# PORT GAMBLE S’KLALLAM TRIBE ADMINISTRATIVE CAMPUS MASTER PLAN

> Briefs, arguments, decisions, and more.

URL: https://www.frixlaw.com/law-library/documents/tribal%3Aport_gamble_sklallam%3A4baf4d64880672e7

## Record

- **Collection:** Tribal code
- **Document type:** Tribal code

## Text

Chapter 06

Appendices

PORT GAMBLE S’KLALLAM TRIBE ADMINISTRATIVE CAMPUS MASTER PLAN

CHAPTER 6: APPENDICES

A
Utilities
Report

PORT GAMBLE S’KLALLAM TRIBE ADMINISTRATIVE CAMPUS MASTER PLAN

CHAPTER 6: APPENDICES

PGST UTILITIES MEMO
A technical memorandum for the utilities
within the administrative campus.

October 11, 2024

Prepared for:
The Port Gamble S'Klallam Tribe
Prepared by:
Zach Barbarick EI,
Jonathan Sweet PE
Ryan Whittle PE
Project Number:
2042681800

PGST Utilities memo

Revision

Description

Author

Date

1.0

Existing utility
conditions

Zach
Barbarick

03/28/2024

2.0

Preliminary
Design

Jonathan
Sweet

07/08/2024

Quality
Check

Project Number: 2042681800

Date

Independent
Review

Date

PGST Utilities memo

The conclusions in this memo are Stantec’s professional opinion, as of the time of the memo, and
concerning the scope described in the memo. The opinions are based on conditions and information
existing at the time the scope of work was conducted and do not take into account any subsequent
changes. This memo relates solely to the specific project for which Stantec was retained and the stated
purpose for which the memo was prepared. It is not to be used or relied on for any variation or extension
of the project, or for any other project or purpose, and any unauthorized use or reliance is at the
recipient’s own risk.
Stantec has assumed that all the information received from The Port Gamble S'Klallam Tribe (the “Client”)
and third parties in the preparation of this memo to be correct. While Stantec has exercised a customary
level of judgment or due diligence in the use of such information, Stantec assumes no responsibility for
the consequences of any error or omission contained therein.
This memo is intended solely for use by the Client in accordance with Stantec’s contract with the Client.
While it may be provided by the Client to applicable authorities having jurisdiction and to other third
parties in connection with the project, Stantec disclaims any legal duty based upon warranty, reliance or
any other theory to any third party, and will not be liable to such third party for any damages or losses of
any kind that may result.

Prepared by:
Signature

Printed Name

Reviewed by:
Signature

Printed Name

Approved by:
Signature

Printed Name
Project Number: 2042681800

PGST Utilities memo

Table of Contents

1

EXECUTIVE SUMMARY ..................................................................................................5

2

GENERAL .........................................................................................................................6

Existing Condition .......................................................................................................................................... 6
Demands 6
Utility Corridor ................................................................................................................................................ 6

3

WATER SYSTEM..............................................................................................................7

Existing Condition .......................................................................................................................................... 7
3.1.1
Supply............................................................................................................................................. 7
3.1.2
Distribution Pressure Zones ........................................................................................................... 7
Demand 8
Recommendations ......................................................................................................................................... 8
3.1.3
Water System Plan......................................................................................................................... 8
3.1.4
Transmission Main ......................................................................................................................... 8
3.1.5
Pressure zones .............................................................................................................................. 8

4

SANITARY SEWER ....................................................................................................... 10

Existing Conditions ........................................................................................................................................ 9
Demand 5
Recommendations ....................................................................................................................................... 11
4.1.1
Septic Tanks ................................................................................................................................. 11
4.1.2
Grease Traps ............................................................................................................................... 11
4.1.3
Sewer System Plan ...................................................................................................................... 11

5

STORMWATER MANAGEMENT .................................................................................. 12

Existing Conditions ...................................................................................................................................... 10
5.1.1
Runoff Capture ............................................................................................................................. 12
5.1.2
Conveyance ................................................................................................................................. 12
5.1.3
Treatment ..................................................................................................................................... 12
Demand 1
Recommendations ......................................................................................................................................... 1
5.1.4
Subarea 1 – The Bluff .................................................................................................................... 1
5.1.5
Subarea 2 – Administrative Campus ............................................................................................. 1
5.1.6
Subarea 3 – Baseball field area ..................................................................................................... 1

6

ELECTRIC POWER ..........................................................................................................2

Existing Conditions ........................................................................................................................................ 1
Demands 5
Recommendations ......................................................................................................................................... 2

7

GAS ...................................................................................................................................3

Existing Conditions ........................................................................................................................................ 2
Demand 3
Recommendations ......................................................................................................................................... 3

8

TELECOMMUNICATIONS ...............................................................................................2

Existing Conditions ........................................................................................................................................ 2
Demand 3
Recommendations ......................................................................................................................................... 3

Project Number: 2042681800

PGST Utilities memo

9

IMPACTED UTILITIES......................................................................................................3

LIST OF TABLES
Table 1 - Avavilable Service ........................................................................................................................ 3

Project Number: 2042681800

PGST Utilities memo

1

EXECUTIVE SUMMARY

In support of the planned redevelopment of the Port Gamble S’Klallam Tribe (Client) administrative
campus as presented in the 2024 Administrative Campus Master Plan, this memo summarizes the
existing utilities serving Subareas 1-3, discusses utilities that will be impacted by planned redevelopment,
and proposes modifications to the various utility systems present on the campus.
The existing utility information contained in this memo was collected from GIS data provided by the Client,
coordination with their staff, as-built plans, and site observation. Site observation was made both in
person and via Google Street View (images dated August 2018). These limited information sources are
adequate given the planning nature of this memo, but the location and size of existing utilities should be
verified by a licensed Surveyor prior to any future design or construction effort. This memo is intended as
a supplement to Campus Development Utility Analysis (Gray & Osborne, Inc, 2018), with an emphasis on
the geographic region of the administrative campus and utilities that are impacted by the proposed
redevelopment described in the 2024 Master Plan update.

Project Number: 2042681800

PGST Utilities memo

2

GENERAL

Ownership
The Client owns and operates the water, sanitary sewer, and stormwater management infrastructure
within the Lower Reservation. Electric and communication infrastructure is owned and maintained by third
parties.

Utility Corridor
Establish a utility corridor whose purpose is to consolidate utility development and operation, present and
future, within a narrow zone through the administrative campus. This will disentangle existing utilities in
time, which will help future planning efforts, minimize service disruption, and maximize developable area
elsewhere on the campus. The utility corridor could be roughly under or alongside the existing campus
circulation road that runs from Little Boston Road, south between the police/courts and the proposed
Administration Buildings, then west along the southernmost circulation road past the youth center and
connecting again to Little Boston Road. Reserve future development within this corridor for utilities and
transportation only.
See Appendix B for location of recommended utility corridor.

Project Number: 2042681800

PGST Utilities memo

3

WATER SYSTEM

Existing Condition
Supply
Two wells actively provide a combined capacity of 288,000 gallons of raw water per day (Gray &
Osborne, Inc, 2018). The active wells are located between the Cultural Resources and Housing/Planning
buildings, and northwest of the Ball Field’s equipment shed. A third emergency/backup well is located
near Gliding Eagle Market; its capacity was not verified and was outside of the scope of this memo.
Raw water from the active wells is conveyed to the Treatment Station located on the North end of the Ball
Field adjacent to Little Boston Road, then to a concrete water reservoir (Main Tank).
A connection from the Kitsap County’s Public Utility District No. 1 (PUD1) water main near Hansville Road
provides pressure and volume during emergency conditions (i.e. low pressure events).

Distribution Pressure Zones
Lower Pressure Zone
The portion of potable water distributed to the PGST community from the main tank under gravity
head and is designated as the Lower Pressure Zone (LPZ). It provides potable water to portions of
the administrative campus, as well as various residential neighborhoods.
Buildings within the administrative campus that are served by the LPZ include the Education Center,
Elder Center, Childhood Education, Cultural Resources, Community Services, and Human
Resources.
Analysis by Gray & Osborne, 2018 determines that the LPZ is not adequate for fire service on
campus.

Upper Pressure Zone
A booster station located north of the campus near Little Boston Road provides additional pressure
for portions of the PGST community at higher elevations known as the Upper Pressure Zone (UPZ).
The UPZ is connected to the LPZ in several other locations via pressure reducing valves (PRV), one
of which is located on campus, southeast of the Administration Building and the Youth Center. The
UPZ provides potable and fire water to portions of the administrative campus, communities east of
and including Cubby Sparks, and the Bud Purser community.
Buildings within the administrative campus that are served by the UPZ include the Administration
Building, Kitchen, Housing/Planning, Library, Health Clinic, Fisheries Wet Lab, and Youth Center.
Analysis by Gray & Osborne, 2018 showed that taking fire flow from the UPZ results in an
unacceptable low pressure in uphill neighborhoods (i.e. S’Klallam Hill), except in the case where the
UPZ is extended by a booster pump provided near the North Reservoir to serve the East
Project Number: 2042681800

PGST Utilities memo

Salmonberries development. GIS indicates that such an improvement has been made to the UPZ, in
which case volume and pressure of the UPZ are expected to adequately service fire flows at the
administrative campus.
See Appendix A – Existing Conditions.

Demand
The new buildings will be sprinklered for fire protection. There will also be increased domestic demand
due to the proposed kitchens, locker rooms, and increased restrooms.

Recommendations
Water System Plan1
Create a water system plan for the Reservation’s water system, as recommended by G&O in 2018.
Having a mathematical model of the entire Reservation’s water system allows the Client to better
understand system-wide impacts resulting from local changes, for example the proposed addition of a
CPZ. A water system plan also enables the Client to discover deficiencies before they manifest, for
example fire flows or emergency conditions, and plan for their resolution before they become a problem.

Transmission Main
It is recommended to convert the existing high pressure main (above 80 psi), currently produced by
pumping to serve the higher elevations of the Upper Reservation, into a transmission main. The
transmission main will distribute water to pressure zones (discussed in detail below) throughout the
Reservation. The transmission main is not suitable for direct domestic or fire service because the
pressure is too high. The transmission main would be routed through Little Boston Road to stay clear of
future Campus redevelopment.

Pressure zones
Campus Pressure Zone (CPZ)
Create a new pressure zone to serve the Campus only. This new Campus Pressure Zone (CPZ) would be
served by the newly created transmission main, with Pressure Reducing Valves (PRV) set to provide
ideal domestic and fire pressures to the Campus, with a service main centrally located within the new
utility corridor, and domestic and fire services to individual campus buildings branching off of this service

1 A detailed evaluation of this intertie’s effectiveness is recommended during the design phase. Interviews

with operations staff revealed that a valve must be manually opened. If this intertie is intended for
emergencies, a more automated solution is recommended. This solution should detect the hydrologic
conditions of the main in real time. See Appendix ? for intertie as-built.
Project Number: 2042681800

PGST Utilities memo

main. Conveyance for the CPZ may utilize existing piping currently serving the UPZ and LPZ onsite
where appropriate.

Lower Pressure Zone (LPZ)
Maintain the pressure zone that currently serves the residential portions of the Lower Reservation south
of the Administrative Campus by connecting to the transmission main via PRVs with set pressure to
provide adequate domestic and residential fire service. The campus will no longer be served by the LPZ.

Upper Pressure Zone (UPZ)
Maintain the pressure zone that currently serves the higher elevation residential neighborhoods. The
campus will no longer be served by the UPZ.
See Appendix B for proposed water layout.

Project Number: 2042681800

PGST Utilities memo

4

SANITARY SEWER

Existing Condition
Service
Each building on the administrative campus is served by sanitary sewer except for the Longhouse
and the Gym because they do not have bathrooms. Each building served with sanitary sewer has
its own septic tank.
The peak sewer flow rate has been calculated at 3,260 gallons per day for the administrative
campus (Gray & Osborne, Inc, 2018).

Conveyance
Buildings drain via gravity pipe from the buildings, through septic tanks, then by gravity sewer
south along Little Boston Road to a pump station, then by force main to the Wastewater
Treatment Facility at the Upper Reservation.

Treatment
A wastewater treatment plant on the Upper Reservation provides sewage treatment for the
majority of the Reservation and has been assessed in the General Sewer/Wastewater Facility
Plan (Gray & Osborne 2013) to be sufficient in capacity to receive and treat all of the sewage
produced on the Reservation through the 20-yr planning period. As a result, we do not see a
further need to analysis the treatment system.
See Appendix A – Existing Conditions.

Demand
In addition to maintaining sewer service to existing buildings to remain, the proposed Administration
Buildings will also require sewer service.

Recommendations
Septic Tanks
Consolidate the existing septic tank effluent pumping (STEP) infrastructure by removing septic tanks at
individual campus buildings and replace with two tanks serving the north and south portions of campus,
with additional capacity in each tank for future growth. This would allow for reduced maintenance and
reduced cost of future development on the campus. If any building sewers are pumped, this would also
allow for consolidation of pumping infrastructure. The north system would serve the Health Clinic,
Childhood Education, Housing/Planning, Library, Longhouse, Elder Center and Education Center. The

Project Number: 2042681800

PGST Utilities memo

south system would serve the new Administration Buildings, Police/Courts, Children and Family Services,
Cultural Resources Center, Fisheries Lab, and Youth Center.

