## Section

- **Citation:** 50 C.F.R. § 86.72 (2026)
- **Heading:** What if I cannot complete the project during the period of performance?
- **Jurisdiction:** Federal
- **Kind:** Regulations
- **Status:** In force
- **Text as of:** August 14, 2026
- **Source:** Compiled text
- **Location:** Title 50 CFR: Wildlife and Fisheries / Chapter I: UNITED STATES FISH AND WILDLIFE SERVICE, DEPARTMENT OF THE INTERIOR / Part 86: BOATING INFRASTRUCTURE GRANT PROGRAM / Subpart F: Grant Administration / § 86.72: § 86.72   What if I cannot complete the project during the period of performance?

## Text

(a) If you cannot complete the project during the 3-year period of performance, you may ask us for an extension. Your request must be in writing, and we must receive it before the end of the original period of performance.
(b) An extension is considered a revision of a grant and must follow guidance at § 86.101.
(c) We will approve an extension up to 2 years if your request:
(1) Describes in detail the work you have completed and the work that you plan to complete during the extension;
(2) Explains the reasons for delay;
(3) Includes a report on the status of the project budget; and
(4) Includes assurance that you have met or will meet all other terms and conditions of the grant.
(d) If you cannot complete the project during the extension period, you may ask us for a second extension. Your request must be in writing, and we must receive it before the end of the first extension. Your request for a second extension must include all of the information required at paragraph (b) of this section and, it must show that:
(1) The extension is justified;
(2) The delay in completion is not due to inaction, poor planning, or mismanagement; and
(3) You will achieve the project objectives by the end of the second extension.
(e) We require that the Regional Director and the Service's Assistant Director for the Wildlife and Sport Fish Restoration Program approve requests to extend a project beyond 5 years of the grant start date.

## Nearby sections

- [50 C.F.R. § 86.70 (2026) § 86.70   What standards must I follow when constructing a BIG-funded facility?](https://www.frixlaw.com/law-library/statutes/CFR_T50_P86_S86_70.md)
- [50 C.F.R. § 86.71 (2026) § 86.71   How much time do I have to complete the work funded by a BIG grant?](https://www.frixlaw.com/law-library/statutes/CFR_T50_P86_S86_71.md)
- [50 C.F.R. § 86.72 (2026) § 86.72   What if I cannot complete the project during the period of performance?](https://www.frixlaw.com/law-library/statutes/CFR_T50_P86_S86_72.md)
- [50 C.F.R. § 86.73 (2026) § 86.73   How long must I operate and maintain a BIG-funded facility, and who is responsible for the cost of facility operation and maintenance?](https://www.frixlaw.com/law-library/statutes/CFR_T50_P86_S86_73.md)
- [50 C.F.R. § 86.74 (2026) § 86.74   How do I determine the useful life of a BIG-funded facility?](https://www.frixlaw.com/law-library/statutes/CFR_T50_P86_S86_74.md)
- [50 C.F.R. § 86.75 (2026) § 86.75   How should I credit BIG?](https://www.frixlaw.com/law-library/statutes/CFR_T50_P86_S86_75.md)
- [50 C.F.R. § 86.76 (2026) § 86.76   How can I use the logo for BIG?](https://www.frixlaw.com/law-library/statutes/CFR_T50_P86_S86_76.md)
- [50 C.F.R. § 86.77 (2026) § 86.77   How must I treat program income?](https://www.frixlaw.com/law-library/statutes/CFR_T50_P86_S86_77.md)
- [50 C.F.R. § 86.78 (2026) § 86.78   How must I treat income earned after the period of performance?](https://www.frixlaw.com/law-library/statutes/CFR_T50_P86_S86_78.md)

---

Source: Frix Law Library, https://www.frixlaw.com/law-library/statutes/CFR_T50_P86_S86_72. Check the current official text before relying on it. Not legal advice.