# Approval and Promulgation of Air Quality Implementation Plans; District of Columbia; GSA Central and West Heating Plants

> Briefs, arguments, decisions, and more.

URL: https://www.frixlaw.com/law-library/documents/fr%3A95-10706

## Record

- **Collection:** Federal Register
- **Document type:** Rule
- **Published:** May 2, 1995
- **Citation:** 60 FR 21453

## Text

ENVIRONMENTAL PROTECTION AGENCY
40 CFR Part 52

[DC23-1-6790a; FRL-5181-2]

Approval and Promulgation of Air Quality Implementation Plans;
District of Columbia; GSA Central and West Heating Plants

AGENCY: Environmental Protection Agency (EPA).

ACTION: Direct final rule.

-----------------------------------------------------------------------

SUMMARY: EPA is approving a State implementation plan (SIP) revision
submitted by the District of Columbia. This revision will limit air
pollution from two steam-generating facilities located in the District
of Columbia. The intended effect of this action is to approve a permit-
to-operate issued by the District of Columbia to General Services
Administration for its Central and West Heating Plants. This action is
being taken under section 110 of the Clean Air Act.

DATES: This final rule is effective July 3, 1995, unless notice is
received on or before June 1, 1995, that adverse or critical comments
will be submitted. If the effective date is delayed, timely notice will
be published in the Federal Register.

ADDRESSES: Comments may be mailed to Marcia L. Spink, Associate
Director, Air Programs (3AT00), U.S. Environmental Protection Agency,
Region III, 841 Chestnut Building, Philadelphia, Pennsylvania 19107.
Copies of the documents relevant to this action are available for
public inspection during normal business hours at the Air, Radiation,
and Toxics Division, U.S. Environmental Protection Agency, Region III,
841 Chestnut Building, Philadelphia, Pennsylvania 19107; the Air and
Radiation Docket and Information Center, U.S. Environmental Protection
Agency, 401 M Street, SW, Washington, DC 20460; and District of
Columbia Department of Consumer and Regulatory Affairs, 2100 Martin
Luther King Ave, S.E., Washington, DC 20020.

FOR FURTHER INFORMATION CONTACT: David J. Campbell, Technical
Assessment Section (3AT22), U.S. Environmental Protection Agency,
Region III, 841 Chestnut Building, Philadelphia, Pennsylvania 19107,
phone: (215) 597-9781.

