrary and

capricious.

Plaintiffs argue that the Corps’ FONSI was also arbitrary and capricious because

the Corps did not consider the reasonably foreseeable impacts associated with future

phases of the Timber Branch II development, which recent events have demonstrated

are in the works. Given those recent events such as the land-owner seeking zoning

variances, and showing expansion plans to neighbors, the expansion of Timber Branch

II at some point in the future is more than speculative. But the events that Plaintiffs point

to occurred many months after the Corps’ permitting decision and therefore do not

render the Corps’ failure to address future aspects of Timber Branch II arbitrary and

capricious.

The administrative record supports the Corps’ contention that it considered

potential impacts on the floodplains but ultimately concluded there was no significant

impact. Plaintiffs have not demonstrated that the FONSI was arbitrary and capricious for

failure to properly consider cumulative impacts. The Corps’ decision that no EIS was

required did not violate NEPA at least insofar as cumulative impacts are concerned.16

Plaintiffs argue that another basis for concluding that the FONSI was arbitrary

and capricious is that the Corps failed to articulate how the mitigation measures

required for the Timber Branch II permit are related to the FONSI. Plaintiffs complain

that the EA does not expressly foreclose that the Corps relied on mitigation measures to

reduce the impact levels below the significance threshold requiring a full-flown EIS.

Further, the Corps failed to explain how the mitigation credits compensate for the

localized environmental impacts of the Timber Branch II development, including the loss

of flood-absorbing capacity.

The MOR describes the types of avoidance and mitigation measures required by

Corps’ regulations, the type of compensatory mitigation required, and the amount of

acreage as calculated using the LRAM. (TB-AR0036-37; TB-AR0060-64). The Corps

16 The Court recognizes that the CWA also requires consideration of cumulative impacts but the

Court is not persuaded that the specific cumulative impacts concerns raised by Plaintiffs actually

implicate the CWA’s zone of interests pertaining to the discharge of dredge or fill materials into

navigable waters.

required All State to purchase 58.4 acres of pine flatwood/savanna wetland from

mitigation banks for Timber Branch II. (TB-AR0056). The Corps determined the

“compensatory mitigation should minimize any negative impacts to wetland resources.”

(TB-AR0030).

There is no suggestion from either the MOR or the administrative record that the

mandatory mitigation measures are related to the FONSI, in other words, that the Corps

relied on the mitigation measures to reduce the potential impacts of Timber Branch II

below the significance level that would have triggered an EIS. The Corps did not

reference mitigation in the FONSI, (TB-AR0043), and the mitigation is expressly

referred to as compensatory in nature, (TB-AR0021). The Corps concluded that the

potential impacts from the permit would not meet the “significance” threshold under

NEPA that would require an EIS regardless of mitigation. The FONSI was not arbitrary

and capricious for failing to relate the required mitigation measures to the FONSI.

Plaintiffs argue that the Corps violated NEPA and the CWA because it did not

consider whether the Timber Branch II project as sited in the permit is the least

damaging alternative. It is undisputed that the Timber Branch II project is not “water

dependent” therefore the guidelines impose a presumption that practicable alternatives

to wetlands exist. Plaintiffs complain that the Corps did not hold All State to its burden of

rebutting the presumption but merely accepted All State’s alternative sites analysis

without subjecting it to an independent analysis. Further, Plaintiffs complain that the

Corps gave too much consideration to the applicant’s profit and economic

considerations when approving the Timber Branch II alternative selected by All State.17

In support of the permit application All State submitted a detailed site analysis for

alternatives. (TB-AR0104-0166). The alternative site analysis performed by Blossman

Appraisal Service outlines in detail the requirements of the Timber Branch II project and

the practicable alternatives in light of the project’s goals. The Corps therefore

considered seven (7) offsite alternatives and two (2) onsite alternatives. (TB-AR0026-

0028). The Corps ultimately determined that All State’s preferred alternative impacted

the least amount of wetlands while still maintaining the overall project goals. (TB-

AR0027).

