# 35 Ill. Adm. Code 310.111: Section 310.111 New Source

> Illinois · Regulations · In force

URL: https://www.frixlaw.com/law-library/statutes/STATE_IL_IAC_T35_P310_S310_111

## Section

- **Citation:** 35 Ill. Adm. Code 310.111
- **Heading:** Section 310.111 New Source
- **Jurisdiction:** Illinois
- **Kind:** Regulations
- **Status:** In force
- **Text as of:** August 14, 2026
- **Source:** Compiled text
- **Location:** Illinois Administrative Code / Title 35 ENVIRONMENTAL PROTECTION / CHAPTER I: POLLUTION CONTROL BOARD / Part 310 PRETREATMENT PROGRAMS / Section 310.111 New Source

## Text

Section 310
Section 310.111  New Source
a)         "New source" means any building, structure, facility,
or installation from which there is or may be a discharge of pollutants, the
construction of which commenced after the date specified in 35 Ill. Adm. Code
307 for the particular source category or subcategory applicable to the source,
if one of the following is true:
1)         The building, structure, facility, or installation is
constructed at a site at which no other source is located;
2)         The building, structure, facility, or installation totally
replaces the process or production equipment that causes the discharge of
pollutants at an existing source; or
3)         The production or wastewater generating processes of the
building, structure, facility, or installation are substantially independent of
an existing source at the same site.  In determining whether these are
substantially independent, factors such as the extent to which the new facility
is integrated with the existing plant and the extent to which the new facility
is engaged in the same general type of activity as the existing source should
be considered.
b)         Construction on a site at which an existing source is located
results in a modification, rather than a new source, if the construction does
not create a new building, structure, facility, or installation that meets the
criteria of subsection (a)(2) or (a)(3), but which otherwise alters, replaces,
or adds to existing process or production equipment
sting source should
be considered.
b)         Construction on a site at which an existing source is located
results in a modification, rather than a new source, if the construction does
not create a new building, structure, facility, or installation that meets the
criteria of subsection (a)(2) or (a)(3), but which otherwise alters, replaces,
or adds to existing process or production equipment.
c)         Construction of a new source, as defined in this Section, has
commenced if the owner or operator has done either of the following:
1)         It has begun or caused either of the following to begin as
part of a continuous on-site construction program:
A)        Any placement, assembly, or installation of facilities or
equipment; or
B)        Significant site preparation work, including clearing,
excavation, or removal of existing buildings, structures, or facilities, that
is necessary for the placement, assembly, or installation of new source
facilities or equipment; or
2)         It has entered into a binding contractual obligation for the
purchases of facilities or equipment that are intended to be used in its
operation within a reasonable time.  An option to purchase or a contract that
can be terminated or modified without substantial loss and contracts for
feasibility, engineering, and design studies does not constitute a contractual
obligation under this subsection (c)(2).
d)         A new source must install and have in operating condition and must
"start up " all pollution control equipment required to meet
applicable pretreatment standards before beginning to discharge.  Within the
shortest feasible time (not to exceed 90 days), a new source must meet all
applicable pretreatment standards.
BOARD NOTE:
Derived from 40 CFR 403.3(m) (2005), as renumbered and amended at 70 Fed. Reg.
60134 (Oct. 14, 2005).

## Nearby sections

- [35 Ill. Adm. Code 310.101 Section 310.101  Applicability](https://www.frixlaw.com/law-library/statutes/STATE_IL_IAC_T35_P310_S310_101.md)
- [35 Ill. Adm. Code 310.102 Section 310.102  Objectives](https://www.frixlaw.com/law-library/statutes/STATE_IL_IAC_T35_P310_S310_102.md)
- [35 Ill. Adm. Code 310.103 Section 310.103  Federal Law](https://www.frixlaw.com/law-library/statutes/STATE_IL_IAC_T35_P310_S310_103.md)
- [35 Ill. Adm. Code 310.104 Section 310.104  State Law](https://www.frixlaw.com/law-library/statutes/STATE_IL_IAC_T35_P310_S310_104.md)
- [35 Ill. Adm. Code 310.105 Section 310.105  Confidentiality](https://www.frixlaw.com/law-library/statutes/STATE_IL_IAC_T35_P310_S310_105.md)
- [35 Ill. Adm. Code 310.107 Section 310.107  Incorporations by Reference](https://www.frixlaw.com/law-library/statutes/STATE_IL_IAC_T35_P310_S310_107.md)
- [35 Ill. Adm. Code 310.110 Section 310.110  Definitions](https://www.frixlaw.com/law-library/statutes/STATE_IL_IAC_T35_P310_S310_110.md)
- [35 Ill. Adm. Code 310.111 Section 310.111  New Source](https://www.frixlaw.com/law-library/statutes/STATE_IL_IAC_T35_P310_S310_111.md)
- [35 Ill. Adm. Code 310.112 Section 310.112  Significant Industrial User](https://www.frixlaw.com/law-library/statutes/STATE_IL_IAC_T35_P310_S310_112.md)

---

Source: Frix Law Library, https://www.frixlaw.com/law-library/statutes/STATE_IL_IAC_T35_P310_S310_111. Check the current official text before relying on it. Not legal advice.