# Secondary Market Transactions on Interstate Natural Gas Pipelines

> Briefs, arguments, decisions, and more.

URL: https://www.frixlaw.com/law-library/documents/fr%3A96-20179

## Record

- **Collection:** Federal Register
- **Document type:** Notice
- **Published:** August 8, 1996
- **Citation:** 61 FR 41401

## Text

DEPARTMENT OF ENERGY
[Docket No. RM96-14-001]

Secondary Market Transactions on Interstate Natural Gas Pipelines

Issued July 31, 1996.

AGENCY: Federal Energy Regulatory Commission.

ACTION: Proposed Experimental Pilot Program to Relax the Price Cap for
Secondary Market Transactions, and Request for Office of Management and
Budget Emergency Processing of Submission of Collection of Information

-----------------------------------------------------------------------

SUMMARY: The Federal Energy Regulatory Commission is issuing an order
establishing a proposed pilot program to release the price cap for
releases of capacity and sales of interruptible and short-term firm
transportation in certain geographic areas.
Because the Commission anticipates implementing the pilot program
for the 1996-97 winter heating season, the Commission, pursuant to 5
CFR 1320.13, is providing notice of its request to the Office of
Management and Budget (OMB) for emergency processing of the proposed
collection of information relating to the pilot program.

DATES: The Commission requests applications for the pilot program by
August 30, 1996. Comments on the applications will be due 15 days after
filing of applications to participate. Applications and comments on the
applications should be filed with the Office of the Secretary and
should refer to Docket No. RM96-14-001.
Because the Commission has requested OMB to process the proposed
collection of information in Docket No. RM96-14-001 on an emergency
basis, comments on this collection of information should be filed with
OMB, attention Desk Officer FERC, as soon as possible.

ADDRESSES: Federal Energy Regulatory Commission, 888 First Street, NE,
Washington, DC 20426.

FOR FURTHER INFORMATION CONTACT: Michael Goldenberg, Office of the

[[Page 41402]]

General Counsel, Federal Energy Regulatory Commission, 888 First
Street, NE, Washington, DC 20426, (202) 208-2294.
For information relating to the data template, contact:

Marvin Rosenberg, Office of Economic Policy, Federal Energy Regulatory
Commission, 888 First Street, NE, Washington, DC 20426, (202) 208-1283.
Elizabeth A. Taylor, Office of Pipeline Rates, Federal Energy
Regulatory Commission, 888 First Street, NE., Washington, DC 20426,
(202) 208-0826.

SUPPLEMENTARY INFORMATION: In addition to publishing the full text of
this document in the Federal Register, the Commission provides all
interested persons an opportunity to inspect or copy the contents of
this document during normal business hours in Room 2A, 888 First
Street, N.E., Washington D.C. 20426.
The Commission Issuance Posting System (CIPS), an electronic
bulletin board service, provides access to the texts of formal
documents issued by the Commission. CIPS is available at no charge to
the user and may be accessed using a personal computer with a modem by
dialing 202-208-1397 if dialing locally or 1-800-856-3920 if dialing
long distance. To access CIPS, set your communications software to
19200, 14400, 12000, 9600, 7200, 4800, 2400, 1200bps, full duplex, no
parity, 8 data bits, and 1 stop bit. The full text of this document
will be available on CIPS indefinitely in ASCII and WordPerfect 5.1
format for one year. The complete text on diskette in WordPerfect
format may also be purchased from the Commission's copy contractor, La
Dorn Systems Corporation, also located in Room 2A, 888 First Street,
NE., Washington, DC 20426.
The Commission's bulletin board system also can be accessed through
the FedWorld system directly by modem or through the Internet. To
access the FedWorld system by modem:
Dial (703) 321-3339 and logon to the FedWorld system.
After logging on, type: /go FERC
To access the FedWorld system, through the Internet:
Telnet to: fedworld.gov
Select the option: [1] FedWorld
Logon to the FedWorld system
Type: /go FERC
Or:
Point your Web Browser to: http://www.fedworld.gov
Scroll down the page to select FedWorld Telnet Site
Select the option: [1] FedWorld
Logon to the FedWorld system
Type: /go FERC

Secondary Market Transactions on Interstate Natural Gas Pipelines

Docket No. RM96-14-001

Proposed Experimental Pilot Program To Relax the Price Cap for
Secondary Market Transactions
Issued July 31, 1996.

Before Commissioners: Elizabeth Anne Moler, Chair; Vicky A.
Bailey, James J. Hoecker, William L. Massey, and Donald F. Santa,
Jr.

