DEPARTMENT OF AGRICULTURE

Forest Service

Duck-Sheriff Project, Allegheny National Forest

AGENCY: Forest Service, USDA.

ACTION: Notice of intent to prepare an Environmental Impact Statement.

-----------------------------------------------------------------------

SUMMARY: In accordance with the National Environmental Policy Act,
notice is hereby given that the Forest Service, Allegheny National
Forest (ANF), will prepare an Environmental Impact Statement to
disclose the environmental consequences of the proposed Duck-Sheriff
project.
The purpose of this project is to move the ANF from the existing
condition towards the desired future condition (DFC) as detailed in the
Allegheny National Forest Land and Resource Management Plan (Forest
Plan). The Forest Plan allocates land to management where wood
production is one of the featured objectives (Management Area [MA]
3.0). Equally important, the Forest Plan allocates land to management
that emphasizes wildlife and recreation (MA 6.1). The Duck-Sheriff
project contains both of these management areas.
In order to move toward the DFC, the acres in early successional
age class (0-20 year age) need to increase; healthy forested stands
capable of producing high quality, high value sawtimber need to be
maintained; and understories dominated by fern, grass or undesirable
vegetation need to develop desirable seedlings. Project proposals
include timber harvesting as a means for making desired changes to
forest vegetation and satisfying the demonstrated public need for wood
products. Management actions necessary to meet the purpose and need
include: 1,364 acres of regeneration harvest to ensure future forests;
herbicide, fertilizer, fencing, mechanical site preparation, and/or
planting to ensure seedling establishment and growth in understories.
An additional 1,842 acres of intermediate harvests are planned to
reduce the competition for light and nutrients, thereby improving the
health, vigor, and growth of residual trees and to restore the
understory within mature forests. Activities associated with these
silvicultural practices include 3 miles of new road construction, 28
miles of road restoration, 9 miles of road betterment, and 7 acres of
stone pit development to provide an adequate long-term transportation
system.
Additional areas need to be designated for management of late
successional values, riparian areas need protection and enhancement,
sections of the North Country Trail need improvement, water borne
recreation needs enhancement, wildlife habitat needs improvement, and
interpretation of wildland heritage needs to be increased. Project
proposals (management actions) were designed to address these needs.
During project analysis issues will be identified that focus on the
management of the area. Alternatives will be developed to show various
ways to address the issues. This process is driven by comments received
from the public, other agencies, and internal Forest Service concerns.
To assist in commenting, a scoping letter providing more detailed
information on the project proposal has been prepared and is available
to interested parties.
After analysis, the responsible official will select an alternative
that maximizes net public benefits for the Duck-Sheriff Project area.

DATES: Comments, suggestions, and recommendations for achieving the
purpose and need for the Duck-Sheriff Project are now being accepted.
The public comment period will be for 30 days from the date this notice
is published in the Federal Register. Comments and suggestions should
be submitted in writing and postmarked by March 4, 1999 to ensure
timely consideration.

CONTACT PERSONS & ADDRESSES: Submit written comments and suggestions
concerning the proposed action to: ``Duck-Sheriff Project'', attention
Sue Wingate--ID Team Leader, Bradford Ranger District, HC1 Box 88,
Bradford, PA 16701. For further information, contact Sue Wingate @
(814) 362-4613. The responsible official for this project is John R.
Schultz, District Ranger,

[[Page 5020]]

Bradford Ranger District, HC1 Box 88, Bradford, PA 16701.