Grease Traps
Buildings with kitchens will require a dedicated grease trap. The south system will also have a
conveyance main that utilizes the new utility corridor. In the long-term, connections from the north zone
could migrate to the south to further leverage the utility corridor.

Sewer System Plan
Create a system plan for the Reservation’s sanitary sewer system. Having a mathematical model of the
entire Reservation’s sewer system allows the Client to better understand system-wide impacts resulting
from local changes, for example, to verify capacity of conveyance within the campus or downstream lift
station serving much of the Reservation. A sewer system plan also the Client to plan for future demand.
See Appendix B for proposed sewer layout.

Project Number: 2042681800

PGST Utilities memo

5

STORMWATER MANAGEMENT

Existing Condition
Runoff Capture
Stormwater from the Longhouse roof drains west directly onto a french drain. The four buildings
adjacent to the Longhouse (Library, Housing/Planning, Elder Center, and Education Center) have
drip chains to french drains. All other buildings on campus have conventional roof drains that are
conveyed with underground piping. Parking lots and site roadways mostly drain to catch basins.

Conveyance
Conveyance from the campus ultimately discharges into one of two natural drainage channels
that flow from east to west into Port Gamble Bay. There is a natural channel north of the campus
opposite Little Boston Road, and another is immediately south of the campus.
Roof drains from the Kitchen, Gym and Administration Building daylight to a vegetated swale that
is east of and parallel to Little Boston Road.
Roof drains from the Food Bank/Special Projects Building, Human Resources Building, and
Community Services Building daylight to a vegetated swale that is in the southeast of the
campus.
Roof drains from the Fisheries Wet Lab flows to a dispersion trench located adjacent to the
southern natural channel.
GIS data provided by the Client did not include stormwater conveyance information.

Treatment
Runoff from parking and site roadways south of the Administration Building are treated in
bioretention ponds located in parking islands south of the Administration Building. Another larger
bioretention pond located in the southwest of the site treats runoff from the Administration
Building roof drains and asphalt surfaces west and south of the Administration Building.
See Appendix A – Existing Conditions.

Project Number: 2042681800

PGST Utilities memo

Demand
The new buildings are likely to increase impervious area on the campus, requiring additional stormwater
treatment capacity.

Recommendations
An Urban Stormwater Assessment is being developed concurrently and is expected to be adopted as
early as October 2024. This document will provide various approved measure to promote protection of
the Bluff. Any stormwater improvements within Subareas 1, 2, or 3 should be in alignment with this Urban
Stormwater Assessment.

Subarea 1 – The Bluff
Improvements along Little Boston Road should be intercepted, possibly via bioswale, to prevent erosive
runoff over the bluff.

Subarea 2 – Administrative Campus
Create a new stormwater facility in front of the proposed Administration Buildings along the frontage of
Little Boston Rd to serve new stormwater demands.

Subarea 3 – Baseball field area
The Master Plan proposes that the existing ball field be converted into a gravel overflow parking lot.
Runoff generated from the new gravel lot should generally slope west and intercepted either by area
drains or a conveyance ditch, where it is to be convey to the existing ditch along Little Boston Road ditch,
and eventually on to an existing stormwater pond. Expand the existing pond as necessary to account for
the increase in runoff.

Project Number: 2042681800

A-1

PGST Utilities memo

6

ELECTRIC POWER + TELECOMMUNICATIONS

Existing Condition
There is a mix of overhead and underground power and telecommunications lines within the
administrative campus.
Campus as-built drawings provided location of lines on parts of the site, supplemented by poles, junction
boxes, meters and building service lines observed using Google Street View.
See Appendix A – Existing Conditions.

Demands
The new Administration Buildings will need electrical power and telecommunications service, but are
anticipated to draw a similar amount of power as the previous Administration Buildings.
The Client has expressed interest in undergrounding of overhead lines on Little Boston Road to achieve a
more scenic view of Port Gamble Bay from the proposed Administration Buildings.

Recommendations
Provide an electrical and telecommunications backbone through the south portion of the new utility
corridor to serve the new Administration Buildings. Other buildings whose electrical or
telecommunications service is disrupted by development of the Administration Buildings can also take
service from these new backbones. Future development should include an extension of this backbone
through the north portion of the utility corridor.
Undergrounding of overhead lines in Little Boston Road would incur a significant cost. It is recommended
that this improvement not be performed at this time, but be reconsidered by the Client after the new
Administration buildings have been occupied for some.
See Appendix B for proposed electrical and telecommunications layout.

Project Number: 2042681800

A-2

PGST Utilities memo

7

GAS

Existing Condition
No indicators of piped natural gas were observed using Google Street View and no natural gas data was
available by GIS. A 50-lb propane tank was observed west of the Health Clinic and maps from Client staff
indicate that other propane tanks exist on the Campus, further suggesting that no piped natural gas is
available.

Demand
The new buildings include multiple kitchens and will therefore need gas supply.

Recommendations
Provide propane tank service to proposed kitchens, consistent with current gas services on the campus.
Future development of gas infrastructure should utilize the new utility corridor.

Project Number: 2042681800

A-3

EXISTING LEGEND
CAMPUS BOUNDARY

WATER METER

EXISTING BUILDING

POST INDICATOR VALVE

UNDERGROUND ELECTRICAL

WATER VALVE

OVERHEAD ELECTRICAL

PRESSURE REDUCING VAULT

TELECOMMUNICATIONS

SEWER CLEANOUT

SEWER FORCEMAIN

TELECOM BOX

GRAVITY SEWER

FIRE DEPARTMENT CONNECTION

STORM POND

STREET LIGHT

UPPER ZONE WATER LINE

SANITARY SEWER MANHOLE

LOWER ZONE WATER LINE

SEPTIC TANK

WELL SUPPLY LINE

PAD MOUNTED TRANSFORMER

WELL

STORM POND

FIRE HYDRANT

WORKING DRAFT - For Discussio

2024.7.31

Stantec Consulting Services Inc.
1687 114th Avenue SE, Suite 100
Bellevue, Washington 98004
Tel:425-289-7333
www.stantec.com

EXISTING LEGEND
CAMPUS BOUNDARY
EXISTING BUILDING
UPPER ZONE WATER LINE
LOWER ZONE WATER LINE
WELL SUPPLY LINE
WELL
FIRE HYDRANT
WATER METER
POST INDICATOR VALVE
WATER VALVE
PRESSURE REDUCING VAULT
FIRE DEPARTMENT CONNECTION
SERVED BY UPPER ZONE WATER LINE
SERVED BY LOWER ZONE WATER LINE

WORKING DRAFT - For Discussio

2024.7.31

Stantec Consulting Services Inc.
1687 114th Avenue SE, Suite 100
Bellevue, Washington 98004
Tel:425-289-7333
www.stantec.com

EXISTING LEGEND
CAMPUS BOUNDARY
EXISTING BUILDING
SEWER FORCEMAIN
GRAVITY SEWER
SEWER CLEANOUT
SANITARY SEWER MANHOLE
SEPTIC TANK
STORM POND

WORKING DRAFT - For Discussio

2024.7.31

Stantec Consulting Services Inc.
1687 114th Avenue SE, Suite 100
Bellevue, Washington 98004
Tel:425-289-7333
www.stantec.com

EXISTING LEGEND
CAMPUS BOUNDARY
EXISTING BUILDING
UNDERGROUND ELECTRICAL
OVERHEAD ELECTRICAL
TELECOMMUNICATIONS
TELECOM BOX
STREET LIGHT
PAD MOUNTED TRANSFORMER

WORKING DRAFT - For Discussio

2024.7.31

Stantec Consulting Services Inc.
1687 114th Avenue SE, Suite 100
Bellevue, Washington 98004
Tel:425-289-7333
www.stantec.com

W

W

W

W

W

W

PRV

TRANSMISSION
- CONTINUE EXISTING UPZ THROUGH
LITTLE BOSTON ROAD.
-TRANSMISSION SERVES LPZ AND CPZ
(SHOWN) AND UPZ (NOT SHOWN).

L
TE
E

E

BOOSTER PUMP

E

W

W

TEEL

W

W

W

TEEL

W

W

E

W

W

W

E

W

TEEL

W

W

E

W

W

TEEL

CAMPUS PRESSURE ZONE (CPZ)
- REPURPOSE EXISTING UPZ AND LPZ PIPING ON CAMPUS.
- CONNECT TO UPZ IN TWO PLACES VIA PRV.
- SET PRV PRESSURES TO ADEQUATELY SERVE CAMPUS'
DOMESTIC AND FIRE SERVICE DEMANDS WITHIN A SINGLE
PRESSURE ZONE.

W

W

W

W

W

W

W
W

W

W

E

W

W

W

W

W
SS

W

E

W

W

SS

TEL

W

E

W

W

W

W

W

W

W

TEL

W

W

E

SS
SS

E

TEL

W

W

E

W

W

E

SS

W

W

PROPOSED LEGEND

E

SS

EXISTING LEGEND
SS

TEL

W

W

CAMPUS BOUNDARY

E

EXISTING BUILDING

W

W

XE

ELECTRICAL LINE

XT

XT

TELECOMMUNICATION LINE

XFM

XFM

SEWER FORCEMAIN

XSS

XSS

GRAVITY SEWER

E

E
TEL

E

SS

XE

TEL

W

W

SS

W

W

W

W

W

E

SS

SS

STORM POND

W
W

W

E

W
W

SS

E

W

SS

SS

W
W

WATER LINE - ADMIN PRESSURE ZONE
W

W

TEEL

FIRE HYDRANT
WM

TEEL

SS
E

WATER LINE - WELL SUPPLY
WELL

WATER METER
POST INDICATOR VALVE
WATER VALVE

L
TEE

SS

PRV

E

TELE

WATER LINE - LOW PRESSURE ZONE

SS

W

W

W

XW

E

W

PRV

XW

SS

W

W

WATER LINE - HIGH PRESSURE ZONE

SS

W

E

E

XW

SS

W

W

SS

PRV

PRESSURE REDUCING VAULT

SCO

SEWER CLEANOUT

TELE

TELECOM BOX

PRV

W

FIRE DEPARTMENT CONNECTION
STREET LIGHT
SANITARY SEWER MANHOLE
SEPTIC TANK

W

LOWER PRESSURE ZONE (LPZ)
-CONNECT TO UPZ VIA PRV TO MAINTAIN
SERVICE TO LITTLE BOSTON COMMUNITY.
- LPZ NO LONGER SERVES CAMPUS.

TEEL

SS

W

W

SS

W

TEEL

SS

W

XW

TFMR

PAD MOUNTED TRANSFORMER
UTILITY CORRIDOR

WORKING DRAFT - For Discuss

2024.9.26

Stantec Consulting Services Inc.
1687 114th Avenue SE, Suite 100
Bellevue, Washington 98004
Tel:425-289-7333
www.stantec.com

E

L
TE
E

PRV

W

W

W

W

W

W

E

W

W
TEEL

W

W

W

TEEL

W

W

E

W
TEEL

W

W

E

W

W

TEEL

W

W

E

W

W

W

W

W

W

W

W

W

W

W

E

W

W

W

W

W
SS

W

E

W

W

SS

TEL

W

E

W

W

W

W

W

W

W

TEL

W

W

E

SS

SS
E

TEL

W

W

E

W

W

E

SS

W

W

CONSOLIDATED STEP SYSTEM - NORTH ZONE
- REMOVE SEPTIC TANKS AT INDIVIDUAL BUILDINGS.
- INSTALL SINGLE SEPTIC TANK OVER EXISTING LINE.
- PROVIDE ADDITIONAL CAPACITY FOR FUTURE GROWTH.

PROPOSED LEGEND

E

SS

EXISTING LEGEND
SS

TEL

W

W

CAMPUS BOUNDARY

E

EXISTING BUILDING

W

W

XE

ELECTRICAL LINE

XT

XT

TELECOMMUNICATION LINE

XFM

XFM

SEWER FORCEMAIN

XSS

XSS

GRAVITY SEWER

E

E
TEL

E

SS

XE

TEL

W

W

W

E

SS

W
W

W
W

SS

SS

SS

W
W

WATER LINE - LOW PRESSURE ZONE
WATER LINE - ADMIN PRESSURE ZONE

W

W

W

W

W

WATER LINE - WELL SUPPLY

FIRE HYDRANT

TEEL

WM

TEEL

SS
E

W

WELL

WATER METER
POST INDICATOR VALVE
WATER VALVE

L
TEE

SS

PRV

E

TELE

XW

SS

W

W

W

XW

E

W

PRV

WATER LINE - HIGH PRESSURE ZONE

SS

W

W

XW

SS

E

W

E

XW

SS

W

W

E

SS

W
W

STORMWATER MANAGEMENT
- INSTALL BIORETENTION PONDS ALONG
LITTLE BOSTON ROAD FRONTAGE.

