Opinion

Billie v. Village of Channahon

Court
District Court, N.D. Illinois
Filed
Jun 7, 2021
Cited by
0 cases
Authority
More cited than 21.0%

“to seek redress through § 1983 [. . .] a plaintiff must assert the violation of a federal right, not merely a violation of federal law

How later courts described this case

  • “to seek redress through § 1983 [. . .] a plaintiff must assert the violation of a federal right, not merely a violation of federal law
  • Plaintiff may not claim his land has been taken when the condition that devalues his lot was created by his predecessor in title
  • finding no private right of action in § 40127(a) of the ADA and granting motion to dismiss
  • allegations that governmental entity allowed third parties to construct obstruction within a floodplain which caused plaintiff’s property to flood did not constitute a taking

Written by the judges who cited it.

The opinion

IN THE UNITED STATES DISTRICT COURT

FOR THE NORTHERN DISTRICT OF ILLINOIS

EASTERN DIVISION

CRAIG BILLIE, et al,

Plaintiffs,

Case No. 20-cv-3294

v.

Judge Mary M. Rowland

VILLAGE OF CHANNAHON, et al,

Defendants.

MEMORANDUM OPINION AND ORDER

Plaintiffs Craig Billie, Dawn Billie, Sara DeLucio, Janet Hopman, Andrew

Kittl, Sharon Kittl, Donald Mladic, Susan Mladic, Gerard Sabo, Donna Sabo, Todd

Stonitsch, and Rebecca Stonitsch allege the Village of Channahon (“the Village”), as

well as several of its Trustees and employees (James Bowden, Wayne Chesson,

Joseph Cook, Jr., Edward Dolezal, Thomas Durkin, Samuel Greco, Chantal Host,

Scott McMillian, Thomas Pahnke,1 Patricia Perinar, Mark Scaggs, Janet

Schumacher, David Silverman, and Scott Slocum, Jr., together “the individual

Defendants”) violated their federal constitutional and statutory rights under the

Takings Clause of the Fifth Amendment, the National Flood Insurance Act of 1968

(“NFIA”), 42 U.S.C. § 4001 et seq., and the Flood Disaster Protection Act of 1973

(“FDPA”), 42 U.S.C. § 4002. Count I is a Monell claim brought pursuant to 42 U.S.C.

1 On April 19, 2021 the Court granted the Defendants leave to substitute a party for Thomas Pahnke,

recently deceased. (Dkt. 59). Plaintiffs have filed a Second Amended Complaint naming the

administrator of Pahnke’s estate, Jeffrey D. Corso, as a Defendant. (Dkt. 60). For the sake of clarity,

the Court will continue to refer to Pahnke in this order.

§ 1983 alleging that the Village had a policy or practice of violating the federal

statutory rights and the Fifth Amendment rights of the Plaintiffs. Count II and III,

brought under § 1983, assert that the individual Defendants deprived Plaintiffs of

their Fifth Amendment rights to compensation for a taking and deprived the

Plaintiffs of federal statutory rights, respectively. Plaintiffs also raise state law

claims of inverse condemnation (Count IV), nuisance (Count V), and trespass (Count

VI) against the Village. Finally, Plaintiffs bring a claim for deprivation of the right of

access to the courts against all Defendants pursuant to § 1983 (Count VII). For the

reasons stated herein, Defendant’s motion to dismiss (Dkt. 41) is granted.

I. Background

The following factual allegations are taken from the corrected Amended

Complaint (Dkt. 35) and are accepted as true for purposes of this motion to dismiss.

See W. Bend Mut. Ins. Co. v. Schumacher, 844 F.3d 670, 675 (7th Cir. 2016). Plaintiffs

own homes in a Channahon, Illinois subdivision called Indian Trails North. Plaintiffs’

homes are located in or around the FEMA-designated DuPage River Special Flood

Hazard Area (“SFHA”).2 When the water table around the DuPage River rises, their

basements are flooded with water for several reasons. First, the basements were

constructed at a depth of between 518 and 520 feet above the National Geodetic

Vertical Datum (a standardized measure of elevation based on sea level) in an area

where the base flood elevation is only 524 feet and the water table is only eight to ten

2 The Amended Complaint states that “Lots 13 through 21 were within the SFHA.” (Dkt. 35, ¶ 58).

This means that the lots belonging to Donald Mladic and Susan Mladic (Lot 11), as well as the lot

belonging to Gerard Sabo and Donna Sabo (Lot 12) are outside of the SFHA. Id.

feet below ground. Second, the Channahon Dam impedes the flow of the river. And

third, the soil is porous. The Plaintiffs’ basements flooded in 1996, 2001, 2007, twice

in 2008, 2009, 2013, 2017, and 2020.

