# COMAR 20.50.09.05: COMAR 20.50.09.05. Interconnection Request Processing Fees

> Maryland · Regulations · In force

URL: https://www.frixlaw.com/law-library/statutes/STATE_MD_COMAR_20_50_09_05

## Section

- **Citation:** COMAR 20.50.09.05
- **Heading:** COMAR 20.50.09.05. Interconnection Request Processing Fees
- **Jurisdiction:** Maryland
- **Kind:** Regulations
- **Status:** In force
- **Text as of:** August 14, 2026
- **Source:** Compiled text
- **Location:** Code of Maryland Regulations / Title 20 PUBLIC SERVICE COMMISSION / Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES / Chapter 09 Small Generator Facility Interconnection Standards / COMAR 20.50.09.05

## Text

A. A utility may only charge a small generator interconnection request fee for a Level 2, Level 3, or Level 4 interconnection request.
B. A utility may not charge interconnection request fees for interconnection requests determined to be under PJM Interconnection, LLC jurisdiction pursuant to Regulation .01 of this chapter .
C. The utility shall specify the interconnection [processing] request fees charged under this regulation in its tariff.

## Nearby sections

- [COMAR 20.50.09.01 COMAR 20.50.09.01. Scope](https://www.frixlaw.com/law-library/statutes/STATE_MD_COMAR_20_50_09_01.md)
- [COMAR 20.50.09.02 COMAR 20.50.09.02. Definitions](https://www.frixlaw.com/law-library/statutes/STATE_MD_COMAR_20_50_09_02.md)
- [COMAR 20.50.09.03 COMAR 20.50.09.03. Acceptable Standards](https://www.frixlaw.com/law-library/statutes/STATE_MD_COMAR_20_50_09_03.md)
- [COMAR 20.50.09.04 COMAR 20.50.09.04. Interconnection Requests](https://www.frixlaw.com/law-library/statutes/STATE_MD_COMAR_20_50_09_04.md)
- [COMAR 20.50.09.05 COMAR 20.50.09.05. Interconnection Request Processing Fees](https://www.frixlaw.com/law-library/statutes/STATE_MD_COMAR_20_50_09_05.md)
- [COMAR 20.50.09.06 COMAR 20.50.09.06. General Requirements](https://www.frixlaw.com/law-library/statutes/STATE_MD_COMAR_20_50_09_06.md)
- [COMAR 20.50.09.07 COMAR 20.50.09.07. Certified and Approved Equipment](https://www.frixlaw.com/law-library/statutes/STATE_MD_COMAR_20_50_09_07.md)
- [COMAR 20.50.09.08 COMAR 20.50.09.08. Determination of Interconnection Jurisdiction and Level of Utility Review of Interconnection Request](https://www.frixlaw.com/law-library/statutes/STATE_MD_COMAR_20_50_09_08.md)
- [COMAR 20.50.09.09 COMAR 20.50.09.09. Level 1 Review](https://www.frixlaw.com/law-library/statutes/STATE_MD_COMAR_20_50_09_09.md)
- [COMAR 20.50.09.10 COMAR 20.50.09.10. Level 2 Review](https://www.frixlaw.com/law-library/statutes/STATE_MD_COMAR_20_50_09_10.md)
- [COMAR 20.50.09.11 COMAR 20.50.09.11. Level 3 Review](https://www.frixlaw.com/law-library/statutes/STATE_MD_COMAR_20_50_09_11.md)
- [COMAR 20.50.09.12 COMAR 20.50.09.12. Level 4 Study Review](https://www.frixlaw.com/law-library/statutes/STATE_MD_COMAR_20_50_09_12.md)
- [COMAR 20.50.09.13 COMAR 20.50.09.13. Dispute Resolution](https://www.frixlaw.com/law-library/statutes/STATE_MD_COMAR_20_50_09_13.md)
- [COMAR 20.50.09.14 COMAR 20.50.09.14. Record Retention and Reporting Requirements](https://www.frixlaw.com/law-library/statutes/STATE_MD_COMAR_20_50_09_14.md)

---

Source: Frix Law Library, https://www.frixlaw.com/law-library/statutes/STATE_MD_COMAR_20_50_09_05. Check the current official text before relying on it. Not legal advice.