# 62 Ill. Adm. Code 1816.22: Section 1816.22 Topsoil and Subsoil

> Illinois · Regulations · In force

URL: https://www.frixlaw.com/law-library/statutes/STATE_IL_IAC_T62_P1816_S1816_22

## Section

- **Citation:** 62 Ill. Adm. Code 1816.22
- **Heading:** Section 1816.22 Topsoil and Subsoil
- **Jurisdiction:** Illinois
- **Kind:** Regulations
- **Status:** In force
- **Text as of:** August 14, 2026
- **Source:** Compiled text
- **Location:** Illinois Administrative Code / Title 62 MINING / CHAPTER I: DEPARTMENT OF NATURAL RESOURCES / Part 1816 PERMANENT PROGRAM PERFORMANCE STANDARDS – SURFACE MINING ACTIVITIES / Section 1816.22 Topsoil and Subsoil

## Text

Section 1816
Section 1816.22  Topsoil and
Subsoil
a)         Removal.
1)         All topsoil shall be removed as a separate layer from the area
to be disturbed, and segregated.  Where topsoil is of insufficient quantity or
poor quality for sustaining vegetation, the materials approved by the
Department in accordance with subsection (b) shall be removed as a separate
layer from the area to be disturbed, and segregated.
2)         If topsoil is less than 6 inches thick and no substitutes or
supplements are approved in accordance with subsection (b), the operator shall
remove a 6 inch layer that includes the A horizon and the unconsolidated
materials immediately below or the A horizon and all unconsolidated materials
if the total available is less than 6 inches and treat the mixture as topsoil.
3)         The Department shall not require the removal of topsoil for
minor disturbances which:
A)        Occur at the site of small structures, such as power poles,
signs, fence lines or markers; or
B)        Will not destroy the existing vegetation, will not cause
erosion and will not degrade the quality or limit the future use of the soil.
4)         All material to be removed under this Section shall be removed
after the vegetative cover that would interfere with its salvage is cleared
from the area to be disturbed, but before any drilling, blasting, mining or
other surface disturbance takes place.
b)         Substitutes and supplements.
Selected
overburden materials may be substituted for, or used as a supplement to topsoil
if the operator demonstrates to the Department that the resulting soil medium
is equal to, or more suitable for sustaining vegetation than, the existing
topsoil, and the resulting soil medium is the best available in the permit area
to support revegetation.  The demonstration shall be based upon the information
requirements of 62 Ill. Adm. Code 1780.18(b)(4).
c)         Storage
ent to topsoil
if the operator demonstrates to the Department that the resulting soil medium
is equal to, or more suitable for sustaining vegetation than, the existing
topsoil, and the resulting soil medium is the best available in the permit area
to support revegetation.  The demonstration shall be based upon the information
requirements of 62 Ill. Adm. Code 1780.18(b)(4).
c)         Storage.
1)         Materials removed under subsection (a) if not redistributed
immediately shall be segregated and stockpiled.
2)         Stockpiled materials shall:
A)        Be selectively placed on a stable site within the permit area;
B)        Be protected from contaminants and unnecessary compaction that
would interfere with revegetation;
C)        Be protected from wind and water erosion through prompt
establishment and maintenance of an effective, quick growing vegetative cover
or through other measures equally effective in controlling erosion approved by
the Department; and
D)        Not be moved until required for redistribution unless approved
by the Department.
3)         Where long-term surface disturbances will result from
facilities such as support facilities and preparation plants and where
stockpiling of materials removed under subsection (a)(1) would be detrimental
to the quality or quantity of those materials, the Department may approve the
temporary distribution of the soil materials so removed to an approved site
within the permit area to enhance the current use of that site until needed for
later reclamation provided that:
A)        Such action will not permanently diminish the capability of the
topsoil of the host site; and
B)        The material will be retained in a condition more suitable for
redistribution than if stockpiled.
d)         Redistribution
soil materials so removed to an approved site
within the permit area to enhance the current use of that site until needed for
later reclamation provided that:
A)        Such action will not permanently diminish the capability of the
topsoil of the host site; and
B)        The material will be retained in a condition more suitable for
redistribution than if stockpiled.
d)         Redistribution.
1)         Topsoil materials and topsoil substitutes and supplements removed
under subsections (a) and (b) shall be redistributed in a manner that:
A)        Achieves an approximate uniform, stable thickness when consistent
with the approved post-mining land use, contours and surface-water drainage
systems.  Soil thickness may also be varied to the extent such variations help
meet the specific revegetation goals identified in the permit;
B)        Prevents excess compaction of the materials; and
C)        Protects the materials from wind and water erosion and
contamination before and after seeding and planting.
2)         Before redistribution of the material removed under subsection
(a) the regraded land shall be treated if necessary to reduce potential
slippage of the redistributed material and to promote root penetration.  If no
harm will be caused to the redistributed material and reestablished vegetation,
such treatment may be conducted after such material is replaced.
3)         The Department shall not require the redistribution of topsoil
or topsoil substitutes on the approved post-mining embankments of permanent
impoundments or of roads if it determines that:
A)        Placement of topsoil or topsoil substitutes on such embankments
is inconsistent with the requirement to use the best technology currently
available to prevent sedimentation; and
B)        Such embankments will be otherwise stabilized.
4)         Nutrients and soil amendments shall be applied to the
initially redistributed material when necessary to establish the required
vegetative cover.
e)         Subsoil segregation
psoil substitutes on such embankments
is inconsistent with the requirement to use the best technology currently
available to prevent sedimentation; and
B)        Such embankments will be otherwise stabilized.
4)         Nutrients and soil amendments shall be applied to the
initially redistributed material when necessary to establish the required
vegetative cover.
e)         Subsoil segregation.  The Department may require that the B
horizon, C horizon, or other underlying strata, or portions thereof, be removed
and segregated, stockpiled, and redistributed as subsoil in accordance with the
requirements of subsections (c) and (d) if it finds that such subsoil layers
are necessary to comply with the revegetation requirements of Sections 1816.111,
1816.113, 1816.114, 1816.116 and 1816.117.

