# 140 FERC ¶ 61,061: Allocation of Capacity on New Merchant Transmission Projects and New Cost-Based, Participant-Funded Transmission Projects & Priority Rights To New Participant-Funded Transmission (Proposed Policy Statement)

> Federal · Agency guidance · In force

URL: https://www.frixlaw.com/law-library/statutes/FERC_AD12_9_000_20120719

## Section

- **Citation:** 140 FERC ¶ 61,061
- **Heading:** Allocation of Capacity on New Merchant Transmission Projects and New Cost-Based, Participant-Funded Transmission Projects & Priority Rights To New Participant-Funded Transmission (Proposed Policy Statement)
- **Jurisdiction:** Federal
- **Kind:** Agency guidance
- **Status:** In force
- **Text as of:** August 14, 2026
- **Source:** Compiled text
- **Location:** FERC Policy Statements / Allocation of Capacity on New Merchant Transmission Projects and New Cost-Based, Participant-Funded Transmission Projects & Priority Rights To New Participant-Funded Transmission (Proposed Policy Statement)

## Text

140 FERC ¶ 61,061
UNITED STATES OF AMERICA
FEDERAL ENERGY REGULATORY COMMISSION

18 CFR Parts 2 and 35

[Docket Nos. AD12-9-000 and AD11-11-000]

ALLOCATION OF CAPACITY ON NEW MERCHANT TRANSMISSION PROJECTS
AND NEW COST-BASED, PARTICIPANT-FUNDED TRANSMISSION PROJECTS

PRIORITY RIGHTS TO NEW PARTICIPANT-FUNDED TRANSMISSION

(Issued July 19, 2012)

AGENCY: Federal Energy Regulatory Commission.
ACTION: Proposed Policy Statement.
SUMMARY: The Commission seeks comment on this proposed policy statement, which
clarifies and refines current policies governing the allocation of capacity for new
merchant transmission projects and new nonincumbent, cost-based, participant-funded
transmission projects. The Commission proposes to allow developers of such projects to
select a subset of customers, based on not unduly discriminatory or preferential criteria,
and negotiate directly with those customers to reach agreement on the key terms and
conditions for procuring capacity, when the developers (1) broadly solicit interest in the
project from potential customers, and (2) file a report with the Commission describing the
solicitation, selection and negotiation process. The Commission proposes these policy
reforms to ensure transparency in the capacity allocation process while providing

Docket Nos. AD12-9-000 and AD11-11-000
- 2 -

developers the ability to bilaterally negotiate rates, terms, and conditions for the full
amount of transmission capacity with potential customers.
DATES: Comments on the proposed policy statement are due on or before [Insert_Date
60 days after publication in the FEDERAL REGISTER]

FOR FURTHER INFORMATION CONTACT:
Becky Robinson
Office of Energy Policy and Innovation
888 First Street, NE
Washington, DC 20426
(202) 502-8868
becky.robinson@ferc.gov

Andrew Weinstein
Office of General Counsel
888 First Street, NE
Washington, DC 20426
Comments on the proposed policy statement are due on or before [Insert_Date
60 days after publication in the FEDERAL REGISTER]

FOR FURTHER INFORMATION CONTACT:
Becky Robinson
Office of Energy Policy and Innovation
888 First Street, NE
Washington, DC 20426
(202) 502-8868
becky.robinson@ferc.gov

Andrew Weinstein
Office of General Counsel
888 First Street, NE
Washington, DC 20426
(202) 502-6230
andrew.weinstein@ferc.gov

Brian Bak
Office of Energy Policy and Innovation
888 First Street, NE
Washington, DC 20426
(202) 502-6574
brian.bak@ferc.gov

SUPPLEMENTARY INFORMATION:

140 FERC ¶ 61,061
UNITED STATES OF AMERICA
FEDERAL ENERGY REGULATORY COMMISSION

Before Commissioners: Jon Wellinghoff, Chairman;
Philip D. Moeller, John R. Norris,
Cheryl A. LaFleur, and Tony T. Clark.

Allocation of Capacity on New Merchant Transmission
Projects and New Cost-Based, Participant-Funded
Transmission Projects

Priority Rights to New Participant-Funded
Transmission
Docket Nos. AD12-9-000

AD11-11-000

PROPOSED POLICY STATEMENT

(Issued July 19, 2012)

I.
Introduction
1.
The Commission seeks comment on this proposed policy statement, which
clarifies and refines current policies governing the allocation of capacity for new
merchant transmission projects and new nonincumbent, cost-based, participant-funded
transmission projects. In recent years, a number of merchant and nontraditional
transmission developers have sought guidance from the Commission regarding
application of open access principles to new transmission facilities through petitions for
declaratory orders. As the Commission addressed these requests, its policies have
evolved over time to provide potential customers adequate opportunities to obtain service
while also providing transmission developers adequate certainty to assist with financing
transmission projects
Commission regarding
application of open access principles to new transmission facilities through petitions for
declaratory orders. As the Commission addressed these requests, its policies have
evolved over time to provide potential customers adequate opportunities to obtain service
while also providing transmission developers adequate certainty to assist with financing
transmission projects. As a result of these evolving policies, different rules have been

Docket Nos. AD12-9-000 and AD11-11-000
- 2 -
adopted regarding capacity allocation for merchant transmission projects and
nonincumbent, cost-based, participant-funded transmission projects.
2.
With the benefit of experience regarding the unique characteristics of merchant
and other nontraditional transmission project proposals, and in consideration of industry
input on Commission policies regarding the allocation of capacity on such projects, the
Commission proposes to streamline its capacity allocation policies by establishing
consistent policies regarding capacity allocation for both merchant transmission projects
and nonincumbent, cost-based, participant-funded transmission projects. Specifically, the
Commission proposes to allow developers of such projects to select a subset of
customers, based on not unduly discriminatory or preferential criteria, and negotiate
directly with those customers to reach agreement on the key terms and conditions for
procuring capacity, when they (1) broadly solicit interest in the project from potential
customers, and (2) submit a report to the Commission describing the solicitation,
selection and negotiation process. The Commission proposes these policy reforms to
ensure transparency in the capacity allocation process while providing developers the
ability to negotiate bilaterally with potential customers the rates, terms, and conditions for
the full amount of transmission capacity
tential
customers, and (2) submit a report to the Commission describing the solicitation,
selection and negotiation process. The Commission proposes these policy reforms to
ensure transparency in the capacity allocation process while providing developers the
ability to negotiate bilaterally with potential customers the rates, terms, and conditions for
the full amount of transmission capacity. These policy reforms would be implemented
within the existing four factor analysis used to evaluate requests for negotiated rate