In a Notice of Proposed Rulemaking (NOPR) issued in this docket and
published in the Federal Register of August 7, 1996, the Federal Energy
Regulatory Commission (Commission) proposes to permit shippers
releasing capacity, and pipelines selling interruptible transportation,
to sell at rates above the pipeline's maximum tariff rate when they can
demonstrate they do not possess market power in the secondary market.
The Commission further intends to hold a technical conference to
explore issues related to the proposal and the methods for measuring
market power. To complement the NOPR and provide additional record
evidence for evaluating the criteria for evaluating market power, the
Commission is proposing an experimental pilot program to remove the
price ceiling for releases of capacity and pipeline sales of
interruptible and short-term firm transportation into qualifying
markets.

Background

Under Commission policy, price ceilings can be removed when
pipelines and shippers do not possess market power, because, without
the ability to control price or output, shippers are unable to exact
charges above the competitive level and hence their rates are just and
reasonable under the Natural Gas Act (NGA).1 The NOPR proposes to
require pipelines and shippers seeking to sell capacity above the cap
to make filings to demonstrate that they do not possess market power.
These filings could be based on the criteria for assessing market power
in the Commission's Policy Statement on Alternatives to Cost-of-Service
Ratemaking or on modifications to that policy that the Commission
adopts after consideration of the comments on the NOPR.
---------------------------------------------------------------------------

\1\ Policy Statement on Alternatives to Cost-of-Service
Ratemaking, 74 FERC para. 61,076 (1996).
---------------------------------------------------------------------------

In the NOPR, the Commission also identifies certain additional
prerequisites that must be present for pipelines and LDCs to establish
that they lack market power. In order to ensure that capacity release
is fully competitive with pipeline services, pipelines would have to
implement tariff provisions ensuring that they treat capacity release
transactions comparably to their own interruptible and short-term
services. Without comparability, pipeline services may, in many
respects, be superior to capacity release and have a competitive
advantage in the marketplace.
For LDCs, the necessary prerequisite would be a showing that they
provide an acceptable open access transportation service on their own
facilities. In the absence of a viable open access program, LDCs may
well be able to exercise market power over customers behind their city-
gates. The LDC may be able to structure its intrastate service so that
the end-user's ability to obtain released interstate capacity from
shippers other than its own LDC is limited. An LDC's control over
primary delivery points also may give rise to market power over the
LDC's customers.
To deal with issues of market power over customers behind the city-
gate, the NOPR proposes that an LDC must provide customers with
identical open access transportation service on the LDC's system,
regardless of whether the customer purchases interstate capacity from
the LDC or another shipper. In addition, open access service would need
to include a right for customers behind the city-gate to use the LDC's
city-gate as a primary delivery point, regardless of whether they
purchase interstate capacity from the LDC. As explained in the NOPR, if
a customer cannot use the LDC's city-gate as a primary delivery point,
it may not have available adequate alternative sources of capacity,
because the purchase of interstate capacity from a shipper other than
its own LDC (with the resulting use of the city-gate delivery point on
a secondary basis) may not be the equivalent of purchasing primary
point capacity from its own LDC.

Proposed Pilot Program

In conjunction with the NOPR, the Commission is proposing this
pilot program to help assess whether compliance with the criteria
identified in the NOPR is indicative of a lack of market power. Under
this program, the price cap will be lifted for released capacity and
pipeline interruptible and short-term firm capacity in a designated
geographic area. Specifically, the cap will be released for capacity
released by an LDC to delivery points in its delivery area, for
interruptible and short-term

[[Page 41403]]

firm transportation sold by the pipeline into the same area, and for
capacity released by other shippers into the area. The cap would be
released only for the duration of the experiment.2 Because prices
for released capacity generally approach the maximum rate only during
peak periods, the Commission anticipates the pilot program needs to
last at least through the 1996-1997 winter heating season, if not
longer.
---------------------------------------------------------------------------

\2\ Thus, if shippers entered into a long-term capacity release
transaction, the ability to release above the cap would not extend
beyond the end of the experiment.
---------------------------------------------------------------------------

Applications to participate in the program should include
information showing why the pipelines and the LDCs cannot exercise
market power in the relevant area, although this showing need not
constitute the detailed market power analysis set out in the
Commission's Policy Statement on Alternatives to Cost-Of-Service
Ratemaking. One item of information that should be included in the
application is the name of each shipper on the pipeline, together with
the amount of its firm capacity that could be used to effect deliveries
to the LDC's delivery area.3
---------------------------------------------------------------------------

\3\ For example, such data might include all firm capacity in
the same zone as the LDC and any downstream zone.
---------------------------------------------------------------------------

