## Text

DEPARTMENT OF AGRICULTURE

Forest Service

Supplemental Environmental Impact Statement, Central Prince of
Wales Project, Tongass National Forest, Ketchikan Area, AK

AGENCY: Forest Service, USDA.

ACTION: Notice of intent to prepare a supplemental environmental impact
statement.

-----------------------------------------------------------------------

SUMMARY: The Tongass National Forest--Ketchikan Area proposes to review
and analyze information on ``falldown'' and to calculate its effect, if
any, on ``sustainable'' timber harvest in the Central Prince of Wales
project area covered in the previous environmental impact statement and
record of decision issued August 6, 1993. The proposed action is to
provide approximately 290 million board feet of timber in support of
the Ketchikan Pulp Company Long-Term Timber Sale Contract, Contract
Number A10fs-1042.

ADDRESSES: Send written comments to Forest Supervisor, Tongass NF--
Ketchikan Area, Federal Building, Ketchikan, AK 99901.

FOR FURTHER INFORMATION CONTACT:
Questions concerning the proposed analysis and supplemental
environmental impact statement should be directed to Pete Griffin,
Tongass NF--Ketchikan Area, Federal Building, Ketchikan, AK 99901,
phone: (907) 225-3101.

SUPPLEMENTARY INFORMATION: The purpose of the project is to provide
approximately 290 million board feet of timber in support of the
Ketchikan Pulp Company Long-Term Timber Sale Contract, Contract Number
A10fs-1042. The purpose of the supplement is to evaluate information
available to the Forest Service with regard to falldown. The effects of
falldown as related to sustainable harvest levels will also be
analyzed. Factors related to falldown include economic, biological, and
physical.
Alternatives to be analyzed will include those alternatives as
described in the CPOW FEIS including the no action alternative.
The following issues have been identified:
1. Falldown.
2. Sustainability.
Scoping was completed for the CPOW project in 1992. Council on
Environmental Quality regulations (40 CFR 1502.9(c)(4)) do not require
scoping for a supplement. Additional public scoping meetings are not
planned. Public comment during the analysis is welcome and the public
will have an opportunity to comment on the draft supplement when
issued.
The draft supplemental environmental impact statement is expected
to be issued in May 1995. The comment period on the draft supplemental
environmental impact statement will be 45 days from the date the
Environmental Protection Agency publishes the notice of availability in
the Federal Register.
The Forest Service believes, at this early stage, it is important
to give reviewers notice of several court rulings related to public
participation in the environmental review process.
First, reviewers of draft environmental impact statements must
structure their participation in the environmental review of the
proposal so that it is meaningful and alerts an agency to the
reviewer's position and contentions. Vermont Yankee Nuclear Power Corp.
v NRDC, 435 U.S. 519, 553, (1978).
Also, environmental objections that could be raised at the draft
environmental impact statement stage but that are not raised until
after completion of the final environmental impact statement may be
waived or dismissed by the courts. City of Angoon v. Hodel, 803 F.2d
1016, 1022, (9th Cir. 1986) and Wisconsin Heritages, Inc., v. Harris,
490 F. Supp. 1334, 1338 (E.D. Wis. 1980).
Because of these court rulings, it is very important that those
interested in this proposed action participate by the close of the
comment period so that substantive comments and objections are made
available to the Forest Service at a time when it can meaningfully
consider them and respond to them in the supplemental environmental
impact statement.
To assist the Forest Service in identifying and considering issues
and concerns on the proposed action, comments on the draft
environmental impact statement should be as specific as possible. It is
also helpful if comments refer to specific pages or chapters of the
draft statement. [[Page 17313]] Comments may also address the adequacy
of the draft environmental impact statement or the merits of the
alternatives formulated and discussed in the statement. Reviewers may
wish to refer to the Council on Environmental Quality Regulations for
implementing the procedural provisions of the National Environmental
Policy Act at 40 CFR 1503.3 in addressing these points.
Issuance of the final supplemental environmental impact statement
is projected in September 1995. The responsible official for the
decision is the Forest Supervisor, Tongass NF--Ketchikan Area, Federal
Building, Ketchikan, AK 99901.

Dated: March 28, 1995.
David D. Rittenhouse,
Forest Supervisor.
[FR Doc. 95-8323 Filed 4-4-95; 8:45 am]
BILLING CODE 3410-11-M

---