DEPARTMENT OF TRANSPORTATION

Federal Transit Administration

Environmental Impact Statement on the Central Phoenix /East
Valley Light Rail Transit System

AGENCY: Federal Transit Administration, DOT.

ACTION: Notice of intent to prepare an Environmental Impact Statement
(EIS).

-----------------------------------------------------------------------

SUMMARY: The Federal Transit Administration (FTA) and the Phoenix
Regional Public Transportation Authority (RPTA), in cooperation with
the cities of Phoenix, Tempe, and Mesa intend to prepare an
Environmental Impact Statement (EIS) in accordance with the National
Environmental Policy Act (NEPA) on the proposed Central Phoenix/East
Valley light rail transit project in Maricopa County, Arizona. The EIS
will evaluate the following alternatives: a no-build alternative and
light rail transit alignment options (including station locations,
support facilities, and a supporting bus system) plus any additional
alternatives that emerge from the scoping process. Scoping will be
accomplished through correspondence and discussions with interested
persons, organizations, and Federal, State and local agencies, and
through public meetings.

DATES: Comment Due Date: Written comments on the scope of alternatives
and impacts to be considered should be sent to the RPTA, 302 N. First
Avenue, Suite 600, Phoenix, AZ 85003 by April 2, 1999.
Scoping Meetings: RPTA and the cities of Phoenix, Tempe, and Mesa
will conduct public scoping meetings on the following dates and
locations:
Tuesday, March 16, 1999, 5:00 pm--7:00 pm--Program Room,
Tempe Public Library, 3500 S. Rural Road, Tempe, Arizona
Wednesday, March 17, 1999, 5:00 pm--7:00 pm--Music Room
(4th Floor), Central Phoenix/Main Library (Burton Barr Public Library),
1221 N. Central Avenue, Phoenix, Arizona.
Thursday, March 18, 1999, 5:00 pm--7:00 pm, Saguaro Room,
(2nd Floor), Mesa Public Library, 64 East 1st Avenue, Mesa, Arizona and
Friday, March 19, 1999, 10:30 am--1:00 pm, Phoenix City
Hall Assembly Room, A&B, 200 W. Washington Street, Phoenix, Arizona.

ADDRESSES: Written comments on the project scope should be sent to Mr.
Wulf Grote PE, Project Director, RPTA, 302 N. First Avenue, Suite 600,
Phoenix, AZ 85003. Scoping meetings will be at the locations stated
above.

FOR FURTHER INFORMATION CONTACT: Mr. Robert E. Hom, Director, Office of
Planning and Program Development Federal Transit Administration, Region
IX, (415) 744-3133.

SUPPLEMENTARY INFORMATION:

I. Scoping

The FTA and the RPTA, in cooperation with the cities of Phoenix,
Tempe and Mesa invite written comments until April 2, 1999.
During scoping, comments should focus on identifying specific
social, economic, or environmental impacts to be evaluated and
suggesting alternatives that are less costly or less environmentally
damaging which achieve similar objectives. Comments should focus on the
issues and alternatives for analysis, and not on a preference for a
particular alternative. Individual preference for a particular
alternative should be communicated during the comment period for the
Draft EIS. If you wish to be placed on the mailing list to receive
further information as the project continues, contact Mr. Wulf Grote at
the RPTA; (see ADDRESSES above). A scoping package describing the light
rail alignment alternative in greater detail is also available by mail
from Mr. Wulf Grote at (602) 262-7242.