Docket Nos. AD12-9-000 and AD11-11-000
- 3 -
authority.1 The Commission seeks comment regarding this proposed change in policy, as
discussed below.
II.
Background
3.
The Commission first granted negotiated rate authority to a merchant
transmission project developer over a decade ago, finding that merchant transmission can
play a useful role in expanding competitive generation alternatives for customers.2
Unlike traditional utilities recovering their costs-of-service from captive and wholesale
customers, investors in merchant transmission projects assume the full market risk of
development.3 Over the course of a number of early proceedings, the Commission
developed ten criteria to guide its analysis in making a determination as to whether
negotiated rate authority would be just and reasonable for a given merchant transmission
project.4 Two of these criteria were that (1) an open season process should be employed
to initially allocate all transmission capacity and (2) the results of the open season should

1 See infra note 29.
2 TransEnergie U.S., Ltd. 91 FERC ¶ 61,230, at 61,838 (2000) (TransEnergie).
3 Id. at 61,836.
4 Id.; Neptune Regional Transmission System, LLC, 96 FERC ¶ 61,147, at 61,633
(2001) (Neptune); Northeast Utilities Service Co., 97 FERC ¶ 61,026, at 61,075 (2001)
(Northeast Utilities I); Northeast Utilities Service Co., 98 FERC ¶ 61,310, at 62,327
1 See infra note 29.
2 TransEnergie U.S., Ltd. 91 FERC ¶ 61,230, at 61,838 (2000) (TransEnergie).
3 Id. at 61,836.
4 Id.; Neptune Regional Transmission System, LLC, 96 FERC ¶ 61,147, at 61,633
(2001) (Neptune); Northeast Utilities Service Co., 97 FERC ¶ 61,026, at 61,075 (2001)
(Northeast Utilities I); Northeast Utilities Service Co., 98 FERC ¶ 61,310, at 62,327
(2002) (Northeast Utilities II).

Docket Nos. AD12-9-000 and AD11-11-000
- 4 -
be posted on an Open Access Same-Time Information System (OASIS) and filed in a
report with the Commission.5
4.
In Chinook, the Commission refined its approach to evaluating merchant
transmission by adopting a four-factor analysis.6 Under this analysis, the Commission
continues to rely upon an open season and a post-open season report as a means to
provide transparency in the allocation of initial transmission capacity and ensure against
undue discrimination among potential customers in the award of transmission capacity.
Specifically, the Commission evaluates the terms and conditions of the open season as

5 The ten criteria are: (1) the merchant transmission facility must assume full
market risk; (2) the service should be provided under the open access transmission tariff
(OATT) of the Independent System Operator (ISO) or Regional Transmission
Organization (RTO) that operates the merchant transmission facility and that operational
control be given to that ISO or RTO; (3) the merchant transmission facility should create
tradable firm secondary transmission rights; (4) an open season process should be
employed to initially allocate transmission rights; (5) the results of the open season
should be posted on the OASIS and filed in a report to the Commission; (6) affiliate
concerns should be adequately addressed; (7) the merchant transmission facility not
preclude access to essential facilities by competitors; (8) the merchant transmission
facilities should be subject to
son process should be
employed to initially allocate transmission rights; (5) the results of the open season
should be posted on the OASIS and filed in a report to the Commission; (6) affiliate
concerns should be adequately addressed; (7) the merchant transmission facility not
preclude access to essential facilities by competitors; (8) the merchant transmission
facilities should be subject to market monitoring for market power abuse; (9) physical
energy flows on merchant transmission facilities should be coordinated with, and subject
to, reliability requirements of the relevant ISO or RTO; and (10) merchant transmission
facilities should not impair pre-existing property rights to use the transmission grids of
inter-connected RTOs or utilities. E.g., Northeast Utilities I, 97 FERC at 61,075.
6 The four factors are: (1) the justness and reasonableness of rates; (2) the
potential for undue discrimination; (3) the potential for undue preference, including
affiliate preference; and (4) regional reliability and operational efficiency requirements.
E.g., Chinook Power Transmission, LLC, 126 FERC ¶ 61,134, at P 37 (2009) (Chinook).

Docket Nos. AD12-9-000 and AD11-11-000
- 5 -
part of ensuring no undue discrimination (second factor),7 and uses the open season as an
added protection in overseeing any affiliate participation, to ensure no undue preference
or affiliate concerns (third factor).
5.
The Chinook order also marked a change in Commission policy on capacity
allocation, as in that order the Commission for the first time authorized developers to
allocate some portion of capacity through anchor customer presubscriptions, while
requiring that the remaining portion be allocated in a subsequent open season
, to ensure no undue preference
or affiliate concerns (third factor).
5.
The Chinook order also marked a change in Commission policy on capacity
allocation, as in that order the Commission for the first time authorized developers to
allocate some portion of capacity through anchor customer presubscriptions, while
requiring that the remaining portion be allocated in a subsequent open season. The
Commission implemented this policy to achieve the dual goals of requiring an open
season process that ensures capacity on a merchant transmission project is allocated
transparently in an open, fair, and not unduly discriminatory manner, while permitting an
anchor customer model that enables developers of merchant transmission projects to meet
the financial challenges unique to merchant transmission development.8 Since the
Chinook order, the Commission has issued orders on several new merchant and other

7 Also, the Commission looks to a developer’s own OATT commitments or its
commitment to turn operational control over to an RTO or ISO. See id. P 40. Guidance
given in this policy statement with regards to satisfying the second factor is directed at
the open season requirement; the Commission will continue to require merchant and
other transmission developers either to file an OATT or to turn over control to an RTO or
ISO.
8 See id. P 46.

Docket Nos. AD12-9-000 and AD11-11-000
- 6 -
nontraditional transmission development proposals, including granting requests to
allocate up to 75 percent of a transmission project’s capacity to anchor customers.9
6.
The Commission also has received proposals from transmission developers
regarding the allocation of capacity on cost-based, participant-funded transmission
projects
. P 46.