SUPPLEMENTARY INFORMATION: On October 24, 1994, the District of
[[Page 21454]] Columbia submitted a request that EPA approve a revision
to the District of Columbia SIP. The revision consists of a September
8, 1994 operating permit issued by the District of Columbia to GSA for
its Central and West Heating Plants. The permit establishes general
operating procedures at GSA's Central Heating Plant (CHP) and West
Heating Plant (WHP), including the exclusive combustion of natural gas
(with the provision for the combustion of low-sulfur oil in the event
of a natural gas service interruption).
The permit also defines annual and short-term emission limitations
for SO2, particulate matter (PM-10), nitrogen oxides (NOX),
volatile organic compounds (VOCs), and carbon monoxide (CO) for both of
the plants. Since this permit establishes more stringent emission
limitations than the existing SIP or applicable new source performance
standards (NSPS), the ambient air quality with respect to each of the
criteria pollutants mentioned above shall be significantly improved.
The permit-to-operate issued to GSA promotes continued maintenance
of the national ambient air quality standards (NAAQS) for SO2, PM-
10, and NOX in the areas surrounding the CHP and WHP. The District
of Columbia is currently designated as nonattainment for the NAAQS for
CO. Although the emissions limits established in the permit for CO will
not affect the attainment status of the District, they do provide for
CO emissions reductions at these two facilities which were previously
uncontrolled for CO. The permit also regulates particulate matter and
VOC emissions.
In order to achieve these emission reductions, GSA is restricted by
its September 8, 1994 operating permit to the combustion of natural
gas. The District restricted the fuel capabilities at the two
facilities primarily to minimize SO2 emissions from the Plants.
Modeling analyses performed in 1990 as part the permitting process for
GSA's proposed refurbishment of various boilers at CHP and WHP
indicated that elevated ambient concentrations of SO2 were
predicted for the areas immediately surrounding the two facilities when
the Plants burned coal under typical winter day conditions.
Along with the restrictions on fuel usage, the permit limits the
hourly and annual emissions of various pollutants from the facilities.
The permit drastically reduces SO2 emissions from the plant to the
point where such emissions present negligible potential for impact on
the surrounding areas. For instance, the average annual SO2
emissions from CHP and WHP were 523 and 626 tons per year,
respectively, during the period of 1980 to 1990, inclusive. The current
permit-to-operate restricts annual SO2 emissions to 4 tons per
year at CHP and 5 tons per year at WHP. This is an average overall
reduction of 1140 tons per year of SO2 emissions in the vicinity
of the two facilities. Annual emissions of PM-10, NOX, CO, and
VOCs from the two plants are restricted to a degree that further limits
the potential for violation of the relevant annual NAAQS in the
vicinity of these facilities.
The operating permit is also protective of the short-term NAAQS.
For each of the pollutants discussed above, hourly emission limitations
are established in the permit. These hourly emission limits are, in
every instance, as stringent or more restrictive than the applicable
limits in the District's existing SIP or new source performance
standards (NSPS) limits.
As mentioned above, the operating permit requires the combustion of
natural gas at all times at GSA's CHP and WHP. However, there is a
provision for the use of No. 2 ``on-road diesel'' with a maximum sulfur
content of five hundredths weight percent (0.05%wt) during periods
of service interruptions by the supplier. It should be noted that GSA
must comply with its annual and short-term emission rates regardless of
the fuel it uses. In the event of a service interruption, the permit
contains explicit instructions for the notification of the District of
this event and recordation of pertinent information.
The permit also requires GSA to report an extensive amount of
information to ensure continuous compliance with the annual and short-
term emission limits. The principal means for compliance determination
is the use of continuous emissions monitoring data collected at the
facilities. The District relies primarily on the procedures established
in 40 CFR part 60 for monitor operation and data quality assurance.
Daily emissions reports that provide hourly emission rates for
SO2, NOX, VOCs, and CO are to be prepared by GSA. GSA must
also submit a quarterly report documenting the hourly status of each
boiler at CHP and WHP including; hours of service, types and quantities
of fuel combusted, fuel composition and heat content, service
interruptions, and total tons of SO2, NOX, PM-10, VOCs, and
CO emitted on a monthly basis and as part of a rolling, 12-month annual
average. A monthly report is to be prepared demonstrating GSA's
maintenance of the NAAQS for SO2 in the vicinity of the two
facilities. Sulfur-in-fuel reports are due each month detailing
specific information about the fuel oil, if any, that was burned during
the month. The level of reporting detailed above provides adequate
assurances that the compliance status of GSA can be quickly and
accurately tracked at all times.

EPA Evaluation

EPA has evaluated the District of Columbia's SIP revision request
and concluded the following: (1) The operational and emission
limitations imposed on GSA's Central and West Heating Plants adequately
promote continued maintenance of the NAAQS; (2) the operational and
emission limitations are clearly enforceable; and (3) the applicable
requirements of CFR part 51 have been met. A more detailed evaluation
is provided in the Technical Support Document for this action which is
available upon request from the EPA Region III office listed in the
ADDRESSES section of this document.
EPA is approving this SIP revision without prior proposal because
the Agency views this as a noncontroversial amendment and anticipates
no adverse comments. However, in a separate document in this Federal
Register publication, EPA is proposing to approve the SIP revision
should adverse or critical comments be filed. This action will be
effective July 3, 1995, unless, by June 1, 1995, adverse or critical
comments are received.
If EPA receives such comments, this action will be withdrawn before
the effective date by publishing a subsequent notice that will withdraw
the final action. All public comments received will then be addressed
in a subsequent final rule based on this action serving as a proposed
rule. EPA will not institute a second comment period on this action.
Any parties interested in commenting on this action should do so at
this time. If no such comments are received, the public is advised that
this action will be effective on July 3, 1995.

