# WAC 194-50-050: WAC 194-50-050. ASHRAE Standard 100, 2018 — Section 5 — Energy management plan

> Washington · Regulations · In force

URL: https://www.frixlaw.com/law-library/statutes/STATE_WA_ADC_194_50_050

## Section

- **Citation:** WAC 194-50-050
- **Heading:** WAC 194-50-050. ASHRAE Standard 100, 2018 — Section 5 — Energy management plan
- **Jurisdiction:** Washington
- **Kind:** Regulations
- **Status:** In force
- **Text as of:** August 14, 2026
- **Source:** Compiled text
- **Location:** Washington Administrative Code / Title 194 / Chapter 194-50 / Section 194-50-050

## Text

Exception to 5.1.1 - Not adopted.
5.1.2.1 Energy accounting in accordance with Section 5.2.
5.1.2.2 In the initial year of compliance, the building's weather normalized energy use intensity (WNEUI) and energy use intensity (EUI) .
5.1.2.3 Annual updates of the net energy use, WNEUI and EUI .
5.1.2.4 Annual comparison of the net WNEUI and EUI to the energy target.
5.1.2.5 Documentation of original, current, and changes in number of occupants, weekly operating hours, or time of day scheduled for occupancy, production rates, and energy using equipment that would have caused change in the measured WNEUI and EUI .
Exceptions to 5.1.2.12:
1. Buildings and grouped buildings that meet the EUI t .
2. Buildings that have implemented a utility program lighting upgrade covering 75 percent of the building's GFA, within the previous five years, can use the lighting schedule provided by the utility program.
3. Tier 2 covered buildings.
4. Buildings not meeting the definition of covered building .
5.1.2.13 The current lighting satisfaction survey and lighting checklist as described in Appendix D of Performance Measurement Protocols for Commercial Buildings 1 or as approved by the AHJ .
Exceptions to 5.1.2.13:
1. Buildings and grouped buildings that meet the EUI t .
2. Buildings that have implemented a utility program lighting upgrade covering 75 percent of the building's GFA through a utility program within the previous five years.
3. Tier 2 covered buildings.
4. Buildings not meeting the definition of covered building .
5.1.2.14 Operations and Maintenance Plan including:
1. An operations and maintenance ( O&M ) program as defined in Section 6.
2. An O&M implementation plan as specified in Normative Annex L.
3. Implementation documentation as specified in L2.2.5 Documentation.
5.1.3 The EM shall provide access to the energy management plan to the building occupants annually
ing the definition of covered building .
5.1.2.14 Operations and Maintenance Plan including:
1. An operations and maintenance ( O&M ) program as defined in Section 6.
2. An O&M implementation plan as specified in Normative Annex L.
3. Implementation documentation as specified in L2.2.5 Documentation.
5.1.3 The EM shall provide access to the energy management plan to the building occupants annually.
5.2.1 Provide measured net energy use data for each covered building , including all forms of imported and exported energy from at least 12 consecutive months of data monitored in a period not to exceed two years prior to the efficiency audit. The net energy concept is illustrated in Figure 5-1, Table 5-1, Table 5-2 and is calculated in accordance with Section 5.2.4 as follows:
Building net energy use = (1a + 1b + 1c + 1d) – (3a + 3b + 3c + 3d + 3e)
Where 1a, 1b, 1c, and 1d are metered energy supplies that are used in the building (this includes bulk energy sources), and 3a, 3b, 3c, 3d, and 3e are metered energy excesses that are supplied to another building or grid as useful energy.
Table 5-2 Campus Energy Flow Definitions
Energy Input in to District Energy System(s) Energy Delivered to Buildings (other than from District Energy System(s)) Campus Renewable Energy Production Energy Exported from Campus for Beneficial Use 1a. Electrical 2a. Electrical 3a. Electrical 4a. Excess solar thermal 1b. Gas 2b. Gas 3b. Thermal 4b. Excess solar or wind electrical 1c. Bulk fuel 2c. Bulk fuel (coal/biomass/propane/oil) 3c. Waste heat 4c. Excess or recovered thermal energy 4d. Excess co-gen electrical 4e. Excess co-gen thermal
Energy Input in to District Energy System(s)
Energy Delivered to Buildings (other than from District Energy System(s))
Campus Renewable Energy Production
Energy Exported from Campus for Beneficial Use
1a. Electrical
2a. Electrical
3a. Electrical
4a. Excess solar thermal
1b. Gas
2b. Gas
3b. Thermal
4b. Excess solar or wind electrical
1c. Bulk fuel
2c. Bulk fuel (coal/biomass/propane/oil)
3c. Waste heat
4c
Input in to District Energy System(s)
Energy Delivered to Buildings (other than from District Energy System(s))
Campus Renewable Energy Production
Energy Exported from Campus for Beneficial Use
1a. Electrical
2a. Electrical
3a. Electrical
4a. Excess solar thermal
1b. Gas
2b. Gas
3b. Thermal
4b. Excess solar or wind electrical
1c. Bulk fuel
2c. Bulk fuel (coal/biomass/propane/oil)
3c. Waste heat
4c. Excess or recovered thermal energy
4d. Excess co-gen electrical
4e. Excess co-gen thermal
5.2.1.1 End use deductions. Where submetered from a building's meter, the following end use energy consumption may be deducted from the building's measured net energy use :
1. Electric vehicle charging equipment that transfers electricity to batteries or other energy storage devices in electric vehicles.
2. Electric loads related to broadcast antennas, on-site cell phone towers or other communications equipment that is unrelated to the primary purpose of the building .
3. The AHJ may add additional end use deductions based on technological advancements.
5.2.1.2 Connected buildings. Where energy use is not monitored at the covered building level:
1. Tier 1 covered buildings : Net energy use data may be provided at the connected building level.
2. Tier 2 covered buildings : Net energy use data shall be provided at the connected building level.
5.2.1.3 Campuses. Campuses with district energy systems use the campus net energy use outlined in Table 5-2. Provide measured net energy use data for the campus including all forms of imported and exported energy from at least 12 consecutive months of data monitored in a period not to exceed two years prior to the efficiency audit. Provide measured energy on the input side of the district energy system and include net energy use data for each covered building. Campus net energy use is calculated as follows:
Campus net energy use = (1a + 1b + 1c + 2a + 2b + 2c) – (4a + 4b + 4c + 4d + 4e)
5.2.1.4 Decarbonization plan
ast 12 consecutive months of data monitored in a period not to exceed two years prior to the efficiency audit. Provide measured energy on the input side of the district energy system and include net energy use data for each covered building. Campus net energy use is calculated as follows:
Campus net energy use = (1a + 1b + 1c + 2a + 2b + 2c) – (4a + 4b + 4c + 4d + 4e)
5.2.1.4 Decarbonization plan . Participating campuses' net energy use data shall include all buildings on the campus . Thermal energy for the campus shall be measured at the input side of the district energy system .
5.2.2 Energy use data for each type of energy imported into and exported from the building shall be collected from utility or energy delivery bills (that must include the quantity of energy or fuel delivered) or by monitoring local energy meters (either utility or owner-provided meters). Owner-provided energy meters shall meet the metering accuracy, tolerances and testing requirements of Title 480 WAC or WAC 51-11C-40904 (Section C409.4 of the WSEC ).
5.2.3 Energy conversion factors. The site energy content of different forms of purchased energy shall be converted from the purchased unit to the standard site energy unit using the conversion factors incorporated in Energy Star portfolio manager.
5.2.4 The energy accounting system shall be Energy Star Portfolio Manager as specified in Normative Annex Z.
5.2.4.1 - Not adopted.
5.2.4.2 - Not adopted.
5.2.4.3 - Not adopted.
Table 5-2a Site Energy Conversion Factors - Table not adopted.
Table 5-2b Primary Energy Conversion Factors - Table not adopted.