Docket Nos. AD12-9-000 and AD11-11-000
- 6 -
nontraditional transmission development proposals, including granting requests to
allocate up to 75 percent of a transmission project’s capacity to anchor customers.9
6.
The Commission also has received proposals from transmission developers
regarding the allocation of capacity on cost-based, participant-funded transmission
projects. These proceedings involved incumbent transmission developers,10 while one
involved a nonincumbent transmission developer.11 In NU/NSTAR, the Commission
approved the structure of a transaction whereby a customer was granted usage rights to
transmission capacity in exchange for funding the transmission expansion, under the
reasoning that any potential transmission customer has the right to request transmission
service expansion from a transmission owning utility, and that utility is obligated to make
any necessary system expansions and offer service at the higher of an incremental cost or
an embedded cost rate to the transmission customer. More recently, in National Grid, the
Commission found again that participant funding of transmission projects by incumbent
transmission providers is not inconsistent with the Commission's open access

9 See, e.g., Champlain Hudson Power Express, Inc., 132 FERC ¶ 61,006 (2010);
Rock Island Clean Line LLC, 139 FERC ¶ 61,142 (2012); Southern Cross Transmission
LLC, 137 FERC ¶ 61,207 (2011).
10 See, e.g., Northeast Utilities Service Company, NSTAR Electric Company,
127 FERC ¶ 61,179 (2009) (NU/NStar), order denying reh’g. and clarification,
129 FERC ¶ 61,279 (2009); National Grid Transmission Services Corporation and
Bangor Hydro Electric Company, 139 FERC ¶ 61,129 (2012) (National Grid).
11 See Grasslands Renewable Energy, LLC, 133 FERC ¶ 61,225 (2010).
(2011).
10 See, e.g., Northeast Utilities Service Company, NSTAR Electric Company,
127 FERC ¶ 61,179 (2009) (NU/NStar), order denying reh’g. and clarification,
129 FERC ¶ 61,279 (2009); National Grid Transmission Services Corporation and
Bangor Hydro Electric Company, 139 FERC ¶ 61,129 (2012) (National Grid).
11 See Grasslands Renewable Energy, LLC, 133 FERC ¶ 61,225 (2010).

Docket Nos. AD12-9-000 and AD11-11-000
- 7 -
requirements.12 Cost-based participant-funded projects are similar to merchant projects
in that both involve willing customers assuming part of the risk of a transmission project
in return for defined capacity rights; i.e., there is no direct assignment of costs to captive
customers. Cost-based participant-funded projects differ between incumbents and
nonincumbents, in that incumbent transmission providers have a clearly defined set of
existing obligations under their tariffs for the expansion of their existing transmission
facilities, whereas nonincumbents have no existing obligation to build any transmission
facilities.
7.
To gain feedback regarding the Commission’s capacity allocation policies, the
Commission held a technical conference in March 2011 to discuss the extent to which
nonincumbent developers of transmission should be provided flexibility in the allocation
of rights to use transmission facilities developed on a cost-of-service or negotiated rate
basis.13 Participants at that conference and subsequent commenters acknowledged the
value in widely soliciting new customers, but they also expressed the desire to be able to
allocate 100 percent of their projects’ capacity through bilateral negotiations with
identified customers.14 Based on these comments, the Commission held a follow up

(continued…)
12 National Grid, 139 FERC ¶ 61,129 at P 29.
13 “Priority Rights to New Participant-Funded Transmission,” AD11-11-000,
March 15, 2011
ressed the desire to be able to
allocate 100 percent of their projects’ capacity through bilateral negotiations with
identified customers.14 Based on these comments, the Commission held a follow up

(continued…)
12 National Grid, 139 FERC ¶ 61,129 at P 29.
13 “Priority Rights to New Participant-Funded Transmission,” AD11-11-000,
March 15, 2011. This technical conference also addressed generator lead lines, but those
facilities are not the subject of this proposed policy statement.
14 See, e.g., Clean Line Energy Partners May 5, 2011 Comments at 7 (Clean Line);
LS Power Transmission, LLC May 5, 2011 Comments at 3-4 (LSPT); Transmission

Docket Nos. AD12-9-000 and AD11-11-000
- 8 -
workshop in February 2012 to obtain input on potential reforms to the Commission’s
capacity allocation policies.15 Many participants at the 2012 workshop suggested that the
need for flexibility required something less structured than the traditional open season
process. Specifically, some commenters, including transmission developers, emphasized
the inherent incentive transmission developers have to solicit interest widely and attract
potential customers to their project, so that they can identify customers that are most
likely to be successful in their own generation projects and therefore provide the greatest
certainty that they will be successful in becoming transmission customers.16 In this
respect, these commenters argued that their incentives harmonize with the Commission’s
goals of open access. Further, they argue that their class of transmission developers does
not raise the same concerns that motivated the Commission in Order No. 888,17 where

(continued…)
Developers, Inc., May 5, 2011 Comments at 4-5 (TDI); Western Independent
Transmission Group May 5, 2011 Comments at 6 (WITG); and Tonbridge Power Inc
s
not raise the same concerns that motivated the Commission in Order No. 888,17 where

(continued…)
Developers, Inc., May 5, 2011 Comments at 4-5 (TDI); Western Independent
Transmission Group May 5, 2011 Comments at 6 (WITG); and Tonbridge Power Inc.
April 19, 2011 Comments at 2 (Tonbridge).
15 “Allocation of Capacity on New Merchant Transmission Projects and New
Cost-Based, Participant-Funded Transmission Projects,” Docket No. AD12-9-000
(February 28, 2012).
16 See, e.g., MATL LLP and Montana Alberta Tie, Ltd. March 29, 2012
Comments at 3 (MATL).
17 Promoting Wholesale Competition Through Open Access Non-Discriminatory
Transmission Services by Public Utilities; Recovery of Stranded Costs by Public Utilities
and Transmitting Utilities, Order No. 888, 61 FR 21540 (May 10, 1996), FERC Stats.
& Regs. ¶ 31,036 (1996), order on reh’g, Order No. 888-A, 62 FR 12274 (Mar. 14,
1997), FERC Stats. & Regs. ¶ 31,048, order on reh’g, Order No. 888-B, 81 FERC ¶
61,248 (1997), order on reh’g, Order No. 888-C, 82 FERC ¶ 61,046 (1998), aff’d in

Docket Nos. AD12-9-000 and AD11-11-000
- 9 -
vertically-integrated utilities had an economic incentive to favor their own generation and
discriminate against competitors when providing transmission service.18
8
74 (Mar. 14,
1997), FERC Stats. & Regs. ¶ 31,048, order on reh’g, Order No. 888-B, 81 FERC ¶
61,248 (1997), order on reh’g, Order No. 888-C, 82 FERC ¶ 61,046 (1998), aff’d in

