## Text

ENVIRONMENTAL PROTECTION AGENCY
40 CFR Part 52
[EPA-HQ-OAR-2018-0225; FRL-9980-53-OAR]
RIN 2060-AT92
Determination Regarding Good Neighbor Obligations for the 2008 Ozone National Ambient Air Quality Standard

AGENCY:

Environmental Protection Agency (EPA).

ACTION:

Proposed rule.

SUMMARY:

The EPA is proposing to determine that the Cross-State Air Pollution Rule Update for the 2008 ozone National Ambient Air Quality Standards (NAAQS) (CSAPR Update) fully addresses certain states' obligations under Clean Air Act (CAA) section 110(a)(2)(D)(i)(I) regarding interstate pollution transport for the 2008 ozone NAAQS. The CSAPR Update, published on October 26, 2016, promulgated Federal Implementation Plans (FIPs) for 22 states in the eastern U.S. In the final CSAPR Update, based on information available at that time, the EPA could not conclude that the rule fully addressed CAA section 110(a)(2)(D)(i)(I) obligations for 21 of the 22 CSAPR Update states. This action proposes a determination that, based on additional information and analysis, the CSAPR Update fully addresses this CAA provision for the 2008 ozone NAAQS for all remaining CSAPR Update states. Specifically, EPA proposes to determine

that there will be no remaining nonattainment or maintenance receptors in the eastern U.S. in 2023. Therefore, with the CSAPR Update fully implemented, these states are not expected to contribute significantly to nonattainment in, or interfere with maintenance by, any other state with regard to the 2008 ozone NAAQS. In accord with this proposed determination, the EPA proposes to determine that it has no outstanding, unfulfilled obligation under CAA section 110(c)(1) to establish additional requirements for sources in these states to further reduce transported ozone pollution under CAA section 110(a)(2)(D)(i)(I) with regard to the 2008 ozone NAAQS. As a result of this finding, this action proposes minor revisions to the existing CSAPR Update regulations to reflect that the CSAPR Update FIPs fully address CAA section 110(a)(2)(D)(i)(I). The proposed determination would apply to states currently subject to CSAPR Update FIPs as well as any states for which EPA has approved replacement of CSAPR Update FIPs with CSAPR Update SIPs.

DATES:

Comments must be received on or before August 31, 2018.

ADDRESSES:

Submit your comments, identified by Docket ID No. EPA-HQ-OAR-2018-0225, at
http://www.regulations.gov.
Follow the online instructions for submitting comments. Once submitted, comments cannot be edited or removed from
Regulations.gov
. The EPA may publish any comment received to its public docket. Do not submit electronically any information you consider to be Confidential Business Information (CBI) or other information whose disclosure is restricted by statute. Multimedia submissions (audio, video, etc.) must be accompanied by a written comment. The written comment is considered the official comment and should include discussion of all points you wish to make. The EPA will generally not consider comments or comment contents located outside of the primary submission (
i.e.,
on the web, cloud, or other file sharing system). For additional submission methods, the full EPA public comment policy, information about CBI or multimedia submissions, and general guidance on making effective comments, please visit
http://www2.epa.gov/dockets/commenting-epa-dockets.

Public hearing.
The EPA will be holding one public hearing on the proposed Determination Regarding Good Neighbor Obligations for the 2008 Ozone National Ambient Air Quality Standard. The hearing will be held to accept oral comments on the proposal. The hearing will be held on August 1, 2018 in Washington DC. The hearing will begin at 9:00 a.m. (local time) and will conclude at 6:00 p.m. (local time) or two hours after the last registered speaker. The hearing will be held at the Environmental Protection Agency, William Jefferson Clinton East Building, Main Floor Room 1153, 1201 Constitution Avenue NW, in Washington, DC 20460. Because this hearing is being held at a U.S. government facility, individuals planning to attend the hearing should be prepared to show valid picture identification to the security staff in order to gain access to the meeting room. No large signs will be allowed in the building, cameras may only be used outside of the building, and demonstrations will not be allowed on federal property for security reasons. The EPA website for the rulemaking, which includes the proposal and supporting materials, can be found at
https://www.epa.gov/airmarkets/proposed-csapr-close-out.

If you would like to present oral testimony at the public hearing, please register online at
https://www.epa.gov/airmarkets/forms/public-hearing-proposed-csapr-close-out
or contact Mr. Brian Fisher, U.S. Environmental Protection Agency, Office of Atmospheric Programs, Clean Air Markets Division, (MS 6204-M), 1200 Pennsylvania Avenue NW, Washington, DC 20460, telephone (202) 343 9633, email address is
fisher.brian@epa.gov,
no later than 2 business days prior to the public hearing. If using email, please provide the following information: Time you wish to speak (morning, afternoon, evening), name, affiliation, address, email address, and telephone number.

FOR FURTHER INFORMATION CONTACT:

Brian Fisher, Clean Air Markets Division, Office of Atmospheric Programs, U.S. Environmental Protection Agency, MC 6204M, 1200 Pennsylvania Avenue NW, Washington, DC 20460; telephone number: (202) 343-9633; email address:
fisher.brian@epa.gov.

