# OAR 860-082-0005: OAR 860-082-0005. Scope and Applicability

> Oregon · Regulations · In force

URL: https://www.frixlaw.com/law-library/statutes/STATE_OR_OAR_C860_D82_S860_082_0005

## Section

- **Citation:** OAR 860-082-0005
- **Heading:** OAR 860-082-0005. Scope and Applicability
- **Jurisdiction:** Oregon
- **Kind:** Regulations
- **Status:** In force
- **Text as of:** September 30, 2026
- **Source:** Compiled text
- **Location:** Oregon Administrative Rules / Chapter 860 Public Utility Commission / Division 82 SMALL GENERATOR INTERCONNECTION RULES / OAR 860-082-0005

## Text

(1) OAR 860-082-0005 through 860-082-0085 (the “small generator interconnection rules”) govern the interconnection of a small generator facility with a nameplate rating of 10 megawatts or less to a public utility’s transmission or distribution system. These rules do not apply if the interconnection between the small generator facility and the public utility is subject to the jurisdiction of the Federal Energy Regulatory Commission (FERC).
(2) Except as specified in OAR 860-082-0025(1)(b), the small generator interconnection rules do not apply retroactively to a small generator facility that was interconnected to a public utility’s transmission or distribution system prior to the effective date of the small generator interconnection rules (an “existing small generator facility”). These rules become applicable to an existing small generator facility at the expiration of the agreement governing the terms of the interconnection of the existing small generator facility to the interconnected public utility’s transmission or distribution system. If an existing agreement does not have an expiration date, then the small generator interconnection rules become applicable to the existing small generator facility 10 years after the effective date of the rules. An existing small generator facility must submit an application under OAR 860-082-0025(1)(e) to the interconnected public utility no later than 60 business days before the date that the small generator interconnection rules become applicable.
(3) Except where explicitly noted in OAR chapter 860, division 039, the small generator interconnection rules do not apply to the interconnection of a net metering facility, which is governed by OAR chapter 860, division 039.
(4) A small generator facility that qualifies as a “small power production facility” under OAR 860-029-0010(25) must also comply with the rules in OAR chapter 860, division 029. If there is a conflict between the small generator interconnection rules and the rules in OAR chapter 860, division 029, then the small generator interconnection rules control.

## Nearby sections

- [OAR 860-082-0005 OAR 860-082-0005. Scope and Applicability](https://www.frixlaw.com/law-library/statutes/STATE_OR_OAR_C860_D82_S860_082_0005.md)
- [OAR 860-082-0010 OAR 860-082-0010. Waiver](https://www.frixlaw.com/law-library/statutes/STATE_OR_OAR_C860_D82_S860_082_0010.md)
- [OAR 860-082-0015 OAR 860-082-0015. Definitions](https://www.frixlaw.com/law-library/statutes/STATE_OR_OAR_C860_D82_S860_082_0015.md)
- [OAR 860-082-0020 OAR 860-082-0020. Pre-Application Process](https://www.frixlaw.com/law-library/statutes/STATE_OR_OAR_C860_D82_S860_082_0020.md)
- [OAR 860-082-0025 OAR 860-082-0025. Applications to Interconnect a Small Generator Facility](https://www.frixlaw.com/law-library/statutes/STATE_OR_OAR_C860_D82_S860_082_0025.md)
- [OAR 860-082-0030 OAR 860-082-0030. Construction, Operation, Maintenance, and Testing of Small Generator Facilities](https://www.frixlaw.com/law-library/statutes/STATE_OR_OAR_C860_D82_S860_082_0030.md)
- [OAR 860-082-0033 OAR 860-082-0033. Export Controls](https://www.frixlaw.com/law-library/statutes/STATE_OR_OAR_C860_D82_S860_082_0033.md)
- [OAR 860-082-0035 OAR 860-082-0035. Cost Responsibility](https://www.frixlaw.com/law-library/statutes/STATE_OR_OAR_C860_D82_S860_082_0035.md)
- [OAR 860-082-0040 OAR 860-082-0040. Insurance](https://www.frixlaw.com/law-library/statutes/STATE_OR_OAR_C860_D82_S860_082_0040.md)
- [OAR 860-082-0045 OAR 860-082-0045. Tier 1 Interconnection Review](https://www.frixlaw.com/law-library/statutes/STATE_OR_OAR_C860_D82_S860_082_0045.md)
- [OAR 860-082-0050 OAR 860-082-0050. Tier 2 Interconnection Review](https://www.frixlaw.com/law-library/statutes/STATE_OR_OAR_C860_D82_S860_082_0050.md)
- [OAR 860-082-0055 OAR 860-082-0055. Tier 3 Interconnection Review](https://www.frixlaw.com/law-library/statutes/STATE_OR_OAR_C860_D82_S860_082_0055.md)
- [OAR 860-082-0060 OAR 860-082-0060. Tier 4 Interconnection Review](https://www.frixlaw.com/law-library/statutes/STATE_OR_OAR_C860_D82_S860_082_0060.md)
- [OAR 860-082-0063 OAR 860-082-0063. Supplemental Review](https://www.frixlaw.com/law-library/statutes/STATE_OR_OAR_C860_D82_S860_082_0063.md)

---

Source: Frix Law Library, https://www.frixlaw.com/law-library/statutes/STATE_OR_OAR_C860_D82_S860_082_0005. Check the current official text before relying on it. Not legal advice.