Docket Nos. AD12-9-000 and AD11-11-000
- 9 -
vertically-integrated utilities had an economic incentive to favor their own generation and
discriminate against competitors when providing transmission service.18
8.
However, commenters also focused on the need for negotiation flexibility during
the capacity allocation process,19 pointing out that the transmission developer and
customer need to address a variety of issues, including points of delivery and receipt,
project timing and what happens if schedules change, termination rights of parties at
various development stages, development cost-sharing, length and payments of the initial
term of service, extensions of the term and associated payments.20 These commenters
argued that a rigid open season process that requires developers to offer all customers the
same terms and conditions does not allow for the bilateral exchange of information to
address the unique needs of developers and their potential customers. Moreover, these
commenters pointed out that there have been no claims of undue discrimination resulting
from any of the anchor customer proposals the Commission has approved, to date,21 and

relevant part sub nom. Transmission Access Policy Study Group v. FERC, 225 F.3d 667
(D.C. Cir. 2000), aff’d sub nom. New York v. FERC, 535 U.S. 1 (2002).
18 SunZia Transmission, LLC March 29, 2012 Comments at 7 (SunZia).
19 See, e.g., WITG March 28, 2012 Comments at 5; Clean Line March 28, 2012
Comments at 5-7; SunZia March 29, 2012 Comments at 3-6, 9; LSPT March 29, 2012
Comments at 2-4; and Pattern Transmission March 28, 2012 Comments at 6-7 (Pattern).
20 LSPT March 29, 2012 Comments at 2-3
aff’d sub nom. New York v. FERC, 535 U.S. 1 (2002).
18 SunZia Transmission, LLC March 29, 2012 Comments at 7 (SunZia).
19 See, e.g., WITG March 28, 2012 Comments at 5; Clean Line March 28, 2012
Comments at 5-7; SunZia March 29, 2012 Comments at 3-6, 9; LSPT March 29, 2012
Comments at 2-4; and Pattern Transmission March 28, 2012 Comments at 6-7 (Pattern).
20 LSPT March 29, 2012 Comments at 2-3.
21 TransWest Express LLC March 28, 2012 Comments at 7.

Docket Nos. AD12-9-000 and AD11-11-000
- 10 -
that parties who feel they were unduly discriminated against have had, as an added
protection, the right to file a section 206 complaint.22
9.
However, other commenters at the 2012 workshop voiced concerns with the
merchant transmission model in general, and the opportunity for potentially unduly
discriminatory deals.23 They argued that allowing more flexibility for merchant
transmission developers is tantamount to reverting to the pre-open access Order No. 888
days of transmission regulation, and discouraged the Commission from pursuing policies
that enable anchor customers to exclude or burden generation competitors or engage in
other abusive practices the Commission sought to eradicate in Order No. 888. Such
commenters favor requiring merchant transmission developer participation in the regional
planning process.24 The staff of the Federal Trade Commission similarly questions how
the Commission will restrain merchant transmission developers from exercising market
power.25

22 Duke Energy Corporation March 29, 2012 Comments at 7-8; 16 U.S.C. § 824e
h
commenters favor requiring merchant transmission developer participation in the regional
planning process.24 The staff of the Federal Trade Commission similarly questions how
the Commission will restrain merchant transmission developers from exercising market
power.25

22 Duke Energy Corporation March 29, 2012 Comments at 7-8; 16 U.S.C. § 824e
(2006).
23 See, e.g., Transmission Access Policy Study Group March 29, 2012 Comments
at 6-9 (TAPS); Transmission Dependent Utility Systems March 29, 2012 Comments at 2-
4; New Jersey Division of Rate Counsel March 29, 2012 Comments at 2-4; and the
Federal Trade Commission staff June 14, 2012 Comments at 6-9 (FTC staff).
24 This latter argument is outside the scope of this proceeding and was addressed
in Order No. 1000-A. Transmission Planning and Cost Allocation by Transmission
Owning and Operating Public Utilities, Order No. 1000, FERC Stats. & Regs. ¶ 31,323
(2011), order on reh’g, Order No. 1000-A, 139 FERC ¶ 61,132, at P 297 (2012).
25 FTC staff June 14, 2012 Comments at 9.

Docket Nos. AD12-9-000 and AD11-11-000
- 11 -
10.
The Commission believes that there is a role within its transmission development
policies for both bilateral negotiations for transmission service and uniform rules and
processes through the pro forma OATT for all customers at all times. The policy of open
access and comparable treatment is the underpinning of the Commission’s approach to
ensuring against undue discrimination and permeates many, if not all, of the
Commission’s programs. However, this does not mean that the Commission cannot be
flexible in how it accomplishes open access and comparable treatment. As Order
No. 100026 is implemented around the country, the Commission expects that more
transmission needs will be identified and addressed through the open and transparent
regional transmission planning process
any, if not all, of the
Commission’s programs. However, this does not mean that the Commission cannot be
flexible in how it accomplishes open access and comparable treatment. As Order
No. 100026 is implemented around the country, the Commission expects that more
transmission needs will be identified and addressed through the open and transparent
regional transmission planning process. Nonetheless, bilateral negotiation between
transmission developers and potential customers may be another appropriate vehicle for
new merchant transmission projects and new nonincumbent, cost-based, participant-
funded transmission projects to move forward. In fact, Order No. 1000 allowed for such
a vehicle, noting that some projects may not seek to pursue regional or interregional cost
allocation.27 In addition, there may be projects that are considered in the regional

(continued…)
26 Transmission Planning and Cost Allocation by Transmission Owning and
Operating Public Utilities, Order No. 1000, FERC Stats. & Regs. ¶ 31,323 (2011), order
on reh’g, Order No. 1000-A, 139 FERC ¶ 61,132 (2012).
27 See Order No. 1000, FERC Stats. & Regs. ¶ 31,323 at P 725; Order No. 1000-
A, 139 FERC ¶ 61,132 at PP 728-729 (“[N]othing in Order No. 1000 forecloses the
opportunity for a transmission developer, a group of transmission developers, or one or
more individual transmission customers to voluntarily assume the costs of a new
transmission facility…. Transmission developers who see particular advantages in
participant funding remain free to use it on their own or jointly with others. This simply
28-729 (“[N]othing in Order No. 1000 forecloses the
opportunity for a transmission developer, a group of transmission developers, or one or
more individual transmission customers to voluntarily assume the costs of a new
transmission facility…. Transmission developers who see particular advantages in
participant funding remain free to use it on their own or jointly with others. This simply

Docket Nos. AD12-9-000 and AD11-11-000
- 12 -
planning process that, although not ultimately selected in a regional plan for purposes of
cost allocation, have sufficient value for individual potential customers such that they
wish to pursue them through bilateral negotiations with a potential developer. This
proposed policy statement is intended to provide a “roadmap” for entities to pursue those
projects, while also serving to ensure transparency in the allocations of capacity resulting
from such bilateral negotiation and, in turn, to ensure that transmission service is
provided at rates, terms and conditions that are just and reasonable and not unduly
discriminatory.
11.
Accordingly, the Commission proposes to clarify and refine its policies
governing the allocation capacity for new merchant transmission projects and new
nonincumbent, cost-based, participant-funded transmission projects to ensure that it is
done in an open and transparent manner, giving all interested parties a chance to
participate. The Commission believes that the proposed capacity allocation process
outlined here satisfies our statutory responsibilities, provides sufficient transparency and
protections to market participants, and is responsive to the industry concerns.
III.
Discussion
A. Merchant transmission projects
12
ne in an open and transparent manner, giving all interested parties a chance to
participate. The Commission believes that the proposed capacity allocation process
outlined here satisfies our statutory responsibilities, provides sufficient transparency and
protections to market participants, and is responsive to the industry concerns.
III.
Discussion
A. Merchant transmission projects
12.
The Commission proposes to revise its merchant transmission policy to
streamline the process by which capacity may be allocated on new merchant transmission

means they would not be pursuing regional or interregional cost allocation.”).

