# 121 FERC ¶ 61,221: FERC Hydrokinetic Energy Project Policy Statement

> Federal · Agency guidance · In force

URL: https://www.frixlaw.com/law-library/statutes/FERC_PL08_1_000

## Section

- **Citation:** 121 FERC ¶ 61,221
- **Heading:** FERC Hydrokinetic Energy Project Policy Statement
- **Jurisdiction:** Federal
- **Kind:** Agency guidance
- **Status:** In force
- **Text as of:** August 14, 2026
- **Source:** Compiled text
- **Location:** FERC Policy Statements / FERC Hydrokinetic Energy Project Policy Statement

## Text

121 FERC ¶ 61,221
UNITED STATES OF AMERICA
FEDERAL ENERGY REGULATORY COMMISSION

(Docket No. PL08-1-000)

Policy Statement on Conditioned Licenses for Hydrokinetic Projects

(Issued November 30, 2007)

AGENCY: Federal Energy Regulatory Commission.

ACTION: Policy Statement.

SUMMARY: The Federal Energy Regulatory Commission is giving notice of a new
policy with respect to the issuance of licenses for hydrokinetic projects. In the Policy
Statement, the Commission concludes that, in appropriate cases, where the Commission
has completed its processing of license applications for hydrokinetic projects, but where
other authorizations required under federal law have not yet been received, it will issue
conditioned licenses for hydrokinetic projects, predicated on the licensee being precluded
from commencing construction until the necessary authorizations are received.
EFFECTIVE DATE: This Policy Statement is effective November 30, 2007.
FOR FURTHER INFORMATION CONTACT:

Ann Miles
Federal Energy Regulatory Commission
888 First Street, N.E.
Washington, D.C. 20426
(202) 502-6769

Docket No. PL08-1-000
- 2 -
John Katz
Federal Energy Regulatory Commission
888 First Street, N.E.
Washington, D.C. 20426
(202) 502-8082

SUPPLEMENTARY INFORMATION:

121 FERC ¶ 61,221
UNITED STATES OF AMERICA
FEDERAL ENERGY REGULATORY COMMISSION

Before Commissioners: Joseph T. Kelliher, Chairman;
Suedeen G. Kelly, Marc Spitzer,
Philip D. Moeller, and Jon Wellinghoff.

Policy Statement on Conditioned Licenses
for Hydrokinetic Projects
Docket No. PL08-1-000

POLICY STATEMENT ON CONDITIONED LICENSES
FOR HYDROKINETIC PROJECTS

(Issued November 30, 2007)

1
ssioners: Joseph T. Kelliher, Chairman;
Suedeen G. Kelly, Marc Spitzer,
Philip D. Moeller, and Jon Wellinghoff.

Policy Statement on Conditioned Licenses
for Hydrokinetic Projects
Docket No. PL08-1-000

POLICY STATEMENT ON CONDITIONED LICENSES
FOR HYDROKINETIC PROJECTS

(Issued November 30, 2007)

1.
The Commission is issuing this Policy Statement as part of its ongoing effort to
establish a regulatory climate that supports the development of innovative hydropower
projects that use the forces of currents, waves, and tides (generally referred to herein as
“hydrokinetic projects’) to generate clean, renewable electric energy. In the Policy
Statement, the Commission sets forth a new policy, applicable only to hydrokinetic
projects, pursuant to which the Commission will, in appropriate cases, issue licenses
pending actions by other entities under federal law. The goal of this action is to shorten
the regulatory process and speed the development of meritorious hydrokinetic projects.
I.
Background
2.
In recent years, the Commission has become aware of efforts by the hydrokinetic
industry to test and develop projects that harness the nation’s water resources to produce
new supplies of much-needed electric power. Estimates suggest that new hydrokinetic

Docket No. PL08-1-000
- 2 -

technologies, if fully developed, could double the amount of hydropower production in
the United States, bringing it from just under 10 percent to close to 20 percent of the
national electric energy supply. Given the potential benefits of this new, clean power
source, the Commission has taken steps to lower regulatory barriers to its development.
3
technologies, if fully developed, could double the amount of hydropower production in
the United States, bringing it from just under 10 percent to close to 20 percent of the
national electric energy supply. Given the potential benefits of this new, clean power
source, the Commission has taken steps to lower regulatory barriers to its development.
3.
On December 6, 2006, the Commission held a technical conference on
Hydroelectric Generation from Ocean Waves, Tides, and Currents and from Free-
Flowing Rivers.1 At the conference, the Commission heard from state and federal
regulators, developers, and other stakeholders interested in hydrokinetic projects.
Following the conference, the Commission received public comments. A number of the
comments focused on issues relating to the issuance of preliminary permits for
hydrokinetic projects,2 while other comments discussed the licensing process for such
projects.
4.
On February 15, 2007, the Commission issued a notice of inquiry and interim
statement of policy with respect to preliminary permits for hydrokinetic projects.3 The
Commission explained that there had been a surge in applications for preliminary permits