A. Relevant Statutes

Plaintiffs invoke various statutes as the bases for their claims. The National

Flood Insurance Act of 1968 (“NFIA”) codified at 42 U.S.C. § 4001 et seq. created a

national flood insurance program and empowered a Federal Insurance Adjuster to

enact regulations that would reduce future losses to flood damage. At all times

relevant to this case the Village participated in the National Flood Insurance

Program.

Congress later passed the Flood Disaster Protection Act of 1973 (“FDPA”)

codified at 42 U.S.C. § 4002, which required “[s]tates or local communities, as a

condition of future Federal financial assistance, to participate in the flood insurance

program and to adopt adequate flood plan ordinances with effective enforcement

provisions consistent with Federal standards to reduce or avoid future flood losses.”

§ 4002(b)(3). These “adequate ordinances” would require that participating

municipalities “[r]eview all permit applications to determine whether proposed

building sites will be reasonably safe from flooding” and require certain construction

standards in flood-prone areas, 44 C.F.R. § 60.3(a)(3) 51 Fed. Reg. 30,307 (Aug. 25,

1986), “[o]btain the elevation (in relation to mean sea level) of the lowest floor

(including basement) of all new and substantially improved structures” in areas

designated as flood-prone by the federal government, and “[m]aintain a record of all

such information with the official designated by the community.” 44 C.F.R.

§ 60.3(b)(5) 51 Fed. Reg. 30,307 (Aug. 25, 1986). Participating municipalities also had

to require that any construction in flood-prone areas be above certain depths, 44

C.F.R. § 60.3(c)(7), and prohibit new construction in some flood-prone areas without

hydrologic studies. 44 C.F.R. § 60.3(d)(3).

On April 6, 1992, the Village Board of Trustees passed Ordinance 703,

requiring that the Village “comply with the rules and regulations of the National

Flood Insurance Program codified at 44 CFR 59-79, as amended.” Defendant Thomas

Pahnke, the Building and Zoning Officer, was tasked with enforcing this ordinance.

He was required to “[e]nsure that all development activities within the [flood-prone

areas] of the jurisdiction of the Village meet the requirements of this Ordinance” and

“[i]nspect all development projects before, during and after construction to assure

proper elevation of the structure and to ensure they comply with the provisions of

this Ordinance.” Ordinance 703, § 505.0–506.0.

B. Chronology of Events

On September 29, 1992, the Village Board of Trustees voted to approve

construction of the Indian Trails North subdivision.3 A few months later Village

Attorney Silverman either drafted or approved an agreement annexing the

subdivision to the Village, and on November 16, 1992 that annexation was approved

by the Board. Between September of 1993 and August of 1994 building permit

applications were filed for each of the Plaintiffs’ homes. Defendants Pahnke and

3 The Complaint does not indicate which Defendants constituted the Board at this time.

Silverman, the Building and Zoning Officer and the Village Attorney, reviewed these

applications. They did not require any hydrological analyses, any special inspection,

permitting, or certification for construction in flood-prone areas, and Plaintiffs assert

that their actions were not in compliance with the federal regulations that Ordinance

703 was designed to implement. Each of the Plaintiffs (or their predecessors in

interest) were granted a building permit.

In 1996, the basements at Indian Trails flooded for the first time. Former

Village President Chesson, Trustee Greco, and several FEMA representatives visited

the subdivision to view the damage. The Amended Complaint alleges that during

conversations with these FEMA representatives Chesson and Greco “came to believe

[. . .] the basement floor elevations may have been too deep.” (Dkt. 35 at ¶ 76).