Docket Nos. AD12-9-000 and AD11-11-000
- 13 -
projects and to expect more detail and transparency in the report describing the
developer’s capacity allocation approach. While the Commission’s fundamental
concerns continue to be that new transmission capacity be allocated in a not unduly
discriminatory or preferential manner, the Commission’s experience with new merchant
transmission projects and comments received during the technical conference and
workshop suggest that we can provide more flexibility while addressing these concerns.
The Commission proposes to allow merchant transmission developers to allocate up to
100 percent of their projects’ capacity through bilateral negotiations.28 With the
transparency protections discussed below, the Commission also proposes to allow
capacity allocation to affiliates, when done in a transparent manner, so that other
interested parties can voice concern if they believe the affiliate was treated preferentially
at the expense of another party.29
13
llocate up to
100 percent of their projects’ capacity through bilateral negotiations.28 With the
transparency protections discussed below, the Commission also proposes to allow
capacity allocation to affiliates, when done in a transparent manner, so that other
interested parties can voice concern if they believe the affiliate was treated preferentially
at the expense of another party.29
13.
The flexibility we propose to afford under the policy outlined below is
complemented by the emphasis on additional detail in reports describing the developer’s

28 Commenters in the technical conference and in the workshop specifically
requested that the Commission clarify circumstances under which merchant transmission
developers would be allowed to allocate up to 100 percent of their project’s capacity
through bilateral negotiations.
29 By proposing to adopt the policies herein, the Commission seeks to encourage
merchant transmission developers intending to seek negotiated rate authority to utilize the
guidelines discussed below. To the extent that a merchant transmission developer
substantially complies with any such policies ultimately adopted by the Commission, the
developer would be deemed to have satisfied the second (undue discrimination) and third
(undue preference) factors of the four-factor analysis.

Docket Nos. AD12-9-000 and AD11-11-000
- 14 -
capacity allocation approach. The Commission agrees with commenters that each
merchant transmission project has unique characteristics that require the ability to
negotiate risk-sharing and other details. The Commission also acknowledges that
merchant transmission developers have inherent incentives to solicit interest widely in a
potential project. However, other commenters point out that counter-incentives may exist
that motivate a developer to unduly prefer one or more customers
mission project has unique characteristics that require the ability to
negotiate risk-sharing and other details. The Commission also acknowledges that
merchant transmission developers have inherent incentives to solicit interest widely in a
potential project. However, other commenters point out that counter-incentives may exist
that motivate a developer to unduly prefer one or more customers. To protect against
undue discrimination, the Commission proposes to allow merchant transmission
developers to engage in an open solicitation to identify potential transmission customers,
but with the expectation that they will submit to the Commission reports regarding the
processes that led to the identification of customers and execution of relevant capacity
arrangements. The Commission believes that this approach, when coupled with the
existing opportunity to file complaints under FPA section 206, serves the interest of
customers and developers alike.30

1.
Open solicitation process
14.
In the past, the Commission has required an open season for the allocation of
capacity on new merchant transmission projects. The open season requirement was to
ensure open access to transmission capacity and prevent the withholding of transmission
capacity from interested transmission customers, and also to enable the developer to
assess the size of the market. However, beginning with the Chinook order, the

30 See Chinook, 126 FERC ¶ 61,134 at P 41.
ssion projects. The open season requirement was to
ensure open access to transmission capacity and prevent the withholding of transmission
capacity from interested transmission customers, and also to enable the developer to
assess the size of the market. However, beginning with the Chinook order, the

30 See Chinook, 126 FERC ¶ 61,134 at P 41.

Docket Nos. AD12-9-000 and AD11-11-000
- 15 -
Commission also began to allow the allocation of a portion of transmission capacity
through bilateral negotiations prior to an open season. Thus, current Commission policy
allows a merchant transmission developer to solicit interest through bilateral negotiations
for a portion of its capacity so long as it makes the remainder available through an open
season.
15.
Based on the Commission’s experience with prior cases and information
received from the technical conference and workshop, the Commission believes that
bilateral negotiations, if conducted in a transparent manner, may serve the same purpose
as an open season process by ensuring against undue discrimination or preference in the
provision of transmission service. Hence, the Commission proposes that, in seeking
negotiated rate authority, merchant transmission developers should also engage in an
open solicitation of interest in their projects from potential transmission customers
(without the previous requirement of an open season). Such open solicitation should
include a broad notice issued in a manner that ensures that all potential and interested
customers are informed of the proposed project. For example, such notice may be placed
in trade magazines, regional energy publications, communications with regional
transmission planning groups, and email distribution lists addressing transmission-related
matters
season). Such open solicitation should
include a broad notice issued in a manner that ensures that all potential and interested
customers are informed of the proposed project. For example, such notice may be placed
in trade magazines, regional energy publications, communications with regional
transmission planning groups, and email distribution lists addressing transmission-related
matters. Such notice should include transmission developer points of contact and
pertinent project dates, as well as sufficient technical specifications and contract
information to inform interested customers of the nature of the project, including:

Docket Nos. AD12-9-000 and AD11-11-000
- 16 -
Technical specifications
 Project size/Capacity: MW and/or kV rating (specific value or range of
values)
 End points of line (as specific as possible such as points of
interconnection to existing lines and substations, although it may be
potentially broad, such as Montana to Nevada, if the project is very
early in development)
 Projected construction and/or in-service dates
 Type of line — for example, AC, DC, bi-directional
Contract information
 Precedent agreement (if developed)
 Other capacity allocation arrangements (including how it will address
potential oversubscription of capacity)