1 Docket AD06-13-000.
2 Preliminary permits, issued for a term of up to three years pursuant to section
4(f) of the Federal Power Act, 18 U.S.C. § 797(f) (2000), allow a potential applicant to
develop sufficient information to prepare a license application and give the permit holder
a priority with respect to filing a license application, but confer no property rights in the
project site and no authority to conduct construction or other land-disturbing activity.
3 The notice of inquiry and interim statement of policy is published at FERC
Stats. & Regs. ¶ 35,555.
icant to
develop sufficient information to prepare a license application and give the permit holder
a priority with respect to filing a license application, but confer no property rights in the
project site and no authority to conduct construction or other land-disturbing activity.
3 The notice of inquiry and interim statement of policy is published at FERC
Stats. & Regs. ¶ 35,555.

Docket No. PL08-1-000
- 3 -

to study potential hydrokinetic projects, and noted the potential for new energy
production from those projects. In consequence, the Commission proposed to implement
a “strict scrutiny” approach to reviewing preliminary permit applications, in order to
respond to issues that had been raised at the technical conference, and to encourage
thoughtful permit applications and promote competition.4 The Commission also sought
comment on this proposal, and the great majority of the commenters supported the
Commission’s approach.
5.
On October 2, 2007, the Commission held a Commissioner-led technical
conference, in Portland, Oregon, to discuss a Commission staff proposal for a pilot
licensing process regarding hydrokinetic projects. The staff proposal called for an
expedited licensing process, to be completed in as few as six months. Staff suggested
that pilot project licenses would be available only for proposed projects that are small
(five megawatts or less), are removable or able to be shut down quickly, are not located
in sensitive areas, and are for the purpose of testing new technologies or locating
appropriate sites.5 Staff proposed that pilot project licenses (1) have a short term (five
years), (2) include a standard condition requiring project alteration or shutdown in the
event that there was an unacceptable level of environmental effect, (3) provide the option

4 Id. at ¶ 14, 16.
5 See Notice of Technical Conference and Soliciting Comments, Docket
No. AD07-14-000 (issued July 19 2007).
ate sites.5 Staff proposed that pilot project licenses (1) have a short term (five
years), (2) include a standard condition requiring project alteration or shutdown in the
event that there was an unacceptable level of environmental effect, (3) provide the option

4 Id. at ¶ 14, 16.
5 See Notice of Technical Conference and Soliciting Comments, Docket
No. AD07-14-000 (issued July 19 2007).

Docket No. PL08-1-000
- 4 -
of applying for a standard 30-50 year license, and (4) require decommissioning and site
restoration at license expiration, if a standard license is not sought. The comments filed
regarding the pilot project license proposal were largely supportive of a more expedited,
less burdensome process, and included a number of specific suggestions as to how the
process could be implemented.
II.
Discussion
6.
Based on the Commission’s experience, it has often been the case that
Commission staff has completed its processing of a hydropower license application,
including preparation of an environmental document, but that authorizations required
from other entities under federal laws including the Clean Water Act, the Coastal Zone
Management Act, and the Endangered Species Act, have not yet been received.
Typically, the Commission has not acted in such instances, sometimes resulting in
substantial delays in developers’ abilities to undertake non-construction activities. This
has a concomitant adverse impact on developers' abilities to move quickly with project
construction once the pending authorizations are filed with the Commission.
7.
The Commission has taken a different approach with respect to authorizations
issued under the Natural Gas Act. In those cases, the Commission has issued pipeline
certificates and authorizations to construct liquefied natural gas facilities while action by
act on developers' abilities to move quickly with project
construction once the pending authorizations are filed with the Commission.
7.
The Commission has taken a different approach with respect to authorizations
issued under the Natural Gas Act. In those cases, the Commission has issued pipeline
certificates and authorizations to construct liquefied natural gas facilities while action by

