# Approval and Promulgation of Air Quality Implementation Plans; State of Georgia; Enhanced Motor Vehicle Inspection and Maintenance Program

> Briefs, arguments, decisions, and more.

URL: https://www.frixlaw.com/law-library/documents/fr%3A97-20576

## Record

- **Collection:** Federal Register
- **Document type:** Rule
- **Published:** August 11, 1997
- **Citation:** 62 FR 42916

## Text

ENVIRONMENTAL PROTECTION AGENCY

40 CFR Part 52

[GA-34-2-9716; FRL-5865-9]

Approval and Promulgation of Air Quality Implementation Plans;
State of Georgia; Enhanced Motor Vehicle Inspection and Maintenance
Program

AGENCY: Environmental Protection Agency (EPA).

ACTION: Interim final rule.

-----------------------------------------------------------------------

SUMMARY: EPA is granting interim approval of a State Implementation
Plan (SIP) revision submitted by Georgia. This revision establishes and
requires the implementation of an enhanced motor vehicle inspection and
maintenance (I/M) program in 13 metro Atlanta counties. This action
approves the State's enhanced I/M program for an 18 month interim
period based upon the State's good faith estimate of the program's
performance. This action is being taken under section 110 of the Clean
Air Act (CAA) and section 348 of the National Highway Systems
Designation Act (NHSDA).

DATES: This final rule is effective on September 10, 1997.

ADDRESSES: Copies of the documents relevant to this action are
available for public inspection during normal business hours at the
following locations:

Air, Pesticides, and Toxics Management Division, U.S. Environmental
Protection Agency, Region 4, 61 Forsyth Street, SW., Atlanta, Georgia,
30303
Georgia Department of Natural Resources, Environmental Protection
Division, Air Protection Branch, 4244 International Parkway, Suite 120,
Atlanta, Georgia, 30354
Air and Radiation Docket and Information Center (Air Docket 6102) U.S.
Environmental Protection Agency, 401 M St., SW., Washington, DC 20460

FOR FURTHER INFORMATION CONTACT: Ben Franco, by telephone at: (404)
562-9039, or via e-mail at: Franco.B[email protected]. The mailing
address is U.S. EPA Region 4, 61 Forsyth Street, SW., Atlanta, Georgia,
30303.

SUPPLEMENTARY INFORMATION:

I. Background

On December 13, 1996 (61 FR 65496), EPA published a notice of
proposed rulemaking (NPR) for the State of Georgia. The NPR proposed
conditional interim approval of Georgia's enhanced

[[Page 42917]]