16.
The developer should also specify in the notice the criteria it plans to use to
select transmission customers, such as credit rating; “first mover” status, i.e., customers
who respond early and take on greater project risk; and customers’ willingness to
incorporate project risk-sharing into their contracts. This will contribute to the
transparency of the process, and help interested entities know at the outset the features of
the project and how the bids to the merchant transmission developer will be considered.
17.
Finally, the merchant transmission developer would be expected to update its
posting if there are any material changes to the nature of the project or the status of
capacity allocation.
18
l contribute to the
transparency of the process, and help interested entities know at the outset the features of
the project and how the bids to the merchant transmission developer will be considered.
17.
Finally, the merchant transmission developer would be expected to update its
posting if there are any material changes to the nature of the project or the status of
capacity allocation.
18.
Under this proposed process, once a subset of customers has been identified by
the developer through the open solicitation process, the Commission would allow
developers to engage in bilateral negotiations with each potential customer on the specific
terms and conditions for procuring transmission capacity, as the Commission recognizes
that developers and potential customers may need to negotiate individualized terms that

Docket Nos. AD12-9-000 and AD11-11-000
- 17 -
meet their unique needs.31 In these negotiations, the Commission proposes to allow for
distinctions among prospective customers based on transparent and not unduly
discriminatory or preferential criteria -- so long as the differences in negotiated terms
recognize material differences and do not result in undue discrimination or preference --
with the potential result that a single customer may be awarded up to 100 percent of
capacity. For instance, developers might offer “first mover” customers more favorable
terms and conditions than later customers.

2.
Reporting
19
ential criteria -- so long as the differences in negotiated terms
recognize material differences and do not result in undue discrimination or preference --
with the potential result that a single customer may be awarded up to 100 percent of
capacity. For instance, developers might offer “first mover” customers more favorable
terms and conditions than later customers.

2.
Reporting
19.
In the past, the Commission required that developers file a report, shortly after
the close of the open season, on the results of the open season and any anchor customer
presubscription, including information on the notice of the open season, the method used
for evaluating bids, the identity of the parties that purchased capacity, and the amount,
term, and price of that capacity.32 The Commission required this report to provide
transparency to the allocation of initial transmission rights, and to enable unsuccessful

31 While negotiations for the allocation of initial transmission rights may address
terms and conditions of the transmission service to be ultimately taken once the facilities
are in service, the Commission will adhere to its policy, regardless of any negotiated
agreement, that any deviations from the Commission’s pro forma OATT must be
justified as consistent with or superior to the pro forma OATT when the transmission
developer files its OATT with the Commission and any deviations will be evaluated on
that basis by the Commission when they are submitted. See Chinook, 126 FERC
¶ 61,134 at PP 47, 63.
32 Chinook, 126 FERC ¶ 61,134 at PP 41, 43.
that any deviations from the Commission’s pro forma OATT must be
justified as consistent with or superior to the pro forma OATT when the transmission
developer files its OATT with the Commission and any deviations will be evaluated on
that basis by the Commission when they are submitted. See Chinook, 126 FERC
¶ 61,134 at PP 47, 63.
32 Chinook, 126 FERC ¶ 61,134 at PP 41, 43.

Docket Nos. AD12-9-000 and AD11-11-000
- 18 -
bidders to determine if they were treated in an unduly discriminatory manner so that they
may file a complaint if they believe they were.33
20.
The Commission now proposes to place more emphasis on reporting, as the
success of the capacity allocation approach proposed here and its ability to prevent undue
discrimination relies, to a noticeable degree, on the transparency this report provides.
Open access requires not only that everyone is given an opportunity to seek access, but
also that entities know how their bids were evaluated and, if they were not selected in the
initial allocation of transmission rights, on what basis that decision was made. If a party
feels it was treated in an unduly discriminatory way, it may file a complaint under section
206 of the FPA; however, parties must have access to the relevant information on the
outcomes of the capacity allocation process to evaluate whether or not they were treated
fairly.
21.
To prevent against undue discrimination by merchant transmission developers, a
report should be submitted shortly after the completion of the open solicitation process
and the resulting negotiations describing the processes that led to the identification of
transmission customers and the execution of the relevant contractual arrangements. The
merchant transmission developer should describe the criteria used to select customers,
any price terms, and any risk-sharing terms and conditions that served as the basis for
identifying transmission customers selected versus those that were not
ons describing the processes that led to the identification of
transmission customers and the execution of the relevant contractual arrangements. The
merchant transmission developer should describe the criteria used to select customers,
any price terms, and any risk-sharing terms and conditions that served as the basis for
identifying transmission customers selected versus those that were not. The Commission

33 See Chinook, 126 FERC ¶ 61,134 at P 41; Montana Alberta Tie, Ltd., 116 FERC
¶ 61,071, at P 37 (2006).

Docket Nos. AD12-9-000 and AD11-11-000
- 19 -
proposes that the developer should include, at a minimum, the following information in
the report to provide sufficient transparency to the Commission and interested parties:
(1) Steps the developer took to provide broad notice;
(2) Identity of the parties that purchased capacity, and the amount, term, and price
of that capacity;
(3) Basis for the developer’s decision to prorate, or not to prorate, capacity, if a
proposed project is oversubscribed;
(4) Basis for the developer’s decision not to increase capacity for a proposed
project if it is oversubscribed (including the details of any relevant technical or
financial bases for declining to increase capacity);
(5) Justification for offering more favorable terms to certain customers, such as
“first movers” or those willing to take on greater project risk-sharing;
(6) Criteria used for distinguishing customers and the method used for evaluating
bids. This should include specific details on how each potential transmission
customer (including both those who were and those who were not allocated
capacity) was evaluated and compared to other potential transmission
customers, both at the early stage when the developer chooses with whom to
enter into bilateral negotiations and subsequently when the developer chooses
in the negotiation phase to whom to award transmission capacity;
n how each potential transmission
customer (including both those who were and those who were not allocated
capacity) was evaluated and compared to other potential transmission
customers, both at the early stage when the developer chooses with whom to
enter into bilateral negotiations and subsequently when the developer chooses
in the negotiation phase to whom to award transmission capacity;
(7) Explanation of decisions used to select and reject specific customers. In
particular, the report should identify the facts, including any terms and
conditions of agreements unique to individual customers that led to their
selection, and relevant information about others that led to their rejection. If a
selected customer is an affiliate, the Commission will look more carefully at
the basis for reaching that determination.
22.
The Commission anticipates that, under this proposed policy, those developers
requesting negotiated rate authority will file this report either in conjunction with their
request for negotiated rate authority or as a compliance filing to a Commission order

Docket Nos. AD12-9-000 and AD11-11-000
- 20 -
approving a request for negotiated rate authority.34 This will allow interested entities to
submit comments on the report, or otherwise protest the contents or insufficiency of the
report, to ensure that there is sufficient transparency, as well as to provide Commission
oversight in the capacity allocation process.35
23.
Beyond the reporting process described above, the Commission does not propose
to change its existing requirement that developers seek Commission approval, either
when the developer requests negotiated rate authority or files its report describing its
capacity allocation approach, if an affiliate is expected to participate as a customer on the
proposed merchant transmission project
s.35
23.
Beyond the reporting process described above, the Commission does not propose
to change its existing requirement that developers seek Commission approval, either
when the developer requests negotiated rate authority or files its report describing its
capacity allocation approach, if an affiliate is expected to participate as a customer on the
proposed merchant transmission project. Further, consistent with Commission precedent,