In March of 1998, the Village asked FEMA to remove several empty Indian

Trails lots from the SFHA so that they could be developed.4 Village President Chesson

received a response from FEMA on March 29, 1998. It partially approved the Village’s

request, removing certain empty lots from the SFHA. The letter also noted that

construction on those empty lots “remain[ed] subject to Federal, State, and local

regulations for floodplain management.” (Id. at ¶ 79). FEMA “encourage[d]” the

Village to “require that the lowest adjacent grade and lowest floor (including

basement / crawl space) elevations of any structure placed on [the empty lots that had

been removed from the SFHA] be elevated to a level at or above the base flood

elevation of 525.5 feet.” (Id. at ¶ 79). FEMA also denied the Village’s request in part,

4 These lots do not belong to the Plaintiffs.

keeping some empty lots in the SFHA. Plaintiffs allege that this letter caused former

Village President Chesson, Attorney Silverman, Village Administrator Bowden,

Trustee Greco, Building and Zoning Officer Pahnke, and Director of Public Works

Dolezal to “kn[ow] [. . .] that Lot 11–17 basement floor elevations were too deep and

violated Ordinance 703 and 44 C.F.R. §§ 59.1–60.26.” (Id. at ¶ 82). Plaintiffs also

allege that these Defendants therefore knew that the Plaintiffs’ homes “would

continue without end to have basement flooding.” (Id. at ¶ 83). Plaintiffs assert that

despite this knowledge Defendants engaged in a “conspiracy of silence” and failed to

alert Plaintiffs or their predecessors in interest of the danger of continued flooding.

(Id. at ¶ 84). Various other Defendants not then in office, including Trustee

McMillian, Trustee Slocum, former Village President Cook, Village President

Schumacher, Trustee Host, Trustee Perinar, Trustee Scaggs, and Village

Administrator Durkin are also alleged to have participated in this conspiracy of

silence after learning of the ongoing danger of flooding.

After experiencing flooding in 2001, 2007, and 2008 Indian Trails residents

asked the Village to investigate the problem. The Village hired an engineering firm

“to determine the causes for significant basement flooding” and “propose potential

solutions.” (Id. at ¶ 96). The resulting report was received by then-Village President

Cook and Director of Public Works Dolezal in 2009. It noted that a combination of

factors including the low elevations of the basements, downstream impediments to

water flow at the Channahon Dam,5 and porous soil were responsible for the flooding.

5 This is apparently a pre-existing structure operated by the Illinois Department of Natural Resources.

The report did not investigate the permitting process or the conduct of any Village

officials. It recommended that the Village work with the Illinois Department of

Natural Resources (“IDNR”) to divert water from the Dam, and that the Village

construct a concrete barrier to stop surface runoff from reaching the water table. On

October 5, 2009 the Board voted to have the engineering firm create a hydraulic

model of these proposed solutions.

On October 9, 2009, Plaintiff Dawn Billie wrote to then-Village President Cook

asking that the Village buy Dawn and Craig Billie’s home, on the grounds that it had

approved construction of a basement that was deeper than 524 feet base flood

elevation. President Cook replied, copying Attorney Silverman (who may also have

reviewed or revised the email), Village Administrator Bowden, and Director of Public

Works Dolezal. Cook stated he had “asked [his] staff to investigate” the flooding, and

that this investigation had “not shown that a single state or village regulation was

broken, bent, or overlooked in the approval of any of the homes in question.” (Id. at

¶ 110). It also stated that the Billies’ lot had been “removed from the ‘Special Flood

Hazard Area’ (SFHA) by the Illinois Department of Natural Resources” and that

therefore the property had not been subject to “any state regulations involving

‘Floodplain Development.’” (Id. at ¶ 113). President Cook’s reply finally noted that to

the best of his knowledge the lot had only been subject to state regulations at the time

of construction. Plaintiffs allege these three assertions were fraudulent.

In 2012, Plaintiff Donna Sabo contacted President Cook to inquire about the

status of the proposed Channahon Dam project. Cook responded that this project, a

collaboration with the IDNR, would “increase the level of protection for the study area

basements.” (Id. at ¶ 123). He also stated that the purpose of the 2009 engineer’s

report had been to “determine the cause and the feasibility of mitigating the

problem.” Id. According to Cook’s letter the Village had granted permits to the IDNR

for the construction of dam improvements, but that the IDNR had not made any

improvements and the permits had lapsed. Cook said the Village would reissue them

“without delay” upon the IDNR’s request. (Id. at ¶ 124).

After more flooding in 2013, the county government and the Army Corps of

Engineers did their own study of flooding along the DuPage River. In 2015, various

Plaintiffs and Director of Public Works Dolezal attended a public meeting held by the

Army Corps of Engineers. Plaintiffs’ homes were included in the Army Corps of

Engineers study after Plaintiff Donna Sabo provided proof of flooding and a copy of

the 2009 report commissioned by the Village.