TEEL

SS

E

W

SS

W

TEEL

SS

STORM POND

W

W

SS

PRV

PRESSURE REDUCING VAULT

SCO

SEWER CLEANOUT

TELE

TELECOM BOX

PRV

SS

FIRE DEPARTMENT CONNECTION
W

STREET LIGHT
SANITARY SEWER MANHOLE
W

SEPTIC TANK

CONSOLIDATED STEP SYSTEM - SOUTH ZONE
- REMOVE SEPTIC TANKS AT INDIVIDUAL BUILDINGS.
- LAY SEWER MAIN WITHIN UTILITY CORRIDOR.
- INSTALL SINGLE SEPTIC TANK.
- PROVIDE ADDITIONAL CAPACITY FOR FUTURE GROWTH.

TFMR

PAD MOUNTED TRANSFORMER
UTILITY CORRIDOR

WORKING DRAFT - For Discuss

2024.9.26

Stantec Consulting Services Inc.
1687 114th Avenue SE, Suite 100
Bellevue, Washington 98004
Tel:425-289-7333
www.stantec.com

E
L
TE
E

PRV

W

W

W

W

W

W

E

W

W
TEEL

W

W

W

TEEL

W

W

E

W
TEEL

W

W

E

W

W

TEEL

W

W

E

W

W

W

W

W

W

W

W
W

W

W

E

W

W

W

W

W
SS

W

E

W

W

SS

TEL

W

E

W

W

W

W

W

W

W

TEL

W

W

E

SS
SS
E

TEL

W

W

E

W

W

E

SS

W

W

SS
E

EXISTING LEGEND
SS

TEL

W

W

PROPOSED LEGEND

E

CAMPUS BOUNDARY

W

W

EXISTING BUILDING
XE

ELECTRICAL LINE

XT

XT

TELECOMMUNICATION LINE

XFM

XFM

SEWER FORCEMAIN

XSS

XSS

GRAVITY SEWER

E

SS

XE

TEL

W

W

W

E

SS

W

E

E
TEL

SS

SS

W

W

W

W

STORM POND

W

W

E

TEEL

W
W

XW

WATER LINE - LOW PRESSURE ZONE
WATER LINE - ADMIN PRESSURE ZONE

W

W

SS

WATER LINE - WELL SUPPLY
WELL

TEEL

FIRE HYDRANT
WM

WATER METER
POST INDICATOR VALVE

L
TEE

SS

SS

SS

W

XW

SS

WATER VALVE

E
PRV

PRESSURE REDUCING VAULT

SCO

SEWER CLEANOUT

TELE

TELECOM BOX

SS

PRV

W

FIRE DEPARTMENT CONNECTION
STREET LIGHT
SANITARY SEWER MANHOLE

W

PRV

E

TELE

TEEL

SS

W

W

W

WATER LINE - HIGH PRESSURE ZONE

E

W

PRV

XW

E

W
W

XW

SS

W

W

E

W

SS

W

W

SS

W

TEEL

E

SS

W

SS

W

SS

W

SEPTIC TANK
TFMR

PAD MOUNTED TRANSFORMER
UTILITY CORRIDOR

WORKING DRAFT - For Discussio

2024.9.26

Stantec Consulting Services Inc.
1687 114th Avenue SE, Suite 100
Bellevue, Washington 98004
Tel:425-289-7333
www.stantec.com

B
Soil and
Geotechnical
Report

PORT GAMBLE S’KLALLAM TRIBE ADMINISTRATIVE CAMPUS MASTER PLAN

CHAPTER 6: APPENDICES

Preliminary Geotechnical Study
Port Gamble S’Klallam Tribe – Administrative
Campus Master Plan
Kingston, Washington
for
Port Gamble S’Klallam Tribe
May 15, 2024

1101 South Fawcett Avenue, Suite 200
Tacoma, Washington 98402
253.383.4940

Preliminary Geotechnical Study
Port Gamble S’Klallam Tribe – Administrative
Campus Master Plan
Kingston, Washington
File No. 0181-010-00
May 15, 2024
Prepared for:
Port Gamble S’Klallam Tribe
c/o Stantec Consulting Services, Inc.
720 Third Avenue, Suite 1500
Seattle, Washington 98104
Attention: Ryan Whittle

Prepared by:
GeoEngineers, Inc.
1101 South Fawcett Avenue, Suite 200
Tacoma, Washington 98402
253.383.4940

Christopher R. Newton, PE
Senior Geotechnical Engineer

Dennis (D.J.) Thompson, PE
Associate Geotechnical Engineer
CRN:DJT:atk
Disclaimer: Any electronic form, facsimile, or hard copy of the original document (email, text, table, and/or figure), if provided, and any attachments are only a copy
of the original document. The original document is stored by GeoEngineers, Inc. and will serve as the official document of record.

Port Gamble S’Klallam Tribe c/o Stantec Consulting Services, Inc. | May 15, 2024

Table of Contents
1.0 Introduction and Project Description .............................................................................. 1
2.0 Scope Of Services ......................................................................................................... 1
3.0 Site Conditions ............................................................................................................. 1
3.1 Site Limits and Vicinity.................................................................................................................. 1
3.2 Literature Review .......................................................................................................................... 2
3.2.1

Geologic Mapping .............................................................................................................. 2

3.2.2

Natural Resources Conservation Service Description .................................................... 3

3.2.3

Critical Areas: Geologic Hazards....................................................................................... 4

4.0 Geotechnical Engineering Evaluation ............................................................................. 5
4.1 General .......................................................................................................................................... 5
4.2 Anticipated Soil and Groundwater Conditions ............................................................................ 6
4.3 Seismic Site Class ......................................................................................................................... 6
4.4 Foundation Support ...................................................................................................................... 6
4.5 Retaining Walls and Below-Grade Structures ............................................................................. 7
4.5.1

General............................................................................................................................... 7

4.5.2

Gravity Walls ...................................................................................................................... 8

4.5.3

Shoring and Other Walls ................................................................................................... 8

4.5.4

Preliminary Design ............................................................................................................ 9

4.6 Infiltration Feasibility Assessment ............................................................................................... 9
4.7 Earthwork Considerations ............................................................................................................ 9
4.7.1

Stripping, Clearing, and Subgrade Preparation ............................................................... 9

4.7.2

Wet Weather Considerations .......................................................................................... 10

4.7.3

Cut and Fill Slopes........................................................................................................... 10

4.7.4

Groundwater Handling .................................................................................................... 10

4.7.5

Fill Materials and Compaction ........................................................................................ 11

5.0 Recommendations for Further Studies ......................................................................... 12
6.0 Limitations.................................................................................................................. 13
7.0 References.................................................................................................................. 13
List of Figures
Figure 1. Vicinity Map
Figure 2. Site Plan
Figure 3. Lidar Map
Figure 4. Geologic Map
Figure 5. Soil Survey Map
Figure 6. Seismic Hazards Map

Appendices
Appendix A. Report Limitations and Guidelines for Use
File No. 0181-010-00

i

Port Gamble S’Klallam Tribe c/o Stantec Consulting Services, Inc. | May 15, 2024

Page 1

1.0 Introduction and Project Description
GeoEngineers, Inc. (GeoEngineers) is pleased to present this preliminary geotechnical study for the
Port Gamble S’Klallam Tribe - Administrative Campus Master Plan project. The project site is located at
31912 Little Boston Road NE (Tribal Headquarters) in Kingston, Washington, as shown in the Vicinity Map,
Figure 1.
Our understanding of the project is based on discussions with you and review of Stantec’s Preliminary Base
Maps dated February 2024. We also reviewed the “AS BUILTS, ADMINISTRATION CAMPUS PROJECT: CIVIL
DRAWINGS, PORT GAMBLE INDIAN RESERVATION” dated November 7, 2011, prepared by U.S. Department
of the Interior, Bureau of Indian Affairs.
The overall project consists of developing a master plan for design and construction of a new multi-story
Administration Building with below-grade parking and associated improvements. The proposed
development areas are shown as Subareas 1 through 3 in the Site Plan, Figure 2. The new Administration
Building is planned to be constructed in Subarea 1. The master planning process will include a review and
analysis of the existing site, public engagement to gather input and feedback to proposed master plan
concepts, cost estimates on the preferred and final master plans, and associated phasing and funding
strategies. We envision geotechnical-related project elements could include shallow foundations and
below-grade building wall design, temporary cut slopes and/or shoring, site grading, new pavement areas,
stormwater facilities, and underground utility installation.

2.0 Scope Of Services
For our study, we reviewed existing information in the project vicinity to develop an understanding of surface
and subsurface conditions in the area. Based on this information, we have prepared this report providing
our preliminary opinion on the suitability of the considered Subareas 1 through 3 for future development
with regards to geotechnical considerations. The results of our services are intended to support decisions
regarding site selection, preliminary project engineering, and future planning. This is a preliminary
geotechnical study and is not intended to support final design of site improvements. Additional geotechnical
services, including site specific explorations and other engineering design and analysis will be required to
support final design for future development.
Our services have been provided in accordance with our signed agreement with Stantec dated
January 5, 2024.

3.0 Site Conditions
3.1

SITE LIMITS AND VICINITY

The Tribal Headquarters Campus (Campus) is occupied by several buildings for administration and
education and includes a gymnasium, a library, health clinics, police, court, and other services. A ball field
is located near the northeast corner of the Campus. Other site features include landscaping, asphalt
pavements, sidewalks, and drainage features such as swales and ditches.

File No. 0181-010-00

Port Gamble S’Klallam Tribe c/o Stantec Consulting Services, Inc. | May 15, 2024

Page 2

The proposed development areas are shown as Subareas 1 through 3 in the Site Plan, Figure 2. Subarea 1
is in the southwest quadrant of the site and currently includes the existing Administration Building, Natural
Resources, gymnasium, kitchen, playground, and parking. Subarea 2 is toward the west of the Campus,
and contains a few vacant homes, a tribal arts center, and cemetery. Subarea 3 is in the north-central
portion of the Campus on the northwest edge of the ball field, adjacent to a parking lot driveway and Little
Boston Road NE.
The project site is bordered to the north by Little Boston Road NE and forested area to the east and south.
Little Boston Road NE also intersects the site on the western half between the Campus and Subarea 2 A
bluff separates the upland Subarea 2 from Port Gamble Bay to the west. Overall, project site topography is
generally flat, as shown by the lighter shading in the Lidar Map, Figure 3. Other topographic features at or
near the site shown on the Lidar Map include a stream or creek channel ravine to the north of site, a stream
or creek channel running through the southeast corner of the site, and a shallow ravine on the southwest
corner of the site.

3.2

LITERATURE REVIEW

3.2.1 Geologic Mapping
We reviewed the Washington State Department of Natural Resources (DNR) Geologic Information Portal to
develop an understanding of site geology using the 1:100,000-scale (100k) surface mapping. The mapping
reports glacial soils underlie the site and surrounding areas. Soils present below glacial ice are glacially
overridden (glacially consolidated) and typically dense to very dense; these soils are generally characterized
by relatively high strength, high allowable bearing pressures, and low compressibility. Examples of glacially
consolidated soils include glacial till, advance glacial outwash, and glacial drift. Soils deposited after glacial
recession were not glacially overridden and, in general, are relatively less dense. Examples of post-glacial
soils include alluvium (river and stream deposits) and recessional glacial outwash.
Per the DNR Geologic Information Portal, four geologic units are mapped at or adjacent to the site, and are
shown on the Geologic Map, Figure 4:

■ Continental Glacial Outwash, Fraser-age (Qgo): Mapped along the northwest half of the site and
contains most of Subareas 2 and 3. Glacial outwash typically consists of a mixture of sand and gravel
in a loose to dense condition and can include localized coarser- or finer-grained constituents. Glacial
outwash is deposited from meltwater from a receding glacier and commonly overlies glacial till and is
not glacially consolidated. Cobbles and boulders can be present within glacial outwash deposits. In this
report we refer to material mapped as Continental glacial outwash as “recessional outwash.”

■ Continental Glacial Till, Fraser-age (Qgt): Mapped over the southeast half of the site and contains

most of Subarea 1. Glacial till typically consists of a compact mixture of clay, silt, sand, and gravel.
Cobbles and boulders can be present within glacial till deposits. It is not uncommon for the upper few
feet of glacial till to be weathered and relatively less dense.

■ Continental Glacial Drift, pre-Fraser (Qgp): Mapped at and adjacent to the southwest corner of the
site. In the region, pre-Fraser glacial drift typically consists of clay, silt, sand, and gravel that is in a
medium dense to very dense condition.

File No. 0181-010-00

Port Gamble S’Klallam Tribe c/o Stantec Consulting Services, Inc. | May 15, 2024

Page 3

■ Advance Continental Glacial Outwash, Fraser-age (Qga[t]): Mapped at and adjacent to the southeast

corner of the site. Advance glacial outwash (advance outwash) typically consists of sand and gravel
that is deposited by meltwater in front of an advancing glacier and then overridden by the glacier and
is generally observed to be in a dense to very dense condition. Advance outwash commonly underlies
glacial till, and a gradual transition in material gradation may be present upward into the overlying
glacial till. Cobbles and boulders can be present within advance outwash deposits.

