DEPARTMENT OF AGRICULTURE

Forest Service

Rimrock Projects, Umatilla National Forest, Grant, Morrow, and
Wheeler Counties, Oregon

AGENCY: Forest Service, USDA.

ACTION: Notice of intent to prepare an environmental impact statement.

-----------------------------------------------------------------------

SUMMARY: The Forest Service will prepare an environmental impact
statement (EIS) on a proposal to implement ecosystem management
projects designed to promote long-term resiliant, sustainable watershed
conditions. Project guidance is provided by the Ecosystem Analysis of
the Wall Watersheds (September 1995). The project area is located on
the Heppner Ranger District and lies approximately 25 miles southwest
of Heppner, Oregon, within the Wall Creek watershed (subwatersheds 24A-
G).
Proposed project activities consist of in-channel fish structure
maintenance, hydrologic stability projects (road obliteration/
decomissioning, road resurfacing/reconstruction), wildlife enhancement
projects, aspen habitat enhancement, noxious weed treatments, range
improvements, recreation opportunities, landscape prescribed fire, and
restoration of forest stand structure/composition using a variety of
silvicultural treatments including commercial timber harvest. The
proposed action is designed to reduce risks to ecosystem
sustainability, prevent further degradation of forest health, reduce
risks of catastrophic wildfire, improve or maintain water quality and
aquatic habitat, and provide economic return to local economies. The
proposed projects will be in compliance with the 1990 Land and Resource
Management Plan FEIS for the Umatilla National Forest, as amended,
which provides overall direction for management of this area.

DATES: Written comments concerning the scope of the analysis should be
received on or before March 31, 1999.

ADDRESSES: Send written comments and suggestions to the Responsible
Official, Delanne Ferguson, District Ranger, Heppner Ranger District,
P.O. Box 7, Heppner, Oregon 97836.

FOR FURTHER INFORMATION CONTACT: Charlene Bucha Gentry, Project Team
Leader, Heppner Ranger District, Phone: (541) 676-9781.

SUPPLEMENTARY INFORMATION: The decision area contains approximately
42,000 acres within the Umatilla National Forest in Grant, Morrow, and
Wheeler Counties, Oregon. It is within the boundary of the Wall
watershed which includes Lower, Middle, and Upper Big Wall; Porter;
Lower and Upper Wilson; and Indian subwatersheds. The legal description
of the decision area is as follows: R.25E. T.6S. sections 24-28 and 32-
36; R.25E. T.7S. sections 1-5, 9-15, 23-25, and 36; R.26E. T6S.
sections 16, 19-23, and 26-35; R.26E. T.7S. sections 1-36; R.26E. T.8S.
sections 1-6, 8-16, and 24; R.27E. T.7S. sections 13-36; R.27E. T.8S.
sections 2-10 and 16-19; and R.28E. T.7S. sections 19, 30, and 31, W.M.
surveyed. All proposed activities are outside the boundaries of any
roadless or wilderness areas.
Fish habitat projects include maintenance and restoration of in-
channel structures. Proposed hydrologic stability projects include 34
miles of road obliteration or decommissioning, 37 miles of road
resurfacing, 47 miles of road reconstruction, installation of a culvert
to replace a low-water ford (Forest Road 23), and installation of three
low-water fords designed for fish passage (concrete approaches with a
suspended grate) on Forest Road 23 and 2300100 where they intersect
with Big Wall Creek. Aspen habitat enhancement includes removal of
encroaching conifers, construction of ungulate-proof fences, prescribed
burning, and mechanical root stimulation. Range improvements consist of
the construction of barbed wire fencing on three creeks to protect
riparian areas. Bull Prairie Reservoir has silted in considerably in
the 32 years since its construction. Excavation of three identified
areas along the shoreline of the reservoir would remove cattails,
deepen the lake shoreline, and enhance

[[Page 9311]]