In addition to this information, LDCs need to meet the NOPR's
requirement for open access service. LDCs with state-approved pilot
open access programs meet the requirement. For instance, it appears
from the information available to the Commission that New York and
California may have open access tariffs that would qualify, since these
states provide for open access transportation to non-core industrial
customers as well as to core or residential customers that aggregate
their demand.
However, special discounting programs limited to industrials will
not be sufficient. An LDC that does not meet the open access
requirement still may apply, but it will have to bear a greater burden
of establishing that it lacks market power and, therefore, must present
a more comprehensive analysis of market power.
In order to qualify, pipelines would have to implement tariff
revisions to assure comparability between interruptible service and
capacity release. In the Business Practices Rule in Docket No. RM96-1-
000, the Commission adopted, by reference, a standard timeline for
capacity release transactions established by the Gas Industry Standards
Board. This timeline, in general, provides that, so long as a pipeline
is notified of a non-biddable capacity release 2\1/2\ hours prior to
its nomination deadline, the replacement shipper can nominate under the
deal. 4 Pipelines are to implement these standards by the spring
of 1997. Pipelines seeking to participate in the pilot program can
comply with the comparability requirement by implementing the standard
capacity release timeline early. 5
---------------------------------------------------------------------------

\4\ For biddable short-term deals, the timeline requires
notification to the pipeline the day prior to nomination.
\5\ While the NOPR in this docket proposes the elimination of
the competitive bidding requirement, pipelines need not seek to
implement this recommendation for the pilot program. However, if
they do, they would need to file a separate tariff provision limited
to the LDC or LDCs participating in the program.
---------------------------------------------------------------------------

Pipelines and LDCs may file joint or concurrent applications to
participate. LDCs, however, may file individual applications so long as
the application provides enough information to establish a lack of
market power in the relevant area for both the LDC and the pipeline. If
an LDC files individually, the Commission must obtain, prior to the
Commission's approval of the application, a commitment from the
pipeline to participate in the pilot program by implementing the
comparability requirements and providing the reporting data (outlined
below). After receipt of the applications, the Commission will provide
an opportunity for comment on which applications to accept and on the
design of the program.

Reporting Requirements

To judge whether the market, under these conditions, provides
adequate consumer protection against market power abuses, the
Commission will require the pipelines and LDCs participating in the
program to submit periodic data reports for the period of the
experiment. Additionally, to provide a basis for comparing the use of
capacity and prices, the same data also will be needed for the year
prior to the experiment. Pipelines and LDCs will not be required to
provide these data (including the prior year's data) until after the
Commission has accepted applications to participate in the program
according to a schedule to be established. This information will be
made available to the public to assist in the assessment of the
experiment.
The Commission needs sufficient information to evaluate whether
capacity is being allocated efficiently and whether consumers--options
for buying and selling gas have been expanded. These data will help in
analyzing changes in the number and concentration of market
participants (buyers and sellers) relative to the pre-experimental base
period, as well as the concentration of buyers and sellers
participating in the market each day and the volumes traded by each.
These data further will reveal changes in the use of capacity relative
to the pre-experimental base period. For example, these data will show
any changes in the mix of interruptible, firm, release capacity, and
bundled sales and any changes in the use of storage. These data also
will permit analysis of how daily prices vary depending on the
availability of capacity, which may be suggestive of whether market
power is being exercised.
For pipelines, the information that is needed would include for the
period of the experiment and for one year prior to the start of the
experiment, the following information for all transactions that
potentially could be used to make deliveries to the LDC's delivery
area:

1. For each capacity release and firm transaction into which
parties have entered that affects the relevant area, the name of the
shipper; the contract number; the rate schedule; the rate charged
(including all terms and conditions of the rate); 6 the maximum
rate; the contractual quantity; the beginning and end date of the
transaction; the date on which the parties to a capacity release
transaction posted the transaction to the pipeline; the receipt and
delivery points of the transaction; an identification of any changes
to different primary or secondary receipt or delivery points made by
the replacement shipper; an identification of whether a capacity
release transaction is a segmented release; 7 and an
identification of an affiliate relationship with the pipeline;
---------------------------------------------------------------------------

\6\ Terms and conditions would include, for example, a rate that
varied depending on the volume shipped.
\7\ In a segmented release, the releasing shipper divides its
capacity into one or more segments and either separately releases
multiple segments or releases one or more segments while retaining
some capacity for its own use.
---------------------------------------------------------------------------

2. For each capacity release, interruptible, and firm shipment
made on its system that affects the relevant area, for each day, the
name of the shipper, the contract number, the daily quantity of gas
scheduled, and the daily total revenue derived.
3. The available capacity on the mainline and for receipt and
delivery points, for each day, and any operational flow orders that
are in effect for each day that would affect the relevant area.

For LDCs, the required information would include a map of the LDC's
system, showing its capacity at city-gate delivery points and the
following information for the period of the experiment and for one year
prior to the start of the experiment the following:

1. For its interstate capacity, by pipeline, by rate schedule,
by day, the total quantity of its interstate capacity and the amount
used

[[Page 41404]]

for traditional on-system retail sales at WACOG, for capacity
release, for off-system bundled gas/transportation sales, and for
on-system bundled gas/transportation sales at other than WACOG;
2. For each off-system or on-system bundled gas/transportation
sale at other than WACOG, the name of the shipper, the rate charged
(including all terms and conditions of the rate), the maximum rate
(if applicable), the daily quantity of gas sold, the daily revenue
derived, the receipt and delivery points, and the beginning and end
date of the transaction.