Although not mapped, we anticipate fill placed during previous site development activities (i.e., establishing
building pad elevations and grading for parking lot and driveway surfaces) are present at the site.

3.2.1.1

WATER WELL INFORMATION

We searched the DNR Geologic Information Portal for water well log reports in the project vicinity. Our
search identified two water well log reports located at residential properties about 1 to 1.1 miles north of
the project site. Reported subsurface information from the reviewed water well log reports are shown in
Table 1 below.

TABLE 1. SUBSURFACE INFORMATION FROM WELL LOGS
REPORTED DEPTH TO STATIC GROUNDWATER
(DATE OF MEASUREMENT)

WELL LOCATION

WELL DEPTH

REPORTED SOIL CONDITIONS

33700 Hood
Canal Drive NE

88 feet

57 feet
(09/23/92)

“Till” and sand and gravel

33787 Hood
Canal Drive NE

161 feet

80 feet
(03/18/93)

“Hard pan,” sand and gravel, clay

Soils reported in the reviewed well log reports appear to predominantly consist of glacial deposits. Based
on review of Google Earth, the ground surface elevations between the above two properties appear to differ
by at least 30 feet, with the 33787-property shown to be lower in elevation. We interpret static groundwater
levels reported in the reviewed well log reports to be representative of a deeper regional groundwater
table(s) in the project vicinity. Due to the ground surface elevation difference between the above properties
and where static groundwater levels are reported in each well, it is possible that they are two different
aquifers, with the well installed at the 33787-property targeting a deeper aquifer than the well at the
33700-property. Shallower perched groundwater could also be present in the project vicinity, as described
in the “Anticipated Soil and Groundwater Conditions” section of this report.

3.2.2 Natural Resources Conservation Service Description
According to the Natural Resources Conservation Service (NRCS) Web Soil Survey, the project site is
underlain by the three soil types shown on the Soil Survey Map, Figure 5: Indianola-Kitsap complex, 45 to
70 percent slopes (Map Unit 21), Kitsap silt loam, 2 to 8 percent slopes (Map Unit 28), and Ragnar fine
sandy loam, 0 to 6 percent slopes (Map Unit 44). The parent materials of these soils mapped at the site
are primarily derived from glacial deposits, which is generally consistent with the above geologic mapping.
Additional information pertaining to each mapped soil type is presented in Table 2 below.

File No. 0181-010-00

Port Gamble S’Klallam Tribe c/o Stantec Consulting Services, Inc. | May 15, 2024

Page 4

TABLE 2. NRCS MAPPED SOIL TYPES
EROSION HAZARD
RATING

SOIL TYPE
Indianola-Kitsap
complex

Severe

HYDROLOGIC
SOIL GROUP

PARENT MATERIAL
Indianola: Glacial outwash

Indianola: A

Kitsap: Lacustrine deposits with
volcanic ash in the upper part

Kitsap: C

COMMENTS
Indianola: Described as
“somewhat excessively
drained” with a “high”
capacity of the most limiting
layer to transmit water.
Kitsap: Described as
“moderately well drained”
with a “moderately low to
moderately high” capacity of
the most limiting layer to
transmit water.

Kitsap silt loam

Moderate

Lacustrine deposits with
volcanic ash in the upper part

C

Described as “moderately
well drained” with a
“moderately low to
moderately high” capacity of
the most limiting layer to
transmit water.

Ragnar fine
sandy loam

Slight

Glacial outwash with some
volcanic ash in the upper part

A

Described as “well drained”
with a “high” capacity of the
most limiting layer to transmit
water.

3.2.3 Critical Areas: Geologic Hazards
Per the Kitsap County Critical Areas Map, most of Subarea 2 along the western bluff side is mapped as a
“high” geologically hazardous area, which is categorized for areas of high erosion hazard, and/or landslide
hazard, and/or seismic hazard. We also reviewed the Kitsap County Geologically Hazardous Maps related
to landslide, erosion, and seismic hazards. A general discussion of these geologic hazards is provided in
the sections below and should be reviewed in coordination with other jurisdictional requirements, as project
design progresses.

3.2.3.1

LANDSLIDE HAZARDS

Per the Kitsap County Landslide Hazards Map, Subarea 2 along the western bluff side is mapped as
“moderate” for shallow and deep landslides. The Kitsap County Critical Areas Map defines “moderate”
landslide hazards as:

■ Shallow landslides with factors of safety (FS) of 1.5 to 2.5; and/or
■ “Slopes of 15 percent or greater and not classified as I, U, UOS, or URS (intermediate, unstable,

unstable old slide, or unstable recent slide as defined by the Coastal Zone Atlas), with soils classified
by the U.S. Department of Agriculture NRCS as ‘highly erodible’ or ‘potentially highly erodible; or slopes
of 15 percent or greater with springs or groundwater seepage;” and/or;

■ Slopes in all areas equal to or greater than 40 percent (2.5H:1V [horizontal to vertical]).

File No. 0181-010-00

Port Gamble S’Klallam Tribe c/o Stantec Consulting Services, Inc. | May 15, 2024

Page 5

According to the DNR Geologic Information Portal, no known landslides or landslide hazard areas are
mapped at the site. The Coastal Zone Atlas (presented on the Washington State Department of Ecology’s
online Coastal Atlas Map) appears to have eliminated this site area from their mapping.

3.2.3.2

EROSION HAZARDS

Per the Kitsap County Erosion Hazards Map, most of Subarea 2 along the western bluff side is mapped as
“high” for coastal erosion and the channel migration zone. The Kitsap County Critical Areas Map defines
high erosion hazards as:

■ Areas with coastal erosion having a “sediment source rating value of 0.6 to 1.0;” and/or
■ Channel migration zones that are mapped by the Washington State Department of Ecology.
The Kitsap County Erosion Hazards Map is generally consistent with the NRCS “severe” erosion hazard
rating defined in Table 2 above for the Indianola-Kitsap complex soil unit, which occupies most of
Subarea 2.

3.2.3.3

SEISMIC HAZARDS

Per the Kitsap County Seismic Hazards Map, no seismic hazards were mapped at the site. According to the
DNR Geological Information Portal, the approximate northwest half of the site is mapped as “low” potential
for liquefaction, while the approximate southeast half is mapped as “very low.” Further, the nearest mapped
fault or other seismogenic feature is more than 1 mile away from the site. For reference, a portion of the
seismic hazards map from the DNR Geological Information Portal is reproduced in this report as Figure 6.
Based on the reviewed seismic mapping, our understanding of site geology, and anticipated soil conditions,
it is our opinion the site has low potential for liquefaction and seismic surface rupture caused by faults and
other seismogenic features. Based on our assessment of the potential for soil liquefaction and current site
topography, in our opinion this site also has a low potential for lateral spreading.

4.0 Geotechnical Engineering Evaluation
4.1

GENERAL

Based on our review of soil and geologic information described above, it is our opinion that the project site
is generally suitable for development with regards to geotechnical considerations. However, for
development at Subarea 2, we recommend additional critical area studies be conducted and reviewed in
regard to infrastructure location since most of this area is identified by Kitsap County as a geologic hazard
related to landslides and erosion, as described above. As such, we envision that development at Subarea 2
will be more limited, depending on the results of a geologic critical area study, and likely will be constrained
by slope setback buffers and special erosion protection measures. We anticipate potential erosion hazards
can be mitigated through engineering controls such as limiting ground disturbance, site grading, planting,
and other erosion control measures.
We did not identify geotechnical related conditions that would prohibit or significantly constrain overall
project design and construction at Subareas 1 and 3. Regardless, the project layout and design will need
to incorporate geotechnical considerations as discussed herein. In our opinion, these geotechnical
considerations can be managed through appropriate site layout, engineering design, and construction
methods.

File No. 0181-010-00

Port Gamble S’Klallam Tribe c/o Stantec Consulting Services, Inc. | May 15, 2024

Page 6

Preliminary recommendations provided in the sections below are intended to support initial design
development, preliminary engineering, cost estimating, and future site planning. These recommendations
are not intended to support final project design. Ultimately, we recommend site and project specific
geotechnical explorations and analysis be completed as a part of final design of future improvements. Refer
to the “Recommendations for Further Studies” section below for discussion and considerations on further
geotechnical studies at the site.

4.2

ANTICIPATED SOIL AND GROUNDWATER CONDITIONS

Soil conditions at the site are expected to consist of a variable thickness of topsoil and fill underlain by
glacial soils. Fill thickness is expected to be greatest in areas of past development or areas where prior
grading activities were completed. Topsoil (and forest duff) thicknesses are expected to be greatest in
undeveloped forested areas (east and south edges of the site). Based on overall topography and
surrounding site grade, we expect that, with the exception of isolated areas, topsoil and fill units will likely
be less than a few feet thick at this site.
Underlying the topsoil and fill, and as described above, we anticipate the northwest half of site (Subareas 2
and 3) to consist of recessional outwash (Qgo) and the southeast half (Subarea 1) glacial till (Qgt). The
recessional outwash will likely consist of medium dense sand and gravel with variable silt and cobble
content. The glacial till will likely consist of dense to very dense silty sand with variable gravel and cobble
content. Boulders could be present within these glacial soils at the site. We also anticipate that the upper
few feet of the glacial soils could be weathered and relatively less dense than underlying intact soils.
Based on our understanding of site geology, it is our opinion that the groundwater well data described
above is not enough information to infer groundwater depths at the project site. Typically, in upland areas
of glacial deposits like this project site, we observe static groundwater deeper than 10 feet, and we envision
groundwater to be near the same elevation as the nearby creeks described previously. However, perched
groundwater could be encountered at relatively shallow depths across the site. Perched groundwater is
typically due to infiltration of surface water that slows or terminates atop underlying less permeable layers
of soil (e.g., on top of glacial till deposits). The presence of fill, discontinuities, utilities, and other factors
also influence the presence and volume of perched water.

4.3

SEISMIC SITE CLASS

We assume improvements will be designed in accordance with the International Building Code (IBC). The
2021 edition of the IBC state structures shall resist the effects of earthquake motions in accordance with
American Society of Civil Engineers (ASCE) 7-16 “Minimum Design Loads and Associated Criteria for
Buildings and Other Structures.” In accordance with IBC 2021 and ASCE 7-16, we recommend a seismic
Site Class D be considered for preliminary, simplified code-based seismic design and analysis. As planning
and design progresses, site exploration and testing should be completed to confirm the seismic Site Class.
Based on project location, there is a possibility that Site Class C may be appropriate with additional
explorations and studies.

4.4

FOUNDATION SUPPORT

We envision that structures at this site can be adequately supported on shallow foundations and slab-ongrade floors bearing on existing site soils. Shallow foundations should be established at least 18 inches
below the lowest adjacent grade, primarily for frost protection. Interior column footings can be founded a
minimum of 12 inches below the bottom of the interior floor slabs. Isolated spread footings should have a
minimum width of 24 inches. Continuous spread footings for walls should be at least 18 inches wide.

File No. 0181-010-00

Port Gamble S’Klallam Tribe c/o Stantec Consulting Services, Inc. | May 15, 2024

Page 7

The presence of fill should be evaluated during any final studies to determine if the fill is suitable for bearing
support. Re-compaction and/or removal and replacement of existing fill beneath foundations may be
required depending on the condition, amount of organic and/or deleterious material, and overall matrix.
Ultimately, foundation bearing support recommendations will depend on soil type, structure loads,
foundation elevations, and performance requirements and should be incorporated as part of future
geotechnical studies.
Topsoil, or soils with a high organic content, will need to be completely removed from below foundations
and foundation elements. For preliminary design, we estimate allowable soil bearing resistance of near
surface soils (including existing fill and weathered glacial soils) will be on the order of 2,000 to
3,000 pounds per square foot (psf). Higher bearing resistances (3,000 to 6,000 psf) will likely be
achievable if foundations are supported directly on undisturbed glacially consolidated soils (i.e., glacial till
or advance outwash) at depth. For preliminary planning, increasing these values by about one third may be
considered for transient or infrequent extreme loading conditions, such as forces induced by earthquakes.
For the bearing conditions and resistances presented above, we anticipate that total and differential
foundation settlements can be limited to 1 and ½ inch, respectively, for typical foundation sizes and
structures considered.
Lateral resistance for building design is typically accommodated from backfill around foundation elements
and as friction developed on the bottom of foundations. For published soil types and structural fills
anticipated for this site, we suggest a preliminary value of 300 pounds per cubic foot (pcf) as a passive
resistance for native materials or structural fill against embedded elements. A coefficient of friction for
concrete against anticipated soil materials can be assumed to be around 0.40. These values include a
factor of safety of about 1.5.
Slab-on-grade floors can likely be adequately supported on existing fill and/or underlying glacial soils.
Subgrades for slab-on-grade floors should be compacted to a uniformly firm and unyielding condition. For
preliminary design, floor slab loads should be limited to 300 psf. Typical in-place subgrade modulus values
on the order of 200 to 300 pounds per cubic inch (pci) are common in glacial deposits. For mat foundations
or larger footings, modifications to this value may be required depending on the specific foundation sizes
used in design.