Final Action

EPA is approving the District of Columbia's October 24, 1994
submittal consisting of a permit-to-operate for GSA's Central and West
Heating Plants as a revision to the District of Columbia SIP.
Nothing in this action should be construed as permitting or
allowing or establishing a precedent for any future request for
revision to any state implementation plan. Each request for revision to
the state implementation plan shall be considered separately in light
of specific technical, economic, and environmental factors and in
[[Page 21455]] relation to relevant statutory and regulatory
requirements.
Under the Regulatory Flexibility Act, 5 U.S.C. 600 et seq., EPA
must prepare a regulatory flexibility analysis assessing the impact of
any proposed or final rule on small entities. 5 U.S.C. 603 and 604.
Alternatively, EPA may certify that the rule will not have a
significant impact on a substantial number of small entities. Small
entities include small businesses, small not-for-profit enterprises,
and government entities with jurisdiction over populations of less than
50,000.
SIP approvals under section 110 and subchapter I, part D of the
Clean Air Act do not create any new requirements but simply approve
requirements that the State is already imposing. Therefore, because the
Federal SIP approval does not impose any new requirements, the
Administrator certifies that it does not have a significant impact on
any small entities affected. Moreover, due to the nature of the
Federal-State relationship under the CAA, preparation of a flexibility
analysis would constitute Federal inquiry into the economic
reasonableness of state action. The Clean Air Act forbids EPA to base
its actions concerning SIPs on such grounds. Union Electric Co. v. U.S.
EPA, 427 U.S. 246, 255-66 (1976); 42 U.S.C. 7410(a)(2).
This action has been classified as a Table 3 action for signature
by the Regional Administrator under the procedures published in the
Federal Register on January 19, 1989 (54 FR 2214-2225), as revised by
an October 4, 1993 memorandum from Michael H. Shapiro, Acting Assistant
Administrator for Air and Radiation. The OMB has exempted this
regulatory action from E.O. 12866 review.
Under section 307(b)(1) of the Clean Air Act, petitions for
judicial review of this action must be filed in the United States Court
of Appeals for the appropriate circuit by July 3, 1995. Filing a
petition for reconsideration by the Administrator of this final rule to
approve the permit-to-operate issued to GSA for its Central and West
Heating Plants as a revision to the District of Columbia SIP does not
affect the finality of this rule for the purposes of judicial review
nor does it extend the time within which a petition for judicial review
may be filed, and shall not postpone the effectiveness of such rule or
action. This action may not be challenged later in proceedings to
enforce its requirements. (See section 307(b)(2).)

List of Subjects in 40 CFR Part 52

Environmental protection, Air pollution control, Carbon monoxide,
Incorporation by reference, Nitrogen dioxide, Particulate matter,
Reporting and recordkeeping requirements, Sulfur oxides.

Dated: March 21, 1995.
Stanley L. Laskowski,
Acting Regional Administrator, Region III.

40 CFR part 52 is amended as follows:

PART 52--[AMENDED]

1. The authority citation for part 52 continues to read as follows:

Authority: 42 U.S.C. 7401-7671q.

Subpart J--District of Columbia

2. Section 52.470 is amended by adding paragraph (c)(33) to read as
follows:

Sec. 52.470 Identification of plan.

* * * * *
(c) * * *
(33) Permit-to-operate issued by the District of Columbia to
General Services Administration for its Central and West Heating Plants
submitted on October 24, 1994 by the Environmental Regulation
Administration:
(i) Incorporation by reference.
(A) Letter of October 24, 1994 from the Environmental Regulation
Administration transmitting a permit-to-operate issued by the District
of Columbia to GSA for its Central and West Heating Plants.
(B) September 8, 1994 permit-to-operate issued by the District of
Columbia to GSA for its Central and West Heating Plants requiring the
combustion of natural gas and establishing annual and short-term
emission limits for SO2, NOX, PM-10, VOCs, and CO. The permit
was effective upon its issuance.
(ii) Additional material.
(A) Remainder of the District of Columbia's October 24, 1994
submittal.

[FR Doc. 95-10706 Filed 5-1-95; 8:45 am]