DEPARTMENT OF AGRICULTURE
Forest Service

East Shore Project, Lake Tahoe Basin Management Unit (LTBMU),
Washoe County, Douglas County, and Carson City Rural Area, NV

AGENCY: Forest Service, USDA.

ACTION: Notice, intent to prepare environmental impact statement.

-----------------------------------------------------------------------

SUMMARY: The Forest Service will prepare an environmental impact
statement on a proposal to harvest 30-40 million board feet of both
merchantable and unmerchantable wood products from approximately 8,000
acres of National Forest System lands on the east side of Lake Tahoe in
Nevada. Dead and dying trees would be cut, and a green tree thinning
component is also proposed to improve forest health. Jeffrey pine
beetle suppression comprises part of the project. The proposed action
also uses prescribed fire and analyzes post sale treatments, including
watershed improvement projects.

DATES: Agencies and the public are invited to participate at any stage
of the process; however, the Forest Supervisor requests that
individuals concerned with the scope of the analysis comment by
February 14, 1994.

ADDRESSES: Written comments concerning the DEIS should be sent to the
responsible official, Forest Supervisor, LTBMU, 870 Emerald Bay Road,
Suite 1, South Lake Tahoe, California, 96150.

FOR FURTHER INFORMATION CONTACT:
Direct questions concerning the proposed action and alternatives to
Scott Parsons, Interdisciplinary Team Leader, (916) 573-2600 or the
above address.