4.5

RETAINING WALLS AND BELOW-GRADE STRUCTURES

4.5.1 General
We anticipate retaining walls may be required to maintain desired site grades and construct below-grade
elements (i.e., basement parking for the new Administration Building). The specific retaining wall type used
will depend in part on the application and wall height. For this site, we expect that modular block walls,
cast-in-place walls, structural earth walls, soil nail walls, and soldier piles walls are all feasible for use.
Additional excavation to develop stable temporary slopes behind retaining walls are commonly required for
worker safety and for construction access and should also be considered in overall planning. Sites with
limited area for back slope excavations may require a different type of shoring or retaining wall system.

File No. 0181-010-00

Port Gamble S’Klallam Tribe c/o Stantec Consulting Services, Inc. | May 15, 2024

Page 8

4.5.2 Gravity Walls
Cast-in-place walls may be considered in either cut or fill applications and are typically most efficient for
intermediate wall heights that are taller than about 5 feet but less than about 10 feet. Typically, foundation
base widths of at least half the height of the wall are required for weight and overall stability. This width
can be modified by the use of keyways and other foundation geometry options as determined by a structural
engineer.
Modular block walls typically consist of larger blocks of concrete stacked in a staggered pattern on-top of
each other. Examples include “ecology block” walls and other segmental-type block walls (i.e., Redi-Rock,
Hilfiker, SierraScape, Ultra Block, etc.). Modular block walls are typically most effective for relatively short
walls (less than about 6 feet tall) and can be used in cut and fill grading applications. Modular block walls
taller than about 6 feet will require additional considerations including revised base width design and
additional batter (angle away from vertical).
Structural earth walls are also a type of modular block wall but typically encompass smaller or different
blocks (Keystone, Redi-Rock, Mesa, SierraScape, etc.) as facing and include reinforcing grid or “geo-grid”
installed behind the facing. Typical vertical spacing between the grid is about 18 to 24 inches. Grid lengths
are typically about 70 to 90 percent of the wall height and decrease in overall lengths near the bottom of
the wall. Structural earth walls are best suited for use in fill applications and can be designed to retain
grade differentials greater than 20 feet.

4.5.3 Shoring and Other Walls
Soil nail and soldier pile walls are best suited for cut wall applications and are most often used to retain or
reinforce tall slopes or as temporary shoring to construct below-grade building elements. These wall types
are commonly used where site constraints do not allow for temporary cut slopes, where the excavation
needs to be limited to the building or work area, where movement of nearby structures and/or utilities
needs to be limited or applies a surcharge loading. Both wall types are constructed as the excavation is
advanced, i.e., “top-down construction”. The use of tiebacks for soldier pile walls, or “nails” for soil nail
walls requires horizontal space or soil area behind the wall. The tiebacks or nails may encroach upon
rights-of-way or into other structures. This should be a consideration as a part of determining wall type.
Soldier pile walls are constructed with vertical steel “H” piles installed in a drilled hole (typically 24 to
36 inches in diameter) and filled with lean-mix or structural concrete. The piles are typically spaced 5 to
10 feet apart. The space between piles is typically spanned with wood lagging, shotcrete, or pre-cast
concrete panels. Depending on loading conditions, depth of excavation, and other conditions, tie-back
anchors that are connected to the H piles can be installed for additional lateral support. Typically, soldier
pile walls taller than about 15 feet are more economical to build with the use of tie- back anchors.
Soil nail walls are constructed in lifts by first excavating about 3-to-5-feet and drilling near horizontal 6- to
8-inch diameter holes and installing a steel threadbar nail into the hole. This is done throughout the wall
spacing, typically 6 to 10 feet on-center but with each row staggered. Each lift is completed by placing steel
reinforcing over the cut face and nails, followed by shotcrete facing, and a bearing face plate and nut at
the exposed end of the soil nail. Each 3-to-5-foot lift is finalized before excavating another lift. For some soil
types that are more prone to raveling and caving, vertical elements are drilled and installed before
excavation to help support the cut face while the soil nail wall is constructed.

File No. 0181-010-00

Port Gamble S’Klallam Tribe c/o Stantec Consulting Services, Inc. | May 15, 2024

Page 9

4.5.4 Preliminary Design
For preliminary planning purposes, we recommend evaluating walls using an active equivalent fluid density
of 35 pounds per cubic foot (pcf) (triangular distribution). This assumes that the walls will not be restrained
against rotation when backfill is placed and the backfill behind the wall is level. For walls restrained from
rotation at the top (i.e., at-rest condition), an equivalent fluid density of 55 pcf (triangular distribution) can
be used. These values assume drained conditions behind the wall (i.e., do not account for the effects of
hydrostatic conditions). For sloping backfill conditions up to 2H:1V, this value should be increased by about
50 percent.
Lateral resistance of retaining walls can be evaluated assuming a passive equivalent fluid density of
300 pcf and an allowable frictional resistance of 0.4 (these values include a factor of safety of about 1.5).
These values must be confirmed as part of the final design.
Retaining walls should be designed with a drainage system to prevent the buildup of hydrostatic pressures
behind the wall. This is typically accomplished with a zone of free draining material placed behind the wall,
on the order of 18 inches in thickness, for nearly the full height of the wall. The drainage material should
be connected to a perforated rigid piping placed near the bottom of the wall and sloped to drain to an
appropriate discharge. “Waffle” drain mats can also be considered provided they are protected from the
backfill soil and connect to a drain.

4.6

INFILTRATION FEASIBILITY ASSESSMENT

Stormwater infiltration into the recessional outwash soils as mapped on the northwest half of the site is
anticipated to be feasible but will depend on depth to groundwater and underlying impeding layers
(i.e., glacial till). The glacial till mapped on the southeast half of the site is anticipated to have a relatively
high fines content and have a very low infiltration potential. We envision some infiltration is possible into
near-surface fill or weathered glacial till deposits; however, overall rates will likely be reduced due to soil
layering and shallow depth to intact glacial till. Based on our experience in similar soil conditions, we
recommend intact glacial till soils be considered relatively impermeable for preliminary planning.
Accordingly, new stormwater systems on the southeast half of the site will likely need to consider some
form of detention.

4.7

EARTHWORK CONSIDERATIONS

4.7.1 Stripping, Clearing, and Subgrade Preparation
Existing surfaces within proposed development areas should be cleared and stripped of all vegetation and
organics prior to site development. In areas containing trees and shrubs, we expect that stripping depths
could exceed 6 inches. In existing landscape areas, stripping depths could be around 2 to 4 inches.
Subgrades that will support structural elements and pavements should be thoroughly compacted to a
uniformly firm and unyielding condition on completion of stripping/excavation and before placing structural
fill. If soft or otherwise unsuitable subgrade areas are observed and cannot be compacted to a stable and
uniformly firm condition, we recommend that: (1) the unsuitable soils be scarified (e.g., with a ripper or
farmer’s disc), aerated and recompacted, if practical; or (2) the unsuitable soils be removed and replaced
with compacted structural fill, as needed.

File No. 0181-010-00

Port Gamble S’Klallam Tribe c/o Stantec Consulting Services, Inc. | May 15, 2024

Page 10

Existing structural improvements (e.g., pavements, hardscaping, and foundations) within proposed
development areas should be demolished and removed prior to redeveloping the site. Recycling or
incorporating old foundation or pavement elements into fill areas can be considered but must be evaluated
on a case-by-case basis. All existing utilities within the new building footprint(s) should be re-routed and/or
removed, as needed. If necessary, abandoned utilities may be left in place if properly filled with a controlled
density, cementitious fill.

4.7.2 Wet Weather Considerations
We expect that the majority of the soils at the site will contain a significant percentage of fines (materials
smaller than the No. 200 U.S. sieve) and will be sensitive to small changes in moisture content. If these
moisture sensitive soils become wet, they will be very difficult or impossible to work with and be highly
susceptible to disturbance.
We recommend that earthwork activities at this site be completed during periods of predominantly dry
weather. During dry weather, site soils will be less susceptible to disturbance, provide better support for
construction equipment, and be more likely to meet the required compaction criteria.
If earthwork must occur during wet weather, we recommend that contingencies be included to account for
additional management of materials and over-excavation and replacement of saturated and disturbed
soils. Additionally, if wet weather construction is proposed or required, we recommend considering for a
“net cut” site rather than a balanced cut and fill site, to reduce the amount of overall soil management and
less handling of materials exposed to wet conditions.

4.7.3 Cut and Fill Slopes
To maintain site grading and provide safe working conditions, we recommend planning for temporary
excavations and cut slopes to be inclined no steeper than about 1.5H:1V. Flatter cut slopes will be
necessary where seepage occurs or if surface surcharge loads are anticipated. If 1.5H:1V temporary slopes
are not feasible, temporary shoring, such as a soldier pile or soil nail wall, may be necessary. We envision
this may be the case when excavating the basement for the new Administration Building due to proximity
of surrounding buildings and other improvements. Depending on the depth of excavation, and site layout,
cut slopes in combination with shoring elements, or use of ecology block wall systems may also be
appropriate for temporary shoring. Where dense glacial till deposits are present, there could be an option
to construct steeper 1H:1V temporary slopes provided that these conditions are verified as a final
geotechnical study and during construction.
We recommend permanent slopes with maximum inclination of about 2H:1V be considered for preliminary
planning purposes. Where 2H:1V permanent slopes are not feasible, protective facings and/or retaining
structures should be considered. Where access for landscape maintenance is desired, we recommend a
maximum inclination of 3H:1V. Flatter cut slopes or additional drainage measures could be necessary
where seepage occurs or if surface surcharge loads are anticipated.

4.7.4 Groundwater Handling
The level of effort required for groundwater management during construction will depend to a great extent
on the time of year during which construction is completed. Groundwater handling needs will typically be
lower during the late summer and early fall months. We recommend earthwork be completed in the late
summer or early fall months when the groundwater level is typically at its lowest elevation and to take
advantage of generally dry prevailing conditions.

File No. 0181-010-00

Port Gamble S’Klallam Tribe c/o Stantec Consulting Services, Inc. | May 15, 2024

Page 11

Shallow perched groundwater should be expected to be present where more permeable layers are
underlain by less permeable layers, specifically in areas where fill or weathered zones are over undisturbed
glacial till. Based on our experience in similar glacial soil conditions, slow to moderate groundwater seepage
(3 gallons per minute [gpm] or less) is typical in these soil types, particularly during the wet season. We
anticipate that this type of shallow perched groundwater, if encountered, can be handled adequately with
sumps, pumps, and/or diversion ditches, as necessary.
As described above, static groundwater at the site is anticipated to be deeper than 10 feet below existing
site grades. For preliminary planning purposes, anticipate that excavations extending 10 feet below existing
site grades could require dewatering systems, groundwater cut off elements, wells, or additional sumps in
order to maintain dry conditions. Ultimately, completing subsurface explorations will provide better
information on groundwater levels at the site.

4.7.5 Fill Materials and Compaction
4.7.5.1
REUSE OF ON-SITE SOILS AS STRUCTURAL FILL
We anticipate the majority of the site footprint is underlain by glacial till (Qgt) deposits, which typically
consist of a mixture of silt, sand, gravel and cobbles. Glacial till soils can be considered for reuse as
structural fill provided, they can be adequately moisture conditioned, placed, and compacted, as
recommended and do not contain organic or other deleterious material. Site soils will likely be very difficult
or impossible to properly compact when wet and we recommend they be avoided for reuse if earthwork is
planned during wet weather months.
In addition, it is possible that existing soils will be generated at moisture contents above what is optimum
for compaction. In this case, the soils would need to be moisture conditioned prior to re-use. Space for
drying out material during dryer weather or covering on-site materials generated during wet weather should
be considered and incorporated into schedules and budgets. During wetter or even slightly colder times of
year, accommodations to cover stockpiled material generated on site that will be used as structural fill
should be planned.
If earthwork occurs during a typical wet season, or if the soils are persistently wet and cannot be dried back
due to prevailing wet weather conditions, we recommend project budgets include contingencies for using
imported materials as structural fill.

4.7.5.2

IMPORT STRUCTURAL FILL

Imported structural fill should be free of debris, organic contaminants, and rock fragments larger than
6 inches. For most applications, we recommend that structural fill consist of material similar to “Select
Borrow” or “Gravel Borrow” as described in Section 9-03.14 of the Washington State Department of
Transportation (WSDOT) Standard Specifications.
If imported fill is needed during wet weather conditions, we recommend using fill consisting of well-graded
sand and gravel or crushed rock with a maximum particle size not exceeding 6 inches and less than
5 percent fines by weight based on the minus ¾-inch fraction. In our opinion, material conforming to
WSDOT Standard Specifications Sections 9-03.9 (Aggregates for Ballast and Crushed Surfacing), 9-03.10
(Aggregate for Gravel Base) and 9-03.14 (Borrow) are suitable for use as imported fill material during wet
weather, with the exception that the fines content should be limited to 5 percent or less based on the minus
¾-inch fraction.