The criteria and/or scope of the proposed Timber Branch II project which

included availability, location, proximity, zoning, highway access, and size, affected

practicability of alternatives. (TB-AR0026). Some of the alternatives did not have the

requisite acreage to support the development, did not have the necessary zoning, were

located in an AE flood plain, and/or impacted a larger portion of jurisdictional wetlands,

rendering them not practicable. (TB-AR0026-0027). Timber Branch II requires certain

zoning requirements in order to support the development, including zoning for

commercial and residential properties.(TB-AR0124). Four of the alternatives could not

meet the necessary zoning requirements, and other alternatives could not meet the size

requirements or impacted more wetlands than the proposed site. Further, other issues

affected the practicability of the other alternatives such as flood zones, soil content,

17 Neither NEPA nor the CWA prohibit the Corps from considering the economics of alternatives

being considered. The Corps did consider All State’s profitability but it did not give undue weight

to that consideration.

availability of central water, sewage, and utilities, parcel size and pre-existing property

claims (TB-AR026-27; TB-AR0104-166).

Two possible on-site alternatives were considered. First, the chosen site plan

which would impact 24.82 acres of wetlands and avoid .24 acres by redesign of part of

the project. (TB-AR0027). The second on-site alternative was the original Timber

Branch II design which was larger in scope and would have impacted a total of 24.66

acres of wetlands. Thus, All State’s preferred alternative impacted slightly less wetlands

of the other on-site alternative. (TB-AR0027).

The Corps considered one no-action alternative. (TB-AR0026-27). As expected

the Corps determined that the no action alternative would avoid all adverse

environmental impacts associated with the development and have the least impact on

wetlands. (Id.). But the no action alternative would not meet the needs of the applicant

and the potential benefits of Timber Branch II, e.g., “additional commercial and

residential opportunities, economic benefits in the form of wages, materials purchased,

property taxes, and jobs,” would not be realized. (TB-AR0026-27).

Insofar as NEPA is concerned, which does not militate in favor of

environmentally-friendly alternatives, the Corps was not arbitrary and capricious in its

consideration of practicable alternatives.

Insofar as the CWA is concerned, the Corps evaluated whether the alternatives

were practicable as that term is defined in 40 C.F.R. § 230.10(a)(2), and determined

that each alternative was not practicable. The Corps determined that development of

any of these alternatives would cause more adverse impacts to wetlands than

development of the subject property. (TB-AR0026-28). The Corps complied with the

404(b)(1) guidelines and 40 C.F.R. § 230.10(a) by reviewing, analyzing, and then

concluding that the “no-action alternative” and the several other alternatives (both off-

site and on-site) were “not practicable.”

Further, the record does not demonstrate that the Corps failed to consider and

that All State failed to rebut the presumption applied in cases where the proposed

project is not water dependent. The CWA is not violated simply because the

presumption was not expressly mentioned in the MOR, see Town of Abita Springs, 153

F. Supp. 3d at 921, and the administrative record contains sufficient evidence to rebut

the presumption as to no practicable alternatives not involving wetlands. Plaintiffs

cannot prevail on their CWA arguments regarding the Timber Branch II project

alternatives and the applicable presumptions under § 230.10(a).

Finally, the Court is not persuaded that either NEPA or the CWA was violated

because the Corps did not commission its own alternatives studies but rather relied

upon the Blossman report submitted by All State. The Corps is surely aware that

applicants are not likely to submit reports that fail to support their preferred alternative.

The Corps’ decision to credit the Blossman report does not lead to an inescapable

conclusion that the Corps simply “rubberstamped” All State’s contentions. The Court

agrees that it is of no consequence that the Corps did not engage its own experts to

prepare an alternative site analysis report.

In sum, Plaintiffs have not demonstrated that the Corps’ decision to issue the

Timber Branch II permit MVN-2018-0215-EPP was arbitrary and capricious. Plaintiffs’

motion for summary judgment is therefore granted as to the issue of standing to

challenge the Timber Branch II permit and denied in all other respects as to the Timber

Branch II permit. The Corps’ and All State’s cross motions for summary judgment are

granted as to the Timber Branch II permit.

Accordingly;

IT IS ORDERED that the Motion for Summary Judgment (Rec. Doc. 41) filed

by the plaintiffs, Loretto O’Reilly, Healthy Gulf, Coalition for Responsible Zoning, and

the Sierra Club and its Delta Chapter is GRANTED IN PART AND DENIED IN PART as

explained above.

IT IS FURTHER ORDERED that the Cross Motion for Summary Judgment

(Rec. Doc. 89) filed by All State Financial Co. and the Cross Motion for Summary

Judgment (Rec. Doc. 91) filed by the United States Army Corps of Engineers and Lt.

General Scott A. Spellmon are GRANTED as explained above.

August 15, 2022

5 3 .

eT = \

Shares STRICT JUDGE

Page 39 of 39

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.