DEPARTMENT OF ENERGY

Floodplain Statement of Findings for the Replacement of Four
Bridges on the Savannah River Site

AGENCY: Department of Energy (DOE).
ACTION: Floodplain Statement of Findings.
SUMMARY: This Floodplain Statement of Findings is prepared in
compliance with 10 CFR Part 1022. It is designed to evaluate the impact
to the floodplain of the Savannah River Site (SRS) resulting from work
that is needed to replace selected bridges on SRS Roads 8-1 and 2-1.
The scope of this project is intended to immediately replace three
bridges because of deteriorated, decayed, or rotten timber piles. A
fourth bridge would be scheduled for a later replacement. The proposed
work would involve working in and close to the 100-year floodplain of
Upper Three Runs and Tinker Creek. The creeks associated with these
projects have average annual flows which are greater than 5 cubic feet
per second and a Federal permit pursuant to Section 404 of the Clean
Water Act is not expected to be required for the proposed work. These
impacted areas would include:

Replacement of Bridge 603-13G at the intersection of
the stream Upper Three Runs Creek and SRS Road 8-1.
Replacement of Bridge 603-14G at the intersection of
the stream Tinker Creek and SRS Road 8-1.
Replacement of Bridge 603-15G at the intersection of
the stream Upper Three Runs Creek and SRS Road 2-1.
Replacement of Bridge 603-39G at the intersection of
the stream Tinker Creek and SRS Road 2-1.

DATE: Comments on this Statement of Findings are due on or before
September 15, 1994.
ADDRESSES: Comments should be addressed to Floodplain Comments, Stephen
R. Wright, Director, Environmental and Laboratory Programs Division,
U.S. Department of Energy, Savannah River Operations Office, P. O. Box
A, Aiken, South Carolina 29802. The phone number is (803) 725-3957. Fax
comments to: (803) 725-7688.

FOR FURTHER INFORMATION, PLEASE CONTACT: Ms. Carol M. Borgstrom,
Director, Office of NEPA Oversight (EH-25), U.S. Department of Energy,
1000 Independence Avenue, S.W., Washington, D.C. 20585, Telephone (202)
586-4600 or (800) 472-2756.
A location map showing the project sites and further information
can be obtained from the Savannah River Operations Office (See
ADDRESSES above).

SUPPLEMENTARY INFORMATION: The bridges on SRS Road 8-1 (603-13G and
603-14G) which cross Upper Three Runs Creek and Tinker Creek will be
replaced and raised with minimal short-term impact and no long-term
impact to floodplains. A storm water and sediment control plan will be
required prior to bridge replacement in order to minimize sediments
eroding into the adjacent floodplain.
The work required to replace these two bridges would be
accomplished from the existing road beds using a crane for pile
driving, erection, and demolition. This activity should not have any
significant impact on the floodplain. The only disturbance to the
stream is anticipated to be the installation of pilings to support the
center span of the bridge. Prestressed, precast concrete beams shall be
used to minimize pile installation in the stream by constructing longer
spans. A small amount of sediment would be expected to go into the
stream where the work is close to the channel and temporarily increase
stream's sediment load level. These increased sediment loads would be
less than that encountered after a heavy rain storm. The old bridge
supports would be cut off at the stream bed. The bridges are to be
replaced in kind at their present locations so that there should be no
loss or long term impact to floodplains.
The bridge (603-15G) that spans Upper Three Runs Creek on SRS Road
2-1 would be replaced with minimal short-term impact and no long-term
impact to wetlands or floodplains. The bridge (603-39G) that spans
Tinker Creek on SRS Road 2-1 would be scheduled for replacement in the
future as funding became available.
The conditions of the bridges covered in this Statement of Findings
do not meet Department of Energy, American Association of State Highway
and Transportation Officials, South Carolina Department of
Transportation, or Federal Highway Administration standards and
guidelines and therefore severely limits the type of traffic that may
utilize these bridges on the primary route to the Advanced Tactical
Training Area. Fire control equipment and logging trucks use this route
so that any delay in replacing these bridges would greatly limit the
traffic count and load limits permitted along this route, and would
constitute a safety hazard to SRS personnel. Repair was considered as a
potential alternative but with the present condition of the bridges,
the most cost effective method is replacement. The environmental impact
of repairing these bridges was also evaluated and found to be nearly
identical in scope to that of replacing the bridges. Bridge
rehabilitation strategies were evaluated and concluded replacement of
the bridges over rehabilitation for many reasons, but largely because
replacement of deteriorated piles and backwalls would fail to improve
the load carrying capacity of the bridges for vehicles crossing the
structure. Timber pile and backwall replacement will cause the same
environmental impacts if not, more, because the bridge deck and piling
caps must be completely removed in order to drive new piles and
construct concrete abutments at the edge of the stream in order to
maintain existing span lengths. Replacement of the entire bridge
structure allows the span to be lengthened sufficiently to permit
construction of bridge abutments well away from the stream bed, thereby
reducing impacts, and reducing construction costs.
Several mitigation activities will be implemented to minimize
potential impacts to the floodplain. Silt fences and other erosion
control structures as needed will be installed to ensure there is no
deposition in downslope areas. Long-term construction impacts in the
floodplain and wetland areas will be minimized through the removal of
any excess excavated sidefill and restoration to the original contours
following completion of construction. An erosion control plan will be
developed so that the proposed action complies with applicable State
and local floodplain protection standards and further, to ensure that
no additional impacts will occur due to erosion and sedimentation. Best
management practices will be employed during construction and
maintenance activities associated with this proposed action.

Issued in Washington, D.C., on this 25th day of August, 1994.
Donald F. Knuth,
Acting Deputy Assistant Secretary for Facility Transition and Technical
Support, Defense Programs.
[FR Doc. 94-21541 Filed 8-30-94; 8:45 am]