File No. 0181-010-00

Port Gamble S’Klallam Tribe c/o Stantec Consulting Services, Inc. | May 15, 2024

4.7.5.3

Page 12

TOPSOIL AND STRIPPINGS

Topsoil and strippings (e.g., sod and forest duff) may be placed on site provided they are placed in
non-structural areas that can tolerate some long-term total and differential settlements. Settlements of
organic-rich soils are highly variable and difficult to quantify. Settlement could continue for several years
after construction is completed as the organics break down and decompose. Alternatively, topsoil strippings
can be hauled off site.

4.7.5.4

FILL COMPACTION

In general, we recommend that all structural fills be compacted to at least 95 percent of the maximum dry
density (MDD) based on ASTM D-1557. Provisions for less compaction effort may be considered and
reduced to about 92 percent, where deeper fills are placed, such as below pavement areas. Typically,
landscape areas require about 85 to 90 percent compaction efforts.

5.0 Recommendations for Further Studies
Final site design will need explorations to develop recommendations for foundation support, shoring design
(where necessary), seismic design parameters, and stormwater infiltration. Overall, we recommend
substantial structures include borings as a final consideration for subsurface explorations and geotechnical
design. Borings are typically best suited where refined geotechnical design parameters are necessary. For
example, soil strength parameters and seismic Site Class can be determined from correlations to the
standard penetration test (SPT) completed during sampling. Borings can also be helpful where limited
surface disturbance is necessary, and/or where excavations are planned to be deeper than about 8 to
10 feet. For temporary shoring, borings will be needed for use by shoring designers and should typically
extend at least two times the depth of the proposed excavation and be spaced no greater than about 200
feet of wall length. We recommend borings be considered, at or near corners of proposed buildings, and
one in the center, as applicable, for the majority of structures proposed for this project.
Converting a boring(s) to a groundwater monitoring well(s) is also suggested as it could help characterize
fluctuations in groundwater levels for general construction and temporary excavations and help with design
for shoring, permanent below-grade walls, and for determining depth limits of infiltration facilities. A
piezoelectric pressure transducer can be installed in a monitoring well to record groundwater levels at
programmed intervals throughout the seasons.
For near-grade smaller structures, test pits in many cases may be appropriate for subsurface exploration
and geotechnical design. Test pits are also the primary investigation technique for stormwater infiltration
studies. If stormwater infiltration is included in project design, we recommend field testing, such as Pilot
Infiltration Tests (PITs), be completed to determine design infiltration rates. PITs should be completed within
the footprint of proposed infiltration facilities and at the proposed infiltration depths. PITs are best
completed once preliminary site planning and layout has occurred.

File No. 0181-010-00

Port Gamble S’Klallam Tribe c/o Stantec Consulting Services, Inc. | May 15, 2024

Page 13

6.0 Limitations
We have prepared this report for the exclusive use of Stantec and the Port Gamble S’Klallam Tribe for the
Administrative Campus Master Plan project in Kingston, Washington. Stantec and the Port Gamble
S’Klallam Tribe may distribute copies of this report to authorized agents and regulatory agencies as may
be required for the project.
Within the limitations of scope, schedule and budget, our services have been executed in accordance with
generally accepted practices for geotechnical engineering in this area at the time this report was prepared.
The conclusions, recommendations, and opinions presented in this report are based on our professional
knowledge, judgment, and experience. No warranty, express or implied, applies to the services or this
report.
Any electronic form, facsimile, or hard copy of the original document (email, text, table and/or figure), if
provided, and any attachments are only a copy of the original document. The original document is stored
by GeoEngineers, Inc. and will serve as the official document of record.
Please refer to Appendix A titled “Report Limitations and Guidelines for Use” for additional information
pertaining to use of this report.

7.0 References
American Society of Civil Engineers, 2016, “Minimum Design Loads and Associated Criteria for Buildings
and Other Structures, ASCE/SE 7-2016.”
International Code Council, 2021, “International Building Code.”
Kitsap County Department of Community Development. 2017. “Critical Areas, Kitsap County, Washington.”
April 27.
Kitsap County Department of Community Development. 2017. “Geologically Hazardous Map, Erosion
Hazards, Kitsap County, Washington.” February 23.
Kitsap County Department of Community Development. 2017. “Geologically Hazardous Map, Landslide
Hazards, Kitsap County, Washington.” February 23.
Kitsap County Department of Community Development. 2017. “Geologically Hazardous Map, Seismic
Hazards, Kitsap County, Washington.” February 23.
United States Department of Agriculture, Natural Resources Conservation Service. 2024. Web Soil Survey.
https://websoilsurvey.nrcs.usda.gov/app/WebSoilSurvey.aspx, accessed May 6 and 7, 2024.
United States Department of the Interior, Bureau of Indian Affairs. 2011. “AS BUILTS, ADMINISTRATION
CAMPUS PROJECT: CIVIL DRAWINGS, PORT GAMBLE INDIAN RESERVATION.” Project Number P10
09000. November 7.

File No. 0181-010-00

Port Gamble S’Klallam Tribe c/o Stantec Consulting Services, Inc. | May 15, 2024

Page 14

Washington State Department of Natural Resources. 2024. Washington Geologic Information Portal.
https://geologyportal.dnr.wa.gov/, accessed May 6, 2024.
Washington State Department of Transportation. 2024. “Standard Specifications for Road, Bridge, and
Municipal Construction.” Washington State Department of Transportation and the American Public
Works Association, M41-10.

File No. 0181-010-00

Figures

Legend
Site Boundary
Subarea Boundary

Subarea 3

Little B
Source(s):
· Aerial from Microsoft Bing
Coordinate System: WA State Plane, North Zone, NAD83, US Foot
Disclaimer: This figure was created for a specific purpose and project. Any use of this figure for
any other project or purpose shall be at the user's sole risk and without liability to GeoEngineers.
The locations of features shown may be approximate. GeoEngineers makes no warranty or
representation as to the accuracy, completeness, or suitability of the figure, or data contained
therein. The file containing this figure is a copy of a master document, the original of which is
retained by GeoEngineers and is the official document of record.

Subarea 1

N
0

120
Feet

Port G

Site Plan

amble

P:\0\0181010\CAD\00\Geotech\018101000_F02_Site Plan.dwg 2 Date Exported:5/13/2024 7:49 AM - by Mike C. Rau

d. NE

oston R

Subarea 2

N
N

Port Gamble S’Klallam Tribe
Administrative Campus Master Plan
Kingston, Washington

Figure 2

00181-010-00 Date Exported: 05/06/2024

Stream or Creek Ravine

Site

Stream or Creek
Shallow Ravine

Lidar Map
Notes:

1. This drawing has been reproduced from mapping available online by the Washington State Department of Natural Resources.
GeoEngineers cannot warrant or guarantee the accuracy or completeness of information provided or compiled by others.
2. This drawing is for information purposes. It is intended to assist in showing features discussed in an attached document.
GeoEngineers, Inc. cannot guarantee the accuracy and content of electronic files. The master file is stored by GeoEngineers, Inc. and
will serve as the official record of this communication.
Data Source: 1:100,000-scale Geologic Map, Washington State Department of Natural Resources online Geologic Information Portal

Port Gamble S’Klallam Tribe - Administrative
Campus Master Plan, Kingston, Washington
Figure 3

00181-010-00 Date Exported: 05/06/2024

Map Symbol

Geologic Unit Name

Qgo

Continental glacial outwash, Fraser-age

Qgt

Continental glacial till, Fraser-age

Qgp

Continental glacial drift, pre-Fraser

Qga(t)

Advance continental glacial outwash,
Fraser-age
Site

Qgo

Qgt
Qga(t)
Qgp

Geologic Map
Notes:

1. This drawing has been reproduced from mapping available online by the Washington State Department of Natural Resources.
GeoEngineers cannot warrant or guarantee the accuracy or completeness of information provided or compiled by others.
2. This drawing is for information purposes. It is intended to assist in showing features discussed in an attached document.
GeoEngineers, Inc. cannot guarantee the accuracy and content of electronic files. The master file is stored by GeoEngineers, Inc. and
will serve as the official record of this communication.
Data Source: 1:100,000-scale Geologic Map, Washington State Department of Natural Resources online Geologic Information Portal

Port Gamble S’Klallam Tribe - Administrative
Campus Master Plan, Kingston, Washington
Figure 4

00181-010-00 Date Exported: 05/06/2024

Map
Symbol

Soil Unit Name

Parent Material
Indianola: Glacial
outwash

21

Indianola-Kitsap
complex

Kitsap: Lacustrine
deposits with
volcanic ash in the
upper part
Lacustrine deposits

28

Kitsap silt loam

with volcanic ash in

Site

the upper part

44

Ragnar fine sandy
loam

Glacial outwash with
some volcanic ash
in the upper part

Soil Survey Map
Notes:

1. This drawing has been reproduced from the United States Department of Agriculture (USDA) Natural Resources Conservation Service
(NRCS) Web Soil Survey (WSS). GeoEngineers cannot warrant or guarantee the accuracy or completeness of information provided or
compiled by others.
2. This drawing is for information purposes. It is intended to assist in showing features discussed in an attached document.
GeoEngineers, Inc. cannot guarantee the accuracy and content of electronic files. The master file is stored by GeoEngineers, Inc. and
will serve as the official record of this communication.
Data Source: Parent Material, USDA NRCS Web Soil Survey

Port Gamble S’Klallam Tribe - Administrative
Campus Master Plan, Kingston, Washington
Figure 5

00181-010-00 Date Exported: 05/06/2024

Site

Seismic Hazards Map
Notes:

1. This drawing has been reproduced from seismic hazard mapping available online by the Washington State Department of Natural
Resources. GeoEngineers cannot warrant or guarantee the accuracy or completeness of information provided or compiled by others.
2. This drawing is for information purposes. It is intended to assist in showing features discussed in an attached document.
GeoEngineers, Inc. cannot guarantee the accuracy and content of electronic files. The master file is stored by GeoEngineers, Inc. and
will serve as the official record of this communication.
Data Source: Washington State Department of Natural Resources online Geologic Information Portal

Port Gamble S’Klallam Tribe - Administrative
Campus Master Plan, Kingston, Washington
Figure 6

Appendices

Appendix A

Report Limitations and Guidelines for Use

Port Gamble S’Klallam Tribe c/o Stantec Consulting Services, Inc. | May 15, 2024

Page A-1

Appendix A
Report Limitations and Guidelines for Use1
This appendix provides information to help you manage your risks with respect to the use of this report.

Read These Provisions Closely
It is important to recognize that the geoscience practices (geotechnical engineering, geology and
environmental science) rely on professional judgment and opinion to a greater extent than other
engineering and natural science disciplines, where more precise and/or readily observable data may exist.
To help clients better understand how this difference pertains to our services, GeoEngineers includes the
following explanatory “limitations” provisions in its reports. Please confer with GeoEngineers if you need to
know more how these “Report Limitations and Guidelines for Use” apply to your project or site.

Geotechnical Services Are Performed for Specific Purposes, Persons and Projects
This report has been prepared for the exclusive use of Stantec and the Port Gamble S’Klallam Tribe for the
Administrative Campus Master Plan project. Stantec and the Port Gamble S’Klallam Tribe may distribute
copies of this report to authorized agents and regulatory agencies as may be required for the project. This
report is not intended for use by others, and the information contained herein is not applicable to other
sites.
GeoEngineers structures our services to meet the specific needs of our clients. For example, a geotechnical
or geologic study conducted for a civil engineer or architect may not fulfill the needs of a construction
contractor or even another civil engineer or architect that are involved in the same project. Because each
geotechnical or geologic study is unique, each geotechnical engineering or geologic report is unique,
prepared solely for the specific client and project site. Our report is prepared for the exclusive use of our
Client. No other party may rely on the product of our services unless we agree in advance to such reliance
in writing. This is to provide our firm with reasonable protection against open-ended liability claims by third
parties with whom there would otherwise be no contractual limits to their actions. Within the limitations of
scope, schedule and budget, our services have been executed in accordance with our Agreement with the
Client and generally accepted geotechnical practices in this area at the time this report was prepared. This
report should not be applied for any purpose or project except the one originally contemplated.

A Geotechnical Engineering or Geologic Report Is Based on a Unique Set of
Project-specific Factors.
This report has been prepared for the Port Gamble S’Klallam Tribe - Administrative Campus Master Plan
project located in Kingston, Washington. GeoEngineers considered a number of unique, project-specific
factors when establishing the scope of services for this project and report. Unless GeoEngineers specifically
indicates otherwise, it is important not to rely on this report if it was:

1 Developed based on material provided by GBA, GeoProfessional Business Association; www.geoprofessional.org

File No. 0181-010-00

Port Gamble S’Klallam Tribe c/o Stantec Consulting Services, Inc. | May 15, 2024

Page A-2

■ Not prepared for you,
■ Not prepared for your project,
■ Not prepared for the specific site explored, or
■ Completed before important project changes were made.
For example, changes that can affect the applicability of this report include those that affect:

■ The function of the proposed structure;
■ Elevation, configuration, location, orientation or weight of the proposed structure;
■ Composition of the design team; or
■ Project ownership.
If changes occur after the date of this report, GeoEngineers cannot be responsible for any consequences
of such changes in relation to this report unless we have been given the opportunity to review our
interpretations and recommendations. Based on that review, we can provide written modifications or
confirmation, as appropriate.