## Nearby sections

- [WAC 194-50-001 WAC 194-50-001. Foreword](https://www.frixlaw.com/law-library/statutes/STATE_WA_ADC_194_50_001.md)
- [WAC 194-50-010 WAC 194-50-010. ASHRAE Standard 100, 2018 — Section 1 — Purpose](https://www.frixlaw.com/law-library/statutes/STATE_WA_ADC_194_50_010.md)
- [WAC 194-50-020 WAC 194-50-020. ASHRAE Standard 100, 2018 — Section 2 — Scope](https://www.frixlaw.com/law-library/statutes/STATE_WA_ADC_194_50_020.md)
- [WAC 194-50-030 WAC 194-50-030. ASHRAE Standard 100, 2018 — Section 3 — Definitions](https://www.frixlaw.com/law-library/statutes/STATE_WA_ADC_194_50_030.md)
- [WAC 194-50-040 WAC 194-50-040. ASHRAE Standard 100, 2018 — Section 4 — Compliance requirements](https://www.frixlaw.com/law-library/statutes/STATE_WA_ADC_194_50_040.md)
- [WAC 194-50-050 WAC 194-50-050. ASHRAE Standard 100, 2018 — Section 5 — Energy management plan](https://www.frixlaw.com/law-library/statutes/STATE_WA_ADC_194_50_050.md)
- [WAC 194-50-060 WAC 194-50-060. ASHRAE Standard 100, 2018 — Section 6 — Operations and maintenance requirements](https://www.frixlaw.com/law-library/statutes/STATE_WA_ADC_194_50_060.md)
- [WAC 194-50-070 WAC 194-50-070. ASHRAE Standard 100, 2018 — Section 7 — Energy use analysis and target requirements](https://www.frixlaw.com/law-library/statutes/STATE_WA_ADC_194_50_070.md)
- [WAC 194-50-080 WAC 194-50-080. ASHRAE Standard 100, 2018 — Section 8 — Energy Audit Requirements](https://www.frixlaw.com/law-library/statutes/STATE_WA_ADC_194_50_080.md)
- [WAC 194-50-090 WAC 194-50-090. ASHRAE Standard 100, 2018 — Section 9 — Implementation and verification requirements](https://www.frixlaw.com/law-library/statutes/STATE_WA_ADC_194_50_090.md)
- [WAC 194-50-110 WAC 194-50-110. ASHRAE Standard 100, 2018 — Section 11 — References](https://www.frixlaw.com/law-library/statutes/STATE_WA_ADC_194_50_110.md)
- [WAC 194-50-120 WAC 194-50-120. Normative Annex C Forms](https://www.frixlaw.com/law-library/statutes/STATE_WA_ADC_194_50_120.md)
- [WAC 194-50-130 WAC 194-50-130. Normative Annex L — Operations and maintenance implementation](https://www.frixlaw.com/law-library/statutes/STATE_WA_ADC_194_50_130.md)
- [WAC 194-50-140 WAC 194-50-140. Normative Annex X — Investment criteria — This is a normative annex and is part of the Tier 1 covered building requirements of this standard](https://www.frixlaw.com/law-library/statutes/STATE_WA_ADC_194_50_140.md)

---