# 48 CFR § 44.201-2: 44.201-2 Advance notification requirements

> Federal · Regulations · In force

URL: https://www.frixlaw.com/law-library/statutes/ecfr-48-44.201-2

## Section

- **Citation:** 48 CFR § 44.201-2
- **Heading:** 44.201-2 Advance notification requirements
- **Jurisdiction:** Federal
- **Kind:** Regulations
- **Status:** In force
- **Text as of:** September 22, 2026
- **Source:** Publisher's official text
- **Location:** Title 48—Federal Acquisition Regulations System > CHAPTER 1—FEDERAL ACQUISITION REGULATION > SUBCHAPTER G—CONTRACT MANAGEMENT > PART 44—SUBCONTRACTING POLICIES AND PROCEDURES > Subpart 44.2—Consent to Subcontracts

## Text

Under cost-reimbursement contracts, the contractor is required by statute to notify the contracting officer as follows:
(a) For the Department of Defense, the Coast Guard, and the National Aeronautics and Space Administration, unless the contractor maintains an approved purchasing system, 10 U.S.C. 3322(c) requires notification before the award of any cost-plus-fixed-fee subcontract, or any fixed-price subcontract that exceeds the greater of the simplified acquisition threshold or 5 percent of the total estimated cost of the contract.
(b) For civilian agencies other than the Coast Guard and the National Aeronautics and Space Administration, even if the contractor has an approved purchasing system, 41 U.S.C. 3905 requires notification before the award of any cost-plus-fixed-fee subcontract, or any fixed-price subcontract that exceeds either the simplified acquisition threshold or 5 percent of the total estimated cost of the contract.
[70 FR 11762, Mar. 9, 2005, as amended at 79 FR 24213, Apr. 29, 2014; 87 FR 73900, Dec. 1, 2022]

## Nearby sections

- [48 CFR § 44.101 44.101 Definitions.](https://www.frixlaw.com/law-library/statutes/ecfr-48-44.101.md)
- [48 CFR § 44.201-1 44.201-1 Consent requirements.](https://www.frixlaw.com/law-library/statutes/ecfr-48-44.201-1.md)
- [48 CFR § 44.201-2 44.201-2 Advance notification requirements.](https://www.frixlaw.com/law-library/statutes/ecfr-48-44.201-2.md)
- [48 CFR § 44.202-1 44.202-1 Responsibilities.](https://www.frixlaw.com/law-library/statutes/ecfr-48-44.202-1.md)
- [48 CFR § 44.202-2 44.202-2 Considerations.](https://www.frixlaw.com/law-library/statutes/ecfr-48-44.202-2.md)
- [48 CFR § 44.203 44.203 Consent limitations.](https://www.frixlaw.com/law-library/statutes/ecfr-48-44.203.md)
- [48 CFR § 44.204 44.204 Contract clauses.](https://www.frixlaw.com/law-library/statutes/ecfr-48-44.204.md)
- [48 CFR § 44.301 44.301 Objective.](https://www.frixlaw.com/law-library/statutes/ecfr-48-44.301.md)
- [48 CFR § 44.302 44.302 Requirements.](https://www.frixlaw.com/law-library/statutes/ecfr-48-44.302.md)
- [48 CFR § 44.303 44.303 Extent of review.](https://www.frixlaw.com/law-library/statutes/ecfr-48-44.303.md)
- [48 CFR § 44.304 44.304 Surveillance.](https://www.frixlaw.com/law-library/statutes/ecfr-48-44.304.md)
- [48 CFR § 44.305-1 44.305-1 Responsibilities.](https://www.frixlaw.com/law-library/statutes/ecfr-48-44.305-1.md)
- [48 CFR § 44.305-2 44.305-2 Notification.](https://www.frixlaw.com/law-library/statutes/ecfr-48-44.305-2.md)
- [48 CFR § 44.305-3 44.305-3 Withholding or withdrawing approval.](https://www.frixlaw.com/law-library/statutes/ecfr-48-44.305-3.md)

---

Source: Frix Law Library, https://www.frixlaw.com/law-library/statutes/ecfr-48-44.201-2. Check the current official text before relying on it. Not legal advice.