Environmental Concerns are Not Covered
Unless environmental services were specifically included in our scope of services, this report does not
provide any environmental findings, conclusions, or recommendations, including but not limited to, the
likelihood of encountering underground storage tanks (USTs) or regulated contaminants.

Information Provided by Others
GeoEngineers has relied upon certain data or information provided or compiled by others in the
performance of our services. Although we use sources that we reasonably believe to be trustworthy,
GeoEngineers cannot warrant or guarantee the accuracy or completeness of information provided or
compiled by others.

Subsurface Conditions Can Change
This geotechnical or geologic report is based on conditions that existed at the time the study was performed.
The findings and conclusions of this report may be affected by the passage of time, by man-made events
such as construction on or adjacent to the site, new information or technology that becomes available
subsequent to the report date, or by natural events such as floods, earthquakes, slope instability or
groundwater fluctuations. If more than a few months have passed since issuance of our report or work
product, or if any of the described events may have occurred, please contact GeoEngineers before applying
this report for its intended purpose so that we may evaluate whether changed conditions affect the
continued reliability or applicability of our conclusions and recommendations.

File No. 0181-010-00

Port Gamble S’Klallam Tribe c/o Stantec Consulting Services, Inc. | May 15, 2024

Page A-3

Geotechnical and Geologic Findings are Professional Opinions
Our interpretations of subsurface conditions are based on field observations from widely spaced sampling
locations at the site. Site exploration identifies the specific subsurface conditions only at those points where
subsurface tests are conducted or samples are taken. GeoEngineers reviewed field and laboratory data
and then applied its professional judgment to render an informed opinion about subsurface conditions at
other locations. Actual subsurface conditions may differ, sometimes significantly, from the opinions
presented in this report. Our report, conclusions and interpretations are not a warranty of the actual
subsurface conditions.

Geotechnical Engineering Report Recommendations are Not Final
We have developed the following recommendations based on data gathered from subsurface
investigation(s). These investigations sample just a small percentage of a site to create a snapshot of the
subsurface conditions elsewhere on the site. Such sampling on its own cannot provide a complete and
accurate view of subsurface conditions for the entire site. Therefore, the recommendations included in this
report are preliminary and should not be considered final. GeoEngineers’ recommendations can be
finalized only by observing actual subsurface conditions revealed during construction. GeoEngineers
cannot assume responsibility or liability for the recommendations in this report if we do not perform
construction observation.
We recommend that you allow sufficient monitoring, testing and consultation during construction by
GeoEngineers to confirm that the conditions encountered are consistent with those indicated by the
explorations, to provide recommendations for design changes if the conditions revealed during the work
differ from those anticipated, and to evaluate whether earthwork activities are completed in accordance
with our recommendations. Retaining GeoEngineers for construction observation for this project is the most
effective means of managing the risks associated with unanticipated conditions. If another party performs
field observation and confirms our expectations, the other party must take full responsibility for both the
observations and recommendations. Please note, however, that another party would lack our projectspecific knowledge and resources.

A Geotechnical Engineering or Geologic Report Could Be Subject to Misinterpretation
Misinterpretation of this report by members of the design team or by contractors can result in costly
problems. GeoEngineers can help reduce the risks of misinterpretation by conferring with appropriate
members of the design team after submitting the report, reviewing pertinent elements of the design team’s
plans and specifications, participating in pre-bid and preconstruction conferences, and providing
construction observation.

Give Contractors a Complete Report and Guidance
To help reduce the risk of problems associated with unanticipated subsurface conditions, GeoEngineers
recommends giving contractors the complete geotechnical engineering or geologic report, including these
“Report Limitations and Guidelines for Use.” When providing the report, you should preface it with a clearly
written letter of transmittal that:

File No. 0181-010-00

Port Gamble S’Klallam Tribe c/o Stantec Consulting Services, Inc. | May 15, 2024

Page A-4

■ Advises contractors that the report was not prepared for purposes of bid development and that its
accuracy is limited; and

■ Encourages contractors to confer with GeoEngineers and/or to conduct additional study to obtain the
specific types of information they need or prefer.

Contractors are Responsible for Site Safety on Their Own Construction Projects
Our geotechnical recommendations are not intended to direct the contractor’s procedures, methods,
schedule or management of the work site. The contractor is solely responsible for job site safety and for
managing construction operations to minimize risks to on-site personnel and adjacent properties.

Biological Pollutants
GeoEngineers’ Scope of Work specifically excludes the investigation, detection, prevention or assessment
of the presence of Biological Pollutants. Accordingly, this report does not include any interpretations,
recommendations, findings or conclusions regarding the detecting, assessing, preventing or abating of
Biological Pollutants, and no conclusions or inferences should be drawn regarding Biological Pollutants as
they may relate to this project. The term “Biological Pollutants” includes, but is not limited to, molds, fungi,
spores, bacteria and viruses, and/or any of their byproducts.
A Client that desires these specialized services is advised to obtain them from a consultant who offers
services in this specialized field.

Geotechnical, Geologic and Environmental Reports Should Not Be Interchanged
The equipment, techniques and personnel used to perform an environmental study differ significantly from
those used to perform a geotechnical or geologic study and vice versa. For that reason, a geotechnical
engineering or geologic report does not usually relate any environmental findings, conclusions or
recommendations; e.g., about the likelihood of encountering USTs or regulated contaminants. Similarly,
environmental reports are not used to address geotechnical or geologic concerns regarding a specific
project.

File No. 0181-010-00

C
Natural
Resources
Assessment
Report

PORT GAMBLE S’KLALLAM TRIBE ADMINISTRATIVE CAMPUS MASTER PLAN

CHAPTER 6: APPENDICES

Memo
To:

Joe Sparr, Planning Director

From:

Port Gamble S’Klallam Tribe,
Kingston, WA
Project/File:

2042681800 - Task 1.4.2

Tim Nightengale; Darrell Rowe
(Stantec)
Bellevue, WA

Date:

June 19, 2024

Reference: Environmental Site Analysis (ESA) for the Port Gamble S'Klallam Tribe Administrative
Campus

CONTENTS
1

PROJECT DESCRIPTION / PURPOSE AND NEED STATEMENT ......................................................................... 1

2

ENVIRONMENTAL IMPACTS .................................................................................................................................. 4
2.1
2.2

Methods .............................................................................................................................................................. 4
Existing Conditions and Sensitive Areas............................................................................................................. 4

2.2.1

Subarea 1 ................................................................................................................................... 4

2.2.2

Subarea 2 ................................................................................................................................... 6

2.2.3

Subarea 3 ................................................................................................................................... 6

3

ALTERNATIVES....................................................................................................................................................... 8

4

REFERENCES.......................................................................................................................................................... 9

1

Project Description / Purpose and Need Statement

Stantec and Ferguson Architects are contracted to create an Updated Master Plan for the Port Gamble
S’Klallam Tribe Administrative Campus (Figure 1), focusing on planned improvements and land uses for
three areas of the campus, shown in Figure 2 as Subarea 1, 2, and 3. Subareas 1 and 2 will include future
improvements to the new Administrative Campus, including a new Administration building, community
center, gym, village commons (plaza), and planned subterranean parking garage, along with additional
parking, sidewalks, and park space. Subarea 3 will include structures to support Tribal Public Works and
Facilities Operations and event space parking.
As stated in Chapter 24.04.07 of the Port Gamble S’Klallam Tribe (PGST) Law and Order Code (LOC), the
purpose of the Environmental Site Analysis (ESA) is to “identify design modifications or mitigation measures
that will avoid or minimize adverse environmental impacts and achieve compliance with the purpose and
standards of this title.”
This ESA report has been prepared to: 1) identify any sensitive areas present within and around each of the
proposed subareas on the Administrative Campus; 2) provide an analysis of any potential adverse
environmental impacts by applying the Environmental Standards detailed in Chapter 24.08 of the PGST
LOC; and 3) provide recommendations for potential mitigation or minimization of any potential adverse
environmental impacts. These findings will be applied to the conceptual site planning and incorporated into
the revised Master Plan.

June 19, 2024
Joe Sparr, Planning Director
Page 2 of 9

Reference: 2042681800

Figure 1. Existing Vicinity Map (Source: Google Earth & PGST Master Plans)

June 19, 2024
Joe Sparr, Planning Director
Page 3 of 9

Reference: 2042681800

Figure 2. Subarea Map for the Administrative Campus (Source: Google Earth)

June 19, 2024
Joe Sparr, Planning Director
Page 4 of 9

Reference: 2042681800

2

Environmental Impacts

2.1

Methods

Stantec biologists first performed a desktop review of available public-domain information prior to their
critical areas site visit. These online sources included U.S. Fish and Wildlife Service (USFWS) National
Wetland Inventory (NWI) maps (USFWS 2024a), Washington Department of Fish and Wildlife’s (WDFW)
Statewide Washington Integrated Fish Distribution (SWIFD) mapping (WDFW 2024b), Kitsap County’s GIS
website (maps.kirklandwa.gov) for wetlands, streams, floodplains, and shoreline designations.
A US Fish and Wildlife Service (USFWS) Information Planning and Conservation (IPAC) report was
downloaded from their Trust Resources Database to determine any listed species or designated critical
habitat areas within the vicinity of or in the project area (USFWS 2024b). Also, WDFW’s Priority Habitats
and Species (PHS) lists were downloaded and an official PHS report was obtained for the project area
(WDFW 2024a). GIS maps created by Soundview Consultants showing streams and wetlands on the
Reservation were also reviewed by Stantec biologists for a general information about the Little Boston
Creek, and if any wetlands were within or near the Project Area. Finally, Stantec biologists reviewed the
Environmental Protection regulations (Title 24) within the PGST LOC for details on the environmental
standards to be applied.
On April 11, 2024, Stantec biologists Tim Nightengale, and Darrell Rowe walked Administrative Campus,
around the perimeter of the campus, as well as the length of Little Boston Creek from the mouth to Little
Boston Road, and the strip of land along the bluff on the west side of Little Boston Road. Using an Arrow
100 GNSS receiver in tandem with an iPhone12, Stantec biologists digitally recorded coordinates at each
photograph taken, capturing images of the creek, stormwater drainage features, drainage ditches located
around the perimeter of the ball field, and any potential wetlands and associated vegetation, specifically at
areas where sensitive areas and their buffers would potentially intersect with Subareas 1, 2, or 3. Using the
GPS Kit app, photographs were taken and GPS-located. Attachment A contains representative
photographs from this site visit.

2.2

Existing Conditions and Sensitive Areas

The Administrative Campus is approximately 22.0 acres, currently the located along the eastern side of
Little Boston Road NE before it turns east and then north (Figures 1 and 2). Subarea 1 is approximately 2.9
acres and contains the Administration Building, Gym, Kitchen, Natural Resources Department building, and
playground area. Subarea 2, approximately 4.0 acres, is located to the west of Little Boston Road NE, and
runs along the bluff bordering Port Gamble Bay. Subarea 2 contains the Tribal Arts Center and Tribal
Cemetery; the vacant residence pictured in Figure 2 had been demolished and cleared as of the April 2024
site visit. Subarea 3 is approximately 1.1 acres in size, located to the west of the ball field and south of Little
Boston Road NE. The subarea contains several maintenance buildings and a parking area.

2.2.1

SUBAREA 1

Initial desktop review of critical areas within the vicinity of the Administration Campus revealed that the
closest critical area near Subarea 1 was an unnamed fish bearing stream to the south of the property
(Figure 3). The designated 150-foot stream buffer for fish bearing streams does not extend into Subarea 1,
and only minimally extends onto the campus, near the equipment yard of the Natural Resources Laboratory
area. Stantec biologists walked the perimeter of the campus to observe any other possible critical areas

O

Legend
Fish bearing stream

Wetland
Wetland buffer (50 ft)
Parcels

300
Feet

(At original document size of 8.5x11)
1:3,000

Bluff buffer (150 ft)
Stream buffers (150 ft fish bearing and 100 ft non fish bearing)

150

N

ffi
�

� Stantec
Project Location

Prepared by NZ on 2024.06.18

Kitsap County, WA
Client/Project

Notes
1. Coordinate System: NAO 1983 StatePlane
Washington North FIPS 4601 Feet
2. Data Sources:
3. Background:

Port Gamble S'Klallum Tribe

Figure No.

3

Title

Critical Areas and Buffers Administrative Campus
Disclaimer: This document has been prepared based on information provided by others as cited in the Notes section. Stantec has not verified the accuracy and/or completeness of this information and shall not be responsible for any errors
or omissions which may be incorporated herein as a result. Staniec assumes no responsibility for data supplied in electronic format, and the recipient accepts full responsibility for verifying the accuracy and completeness of the data.

