# Changes in Mammoth Creek Minimum Streamflow Requirements and Point of Measurement, and Changes in Place of Use

> Briefs, arguments, decisions, and more.

URL: https://www.frixlaw.com/law-library/documents/fr%3A97-7773

## Record

- **Collection:** Federal Register
- **Document type:** Notice
- **Published:** March 27, 1997
- **Citation:** 62 FR 14666

## Text

DEPARTMENT OF AGRICULTURE
Forest Service

Changes in Mammoth Creek Minimum Streamflow Requirements and
Point of Measurement, and Changes in Place of Use

AGENCY: Forest Service, USDA.

ACTION: Notice of intent to prepare an environmental impact statement.

-----------------------------------------------------------------------

SUMMARY: The Forest Service, Department of Agriculture, will prepare an
environmental impact statement (EIS) for the proposed amendment to the
existing Master Operating Agreement establishing minimum streamflow
requirements for Mammoth Creek, and Point of Measurement. The Forest
Service, Inyo National Forest, Mono County, California, is acting as
joint lead agency on the project, together with the

[[Page 14667]]

Mammoth Community Water District (District). Under the California
Environmental Quality Act, the District must conduct its own
environmental assessment, and has determined that an Environmental
Impact Report (EIR) is required. In accordance with Federal and State
regulations, a joint EIR/RIS will be prepared. The agency gives notice
of the environmental analysis and decision making processes that will
occur on the proposal so that interested and affected people are aware
of how they may participate and contribute to the final decision.

DATES: Comments regarding the scope of the analysis must be received by
April 30, 1997.

ADDRESSES: Submit written comments and suggestions concerning the
proposed action to the responsible official, Dennis Martin, Forest
Supervisor, Inyo National Forest, 873 North Main Street, Bishop,
California 93154, Attn. MCWD EIR/EIS.

FOR FURTHER INFORMATION CONTACT: Direct questions about this
environmental impact statement to Thom Heller, Special Use Permit
Administrator, Inyo National Forest, P.O. Box 148, Mammoth Lakes,
California 93546, or telephone (619) 924-5513.

SUPPLEMENTARY INFORMATION: The proposed action consists of two specific
components: 1) a change in the minimum streamflow requirements for
Mammoth Creek and the point of measurement, and 2) a change in the
District's authorized Place of Use (POU) for Mammoth Creek water. The
change in minimum streamflow requirements and point of measurement
result in both state and federal actions that require CEQA and NEPA
documentation. Although addressed in the joint EIR/EIS, the change in
the POU is a state action only, and not subject to NEPA. Three
alternatives are currently being considered: changing the minimum
streamflow requirements to the schedule shown on Table 2 (Proposed
action); changing the minimum streamflow requirements to an
alternative, three-flow schedule; and not changing the minimum
streamflow requirements (no action).
Public participation will be specially important at several points
during the analysis. The first point is the scoping process (40 CFR
1501.7). The Forest Service has and is seeking information, comments,
and assistance from Federal, State, and local agencies and other
individuals or organizations who may be interested in or affected by
the proposed action. This input will be used in preparation of the
draft EIR/EIS. The scoping process includes:
1. Identifying potential issues.
2. Identifying issues to be analyzed in depth
3. Eliminating insignificant issues or those which have been
covered by a relevant previous environmental analysis.
4. Exploring additional alternatives.
5. Identifying potential environmental effects of the proposed
action and alternatives (e.g., direct, indirect, and cumulative effects
and connected actions).
6. Determining potential cooperating agencies and task assignments.
Mailings to individuals and agencies that participate in the above
planning efforts will provide them with information about the proposed
project. Public meetings, if held, will be announced locally. Federal,
State, and local agencies, user groups and other organizations who
would be interested in the study will be invited to participate in
scoping the issues that should be considered.
The draft EIR/EIS is scheduled to be completed by September, 1997.
The comment period on this draft EIR/EIS will be 45 days from the date
the Environmental Protection Agency's notice of availability appears in
the Federal Register. It is very important that those interested in the
proposed action participate at that time.
The Forest Service believes, at this early stage, it is important
to give reviewers notice of several court rulings related to public
participation in the environmental review process. First, reviewers of
draft environmental impact statements must structure their
participation in the environmental review of the proposed action so
that it is meaningful and alerts an agency to the reviewer's position
and contentions. Vermont Yankee Nuclear Power Corp. v. NRDC, 435 U.S.
519 (1978). Also, environmental objections that could be raised at the
draft EIR/EIS stage but that are not raised until after completion of
the final EIR/EIS may be waived or dismissed by the courts. City of
Angoon v. Hodel, 803 F.2d 1016, 1022 (9th Cir. 1986) and Wisconsin
Heritages, Inc. v. Harris, 490 F. Supp. 1334, 1338 (E. D. Wis. 1980).
Because of these court rulings, it is very important that those
interested in this proposed action participate by the close of the 45-
day comment period so that substantive comments and objections are made
available to the Forest Service at a time when it can meaningfully
consider them and respond to them in the final EIR/EIS.
To assist the Forest Service in identifying and considering issues
and concerns on the proposed action, comments on the draft EIR/EIS
should be as specific as possible. It is also helpful if comments refer
to specific pages or chapters of the draft document. Comments may also
address the adequacy of the draft EIR/EIS or the merits of the
alternatives formulated and discussed in the document. Reviewers may
wish to refer to the Council on Environmental Quality Regulations for
implementing the procedural provisions of the National Environmental
Policy Act at 40 CFR 1503.3 in addressing these points.
After the comment period ends on the draft EIR/EIS, the comments
will be analyzed and considered by the Forest Service in preparing the
final EIR/EIS, which is expected to be completed by December, 1997. The
Forest Service is required to respond in the final EIS to the comments
received (40 CFR 1503.4). The responsible official will consider the
comments, responses, and environmental consequences discussed in the
final EIS and applicable laws, regulations, and policies in making his
decision on the proposal.
The decision will either be approval of the proposed action as
submitted, approval of the proposed action as modified, or denial of
the proposed action (No. Action). If the proposal is approved, the
existing Memorandum of Agreement would be modified and the revised
minimum flow requirements for Mammoth Creek would be approved. The
responsible official will document the decision and rationale in the
Record of Decision. The decision will be subject to appeal under 36 CFR
215 or regulations applicable at the time of the decision.

Dated: March 21, 1997.
Dennis W. Martin,
Forest Supervisor.
[FR Doc. 97-7773 Filed 3-26-97; 8:45 am]
BILLING CODE 3410-11-M

---

Source: Frix Law Library, https://www.frixlaw.com/law-library/documents/fr%3A97-7773. Public record. Not legal advice.