In 2017, the Plaintiffs’ basements flooded once again. Plaintiff Dawn Billie

wrote to newly elected Village President Schumacher to complain that the Army

Corps of Engineers and the County had not made progress after their study, and that

the IDNR had not made any modifications to the Dam. President Schumacher, whose

own property had flooded, commiserated that this was “the inherent risk of living so

close to water,” a statement that the Plaintiffs characterize as false and deceptive.

(Id. at ¶ 139). She also said: “we will continue to look for and pursue viable remedies.”

Id. The Plaintiffs assert this statement was false because President Schumacher

“knew there were no [. . .] basement flooding solutions or remedies.” Id.

In 2018, Plaintiff Dawn Billie emailed President Schumacher again, blaming

the Village for another bout of flooding. President Schumacher reiterated that the

Village had “followed engineering standards” and that flooding was one of the

“inherent risks of living so close to water.” (Id. at ¶ 1246). Billie forwarded this

correspondence to Trustee Slocum.

In 2019, the Army Corps of Engineers released the results of its multi-year

study, concluding that it would not build the proposed concrete barrier to protect the

Indian Trails subdivision because it did not meet certain cost-benefit requirements.

In 2020, Plaintiff Dawn Billie attended a Village Board of Trustees meeting

attended by President Schumacher, Trustee Greco, Trustee Host, Trustee McMillian,

Trustee Perinar, Trustee Scaggs, and Trustee Slocum, Director of Public Works

Dolezal, Village Administrator Durkin, and Attorney Silverman. At that meeting

Billie asserted that the Village had failed to comply with 44. C.F.R. § 60.3 when it

permitted the construction of the Plaintiffs’ homes. Director Dolezal also spoke at this

meeting, acknowledging that the flooding was caused by the rising water table and

porous soil, but denying that the Village had violated Ordinance 703 or any federal

regulation, and asserting that Attorney Silverman had rendered the same judgment.

After a final buyout request was made and denied in 2020, the Plaintiffs

brought suit against the Village and the individual Defendants.

II. Standard

A motion to dismiss tests the sufficiency of a complaint, not the merits of the

case. See Gibson v. City of Chi., 910 F.2d 1510, 1520 (7th Cir. 1990). “To survive a

motion to dismiss under Rule 12(b)(6), the complaint must provide enough factual

information to state a claim to relief that is plausible on its face and raise a right to

relief above the speculative level.” Haywood v. Massage Envy Franchising, LLC, 887

F.3d 329, 333 (7th Cir. 2018) (quotations and citation omitted). See also Fed. R. Civ.

P. 8(a)(2) (requiring a complaint to contain a “short and plain statement of the claim

showing that the pleader is entitled to relief.”). A court deciding a Rule 12(b)(6)

motion accepts plaintiff’s well-pleaded factual allegations as true and draws all

permissible inferences in plaintiff’s favor. See Fortres Grand Corp. v. Warner Bros.

Entm't Inc., 763 F.3d 696, 700 (7th Cir. 2014). A plaintiff need not plead “detailed

factual allegations”, but “still must provide more than mere labels and conclusions or

a formulaic recitation of the elements of a cause of action for her complaint to be

considered adequate under Federal Rule of Civil Procedure 8.” Bell v. City of Chi.,

835 F.3d 736, 738 (7th Cir. 2016) (citation and internal quotation marks omitted).

Dismissal for failure to state a claim is proper “when the allegations in a

complaint, however true, could not raise a claim of entitlement to relief.” Bell Atl.

Corp. v. Twombly, 550 U.S. 544, 558, 127 S. Ct. 1955, 1966 (2007). Deciding the

plausibility of the claim is “‘a context-specific task that requires the reviewing court

to draw on its judicial experience and common sense.’” McCauley v. City of Chi., 671

F.3d 611, 616 (7th Cir. 2011) (quoting Ashcroft v. Iqbal, 556 U.S. 662, 679, 129 S. Ct.

1937, 1950 (2009)).