34 This flexibility in timing acknowledges that parties have filed and may continue
to file requests for negotiated rate authority at various stages of their project development
process.
35 Commenters opposing the Commission’s merchant transmission policy
generally express concern regarding the use and allocation of scarce rights-of-way. The
Commission appreciates the significance of this issue, but has limited authority to address
it directly. Through Order Nos. 890 and 1000, the Commission has increased
transparency in local and regional transmission planning processes, and through this
proposed policy statement seeks to increase transparency in the negotiation of capacity
allocation with merchant transmission and nonincumbent, cost-based, participant-funded
developers. For example, as noted above, the pre-open solicitation notice requirement
and post-open solicitation reporting requirement proposed here require developers to
provide information on any oversubscription of a proposed project. The Commission
anticipates that this kind of information may be useful for relevant entities (such as siting
authorities) as they evaluate whether a proposed transmission facility satisfies applicable
requirements for use and allocation of rights-of-way.
solicitation reporting requirement proposed here require developers to
provide information on any oversubscription of a proposed project. The Commission
anticipates that this kind of information may be useful for relevant entities (such as siting
authorities) as they evaluate whether a proposed transmission facility satisfies applicable
requirements for use and allocation of rights-of-way.

Docket Nos. AD12-9-000 and AD11-11-000
- 21 -
in order to allow affiliate participation, the Commission will expect an affirmative
showing that the affiliate is not afforded an undue preference.36
B.
Nonincumbent, cost-based, participant-funded projects
24.
The Commission proposes to apply the policy reforms above to nonincumbent,
cost-based, participant-funded transmission developers. The Commission has similar
concerns regarding the capacity allocation process regardless of whether the project is a
nonincumbent, cost-based, participant-funded transmission project or a merchant
transmission project. That is, the Commission is concerned that access is not unduly
discriminatory or preferential. We believe that the process outlined herein will address
our concerns regardless of the manner by which transmission rates are determined.
Commenters and workshop participants support the Commission’s application of these
policy reforms to both merchant transmission developers and nonincumbent, cost-based,
participant-funded transmission developers.37
25.
However, use of this common process does not eliminate the distinction between
these types of projects. In particular, although the negotiations between developers and
potential customers could address a transmission rate, among other issues, the
Commission’s approach to reviewing such a rate would be different for a new merchant
transmission project than for a new nonincumbent, cost-based, participant-funded

36 See Chinook, 126 FERC ¶ 61,134 at PP 49-50
rticular, although the negotiations between developers and
potential customers could address a transmission rate, among other issues, the
Commission’s approach to reviewing such a rate would be different for a new merchant
transmission project than for a new nonincumbent, cost-based, participant-funded

36 See Chinook, 126 FERC ¶ 61,134 at PP 49-50.
37 TAPS March 29, 2012 Comments at 24; Pathfinder Renewable Wind Energy,
LLC March 28, 2012 Comments at 3-4.

Docket Nos. AD12-9-000 and AD11-11-000
- 22 -
transmission project. For a merchant transmission project, the Commission relies on the
processes it sets forth to ensure against undue discrimination in the award of capacity and
the willingness of the transmission developer and customers to negotiate a transmission
rate and terms and conditions, understanding that the customers are not captive
customers.38 For a nonincumbent, cost-based, participant-funded transmission project,
the Commission would review the transmission rate, including any agreed upon return on
equity, in greater detail to ensure that it satisfies Commission precedent regarding cost-
based transmission service.
26.
While we are proposing that this capacity allocation process apply equally to
nonincumbent, cost-based, participant-funded projects, we are not proposing to evaluate
such projects based on the other aspects of the four factor analysis set forth in Chinook.39
To the extent nonincumbent, cost-based, participant-funded transmission projects wish to
use an anchor customer-type model, the effect of the proposed policy would be that the
Commission will deem any capacity allocation process that follows the guidelines of this
proposed policy statement to satisfy its concerns regarding undue discrimination and
undue preference.

38 TransEnergie, 91 FERC ¶ 61,230 at 61,836
ission projects wish to
use an anchor customer-type model, the effect of the proposed policy would be that the
Commission will deem any capacity allocation process that follows the guidelines of this
proposed policy statement to satisfy its concerns regarding undue discrimination and
undue preference.

38 TransEnergie, 91 FERC ¶ 61,230 at 61,836.
39 We note, however, that petitions regarding capacity allocation on nonincumbent,
cost-based, participant-funded transmission projects must continue to be evaluated by the
Commission in accordance with the Commissions’ responsibilities under the FPA.

Docket Nos. AD12-9-000 and AD11-11-000
- 23 -
C. Incumbent, cost-based, participant-funded projects
27.
The Commission does not propose to change its case-by-case evaluation of
requests for cost-based participant-funded transmission projects by incumbent
transmission providers.40 As noted above, incumbents differ from nonincumbents in that
the former have a clearly defined set of existing obligations under their OATTs with
regard to new transmission development, including participation in regional planning
processes and the processing of transmission service request queues. Nonincumbent
transmission developers do not yet own or operate transmission facilities in the region
that they propose to develop transmission and, therefore, are not yet subject to an OATT
in that region. The proposed policy laid out above identifies the Commission's policies
regarding the allocation of capacity for merchant transmission developers and
nonincumbent, cost-based, participant-funded projects during the development of a new
transmission facility. In most instances, we would expect that an incumbent transmission
provider will be able to use existing processes set forth in its OATT to allocate capacity
on a new transmission facility
mmission's policies
regarding the allocation of capacity for merchant transmission developers and
nonincumbent, cost-based, participant-funded projects during the development of a new
transmission facility. In most instances, we would expect that an incumbent transmission
provider will be able to use existing processes set forth in its OATT to allocate capacity
on a new transmission facility. These existing OATT processes do not prohibit
incumbent transmission owners from identifying projects that could be constructed on a
participant-funded basis in conjunction with processing of transmission service requests
or in addition to meeting transmission needs through participation in a regional