II. Description of Study Area and Project Need

The proposed project for environmental review consists of
approximately a 25-mile total light rail transit system. An initial
operating segment consisting of approximately 13 miles, in the core of
the corridor, has been identified as the focus of the preliminary
engineering effort. The total corridor links Phoenix, Tempe, and Mesa
from Mesa Drive in downtown Mesa, through Tempe, west to downtown
Phoenix and north along the Central Avenue Corridor to the vicinity of
19th Avenue and Bethany Home.
For the 25-mile segment, two terminal locations in Phoenix will be
evaluated during the NEPA process. One terminal location is in the
vicinity of Central Avenue and Camelback Road. The other is located in
the vicinity of 19th Avenue and Bethany Home Road, integrated with the
Chris-Town Mall. For the initial operating segment, the exact length of
the LRT segment, station locations, and supporting facilities would
also be determined during the NEPA process.
The new light rail transit alignment will be located either within
existing arterial streets or in the parallel Union Pacific Railroad
(UPRR) corridor or a combination of the alignment locations. The light
rail transit alignment provides the opportunity to connect several
regionally significant activity centers, entertainment venues, and
special event locations. In addition, the light rail project is being
coordinated with the City of Phoenix, Aviation Department and is
included as an integral mobility component of the Sky Harbor
International Airport master plan update. The light rail corridor also
parallels Interstate 10, Interstate 17, and US 60 (Superstition
Freeway) generally considered to be the spine of Maricopa County's
freeway transportation system, carrying the greatest number of people
and vehicles of any corridor in the region and serving many of the
region's primary activity centers. Congestion and delays along these
freeways and along the parallel arterial streets are now considered to
be the major transportation problem facing this rapidly growing region.
With the prospect of continued and accelerated growth in population and
tourism in Maricopa County, travel conditions will continue to
deteriorate at an increasing rate. Between 1990 and 1995, Maricopa
County grew by more than 15 percent to a current population of 2.7
million. By 2020, it is estimated that the population of Maricopa
County will exceed 4 million. The County's growth rate was the third
fastest among the nation's top fifty counties from 1980 through 1994.
In response to this need, the RPTA in cooperation with the cities
of Phoenix, Tempe, and Mesa have completed a

[[Page 10062]]

Major Investment Study (MIS) for the Central Phoenix/East Valley
corridor. The MIS study resulted in a recommended design concept and
scope consisting of a light rail transit alternative operating in one
of several alignment options and a supporting bus system to provide the
required mobility in the Central Phoenix/East Valley corridor and the
region. Copies of the MIS are available from Mr. Wulf Grote at the RPTA
(see Addresses above).

III. Alternatives

The alternatives proposed for evaluation include: (1) No-action,
which involves no change to transportation services or facilities in
the corridor beyond already committed projects, (2) a new light rail
transit alignment located either within the UPRR right-of-way or
selected surface streets or a combination of the UPRR corridor and
surface streets.

IV. Probable Effects

FTA and the RPTA in cooperation with the cities of Phoenix, Tempe,
and Mesa will evaluate all significant environmental, social, and
economic impacts of the alternatives analyzed in the EIS. Primary
environmental issues include: neighborhood protection, traffic
diversion, business access, aesthetics, bicycle facilities,
contamination, alternative modes of transportation, stormwater
management, and archaeological and cultural resources. Environmental
and social impacts proposed for analysis include land use and
neighborhood impacts, traffic and parking impacts near stations, visual
impacts, impacts on cultural resources, and noise and vibration
impacts. Impacts on natural areas, air quality, groundwater and
potentially contaminated sites will also be covered. The impacts will
be evaluated both for the construction period and for the long-term
period of operation. Measures to mitigate any significant adverse
impacts will be developed.

V. FTA Procedures

The EIS for the Central Phoenix/East Valley project will be
prepared simultaneously with preliminary engineering for the
approximately 13-mile initial operating segment in the core of the
corridor. The EIS/preliminary engineering process will assess the
social, economic, and environmental impacts of the proposed
alternatives while refining their design to minimize and mitigate any
adverse impacts. After its publication, the Draft EIS will be available
for public and agency review and comment, and a public hearing will be
held. Based on the Draft EIS and comments received, the RPTA and the
cities of Phoenix, Tempe, and Mesa will select a preferred alternative
to be further detailed in the Final EIS.

Issued on: February 24, 1999.
Leslie T. Rogers,
Regional Administrator.
[FR Doc. 99-5000 Filed 2-26-99; 8:45 am]
BILLING CODE 4910-57-U

---