III. Analysis

A. Federal Claims

Plaintiffs bring four federal claims, each pursuant to 42 U.S.C. § 1983, alleging

that the Defendants violated their federal statutory and constitutional rights while

acting under color of law. See Gonzaga Univ. v. Doe, 536 U.S. 273, 279 (2002) (“§ 1983

actions may be brought against state actors to enforce rights created by federal

statutes as well as by the Constitution.”). Count I, the Monell claim, alleges the

Village had a policy or practice of “den[ying] each plaintiff just compensation for the

physical invasion” by flood water into their basements. (Dkt. 35 at ¶ 164). The Court

understands this to be a Fifth Amendment claim.6 Count I also asserts the Village

had a policy or practice of “failing to obtain and/or maintain complete records.” The

Plaintiffs do not clearly state that this is a violation of a federal statutory right, but

the Court understands this to be their contention because they also describe the

Village concealing the violation of federal regulations.

Count II alleges that the individual Defendants deprived Plaintiffs of just

compensation in violation of the Fifth Amendment, while Count III alleges that the

individual defendants engaged in “federal statutory violations” by failing to comply

with 44 C.F.R. §§ 59.1–60.26. Defendants make various arguments in favor of

dismissal.

6 The Defendants argued Count I may be a due process claim or an access to the courts claim. (Dkt. 51

at 1). Plaintiffs did not respond to the due process argument, so the Court considers any due process

claim waived by the Plaintiffs. Plaintiffs made it clear in their response brief that Count I was not a

“backwards looking denial of access claim.” (Dkt. 49, 6).

1. Counts I and III: Federal Statutory or Regulatory Claims

Plaintiffs accuse Defendants of failing to comply with certain federal flood

regulations and concealing violations of the Ordinance 703 and 44 C.F.R. §§ 59.1 –

60.26. (Dkt. 35, ¶¶ 160, 177, 179). Section 1983 is not a remedy for violations of state

or local laws so Ordinance 703 cannot give rise to a federal cause of action. See Scott

v. Edinburg, 346 F.3d 752, 760 (7th Cir. 2003). Plaintiffs can assert a violation of

federal statutory rights under Section 1983. However, in order to state a claim upon

which relief can be granted, a private right of action must have been created under

the pertinent statute, here: the National Flood Insurance Act of 1968 (“NFIA”), 42

U.S.C. § 4001 et seq., or the Flood Disaster Protection Act of 1973 (“FDPA”), 42 U.S.C.

§ 4002. See Blessing v. Freestone, 520 U.S. 329, 340 (1997) (“to seek redress through

§ 1983 [. . .] a plaintiff must assert the violation of a federal right, not merely a

violation of federal law) (emphasis original).

Plaintiffs object that this inquiry is premature at the motion to dismiss stage

but cite no case law supporting this argument. The Court disagrees. Whether a

federal statute or regulation creates a right cognizable under § 1983 and therefore a

cause of action is not an inquiry that fact discovery would shed any light on. It is

“basically a matter of statutory construction.” Simpson v. Reynolds Metals Co., 629

F.2d 1226, 1238 (7th Cir. 1980) (citing Transamerica Mortgage Advisors, Inc. v.

Lewis, 444 U.S. 11 (1979)). District courts frequently make such determinations when

deciding motions to dismiss. See, e.g., Shebley v. United Cont’l Holdings, Inc., 357 F.

Supp. 3d 684, 690 (N.D. Ill. 2019) (finding no private right of action in § 40127(a) of

the ADA and granting motion to dismiss); Bhattacharya v. Chicago Hous. Auth., No.

14 C 9693, 2017 WL 1197095, at *1 (N.D. Ill. Mar. 31, 2017) (determining whether

§ 1437a of the United States Housing Act created a private right of action at the

motion to dismiss stage).

To determine whether a statute creates a private right of action, courts

consider (i) whether the statute was enacted to benefit a special class to which the

plaintiffs belong; (ii) the statute’s legislative history; (iii) whether a private remedy

should be implied as necessary or helpful to the accomplishment of the statutory

purpose or should not be implied if doing so frustrates the underlying purpose for the

legislative scheme; and (iv) whether the subject matter is principally a concern of the

States.7 See Cannon v. University of Chicago, 441 U.S. 677, 689 (1979) (citing Cort v.

Ash, 422 U.S. 66, 78–85 (1975)). These are subjects upon which Congress and other

courts have opined, and which the parties to this case have briefed, so they are ripe

for this Court’s consideration.

i. Special class of plaintiffs

The NFIA says that

flood disasters have created personal hardships and economic distress which

have required unforeseen disaster relief measures and have placed an

increasing burden on the Nation’s resources, [which necessitates] sharing the

risk of flood losses [and eventually] making flood insurance coverage available

on reasonable terms and conditions to persons who have need for such

protection.