I/M program, submitted to satisfy the applicable requirements of both
the CAA and the NHSDA. The formal SIP revision was submitted by the
Georgia Environmental Protection Division (EPD) on March 27, 1996. A
lack of Acceleration Simulation Mode (ASM) test method specifications
was the reason for the conditional approval.
The NHSDA directs EPA to grant interim approval for a period of 18
months to approvable I/M submittals under this Act. The NHSDA also
directs EPA and the states to review the interim program results at the
end of that 18-month period, and to make a determination as to the
effectiveness of the interim program. Following this demonstration, EPA
will adjust any credit claims made by the State in its good faith
effort, to reflect the emissions reductions actually measured by the
State during the program evaluation period. The NHSDA is clear that the
interim approval shall last for only 18 months, and that the program
evaluation is due to EPA at the end of that period. Therefore, EPA
believes Congress intended for these programs to begin as soon as
possible, which EPA believes should be on or before November 15, 1997,
so that, assuming a twelve month planning period before program
implementation, at least six months of operational program data can be
collected to evaluate the interim programs. EPA believes that in
setting such a strict timetable for program evaluations under the
NHSDA, Congress recognized and attempted to mitigate any further delay
with the start-up of this program. If the State fails to start its
program according to this schedule, this interim approval granted under
the provisions of the NHSDA will convert to a disapproval after a
finding letter is sent to the State. Unlike the other specified
conditions of this rulemaking, which are explicit conditions under
section 110(k)(4) of the CAA and which will trigger an automatic
disapproval should the State fail to meet its commitments, the start
date provision will only trigger a disapproval upon EPA's notification
to the State by letter that the start date has been missed. This letter
will not only notify the State that this rulemaking action has been
converted to a disapproval, but also that the sanctions clock
associated with this disapproval has been triggered as a result of this
failure. Because the start date condition is not imposed pursuant to a
commitment to correct a deficient SIP under 110(k)(4), EPA does not
believe it is necessary to have the SIP approval convert to a
disapproval automatically if the start date is missed. EPA is imposing
the start date condition under its general SIP approval authority of
section 110(k)(3), which does not require automatic conversion.
On January 31, 1997, the Georgia EPD submitted necessary ASM
specifications that were the reason for the condition in the December
13, 1996, notice. These specifications were largely based upon EPA's
specifications for the ASM test. Therefore, the condition noted in the
December 13, 1996, proposal has been met and is removed. Georgia has
also begun its implementation of the I/M program as scheduled and has
met all milestones to date. Georgia has also committed to meet the
ECOS/EPA/STAPPA evaluation workgroup protocol which will meet the
requirements of 40 CFR 51.353(c)(3).
As per the NHSDA requirements, this interim rulemaking will expire
on February 11, 1999. A full approval of Georgia's final I/M SIP
revision is still necessary under section 110 and under section 182,
184 or 187 of the CAA. After EPA reviews Georgia's submitted program
evaluation and regulations, final rulemaking on the State's full SIP
revision will occur.
Additional detailed discussion of the Georgia enhanced I/M SIP and
the rationale for EPA's action are explained in the proposal notice
published December 13, 1996, at 61 FR 65496-65504 and will not be
restated here.

II. Final Rulemaking Action

EPA had initially proposed to grant conditional interim approval to
the Georgia enhanced I/M SIP revision due to the lack of the ASM
specification. However, Georgia has since submitted the required ASM
specifications, thereby meeting the requirements of the condition. EPA
notes the State has demonstrated its good faith efforts by meeting its
I/M program implementation schedule to date.
Under the terms of EPA's December 13, 1996, proposed interim
conditional approval rulemaking, Georgia was required to make
commitments (within 30 days) to remedy one major deficiency with the I/
M program SIP (as specified in the NPR), within twelve months of final
interim approval. On January 10, 1997, Georgia submitted a letter from
Ronald Methier, Chief of the Air Protection Branch, Georgia
Environmental Protection Division, to EPA committing to satisfy the ASM
condition cited in the NPR, by certain dates specified in the letter.
Subsequently, on January 31, 1997, the Georgia EPD submitted the
required ASM specifications. Since the condition has been met by EPA's
receipt of the ASM specifications, and since no comments were received
concerning the December 13, 1996, proposal, EPA is granting final
interim approval to the Georgia I/M SIP under section 110 of the CAA.
As discussed in detail later in this notice, this approval is being
granted on an interim basis, for an 18-month period under authority of
the NHSDA.

III. Further Requirements for Permanent I/M SIP Approval

This approval is being granted on an interim basis for a period of
18 months, under the authority of section 348 of the NHSDA of 1995. At
the end of this period, the approval will lapse. At that time, EPA must
take final rulemaking action upon the SIP, under the authority of
section 110 of the CAA. Final approval of the State's plan will be
granted based upon the following criteria:
(1) EPA's review of the Georgia program evaluation confirms that
the appropriate amount of program credit was claimed by the State and
achieved with the interim program.

IV. Administrative Requirements

Nothing in this action should be construed as permitting or
allowing or establishing a precedent for any future request for
revision to any SIP. Each request for revision to the SIP shall be
considered separately in light of specific technical, economic, and
environmental factors and in relation to relevant statutory and
regulatory requirements.

A. Executive Order 12866

The Office of Management and Budget (OMB) has exempted this
regulatory action from E.O. 12866 review.

B. Regulatory Flexibility Act

Under the Regulatory Flexibility Act, 5 U.S.C. 600 et seq., EPA
must prepare a regulatory flexibility analysis assessing the impact of
any proposed or final rule on small entities. 5 U.S.C. 603 and 604.
Alternatively, EPA may certify that the rule will not have a
significant impact on a substantial number of small entities. Small
entities include small businesses, small not-for-profit enterprises,
and government entities with jurisdiction over populations of less than
50,000.