## Nearby sections

- [62 Ill. Adm. Code 1816.11 Section 1816.11  Signs and Markers](https://www.frixlaw.com/law-library/statutes/STATE_IL_IAC_T62_P1816_S1816_11.md)
- [62 Ill. Adm. Code 1816.13 Section 1816.13  Casing and Sealing of Drilled Holes: General Requirements](https://www.frixlaw.com/law-library/statutes/STATE_IL_IAC_T62_P1816_S1816_13.md)
- [62 Ill. Adm. Code 1816.14 Section 1816.14  Casing and Sealing of Drilled Holes:  Temporary](https://www.frixlaw.com/law-library/statutes/STATE_IL_IAC_T62_P1816_S1816_14.md)
- [62 Ill. Adm. Code 1816.15 Section 1816.15  Casing and Sealing of Drilled Holes: Permanent](https://www.frixlaw.com/law-library/statutes/STATE_IL_IAC_T62_P1816_S1816_15.md)
- [62 Ill. Adm. Code 1816.21 Section 1816.21  Topsoil:  General Requirements (Repealed)](https://www.frixlaw.com/law-library/statutes/STATE_IL_IAC_T62_P1816_S1816_21.md)
- [62 Ill. Adm. Code 1816.22 Section 1816.22  Topsoil and Subsoil](https://www.frixlaw.com/law-library/statutes/STATE_IL_IAC_T62_P1816_S1816_22.md)
- [62 Ill. Adm. Code 1816.23 Section 1816.23  Topsoil:  Storage (Repealed)](https://www.frixlaw.com/law-library/statutes/STATE_IL_IAC_T62_P1816_S1816_23.md)
- [62 Ill. Adm. Code 1816.24 Section 1816.24  Topsoil:  Redistribution (Repealed)](https://www.frixlaw.com/law-library/statutes/STATE_IL_IAC_T62_P1816_S1816_24.md)
- [62 Ill. Adm. Code 1816.25 Section 1816.25  Topsoil:  Nutrients and Soil Amendments (Repealed)](https://www.frixlaw.com/law-library/statutes/STATE_IL_IAC_T62_P1816_S1816_25.md)
- [62 Ill. Adm. Code 1816.41 Section 1816.41  Hydrologic Balance Protection](https://www.frixlaw.com/law-library/statutes/STATE_IL_IAC_T62_P1816_S1816_41.md)
- [62 Ill. Adm. Code 1816.42 Section 1816.42  Hydrologic Balance: Water Quality Standards and Effluent Limitations](https://www.frixlaw.com/law-library/statutes/STATE_IL_IAC_T62_P1816_S1816_42.md)
- [62 Ill. Adm. Code 1816.43 Section 1816.43  Diversions](https://www.frixlaw.com/law-library/statutes/STATE_IL_IAC_T62_P1816_S1816_43.md)
- [62 Ill. Adm. Code 1816.44 Section 1816.44  Hydrologic Balance: Stream Channel Diversions (Repealed)](https://www.frixlaw.com/law-library/statutes/STATE_IL_IAC_T62_P1816_S1816_44.md)
- [62 Ill. Adm. Code 1816.45 Section 1816.45  Hydrologic Balance:  Sediment Control Measures](https://www.frixlaw.com/law-library/statutes/STATE_IL_IAC_T62_P1816_S1816_45.md)

---

Source: Frix Law Library, https://www.frixlaw.com/law-library/statutes/STATE_IL_IAC_T62_P1816_S1816_22. Check the current official text before relying on it. Not legal advice.