7 Neither party addresses this fourth factor in their briefs, and the Court finds that in any case the

first three factors are dispositive.

42 U.S.C.A. § 4001 (emphasis added). Plaintiffs do appear to be “persons in need of

such protection,” and were intended to benefit from this Act. However, the Act

appears equally concerned with the resources of “the Nation” that were being spent

on flood relief. Likewise, the FDPA states

it is in the public interest for persons already living in flood-prone areas to have

both an opportunity to purchase flood insurance and access to more adequate

limits of coverage, so that they will be indemnified, for their losses in the event

of future flood disasters.

42 U.S.C. § 4002 (emphasis added). Plaintiffs are persons living in flood-prone areas,

but once again they are only singled out as a class of individuals who require

insurance coverage to safeguard “the public interest.” This language provides

evidence that Congress intended to protect a special class of plaintiffs that includes

the Plaintiffs, but no evidence that this protection would take the form of a private

cause of action.

ii. Legislative history

Neither party directs the Court to any relevant legislative history. In Mid-

American National Bank of Chicago v. First Savings & Loan Ass’n of S. Holland, the

Seventh Circuit conducted “an analysis of the legislative history and purpose” of the

NFIA and found “that the primary purpose behind the Flood Program was to

diminish, by implementation of sound land use practices and flood insurance, the

massive burden on the federal treasury of escalating federal flood disaster

assistance.” 737 F.2d 638, 642 (7th Cir. 1984). The court therefore declined to find

that insured homeowners had an implied right of action against mortgage providers

who had failed to inform them that the homes they were purchasing were in flood

plains and did not require them to purchase flood insurance. Although this case dealt

with a different section of the NFIA its reasoning is instructive, as is the legislative

history it cites. The Mid-American court quoted House Report No. 1585, which

“addressed the purposes and objectives of the Flood Program” saying:

Heavy losses over the years from hurricanes in the coastal areas and from

storms in inland areas of the Nation dramatize the lack of insurance protection

against flood damage. [. . .] Communities along the seacoast or in a river basin

become completely immobilized following a major flood. Usually they must

depend on the Federal Government and voluntary relief agencies to provide

various forms of assistance. Some State and local governments have limited

programs to assist a flood-stricken area, but disaster relief from all of these

sources is inadequate to provide for the necessary restoration of heavily

damaged areas. These facts underline the need for a program which will make

insurance against flood damage available, encourage persons to become aware

of the risk of occupying the flood plains, and reduce the mounting Federal

expenditures for disaster relief assistance.

Id. at fn. 9, citing H.R.Rep. No. 1585, 90th Cong., 2d Sess., reprinted in [1968] U.S.

Code Cong. & Ad. News 2873, 2966–2967 (emphasis added). This legislative history

contains no language to suggest that Congress intended to create a private right of

action for homeowners against municipal governments based on flooding.

iii. Statutory purpose

The stated purposes of the FDPA are to:

(1) substantially increase the limits of coverage authorized under the national

flood insurance program; (2) provide for the expeditious identification of, and

the dissemination of information concerning, flood-prone areas; (3) require

States or local communities, as a condition of future Federal financial

assistance, to participate in the flood insurance program and to adopt adequate

flood plain ordinances with effective enforcement provisions consistent with

Federal standards to reduce or avoid future flood losses; and (4) require the

purchase of flood insurance by property owners who are being assisted by

Federal programs or by federally supervised, regulated, or insured agencies or

institutions in the acquisition or improvement of land or facilities located or to

be located in identified areas having special flood hazards.

42 U.S.C. § 4002. Similarly, the self-professed purpose of the NFIA was to

authorize a flood insurance program by means of which flood insurance, over

a period of time, can be made available on a nationwide basis through the

cooperative efforts of the Federal Government and the private insurance

industry.