June 19, 2024
Joe Sparr, Planning Director
Page 6 of 9

Reference: 2042681800

that would extend buffers into Subarea 1. Biologists did trace drainage ditches along the perimeter, from the
ball field perimeter, around the southeastern edge of the campus and down to the Natural Resources
Laboratory area (see Attachment A, Photos 12-18). A stormwater drainage system appeared to be recently
installed, with lines running from the ball field down to a storm drain near the Natural Resources Laboratory,
which connected to the stormwater system and eventually flows into a drainage ditch that joins with the
perimeter drainage ditch flow at the northwest corner of the Natural Resources Laboratory area (see
Attachment A, Photos 19-21). The drainage ditches merge and flow into a thicket of Himalayan blackberries
(Rubus armeniacus). Water was not observed beyond this point. Flow lines, signs of swept-away leaf litter,
and deposited sediment was observed along the forested floor to the south of the campus area, but Stantec
biologists did not observe any established stream bed or material, and no signs of wetland (hydrophytic)
indicator plant species that would suggest stream or wetland conditions. It is likely the stormwater and
drainage flows are newer and are infrequent, and that most flows quickly infiltrate into the ground.
Therefore, no critical areas or buffers were observed that would be impacted by development within
Subarea 1.

2.2.2

SUBAREA 2

Initial desktop review of critical areas within the vicinity of the Administration Campus revealed that the
closest critical area near Subarea 2 was the marine bluff along the western edge of the subarea (Figure 2).
Stantec biologists investigated the extent of Subarea 2 to observe any other possible critical areas or
concerns. The top of slope of the bluff was generally 15 feet west of the cleared and mowed limits of the
area. Towards the southern end of Subarea 2, the top of the bluff was typically covered with Himalayan
blackberry, with red alder (Alnus rubra) and Western red cedar trees (Thuja plicata) trees further
downslope. As the biologists neared the Tribal Art Center, the top of slope vegetation shifted to Nootka rose
(Rosa nutkana) clusters, salal (Gaultheria shallon), and low Oregon grape (Mahonia nervosa), with larger
Douglas fir trees (Pseudotsuga menziesii) and a more forested slope existing towards the northern end of
Subarea 2 as it neared Little Boston Creek.
The Environmental Standards stated in Chapter 24.08.01(g) of the PGST LOC give the marine bluff at 150foot setback limit, measured from the mean high-water level or at a distance equal to the height of the bluff,
whichever is greater. The height of the bluff is around 60-70 feet, so a 150-foot buffer was extended inland
from the boundary limit of the reservation (and western parcel boundaries), as shown in Figure 3. The
Marine Bluff Setback regulations also indicate that this applies to structures and activities that are not
marine shoreline dependent, which would include the proposed development use of Subarea 2, with
additional parking and park space. The setback limit appears to extend approximately 30-40 feet beyond
the top of the bluff, leaving the cemetery and art center largely outside of the setback.

2.2.3

SUBAREA 3

Initial desktop review of critical areas within the vicinity of the Administration Campus revealed that Little
Boston Creek is immediately north of the property and could project a stream buffer into Subarea 3. Stantec
biologists investigated Little Boston Creek during the site visit, following it from the creek mouth and the
hatchery, upstream to the diversion structure which routes water to the hatchery. The stream was not
accessible through the impounded area behind the diversion structure, so Stantec biologists walked around
to Little Boston Road NE and re-entered further upstream. The stream lies within a ravine with steep
slopes, with numerous Western red cedar and Douglas fir trees with an understory Western sword fern
(Polystichum munitum). The streambanks featured salmonberry (Rubus spectabilis), osoberry (Oemleria
cerasiformis), vine maple (Acer circinatum), lady fern (Athyrium filix-femina), sword ferns, Western red
cedars, with clusters of youth-on-age (Tolmiea menziesii) and false lily-of-the-valley (Maianthemum
dilatatum). See Attachment A for site photos 1-8.

June 19, 2024
Joe Sparr, Planning Director
Page 7 of 9

Reference: 2042681800

Exiting the stream at its crossing under Little Boston Road NE, Stantec biologists continued along the road,
south towards the ball field. The shallow roadside ditch along the east side of the road was flowing north,
with water running to the creek. Following the ditch further, flow was traced to a potential wetland area
located along the east side of the gravel access road leading to Subarea 3 and the ball field, shown in
Figure 3 (Attachment A, Photos 9-11). The area had standing water and featured filamentous algae growing
throughout, strong indicators of wetland conditions. However, no formal delineation or hydric soil test was
performed; a formal wetland delineation of this feature should be performed to confirm. The biologists
continued to follow the perimeter of the ball field, and found that a shallow ditch was excavated around the
perimeter, possibly to aid in the drainage of the ball field area. The ditch was nearly half full of water at the
time of the site visit. Water likely was draining down to the potential wetland area and then continuing to the
creek via the roadside ditch.
The Environmental Standards stated in Chapter 24.08.01(c) of the PGST LOC places a natural buffer of
150 feet on all fish bearing streams, including Little Boston Creek, and a buffer of 50 feet on all wetlands.
Figure 3 shows the application of this buffer limit on Little Boston Creek, revealing that the buffer extends
across Little Boston Road NE and onto the Administrative Campus, particularly into the northern portions of
Subarea 3 along the roadway. The buffer from the potential wetland also extends across the access road
and into Subarea 3. The PGST LOC does not indicate how buffers should be applied when crossing
existing substantial improvements (typically public infrastructure or buildings), termed “interrupted buffers.”
Other municipal codes and shoreline master programs (SMPs) were reviewed for interrupted buffer
regulations. Washington State Department of Transportation (WSDOT) only applies buffer areas on the
same side of existing roadways as the associated critical area feature (e.g., wetlands or streams). The
reasoning for this decision is that “buffer areas physically separated from a wetland or other water by an
existing road can’t provide functions (such as screening, noise reduction, and water quality improvement)
for the sensitive area” (WSDOT 2023); however, their guidelines also say to always review and apply
regulations from the local municipal code.
The City of Bremerton’s SMP contains regulation for interrupted buffers in Chapter 7.010(b)(3), stating:
“When a buffer contains an existing legally established public or private road, the Director may
allow development on the landward side of the road provided that the development will not have a
detrimental impact to the shoreline. The applicant may be required to provide a report to describe
the potential impacts. In determining whether a report is necessary, the City shall consider the
extent and permanence of the buffer interruption and potential impact on shoreline ecological
functions.”
The City of Tacoma’s Municipal Code (Chapter 3.11, Critical Areas Preservation) also contains similar
language, detailing that where “proposed activities that are within the critical area or buffer but are
separated from the remaining critical area by a permanent substantial improvement, or are located in an
existing permanent substantial improvement, may be allowed provided that the detrimental impact to the
critical area does not increase.” The City of Tacoma also evaluates whether there is a potential of a
hydrologic, geologic, and/or biological habitat connection along with the extent and permanence of the
interruption.
As a final example of interrupted buffer regulations, the City of Tukwila establishes an administrative waiver
process for an interrupted buffer, using criteria that are similar to those stated by Tacoma and Bremerton
regulations. To qualify for the waiver, the existing legal improvement creates a substantial barrier to the
buffer function; the interrupted buffer does not provide additional protection of the critical area from the
proposed development; and the interrupted buffer does not provide significant hydrological, water quality,
and wildlife buffer functions relating to the portion of the buffer adjacent to the critical area.

June 19, 2024
Joe Sparr, Planning Director
Page 8 of 9

Reference: 2042681800

Given that both the stream buffer and the buffer from the potential wetland extend across existing
roadways, the interrupted buffer scenario is applicable. It is unlikely that potential buffer area within
Subarea 3 provides additional protection to Little Boston Creek or the potential wetland area or provides
significant hydrological, water quality or wildlife habitat functions to those critical areas. As such, the
functional buffer limits likely end at the roadway edge, and do not extend across the roadway into Subarea
3, any decision would need to be made at the discretion of Planning Director, in consultation with the
Natural Resources Department.

3

Alternatives

Review of the critical areas within and in the surrounding adjacent areas of the Administrative Campus
during the April 11, 2024 site visit revealed no critical areas or buffers within Subarea 1, but a protective
setback limit from the marine bluff in Subarea 2, and potential buffer areas from Little Boston Creek and a
potential wetland area extending into Subarea 3.
For development within Subarea 2, avoidance of construction within the setback limit should be avoided or
minimized to the greatest extent possible. Should development plans extend into the setback, a
geotechnical review should be conducted to determine any impacts to the slope stability and potential for
erosion impacts. Construction activities near the setback limit should implement temporary erosion and
sediment control (TESC) plans using appropriate storm water Best Management Practices (BMPs; silt
fencing, straw wattles, clean gravel bags, etc.) to avoid and minimize contaminant-laden stormwater from
leaving the Project area. Post-construction activities should include a restoration of vegetation to the top of
the bluff, which would include the removal of invasive plants such as the Himalayan blackberries and scotch
broom (Cytisus scoparius), and enhancements with native plants that would be suitable for the bluff and
marine shoreline habitat.
For development within Subarea 3, mitigation efforts will depend on how the Planning Director and Natural
Resources Department will treat the interrupted buffers that extend into the subarea. At a minimum, any
construction activities should implement TESC plans using appropriate storm water BMPs (silt fencing,
straw wattles, clean gravel bags, etc.) to avoid and minimize contaminant-laden stormwater from leaving
the Project area and entering the potential wetland and roadside ditch, eventually leading to Little Boston
Creek. Additional BMPs would include wheel washes to prevent sediment from tracking out on tires and
sweeping Little Boston Creek Road to prevent any sediment runoff from entering the buffer on the stream
side of the road. Post-construction activities should include a restoration of vegetation on the other side of
the road to enhance and restore buffer functions to the existing buffer. Efforts would include the removal of
invasive plants, replacing them with native plants to match the existing riparian vegetation.
Should the decision be to extend the buffer areas into Subarea 3, avoidance or minimization would require
no structures or development of the northern and eastern edges of the subarea. If that is not possible, a
recommendation would be to employ buffer averaging, which would reduce the standard buffer width of the
stream or wetland in the subarea back to the road edge, and then increase the buffer width in other
locations by an equal or greater amount of area. Those new buffer areas would be receive vegetation
restoration or enhancements to provide protection for water quality and habitat to the stream or wetland.

June 19, 2024
Joe Sparr, Planning Director
Page 9 of 9

Reference: 2042681800

4

References

United States Fish and Wildlife Service (USFWS). 2024a. National Wetland Inventory (NWI) online maps.
< https://fwsprimary.wim.usgs.gov/wetlands/apps/wetlands-mapper/ > Accessed May 2024.
USFWS. 2024b. Information for Planning and Consultation (IPAC).< https://ipac.ecosphere.fws.gov/ >
Accessed June 2024.
Washington Department of Fish and Wildlife (WDFW). 2024a. WDFW’s Priority Habitats and Species (PHS
on the web) maps. < https://geodataservices.wdfw.wa.gov/hp/phs/ > Accessed June 2024.
WDFW. 2020b. Statewide Washington Integrated Fish Distribution (SWIFD) mapping.
< https://geo.nwifc.org/swifd/ > Accessed June 2024.
Washington State Department of Transportation (WSDOT). (2023). How to document buffers for wetlands &
other waters. WSDOT Environmental Services Office. Updated April 2023.
< https://wsdot.wa.gov/sites/default/files/2021-10/Env-Wet-DelinGuideRdwyBuffer.pdf > Accessed
June 2024.

Attachment A. Administrative Campus Site Visit Photo Log

Figure A-1 Administrative Campus Overview Map with Photo Points.

D
Environmental
Site Assessment
Report

PORT GAMBLE S’KLALLAM TRIBE ADMINISTRATIVE CAMPUS MASTER PLAN

CHAPTER 6: APPENDICES

Phase I Environmental Site
Assessment
Port Gamble S'Klallam Tribe
Subarea 2 and 3
Kingston, Washington 98346

Report Date: April 25, 2024
ASTM Expiry Date: September 6, 2024

Prepared for:
Port Gamble S'Klallam Tribe
31912 Little Boston Road Northeast
Kington, Washington 98346
Prepared by:
Stantec Consulting Services Inc.
3400 188th Street SW, Suite 285
Lynnwood, Washington 98037

Project No.: 2042681800

Sign-off Sheet and Signatures of Environmental Professionals

This document entitled Phase I Environmental Site Assessment, Port Gamble S'Klallam Tribe, Subarea 2 and
3, Kingston, Washington 98346 was prepared by Stantec Consulting Services Inc. (“Stantec”) for the account
of Port Gamble S'Klallam Tribe (the “Client”). The conclusions in the Report are Stantec’s

[Text truncated at 120,000 characters. The full text is on the page linked above.]

---

Source: Frix Law Library, https://www.frixlaw.com/law-library/documents/tribal%3Aport_gamble_sklallam%3A4baf4d64880672e7. Public record. Not legal advice.