SUPPLEMENTARY INFORMATION: The analysis of the Duck-Sheriff project is
conducted under the guidance of the National Environmental Policy Act
and the Allegheny National Forest Land and Resource Management Plan.
Preliminary issues were developed based on past public involvement on
other projects, known concerns of other agencies, interdisciplinary
team identification of Forest Service concerns, and identified
opportunities in the project area. The following issues will be carried
forward in the project analysis. They will be modified as additional
issues are identified during scoping: (1) Road management and new
access; (2) deer densities and investments to restore desireable
understory vegetation; (3) vegetation treatments along the North
Country Trail; (4) uneven-aged timber management; and (5) old-growth
forest and contiguous canopy.
Preliminary alternatives were developed to display management
opportunities in response to the known issues. Management actions
within the alternatives respond to the issues in different ways by
varying the size and intensity of the treatments and projects proposed.
The amount of even and uneven-aged management, wildlife, recreation
development, road management, watershed rehabilitation and other
activities differ within the alternatives. The combinations of proposed
activities are likely to be adjusted after all comments are reviewed.
Comments considered beyond the scope of this project which will not
be evaluated. This includes whether or not commercial timber harvest
should occur on National Forest System lands; the validity of the
science of silviculture and forest management; and whether or not to
allow the use of herbicides on the Allegheny National Forest on a
programmatic level.

Commenting

Comments received in response to this solicitation, including names
and addresses of those who comment, will be considered part of the
public record on this proposed action and will be available for public
inspection. In a recent legal opinion, the Forest Service's Office of
General Council (OGC) has determined that names and addresses of people
who respond to a Forest Service solicitation are not protected by the
Privacy Act and can be released to the public. The Forest Service
routinely gives notice of and requests comments on proposed land and
resource management actions accompanied by environmental documents, as
well as on proposed rules and policies. Comments received in response
to such solicitations, including names and addresses of those who
comment, will be considered part of the public record and will be
available for such inspection, upon request. Any person may request the
agency to withhold a submission from the public record by showing how
the Freedom of Information Act (FOIA) permits such confidentiality. The
opinion states that such confidentiality may be granted in only very
limited circumstances, such as to protect trade secrets.
The Draft EIS is expected to be filed with the Environmental
Protection Agency and to be available for public review by May 15,
1999. At that time the Environmental Protection Agency will publish a
notice of availability of the document in the Federal Register. A
public comment period on the Draft EIS will be 45 days from the date
the Environmental Protection Agency publishes the notice of
availability in the Federal Register.
The Forest Service believes, at this early stage, it is important
to give reviewers notice of several court rulings related to public
participation in the environmental review process. First, reviewers of
draft environmental impact statements must structure their
participation in the environmental review of the proposal so that it is
meaningful and alerts an agency to the reviewer's position and
contentions. Vermont Yankee Nuclear Power Corp. v. NRDC, 435 U.S. 519
553 (1978). Also, environmental objections that could be raised at the
draft environmental impact statement stage but that are not raised
until after completion of the final environmental impact statement may
be waived or dismissed by the courts. City of Angoon v. Hodel, 803 F.2d
1016, 1022 (9th Cir. 1986) and Wisconsin Heritages, Inc. v. Harris, 490
F. Supp. 1334, 1338 (E.D. Wis. 1980). Because of these court rulings,
it is very important that those interested in this proposed action
participate by the close of the 45 day comment period so that
substantive comments and objections are made available to the Forest
Service at a time when it can meaningfully consider them and respond to
them in the final environmental impact statement.
To assist the Forest Service in identifying and considering issues
and concerns on the proposed action, comments on the draft
environmental impact statement should be as specific as possible. It is
also helpful if comments refer to specific pages or chapters of the
draft statement. Comments may also address the adequacy of the draft
environmental impact statement or the merits of the alternatives
formulated and discussed in the statement. Reviewers may wish to refer
to the Council on Environmental Quality Regulations for implementing
the procedural provisions of the National Environmental Policy Act at
40 CFR 1503.3 in addressing these points.
After the comment period ends on the Draft EIS, the comments will
be analyzed and considered by the Forest Service in preparing the final
environmental impact statement. The Final EIS is scheduled to be
completed by September 15, 1999. The decision will be subject to appeal
under 36 CFR 215.

Dated: January 27, 1999.
John R. Schultz,
District Ranger.
[FR Doc. 99-2377 Filed 2-1-99; 8:45 am]
BILLING CODE 3410-11-P

---

Source: Frix Law Library, https://www.frixlaw.com/law-library/documents/fr%3A99-2377. Public record. Not legal advice.