42 U.S.C.A. § 4001. Again there is nothing in these statements of purpose to suggest

that Congress intended to create a private cause of action of the sort the Plaintiffs

are advancing.8 Moreover, the regulations Plaintiffs rely on are merely best practices

for flood management that municipalities must implement in order to receive federal

funds from the National Flood Insurance Program. Plaintiffs make no argument and

cite no case law to support the notion that the CFR sections cited create a private

right of action. Cf., Alexander v. Sandoval, 532 U.S. 275, 289 (2001) (when a statutory

imperative is “phrased as a directive to federal agencies engaged in the distribution

of public funds,” [. . .] “[t]here [is] far less reason to infer a private remedy in favor of

individual persons”) (quotations and citations omitted).

To summarize, none of these factors suggest that the NFIA or the FDPA

created a private right of action for homeowners against municipalities that fail to

follow federal flood regulations. Plaintiffs attempt to distinguish the cases

Defendants cite where courts have held that various statutes did not impliedly create

8 See Mid-American National Bank of Chicago v. First Savings & Loan Ass’n of S. Holland, 737 F.2d

638, 642 (7th Cir. 1984) (citing 42 U.S.C. §§ 4053, 4072, and 4104(f), which allow flood insurance

policyholders to sue insurers and homeowners to petition in federal court for a change in their flood-

hazard zone for the proposition that when Congress intends to create a private cause of action under

the NFIA and FDPA, it did so explicitly.).

private rights of action.9 But Plaintiffs cite to no cases in which a court has found that

the FDPA or the NFIA impliedly created a private cause of action. More importantly,

they can point to no part of these statutes or their legislative histories supporting the

existence of such a right. Count III is dismissed with prejudice, and Count I is

dismissed with prejudice to the extent that it alleges violations of the FDPA or the

NFIA.

2. Counts I and II: Fifth Amendment Taking Claims

The Takings Clause of the Fifth Amendment cautions that “private property

[shall not] be taken for public use, without just compensation.” U.S. Const. Amend.

V. This clause is “designed to bar Government from forcing some people alone to bear

public burdens which, in all fairness and justice, should be borne by the public as a

whole.” Arkansas Game & Fish Comm’n v. United States, 568 U.S. 23, 31 (2012). The

Supreme Court acknowledges that certain government actions are always a taking,

such as the “permanent physical occupation of property” and the implementation of

“a regulation that permanently requires a property owner to sacrifice all economically

beneficial uses of his or her land.” Id. But “most takings claims turn on situation-

specific factual inquiries.” Id. at 31–32.

Plaintiffs argue that under Arkansas Game & Fish Comm’n v. United States,

they have adequately pled a Fifth Amendment taking. 568 U.S. 23 (2012). In

9 See, e.g., United States v. St. Bernard Parish, 756 F.2d 1116 (5th Cir. 1985); Mid-Am. Nat’l Bank v.

First Sav. & Loan Ass’n, 737 F.2d 638, 640 (7th Cir. 1984); Hofbauer v. Nw. Nat’l Bank of Rochester,

700 F.2d 1197, 1200 (8th Cir. 1983); Arvai v. First Fed. Sav. & Loan Ass’n, 698 F.2d 683 (4th Cir.1983);

Harris v. Nationwide Mut. Fire Ins. Co., 832 F.3d 593, 596 (6th Cir. 2016); Emody v. Manning, No. 11-

42-DLB, 2011 WL 6258300, at *5 (E.D. Ky. Dec. 15, 2011).

Arkansas Game & Fish the Supreme Court reviewed the actions of the Army Corps

of Engineers, which many years before had built a dam downstream from timber

managed by the Arkansas Game & Fish Commission. The Corps “determine[d] the

rates at which water would be released from the Dam” and for several years slowed

the rate of release (as compared to years prior and the recommendations in their

official Manual), so as to prolong the growing season for farmers below the Dam. Id.

at 27. This caused flooding that interfered with the growth of hardwood trees. Id. at

28. The Supreme Court held “that recurrent floodings, even if of finite duration, are

not categorically exempt from Takings Clause liability.” Id. at 27.

Based on this holding, it appears that flooding of the sort experienced by the

Plaintiffs could be actionable under the Takings Clause. But it does not necessarily

follow that the Plaintiffs state a plausible claim against the Defendants. The

defendants in Arkansas Game & Fish caused the flooding: first by constructing the

dam then by altering the release of water from the dam. This was significant to the

Court, which considered “the degree to which the invasion is intended or is the

foreseeable result of authorized government action” to be highly relevant, Id. at 39,

since flooding must be “government-induced” in order to be compensable. Id. at 34.