Docket No. PL08-1-000
- 5 -

other entities is still pending, and included in the Commission order provisos that
construction may not commence until the necessary authorizations have been received.6
8.
In light of the nation’s interest in the development of its water power resources to
meet the growing need for clean, renewable energy, the Commission has decided to adopt
the natural gas procedural model with respect to new, hydrokinetic projects. Thus, for
new hydrokinetic projects only, we will, in appropriate cases, issue project licenses where
the Commission has completed processing an application but other authorizations remain
outstanding. In such cases, the license will include conditions precluding the licensee
from commencing construction until it has obtained all necessary authorizations.
9.
There are a number of policy reasons to consider adopting the gas pipeline
practice rather than the conventional hydropower practice with respect to conditioned
licensing of hydrokinetic technologies. First, issuing licenses as described will have no
environmental impacts. By the terms of the licenses, licensees will not be permitted to
commence construction until they have obtained all authorizations required by federal
law. When the authorizations are obtained, licensees will be required to file them with
the Commission, and the Commission then will review them and incorporate their terms
in the licenses, as appropriate.
10
have no
environmental impacts. By the terms of the licenses, licensees will not be permitted to
commence construction until they have obtained all authorizations required by federal
law. When the authorizations are obtained, licensees will be required to file them with
the Commission, and the Commission then will review them and incorporate their terms
in the licenses, as appropriate.
10.
Second, issuing an appropriately conditioned license would in no way diminish the

6 See, e.g., Crown Landing LLC, 117 FERC ¶ 61,209 at P 21 and n.19 and n. 36
(2006); Georgia Strait Crossing Pipeline LP, 108 FERC ¶ 61,053 at P 13-16 (2004);
Millennium Pipeline Company, L.P., 100 FERC ¶ 61,277 at P 225-231 (2002).

Docket No. PL08-1-000
- 6 -
authority of the states or other federal agencies. Construction of a hydrokinetic project
could not start without any necessary state and federal authorizations under a conditioned
license. For that reason, states and federal agencies will fully retain their authority to
take action under relevant federal law.
11.
Third, the new procedure is suitable for demonstration projects. The Commission
can issue licenses quickly, leaving state and federal agencies that have not yet completed
their actions the opportunity to do so, ideally quickly, on their own timetable. While it is
not clear whether state and federal resource agencies will complete their actions on
hydrokinetic projects in a shortened timeframe, as suggested in the pilot project license
proposal drafted by Commission staff, issuance of conditioned licenses would likely give
the Commission a greater ability to respond quickly to innovative project proposals.
Also, early issuance of a Commission license will improve the ability of project
developers to secure financing of demonstration projects.
12.
Issuance of a conditioned license will be a final Commission action, as is the case
with other licenses that contain reservations of authority
es would likely give
the Commission a greater ability to respond quickly to innovative project proposals.
Also, early issuance of a Commission license will improve the ability of project
developers to secure financing of demonstration projects.
12.
Issuance of a conditioned license will be a final Commission action, as is the case
with other licenses that contain reservations of authority. Thus, these licenses will be
subject to rehearing, and, once accepted, their terms will be binding on licensees.
Licensees will be able, and required, to comply with all license terms that do not involve
construction, such as those which may require the development of plans and consultation
with stakeholders.

Docket No. PL08-1-000
- 7 -
III.
Comments
13.
Interested persons may submit comments on this Policy Statement. Comments are
due on or before December 14, 2007. Comments must refer to Docket No. PL08-1-000,
and must include the commenter’s name, the organization they represent, if applicable,
and their address.
14.
Commenters are requested to use appropriate headings and to double space their
comments.
15.
Comments may be filed on paper or electronically via the eFiling link on the
Commission’s web site at http://www.ferc.gov. The Commission accepts most standard
word processing formats and commenters may attach additional files with supporting
information in certain other file formats. Commenters filing electronically do not need to
make a paper filing. Commenters that are not able to file comments electronically must
send an original and 14 copies of their comments to: Federal Energy Regulatory
Commission, Office of the Secretary, 888 First Street, NE, Washington, DC 20426.
16.
All comments will be placed in the Commission’s public files and may be viewed,
printed, or downloaded remotely as described in the Document Availability section
below. Commenters are not required to serve copies of their comments on other
commenters.
IV
omments to: Federal Energy Regulatory
Commission, Office of the Secretary, 888 First Street, NE, Washington, DC 20426.
16.
All comments will be placed in the Commission’s public files and may be viewed,
printed, or downloaded remotely as described in the Document Availability section
below. Commenters are not required to serve copies of their comments on other
commenters.
IV.
Document Availability