C. SIP Approval Actions

SIP approvals under section 110 and subchapter I, part D of the CAA
do not create any new requirements but simply approve requirements that
the State is already imposing. Therefore, because the Federal SIP
approval does not impose any new requirements, I certify that it does
not have a significant impact on any small entities affected. Moreover,

[[Page 42918]]

due to the nature of the Federal-State relationship under the CAA,
preparation of a flexibility analysis would constitute Federal inquiry
into the economic reasonableness of state action. The CAA forbids EPA
to base its actions concerning SIPS on such grounds. Union Electric Co.
v. U.S. EPA, 427 U.S. 246, 255-66 (1976); 42 U.S.C. 7410(a)(2) and
7410(k)(3).

D. Unfunded Mandates

Under section 202 of the Unfunded Mandates Reform Act of 1995
(``Unfunded Mandates Act''), signed into law on March 22, 1995, EPA
must prepare a budgetary impact statement to accompany any proposed or
final rule that includes a Federal mandate that may result in estimated
costs to State, local, or tribal governments in the aggregate; or to
the private sector, of $100 million or more. Under section 205, EPA
must select the most cost-effective and least burdensome alternative
that achieves the objectives of the rule and is consistent with
statutory requirements. Section 203 requires EPA to establish a plan
for informing and advising any small governments that may be
significantly or uniquely impacted by the rule.
EPA has determined that the approval action promulgated does not
include a Federal mandate that may result in estimated costs of $100
million or more to either State, local, or tribal governments in the
aggregate, or to the private sector. This Federal action approves pre-
existing requirements under State or local law, and imposes no new
requirements. Accordingly, no additional costs to State, local, or
tribal governments, or to the private sector, result from this action.

E. Submission to Congress and the General Accounting Office

Under 5 U.S.C. 801(a)(1)(A) as added by the Small Business
Regulatory Enforcement Fairness Act of 1996, EPA submitted a report
containing this rule and other required information to the U.S. Senate,
the U.S. House of Representatives and the Comptroller General of the
General Accounting Office prior to publication of the rule in today's
Federal Register. This rule is not a ``major rule'' as defined by 5
U.S.C. 804(2).

F. Petitions for Judicial Review

Under section 307(b)(1) of the CAA, petitions for judicial review
of this action must be filed in the United States Court of Appeals for
the appropriate circuit by October 10, 1997. Filing a petition for
reconsideration by the Administrator of this final rule does not affect
the finality of this rule for the purposes of judicial review nor does
it extend the time within which a petition for judicial review may be
filed, and shall not postpone the effectiveness of such rule or action.
This action may not be challenged later in proceedings to enforce its
requirements. (See section 307(b)(2).)

List of Subjects in 40 CFR Part 52

Environmental protection, Air pollution control, Carbon monoxide,
Hydrocarbons, Incorporation by reference, Intergovernmental relations,
Nitrogen dioxide, Ozone, Reporting and recordkeeping requirements.

Dated: July 12, 1997.
John H. Hankinson, Jr.,
Regional Administrator.

Part 52 of chapter I, title 40, Code of Federal Regulations, is
amended as follows:

PART 52--[AMENDED]

1. The authority citation for part 52 continues to read as follows:

Authority: 42.U.S.C. 7401-7671q.

Subpart L--Georgia

2. Section 52.570 is amended by adding paragraph (c)(50) to read as
follows:

Sec. 52.570 Identification of plan.

* * * * *
(c) * * *
(50) Georgia Enhanced Inspection and Maintenance submitted to EPA
by the Georgia Department of Natural Resources on March 27, 1996.
(i) Incorporation by reference.
(A) Chapter 391-3-20 Enhanced Inspection and Maintenance program
effective on September 24, 1996.
(ii) Other material. None.

[FR Doc. 97-20576 Filed 8-8-97; 8:45 am]
BILLING CODE 6560-50-P

---

Source: Frix Law Library, https://www.frixlaw.com/law-library/documents/fr%3A97-20576. Public record. Not legal advice.