Plaintiffs’ flooding was arguably foreseeable when Defendant Pahnke granted them

the permits they requested without following Ordinance 703. But Defendants did not

induce the flooding. They permitted the Plaintiffs and their predecessors in interest

to build on their own property. Plaintiffs propose reading the required “government

action” out of the equation. Although they attempt to distinguish the Defendants’

cases to the contrary,10 Plaintiffs provide no case other than Arkansas Game & Fish

in support of their position. And Arkansas Game & Fish requires government action

that “induced” the taking.

Counts I and II are dismissed for failure to state a claim.

3. Count VII: Denial of Access

Count VII alleges a denial of access to the courts perpetrated by all Defendants.

Plaintiffs say that, should the other federal claims (Counts, I, II, and III) be time-

barred, “the loss of each such claim represents a deprivation of each plaintiff’s rights

of access to the courts, in violation of the First, Fifth, and Fourteenth Amendments.”

(Dkt. 35, ¶ 203–04). The Court has not determined the other federal counts (Counts

I, II, and III) are time-barred, but has found that Plaintiffs have failed to properly

state a federal claim.

In order to bring a denial of access claim under § 1983, Plaintiffs are required to

identify: “(1) a nonfrivolous, underlying claim; (2) the official acts frustrating the

10 See, e.g., St. Bernard Par. Gov't v. United States, 887 F.3d 1354, 1357 (Fed. Cir. 2018) (plaintiffs

“claimed that the government was liable for flood damage to their properties caused by Hurricane

Katrina” because the state had failed to keep flood protection infrastructure in good repair, but the

court held that “the government cannot be liable on a takings theory for inaction”); Petersen v. Dane

Cnty., 136 Wis. 2d 501, 505–07 (Ct. App. 1987) (Plaintiff may not claim his land has been taken when

the condition that devalues his lot was created by his predecessor in title); Sorrells v. City of Macomb,

2015 IL App (3d) 140763 (municipality’s failure to follow “applicable drainage standards, engineering

standards, laws and ordinances” was not a taking because flooding was caused by private developers);

Sik v. Verhelst Bros., No. A09-329, 2009 WL 4573827, at *2–3 (Minn. Ct. App. Dec. 8, 2009) (county’s

failure to enforce a conditional-use permit did not constitute a taking); Dugan v. Town of Paradise

Valley, No. 1 CA-CV 10-0133, 2011 WL 1483724, at *4 (Ariz. Ct. App. Apr. 19, 2011) (failure to enforce

regulations governing neighbor’s land use did not constitute a regulatory taking); Welgosh v. City of

Novi, 2015 WL 1261470 (Mich. Ct. App. Mar. 19, 2015) (municipality’s failure to enforce building code

was not inverse condemnation although basement flooding followed); and Bargmann v. Neb. Dep’t of

Roads, 257 Neb. 766, 774-75 (1999) (allegations that governmental entity allowed third parties to

construct obstruction within a floodplain which caused plaintiff’s property to flood did not constitute

a taking).

litigation; and (3) a remedy that may be awarded as recompense but that is not

otherwise available in a suit or settlement.” Harer v. Casey, 962 F.3d 299, 308 (7th

Cir. 2020) (citations omitted). Plaintiffs fail on the first prong as they are unable to

establish a nonfrivolous federal claim. Count VII is dismissed.

B. State Claims

Recognizing the particularly local nature of this dispute, and having dismissed

all federal claims, the Court will relinquish supplemental jurisdiction over the state

claims (inverse condemnation, nuisance, and trespass). The Court may do so at its

discretion, if “the district court has dismissed all claims over which it has original

jurisdiction.” 28 U.S.C. § 1367.

IV. Conclusion

For the stated reasons, Defendants’ motion to dismiss (Dkt. 41) is granted.

Count I is dismissed with prejudice to the extent that it alleges violations of the FDPA

or the NFIA. Count III is dismissed with prejudice. Plaintiffs have until July 6, 2021

to file an amended complaint consistent with this opinion or judgment will enter.

ENTER:

Dated: June 7, 2021 [Vi but L/

“MARYM.ROWLAND

United States District Judge

"Winding Plaintiffs have failed to state a federal claim, the Court does not address defendants’ statute

of limitation arguments, qualified and legislative immunity arguments, and Plaintiffs’ failure to plead

personal involvement of each individual defendant for section 1983 purposes.

20

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.