17.
In addition to publishing the full text of this document in the Federal Register, the
Commission provides all interested persons an opportunity to view and/or print the

Docket No. PL08-1-000
- 8 -
contents of this document via the Internet through the Commission’s Home Page
(http://www.ferc.gov) and in the Commission’s Public Reference Room during normal
business hours (8:30 a.m. to 5:00 p.m. Eastern time) at 888 First Street, N.E., Room 2A,
Washington D.C. 20426.
18.
From the Commission’s Home Page on the Internet, this information is available
in the Commission’s document management system, eLibrary. The full text of this
document is available on eLibrary in PDF and Microsoft Word format for viewing,
printing, and/or downloading. To access this document in eLibrary, type the docket
number (excluding the last three digits of the docket number), in the docket number field.
User assistance is available for eLibrary and the Commission’s website during normal
business hours. For assistance, please contact FERC Online Support at (202) 502-6652
(toll-free at 1-866-208-3676) or e-mail at ferconlinesupport@ferc.gov, or the Public
Reference Room at (202) 502-8371, TTY (202) 502-8659. E-mail the Public Reference
Room at public.referenceroom@ferc.gov.
By the Commission.

( S E A L )

Kimberly D. Bose,

Secretary.

## Nearby sections

- [77 FERC ¶ 61,263 Policy Statement Establishing Factors the Commission Will Consider in Evaluating Whether A Proposed Merger is Consistent With the Public Interest](https://www.frixlaw.com/law-library/statutes/FERC_RM96_6_000.md)
- [88 FERC ¶ 61,227 Certification of New Interstate Natural Gas Pipeline Facilities](https://www.frixlaw.com/law-library/statutes/FERC_PL99_3_000.md)
- [109 FERC ¶ 61,186 Policy Statement on Credit-Related Issues for Electric OATT Transmission Providers, ISOs & RTOs](https://www.frixlaw.com/law-library/statutes/FERC_PL05_3_000.md)
- [112 FERC ¶ 61,040 Order Further Clarifying Policy Statement on Natural Gas and Electric Price Indices](https://www.frixlaw.com/law-library/statutes/FERC_PL03_3_006.md)
- [120 FERC ¶ 61,060 Section 203 Supplemental Policy Statement](https://www.frixlaw.com/law-library/statutes/FERC_PL07_1_000.md)
- [121 FERC ¶ 61,221 FERC Hydrokinetic Energy Project Policy Statement](https://www.frixlaw.com/law-library/statutes/FERC_PL08_1_000.md)
- [123 FERC ¶ 61,048 Composition of Proxy Groups for Determining and Oil Pipeline Return on Equity](https://www.frixlaw.com/law-library/statutes/FERC_PL07_2_000.md)
- [123 FERC ¶ 61,156 Revised Policy Statement on Enforcement](https://www.frixlaw.com/law-library/statutes/FERC_PL08_3_000.md)
- [125 FERC ¶ 61,058 Compliance with Statutes, Regulations, and Orders](https://www.frixlaw.com/law-library/statutes/FERC_PL09_1_000.md)
- [125 FERC ¶ 61,208 Material Changes in Facts that Require Notifications Under Commission Regulations Under the Public Utility Holding Company Act of 2005](https://www.frixlaw.com/law-library/statutes/FERC_PL09_2_000.md)
- [128 FERC ¶ 61,060 Smart Grid Policy Statement](https://www.frixlaw.com/law-library/statutes/FERC_PL09_4_000.md)
- [129 FERC ¶ 61,248 Policy Statement On Disclosure Of Exculpatory Materials](https://www.frixlaw.com/law-library/statutes/FERC_PL10_1_000.md)
- [130 FERC ¶ 61,220 Policy Statement On Penalty Guidelines](https://www.frixlaw.com/law-library/statutes/FERC_PL10_4_000_20100318.md)
- [132 FERC ¶ 61,216 Revised Policy Statement On Penalty Guidelines](https://www.frixlaw.com/law-library/statutes/FERC_PL10_4_000.md)

---

Source: Frix Law Library, https://www.frixlaw.com/law-library/statutes/FERC_PL08_1_000. Check the current official text before relying on it. Not legal advice.