In addition, where applicable, LDCs must provide a statement of the
amount of interstate pipeline capacity held by an affiliated marketer,
and for the period of the experiment and one year prior to the
experiment, a list of any capacity release transactions with an
affiliate.
The Commission will require pipelines and LDCs to file these data
in electronic form. The template for reporting the information will be
made available to those making applications, upon request, so they can
comment on the format. Those filing proposals and comments should
discuss the design of the program, including, but not limited to, how
long the experiment should run, the period for filing the year-before
data and the periodic reports (monthly, quarterly).

Application and Comment Procedures

The Commission hopes to be able to begin the pilot program in the
1996-97 winter heating season. LDCs or pipelines, therefore, should
file their applications by August 30, 1996, although later applications
also will be considered. After receiving the requests to participate,
the Commission will provide 15 days for comment on which applications
should be granted as well as on the design of the experiment and
possible improvements. In addition, at the end of the pilot program,
the Commission intends to solicit comments from both buyers and sellers
providing their assessment of the results.
Applications and comments should be submitted to the Office of the
Secretary, Federal Energy Regulatory Commission, 888 First Street, NE,
Washington, DC 20426, and should refer to Docket No. RM96-14-001.
Additionally, the Commission strongly encourages applicants and
commenters to submit a computer diskette of their comments in
WordPerfect version 6.1 format or lower or in ASCII format, with the
name of the filer and Docket No. RM96-14-001 on the outside of the
diskette. Those providing files in ASCII format should take care to
examine the form of an ASCII conversion to ensure, for instance, that
it includes footnotes, headers, and footers, as these have often been
left out in past electronic filings. All written comments will be
placed in the Commission's public files and will be available for
inspection in the Commission's Public Reference Room at 888 First
Street, NE, Washington, DC 20426, during regular business hours.

Information Collection

The Paperwork Reduction Act of 1995, 44 U.S.C. 3507, and Office of
Management and Budget (OMB) implementing regulations at 5 CFR 1320.10
require OMB to approve certain reporting and recordkeeping requirements
(collections of information) imposed by a federal agency. Upon approval
of a collection of information, OMB will assign an OMB control number
and an expiration date.
The proposed pilot program will be done under two new temporary
data collections, FERC-549AP, Gas Pipeline Certificates: Application
for Capacity Release/Pilot Program), (OMB Control No. (to be assigned
by OMB)) (FERC-549AP), and FERC-549P, Gas Pipeline Rates: Capacity
Release/Pilot Program (OMB Control No. (to be assigned by OMB)) (FERC-
549-P). The respondents will be local distribution companies and
interstate natural gas pipelines. Because participation in the program
is voluntary, the Commission is unable to estimate the total number of
applicants, nor can the Commission determine the number of applications
it will approve until after it receives the applications.
The Commission estimates that the average time per respondent for
reviewing the requirements to participate in the program, searching
existing data sources, and preparing the application will be 40 hours,
with a total cost per respondent of about $2,000. For those applicants
chosen to participate in the program, the estimate for extracting and
reporting the year-before and periodic data in the required format will
average 60 hours per respondent, with an estimated cost of about $6,000
per respondent. Participation in this program is purely voluntary, and
the costs are one-time costs that will not be incurred on an annual
basis.
The proposed collection of information is being submitted to OMB
for review. Because the Commission hopes to approve certain
applications to participate in the pilot program in time for the 1996-
97 winter heating season, the Commission has requested applications
within 30 days of this order. Accordingly, the Commission has requested
the Office of Management and Budget (OMB) to provide for emergency
processing of this proposed collection of information by August 15,
1996. Comments on the collection of information, therefore, should be
filed with the Office of Management and Budget as soon as possible to
provide OMB sufficient time for its review. For copies of the OMB
submission, contact Michael Miller at (202)208-1415. Interested persons
may send comments regarding these burden estimates or any other aspect
of these collections of information, including suggestions for
reductions of burden, to the Desk Officer FERC, Office of Management
and Budget, Room 3019 NEOB, Washington, D.C. 20503, phone 202-395-3087
or via the Internet at [email protected]. Comments should be filed
with the Office of Management and Budget. A copy of any comments filed
with the Office of Management and Budget also should be sent to the
following address at the Commission: Federal Energy Regulatory
Commission, Information Services Division, Room 41-17, Washington, DC
20426, Attention: Michael Miller.

By the Commission.
Lois D. Cashell,
Secretary.
[FR Doc. 96-20179 Filed 8-7-96; 8:45 am]
BILLING CODE 6717-01-P

---