40 See, e.g., NU/NSTAR; National Grid.

Docket Nos. AD12-9-000 and AD11-11-000
- 24 -
transmission planning process.41 Furthermore, the Commission will continue to entertain
on a case-by-case basis requests for waiver of any OATT requirements that may be
needed for the incumbent transmission owner to pursue innovative transmission
development that is just, reasonable, and not unduly discriminatory. For example, an
incumbent may seek waiver of serial queue processing requirements so that they may
cluster transmission service requests,42 or they may seek to "ring fence" a transmission
project in order to ensure that new transmission facilities developed for a particular
customer or set of customers do not adversely impact existing customers, including
native load.43 Incumbent developers should address the capacity allocation issues in a

41 See, e.g., Subscription Process for Proposed PacifiCorp Transmission
Expansion Projects, available at
http://www.oasis.pacificorp.com/oasis/ppw/SUBSCRIPTION_PROCESS.PDF (noting
incumbent’s solicitation of interest from third parties in the development of a cost-based
transmission project in advance of receipt of transmission service requests from third
parties under the
41 See, e.g., Subscription Process for Proposed PacifiCorp Transmission
Expansion Projects, available at
http://www.oasis.pacificorp.com/oasis/ppw/SUBSCRIPTION_PROCESS.PDF (noting
incumbent’s solicitation of interest from third parties in the development of a cost-based
transmission project in advance of receipt of transmission service requests from third
parties under the incumbent’s OATT).
42 See, e.g., Portland General Electric Co., 139 FERC ¶ 61,133 (2012) (granting
waiver of serial queue processing requirements, allowing a general facilities study for a
cluster of transmission and interconnection service requests).
43 See, e.g., Mountain States Transmission Intertie, LLC and NorthWestern Corp.,
127 FERC ¶ 61,270, at PP 2, 5 (2009) (incumbent developing an export-only
transmission project through a separate stand-alone company so that their existing
transmission customers will not be required to subsidize the cost of a new transmission
facility to serve off-system markets; the Commission presented the option of this project
proceeding on a cost-of-service basis).

Docket Nos. AD12-9-000 and AD11-11-000
- 25 -
manner that does not constitute undue discrimination or preference and is consistent with
the applicable Commission-accepted tariffs.44
IV.
Comment Procedures
28.
The Commission invites comments on this proposed policy statement
[Insert_Date 60 days after publication in the FEDERAL REGISTER].
V.
Document Availability
29.
In addition to publishing the full text of this document in the Federal Register, the
Commission provides all interested persons an opportunity to view and/or print the
contents of this document via the Internet through FERC's Home Page
(http://www.ferc.gov) and in FERC's Public Reference Room during normal business
hours (8:30 a.m. to 5:00 p.m. Eastern time) at 888 First Street, NE, Room 2A,
Washington DC 20426.
30.
From FERC's Home Page on the Internet, this information is available on
eLibrary
interested persons an opportunity to view and/or print the
contents of this document via the Internet through FERC's Home Page
(http://www.ferc.gov) and in FERC's Public Reference Room during normal business
hours (8:30 a.m. to 5:00 p.m. Eastern time) at 888 First Street, NE, Room 2A,
Washington DC 20426.
30.
From FERC's Home Page on the Internet, this information is available on
eLibrary. The full text of this document is available on eLibrary in PDF and Microsoft
Word format for viewing, printing, and/or downloading. To access this document in
eLibrary, type the docket number excluding the last three digits of this document in the
docket number field.
31.
User assistance is available for eLibrary and the FERC’s website during normal
business hours from FERC Online Support at 202-502-6652 (toll free at 1-866-208-3676)

44 See National Grid, 139 FERC ¶ 61,129 at P 33.

Docket Nos. AD12-9-000 and AD11-11-000
- 26 -

or email at ferconlinesupport@ferc.gov, or the Public Reference Room at (202) 502-
8371, TTY (202)502-8659. E-mail the Public Reference Room at
public.referenceroom@ferc.gov.
By the Commission.

( S E A L )

Nathaniel J. Davis, Sr.,
Deputy Secretary.

## Nearby sections

- [77 FERC ¶ 61,263 Policy Statement Establishing Factors the Commission Will Consider in Evaluating Whether A Proposed Merger is Consistent With the Public Interest](https://www.frixlaw.com/law-library/statutes/FERC_RM96_6_000.md)
- [88 FERC ¶ 61,227 Certification of New Interstate Natural Gas Pipeline Facilities](https://www.frixlaw.com/law-library/statutes/FERC_PL99_3_000.md)
- [109 FERC ¶ 61,186 Policy Statement on Credit-Related Issues for Electric OATT Transmission Providers, ISOs & RTOs](https://www.frixlaw.com/law-library/statutes/FERC_PL05_3_000.md)
- [112 FERC ¶ 61,040 Order Further Clarifying Policy Statement on Natural Gas and Electric Price Indices](https://www.frixlaw.com/law-library/statutes/FERC_PL03_3_006.md)
- [120 FERC ¶ 61,060 Section 203 Supplemental Policy Statement](https://www.frixlaw.com/law-library/statutes/FERC_PL07_1_000.md)
- [121 FERC ¶ 61,221 FERC Hydrokinetic Energy Project Policy Statement](https://www.frixlaw.com/law-library/statutes/FERC_PL08_1_000.md)
- [123 FERC ¶ 61,048 Composition of Proxy Groups for Determining and Oil Pipeline Return on Equity](https://www.frixlaw.com/law-library/statutes/FERC_PL07_2_000.md)
- [123 FERC ¶ 61,156 Revised Policy Statement on Enforcement](https://www.frixlaw.com/law-library/statutes/FERC_PL08_3_000.md)
- [125 FERC ¶ 61,058 Compliance with Statutes, Regulations, and Orders](https://www.frixlaw.com/law-library/statutes/FERC_PL09_1_000.md)
- [125 FERC ¶ 61,208 Material Changes in Facts that Require Notifications Under Commission Regulations Under the Public Utility Holding Company Act of 2005](https://www.frixlaw.com/law-library/statutes/FERC_PL09_2_000.md)
- [128 FERC ¶ 61,060 Smart Grid Policy Statement](https://www.frixlaw.com/law-library/statutes/FERC_PL09_4_000.md)
- [129 FERC ¶ 61,248 Policy Statement On Disclosure Of Exculpatory Materials](https://www.frixlaw.com/law-library/statutes/FERC_PL10_1_000.md)
- [130 FERC ¶ 61,220 Policy Statement On Penalty Guidelines](https://www.frixlaw.com/law-library/statutes/FERC_PL10_4_000_20100318.md)
- [132 FERC ¶ 61,216 Revised Policy Statement On Penalty Guidelines](https://www.frixlaw.com/law-library/statutes/FERC_PL10_4_000.md)

---

Source: Frix Law Library, https://www.frixlaw.com/law-library/statutes/FERC_AD12_9_000_20120719. Check the current official text before relying on it. Not legal advice.