fishing opportunities. Landscape prescribed fire across the analysis
area would reduce the potential for future catastrophic wildfires,
enhance wildlife habitat, maintain forest health, and reduce fuel
loadings. A variety of silvicultural methods would treat approximately
5,500 acres within the area. This would result in an estimated 33,000
ccf (17.5 million board feet) of wood products produced for local
economies. Proposed silvicultural treatments are as follows:
Precommercial Thinning: Saplings (generally up to 6 inch dbh) would
be thinned to a tree per acre variable spacing to promote growth,
restore and maintain a more sustainable species composition, and to
promote visual quality along Hwy 207. This treatment is proposed on
about 380 acres.
Commercial Thinning: Stand densities would be reduced to a residual
square foot of basal area per acre based on recommended stocking levels
appropriate for the plant association to restore a more ecologically
sustainable structure and species composition. All stands would remain
fully stocked upon completion of harvest activities. This treatment is
proposed on approximately 5,100 acres.
Proposed commercial thinning units would be harvested using
tractor, harvester/forwarder, and helicopter logging systems. Access
for harvest would require reconstruction of about 47 miles of existing
roads and construction of approximately 12 miles of temporary roads.
The temporary roads would be closed and obliterated upon completion of
harvest activities. Activities that would occur concurrently or in
association with timber harvest include subsoiling of landings and
temporary roads to mitigate soil compaction, waterbarring, seeding of
skid trails and landings for noxious weed control, and burning of some
slash.
Public participation will be especially important at several points
during the analysis, beginning with the scoping process (40 CFR
1501.7). Scoping will include listing of this EIS in the Spring 1999
issue of the Umatilla National Forest's Schedule of Proposed
Activities; letters to agencies, organizations, and individuals who
have already indicated their interest in such activities; and news
releases in the East Oregonian and other local newspapers. No public
meetings have been planned at this time; they will be scheduled later
as needed. This notice is to encourage members of the public,
interested organizations, federal, state and county agencies, and local
tribal governments to take part in planning this project. They are
encouraged to visit with Forest Service officials at any time during
the analysis and prior to the decision. Any information received will
be used in preparation of the Draft EIS. The scoping process includes:
1. Identifying potential issues
2. Identifying major issues to be analyzed in depth
3. Considering alternatives based on themes which will be derived
from issues recognized during scoping activities
4. Identifying potential environmental effects of project and
alternatives (i.e. direct, indirect, and cumulative effects and
connected actions).
Preiliminary issues include: effects of proposed activities on
water quality and the anadromous and resident fisheries resource;
effects of the proposed activities on Threatened, Endangered and
Sensitive (TES) species and what opportunities exist to improve
habitat; and the ability of proposed activities to restore historic
vegetation composition, structure, and pattern.
A full range of alternatives will be considered, including a ``no-
action'' alternative in which none of the activities proposed above
would be implemented. Based on the purpose and need, as well as issues
gathered through scoping, the action alternatives will vary (1) the
number, type and location of projects, (2) the silvicultural and post-
harvest treatments prescribed, (3) the amount and location of harvest
and thinning, (4) the type and amount of excavation to occur in Bull
Prairie Reservoir, and (5) the type and amount of repairs to occur on
Forest Road 23.
Appropriate Federal, state, and local permits or licenses will be
obtained for activities associated with the project, including Oregon
Division of State Lands Fill and Removal Permit.
The Draft EIS is expected to be filed with the Environmental
Protection Agency (EPA) and to be available to the public for review by
July 1999. At that time, the EPA will publish a Notice of Availability
of the Draft EIS in the Federal Register. The comment period on the
Draft EIS will be 45 days from the date the EPA publishes the notice of
availability in the Federal Register. It is important that those
interested in the management of the Umatilla National Forest
participate at that time.
The Final EIS is scheduled to be completed by October 1999. In the
Final EIS, the Forest Service will respond to comments and responses
received during the comment period that pertain to the environmental
consequences discussed in the Draft EIS and applicable laws,
regulations, and policies considered in making a decision regarding the
proposal.
The Forest Service believes it is important to give reviewers
notice at this early stage of several court rulings related to public
participation in the environmental review process. First, reviewers of
draft environmental impact statements must structure their
participation in the environmental review of the proposal so that it is
meaningful and alerts an agency to the reviewer's position and
contentions. Vermont Yankee Nuclear Power Corp. v. NRDC, 435 U.S.
519,553 (1978). Also, environmental objections that could be raised at
the draft environmental impact statement stage but that are not raised
until after completion of the final environmental impact statement may
be waived or dismissed by the courts. City of Angoon v. Hodel, 803 f.2d
1016, 1022 (9th Cir, 1986) and Wisconsin Heritages, Inc. v. Harris, 490
F. Supp. 1334, 1338 (E.D. Wis. 1980). Because of these court rulings,
it is very important that those interested in this proposed action
participate by the close of the 45-day comment period so that
substantive comments and objections are made available to the Forest
Service at a time when it can meaningfully consider them and respond to
them in the final environmental impact statement.
To assist the Forest Service in identifying and considering issues
and concerns on the proposed action, comments on the draft
environmental impact statement should be as specific as possible. It is
also helpful if comments refer to specific pages or chapters of the
draft statement. Comments may also address the adequacy of the draft
environmental impact statement or the merits of the alternatives
formulated and discussed in the statement. (Reviewers may wish to refer
to the Council on Environmental Quality Regulations for implementing
the procedural provision of the National Environmental Policy Act at 40
CFR 1503.3 in addressing these points).
The Forest Service is the lead agency. Delanne Ferguson, District
Ranger, is the Responsible Official. As the Responsible Official, she
will decide which, if any, of the proposed projects will be
implemented. She will document the decision and reasons for the
decision in the Record of Decision. That decision will be subject to
Forest Service Appeal Regulations (36 CFR part 215).

Dated: February 8, 1999.
Delanne Ferguson,
District Ranger.
[FR Doc. 99-4647 Filed 2-24-99; 8:45 am]
BILLING CODE 3410-11-M

---