# 7 C.F.R. § 1780.63 (2026): Sewage treatment and bulk water sales contracts

> Federal · Regulations · In force

URL: https://www.frixlaw.com/law-library/statutes/CFR_T7_P1780_S1780_63

## Section

- **Citation:** 7 C.F.R. § 1780.63 (2026)
- **Heading:** Sewage treatment and bulk water sales contracts
- **Jurisdiction:** Federal
- **Kind:** Regulations
- **Status:** In force
- **Text as of:** August 14, 2026
- **Source:** Compiled text
- **Location:** Title 7 CFR: Agriculture / Chapter XVII: RURAL UTILITIES SERVICE, DEPARTMENT OF AGRICULTURE / Part 1780: WATER AND WASTE LOANS AND GRANTS / Subpart C: Planning, Designing, Bidding, Contracting, Constructing and Inspections / § 1780.63: § 1780.63   Sewage treatment and bulk water sales contracts.

## Text

Owners entering into agreements with private or public parties to treat sewage or supply bulk water shall have written contracts for such service and all such contracts shall be subject to the Agency concurrence. Section 1780.62 should be used as a guide to prepare such contracts.

## Nearby sections

- [7 C.F.R. § 1780.53 (2026) § 1780.53   General.](https://www.frixlaw.com/law-library/statutes/CFR_T7_P1780_S1780_53.md)
- [7 C.F.R. § 1780.54 (2026) § 1780.54   Technical services.](https://www.frixlaw.com/law-library/statutes/CFR_T7_P1780_S1780_54.md)
- [7 C.F.R. § 1780.55 (2026) § 1780.55   Preliminary engineering reports and environmental review documentation.](https://www.frixlaw.com/law-library/statutes/CFR_T7_P1780_S1780_55.md)
- [7 C.F.R. § 1780.57 (2026) § 1780.57   Design policies.](https://www.frixlaw.com/law-library/statutes/CFR_T7_P1780_S1780_57.md)
- [7 C.F.R. § 1780.61 (2026) § 1780.61   Construction contracts.](https://www.frixlaw.com/law-library/statutes/CFR_T7_P1780_S1780_61.md)
- [7 C.F.R. § 1780.62 (2026) § 1780.62   Utility purchase contracts.](https://www.frixlaw.com/law-library/statutes/CFR_T7_P1780_S1780_62.md)
- [7 C.F.R. § 1780.63 (2026) § 1780.63   Sewage treatment and bulk water sales contracts.](https://www.frixlaw.com/law-library/statutes/CFR_T7_P1780_S1780_63.md)
- [7 C.F.R. § 1780.67 (2026) § 1780.67   Performing construction.](https://www.frixlaw.com/law-library/statutes/CFR_T7_P1780_S1780_67.md)
- [7 C.F.R. § 1780.68 (2026) § 1780.68   Owner's contractual responsibility.](https://www.frixlaw.com/law-library/statutes/CFR_T7_P1780_S1780_68.md)
- [7 C.F.R. § 1780.70 (2026) § 1780.70   Owner's procurement regulations.](https://www.frixlaw.com/law-library/statutes/CFR_T7_P1780_S1780_70.md)
- [7 C.F.R. § 1780.72 (2026) § 1780.72   Procurement methods.](https://www.frixlaw.com/law-library/statutes/CFR_T7_P1780_S1780_72.md)
- [7 C.F.R. § 1780.74 (2026) § 1780.74   Contracts awarded prior to applications.](https://www.frixlaw.com/law-library/statutes/CFR_T7_P1780_S1780_74.md)
- [7 C.F.R. § 1780.75 (2026) § 1780.75   Contract provisions.](https://www.frixlaw.com/law-library/statutes/CFR_T7_P1780_S1780_75.md)
- [7 C.F.R. § 1780.76 (2026) § 1780.76   Contract administration.](https://www.frixlaw.com/law-library/statutes/CFR_T7_P1780_S1780_76.md)

---

Source: Frix Law Library, https://www.frixlaw.com/law-library/statutes/CFR_T7_P1780_S1780_63. Check the current official text before relying on it. Not legal advice.