## Text

DEPARTMENT OF AGRICULTURE

Forest Service

Proposed Brown Creek Timber Sale, Payette National Forest, Idaho

AGENCY: Forest Service, USDA.

ACTION: Notice of intent to prepare an environmental impact statement.

-----------------------------------------------------------------------

SUMMARY: The Forest Service will prepare an environmental impact
statement (EIS) for the proposed Brown Creek Timber Sale, New Meadows
Ranger District, Payette National Forest, Idaho. The proposed action
would harvest timber, obliterate roads to reduce sediment, and close
other roads to reduce wildlife vulnerability. The Forest prepared an
environmental assessment (EA) for this project and issued a decision
notice in September 1998. The Forest withdrew the decision in December
1998 so that an updated analysis of roadless and old growth could be
made and will prepare an EIS. The EA analyzed three alternatives,
including a no action alternative. The proposed action would harvest
within the Patrick Butte Roadless Area; however, no new roads would be
constructed. All actions will follow the Chief's interim rule on road
building. The alternatives considered in the EA, which would be
analyzed in the draft EIS (DEIS), would harvest up to 4.3 million board
feet of timber. Other alternatives will be developed depending on new
issues raised.
The agency gives notice of the full environmental analysis and
decision making process that is continuing on the proposal so that
interested and affected people know how they may participate and
contribute to the final decision. The Forest conducted public scoping
and addressed subsequent issues in the EA. The Forest now invites
comments on the scope of the analysis and the issues to be addressed.

DATES: Comments on the scope of the analysis must be received by April
10, 1999.

ADDRESSES: Submit written comments and suggestions to Jack Irish, Brown
Creek Team Leader, New Meadows Ranger District, Payette National
Forest, PO Box J, New Meadows, Idaho 83654.

FOR FURTHER INFORMATION CONTACT: Questions about the project should be
directed to Jack Irish, phone (208) 347-0300.

SUPPLEMENTARY INFORMATION: The Payette National Forest Plan (1988)
provides Forest-wide direction for management of the resources of the
Payette National Forest, including timber. The environmental impact
statement for the Forest Plan (1988) analyzed a range of alternatives
for management of the Brown Creek watershed. The Plan allocated this
area to general forest, including timber management, and assigned it to
Management Area #11. The area has had previous entries for timber
harvest.
As well as Forest-wide direction, the plan gives specific direction
for this management area. It requires integrated protection of multiple
resources

[[Page 12152]]

including fish, wildlife, range, soil and water, timber, and fire/
fuels.
Public participation will be especially important at several points
during the analysis, particularly during scoping of issues and during
review of the DEIS.
The scoping process includes:

1. Identifying potential issues.
2. Identifying issues to be analyzed in detail.
3. Eliminating insignificant issues or those covered by a relevant
previous environmental analysis.
4. Determining potential cooperating agencies and responsibilities.

Issues that were considered and analyzed in the EA were water
quality and soils, wildlife habitat, vegetation, fire and fuels,
roadless character and wilderness potential, air quality, biodiversity,
economics and socio-economics, fish habitat, heritage resources,
noxious weeds, range, recreation and visual quality, roads and access,
threatened, endangered and sensitive plant species, and wetlands and
floodplains. It is important to bring any new issues to the attention
of the Forest now so that they may be considered in the EIS.
The National Marine Fisheries Service, Department of Commerce, and
the U.S. Fish and Wildlife Service, Department of Interior, have been
consulted on potential impacts to threatened and endangered species.
The second major opportunity for public input is with the DEIS. The
DEIS will analyze a range of alternatives to the proposed action,
including the no-action alternative. The DEIS is expected to be filed
with the Environmental Protection Agency (EPA) and to be available for
public review in May, 1999. EPA will then publish a notice of
availability of the DEIS in the Federal Register. Public comments are
invited.
The comment period on the DEIS will be 45 days from the date the
EPA publishes the notice of availability in the Federal Register.
The Forest Service believes, at this early stage, it is important
to give reviewers notice of several court rulings related to public
participation in the environmental review process. First, reviewers of
DEIS's must structure their participation in the environmental review
of the proposal so that it is meaningful and alerts the agency to the
reviewers position and contentions. Vermont Yankee Nuclear Power Corp
v. NRDC, 435 U.S. 519, 553 (1978). Also, environmental objections that
could be raised at the DEIS stage but that are not raised until after
completion of the final environmental impact statement (FEIS) may be
waived or dismissed by the courts. City of Angoon v. Hodel, 803 F.2d
1016, 1022 (9th Cir. 1986) and Wisconsin Heritages, Inc. v. Harris, 490
F. supp. 1334, 1338 (E.D. Wis. 1980). Because of these court rulings,
it is very important that those interested in this proposed action
participate by the close of the 45 day comment period so that
substantive comments and objections are made available to the Forest
Service at a time when it can meaningfully consider them and respond to
them in the FEIS.
To assist the Forest Service in identifying and considering issues
and concerns on the proposed action, comments on the DEIS should be as
specific as possible. It is also helpful if comments refer to specific
pages or chapters of the draft statement. Comments may also address the
adequacy of the DEIS or the merits of the alternatives formulated and
discussed in the statement. Reviewers may wish to refer to the Council
on Environmental Quality Regulations for implementing the procedural
provisions of the National Environmental Policy Act at 40 CFR 1503.3 in
addressing these points.
In the FEIS the Forest Service is required to respond to comments
received (40 CFR 1503.4). The responsible official will consider the
comments, responses, environmental consequences discussed in the FEIS,
which is expected to be completed in August, 1999, and applicable laws,
regulations, and policies in making the final decision regarding this
proposal. The responsible official will document the decision and
reasons for it in the Record of Decision. That decision will be subject
to appeal under 36 CFR 215.
David F. Alexander, Forest Supervisor of the Payette National
Forest, McCall, Idaho, is the responsible official for this EIS.

Dated: March 4, 1999.
David F. Alexander,
Forest Supervisor.
[FR Doc. 99-6037 Filed 3-10-99; 8:45 am]
BILLING CODE 3410-11-M

---

Source: Frix Law Library, https://www.frixlaw.com/law-library/documents/fr%3A99-6037. Public record. Not legal advice.