SUPPLEMENTARY INFORMATION: The proposed action harvests dead, dying,
and diseased trees, many of which are beetle-infested, over
approximately 8,000 acres of an 11,000-acre study area. Green trees
would be thinned from overstocked stands, over about 2,000 acres, some
of which overlap the salvage acreage, and some of which is separate.
Some of the 30 to 40 million board feet removed will be useful lumber;
much of the timber removed will have no commercial value.
Trees would be removed from gentle slopes by tractor skidding
systems. Trees would be flown from steeper terrain by helicopter. No
new permanent roads would be constructed; however, construction of
additional temporary access roads and landing sites would be required,
as well as reconstruction and restoration of existing historic roads.
This proposed action includes treatments that will follow removal
of the trees. This includes (but is not limited to) site preparation,
planting, treatment of slash generated by the project, obliteration of
temporary and unneeded roads, and restoration of landings. Monitoring
how effectively the project prevents future beetle attacks is part of
``post sale'' work. The use of prescribed fire will be analyzed, both
as a post-harvest treatment and as a long-term management tool. This
alternative treats the most acres with prescribed fire.
Heritage (historic archaeological) resources are dispersed
throughout the study area. Most are the remains of 19th century
logging, and not all of them will be protected. In addition to
mitigation negotiated with the Advisory Council of Historic
Preservation, a key component of the analysis is to seek and address
enhancement opportunities for representative heritage properties.
Watershed restoration projects, road closures, and mistletoe
reduction opportunities may also be included in the proposed action if
they are, in the language of the National Environmental Policy Act
(NEPA), ``connected'', ``cumulative'' in their effects with the removal
of dead trees, or are ``ripe for decision''.
This action is proposed because of current forest mortality
stemming from historical activities. Beginning in the 1850's many of
the 200-500 year old pine trees around Lake Tahoe were harvested in
support of silver mining activities of the Comstock Lode. Earlier, the
forest and consisted of diverse species that resisted drought and
insect attacks. After logging slowed in the 1890's, the area began to
revegetate naturally. But a new and different forest grew to replace
the old. In the absence of frequently recurring fires, dense thickets
of moisture-loving fir trees replaced much of the open pine forest that
had been cut. The drought that began in 1987 weakened and killed those
fir trees that had sprouted after the massive Comstock cutting.
Forty years of fire suppression has dramatically increased the
density of trees and the amount of dead wood, standing or on the
ground. Members of the public have expressed concern over the large
numbers of dead trees the amount of forest fuels now present. Many
requests have been made for projects to remove timber to reduce safety
hazards, fire danger, and to improve visual quality. Such projects
would reduce the ``fuel loading'' and could decrease the risk and
severity of a catastrophic fire. Additionally, thinning of overstocked
stands can be an effective way to prevent future catastrophic insect
and disease outbreaks.
The environmental analysis provides the decisionmaker--the LTBMU
Forest Supervisor with an evaluation of what will happen if nothing is
done, and what may result from the proposed action, and other
alternatives Such disclosure will allow a reasoned choice between
management options. If an alternative other than No Action is
preferable, then the work has to proceed quickly. If actively infested
trees are removed before the onset of summer when the beetles fly, then
fewer healthy trees may be attacked. On small scale, high value areas,
such as the East Shore beaches, beetle suppression work may reduce the
number of large Jeffrey pines that die. Further, trees that are
harvested quickly will have more commercial value. The high cost of a
predominantly helicopter operation could deter potential bidders as the
soundness of the trees declines. Consequently, project implementation
is expected to begin during the summer or fall of 1994.
Over sixty agencies, organizations, and individuals were notified
of this proposed project through the LTBMU NEPA Status Report. A public
meeting was held on October 5, 1993 as part of the scoping process.
Some people also provided written comments. Tahoe Regional Planning
Agency staff was briefed about the project on November 10, 1993. The
Nevada State Historic Preservation Officer has also been briefed.
Originally conceived and publicly scoped as a project whose
environmental analysis would be documented in an environmental
assessment, it was determined in late December 1993 that its potential
environmental effects warrant an Environmental Impact Statement (EIS).
Project activities will adversely affect heritage resources in a
National Register-eligible historic district.
While the type of NEPA documentation has changed since the
project's conception, the project itself has not changed. Consequently,
only minimal additional public scoping will occur. A public and agency
briefing on the project, to be announced in the Tahoe Daily Tribune and
through letters sent to those parties who have expressed interest in
the East Shore Project, will be held on January 26, 1994, at the El
Dorado County Library at 1000 Rufus Allen Boulevard in South Lake
Tahoe. Participants in the planning process will be sent copies of the
draft EIS for the public comment period. Availability of the draft EIS
will also be noticed in the Federal Register, and the Tahoe Daily
Tribune, the LTBMU's newspaper of record. Written comments and
suggestions received by January 24, 1994 will be addressed in the draft
EIS.
The ``no action'' alternative proposes a continuation of the
current types of management activities currently conducted in the study
areas, without imposing impacts from logging to heritage resources.
Trees which pose hazards to life and property will be taken down. While
the long-term management of the Genoa Peak road system is primarily for
off-highway vehicle use, road reconstruction and maintenance at a
logging truck standard along a portion of the road will be required to
accommodate log haul for timber sales on the adjacent Toiyabe National
Forest, as analyzed in the Carson District's Spooner Salvage Sale
environmental assessment. Short-term road closures will prevent public
recreation use of parts of the area during timber sale operations.
Obliteration of nonhistoric nonsystem roads, maintenance of existing
system roads and trails, watershed improvement projects, and study and
management of the proposed National Register District will continue as
part of ongoing programs.
The ``salvage only'' alternative harvests dead, dying, and diseased
trees, many of which are beetle-infested, over approximately 6,600
acres. No green tree thinning will occur. Removal of about 30 MMBF of
both merchantable and unmerchantable material is anticipated. This
alternative includes all components of the proposed action, except when
modified as described: (1) While treatment of activity fuels will
occur, only limited use of prescribed fire as a management tool is
proposed, in selected areas, such as for use as a fuelbreak near urban
areas; (2) site preparation and planting will occur on high value areas
only (such as at the beaches and along roadway corridors) and natural
regeneration only will occur in general forest zones; and (3) only
temporary roads and landings used as part of the project will be
obliterated.
The fourth alternative emphasizes helicopter harvesting in areas
with significant heritage resources. It harvests dead, dying, and
diseased trees, many of which are beetle-infested, over approximately
6,750 acres--with approximately 550 acres less tractor logging than
alternatives two or three. Green trees would be thinned from
overstocked stands only within those areas entered for salvage
activities. Removal of 30 to 35 MMBF of both merchantable and
unmerchantable material is anticipated. This alternative includes all
components of the proposed action, except when modified as described:
(1) While treatment of activity fuels will occur, only limited use of
prescribed fire as a management tool is proposed, in selected areas,
such as for use as a fuelbreak near urban areas.
Implementation of this project requires a permit from the Tahoe
Regional Planning Agency (TRPA). It is in a classification of actions
requiring TRPA Governing Board review and approval. Additionally,
encroachment permits from the Nevada Department of Transportation are
required for project implementation. Consultation with the Nevada State
Historic Preservation Office (SHPO) and the Advisory Council on
Historic Preservation (ACHP) in accordance with the National Historic
Preservation Act of 1966 (16 U.S.C. 470 et seq.) is required.
Concurrence from the U.S. Fish and Wildlife Service is needed if the
Forest Service Biological Assessment results in a ``may affect''
determination.
The decision on this analysis, pursuant to NEPA, is made by Lake
Tahoe Basin Management Unit Forest Supervisor, Robert Harris, as the
Forest Service is the lead agency under NEPA. There is no other joint
lead agency and no cooperating agencies under NEPA.
The draft EIS is anticipated to be filed with the Environmental
Protection Agency and made available to the public for comment in
February of 1994. The final EIS and its Record of Decision is expected
in May of 1994. The decision will be appealable under Forest Service
regulations found at 36 CFR part 215.
The comment period for the draft EIS will be 45 days from the date
the Environmental Protection Agency's notice of availability appears in
the Federal Register. The public will also be informed of the
availability of the DEIS by news releases issued to the media in the
Lake Tahoe region. It is very important that those interested in this
proposed action participate at that time. To be the most helpful,
comments on the draft EIS should be as specific as possible and may
address the adequacy of the statement or the merits of the alternatives
discussed (see the Council on Environmental Quality Regulations for
implementing the procedural provisions of NEPA at 40 CFR 1503.3).
In addition, Federal court decisions have established that
reviewers of draft EIS' must structure their participation in the
environmental review of the proposal so that it is meaningful and
alerts an agency to the reviewers' position and contentions. Vermont
Yankee Nuclear Power Corp. v. NRDC, 435 U.S. 519, 553 (1978).
Environmental objections that could have been raised at the draft stage
may be waived if not raised until after completion of the final EIS.
City of Angoon v. Hodel, (9th Circuit, 1986) and Wisconsin Heritages,
Inc. v. Harris, 490 F. Supp. 1334, 1338 (E.D. Wis. 1980). The reason
for this is to ensure that substantive comments and objections are made
available for the Forest Service at a time when it can meaningfully
consider them and respond to them in the final.

Dated: January 4, 1994.
John R. Swanson,
Acting Forest Supervisor.
[FR Doc. 94-917 Filed 1-13-94; 8:45 am]