SUPPLEMENTARY INFORMATION:

Regulated entities.
Entities regulated under the CSAPR Update are fossil fuel-fired boilers and stationary combustion turbines that serve generators producing electricity for sale, including combined cycle units and units operating as part of systems that cogenerate electricity and other useful energy output. Regulated categories and entities include:

Category

NAICS *
code

Examples of
potentially
regulated
industries

Industry
221112
Fossil fuel-fired electric power generation.

* North American Industry Classification System.

This table is not intended to be exhaustive, but rather provides a guide for readers regarding entities likely to be regulated. To determine whether your facility is affected by this action, you should carefully examine the applicability provisions in 40 CFR 97.804. If you have questions regarding the applicability of the CSAPR Update to a particular entity, consult the person listed in the
FOR FURTHER INFORMATION CONTACT
section above.

Outline.
The following outline is provided to aid in locating information in this preamble.

I. General Information

States Covered by This Action

II. Background and Legal Authority

A. Ground-Level Ozone Pollution and Public Health

B. The EPA's Statutory Authority for This Proposed Action

C. Good Neighbor Obligations for the 2008 Ozone NAAQS

D. Summary of the CSAPR Update

III. Proposed Determination Regarding Good Neighbor Obligations for the 2008 Ozone NAAQS

A. Analytic Approach

B. Selection of a Future Analytic Year

1. Attainment Dates for the 2008 Ozone NAAQS

2. Feasibility of Control Strategies To Reduce Ozone Season NO
X

3. Focusing on 2023 for Analysis

C. Air Quality Analysis

1. Definition of Nonattainment and Maintenance Receptors

2. Overview of Air Quality Modeling Platform

3. Emissions Inventories

4. Air Quality Modeling To Identify Nonattainment and Maintenance Receptors

5. Pollutant Transport From Upwind States

D. Proposed Determination

IV. Statutory Authority and Executive Order Reviews

A. Executive Order 12866: Regulatory Planning and Review, and Executive Order 13563: Improving Regulation and Regulatory Review

B. Executive Order 13771: Reducing Regulations and Controlling Regulatory Costs

C. Paperwork Reduction Act

D. Regulatory Flexibility Act

E. Unfunded Mandates Reform Act

F. Executive Order 13132: Federalism

G. Executive Order 13175: Consultation and Coordination With Indian Tribal Governments

H. Executive Order 13045: Protection of Children From Environmental Health and Safety Risks

I. Executive Order 13211: Actions That Significantly Affect Energy Supply, Distribution, or Use

J. National Technology Transfer Advancement Act

K. Executive Order 12898: Federal Actions To Address Environmental Justice in Minority Populations and Low-Income Populations

L. Determinations Under Section 307(b)(1) and (d)

I. General Information

Within this document “we,” “us,” or “our” should be interpreted to mean the U.S. EPA.

Where can I get a copy of this document and other related information?

The EPA has established a docket for this action under Docket ID No. EPA-HQ-OAR-2018-0225 (available at
http://www.regulations.gov
). Information related to the proposed action and the public hearing is available at the website:
https://www.epa.gov/airtransport.

States Covered by This Action

In the CSAPR Update, 81 FR 74504 (Oct. 26, 2016), the EPA promulgated FIPs intended to address 22 eastern states' obligations under CAA section 110(a)(2)(D)(i)(I), also known as the “good neighbor provision,” with respect to the 2008 ozone NAAQS. The good neighbor provision requires upwind states to control their emissions that impact air quality problems in downwind states. Based on information available when the CSAPR Update was finalized, the EPA was unable to determine at that time that the FIPs fully addressed good neighbor obligations under this NAAQS for 21 of the 22 states. The EPA has subsequently proposed to approve a draft SIP which, if finalized, would fully address the good neighbor obligation for one of these states, Kentucky. In this action, the EPA proposes to determine that, with CSAPR Update implementation, the 20 remaining states' good neighbor obligations for the 2008 ozone NAAQS are fully addressed. In accord with this determination, the EPA would have no further obligation under CAA section 110(c) to establish requirements for power plants or any other emissions sources in these states to further reduce transported ozone pollution under CAA section 110(a)(2)(D)(i)(I) with regard to this NAAQS.

The two states among the 22 CSAPR Update states that are not covered by this action are Tennessee and Kentucky. With respect to Tennessee, the EPA already determined in the final CSAPR Update that implementation of the state's emissions budget would fully eliminate the state's significant contribution to downwind nonattainment and interference with maintenance of the 2008 ozone NAAQS because the downwind air quality problems to which the state was linked were projected to be resolved after implementation of the CSAPR Update. 81 FR 74540. With respect to Kentucky, the EPA has proposed in a separate action to approve the state's draft SIP submittal demonstrating that no additional emissions reductions beyond those required by the CSAPR Update are necessary to address the state's good neighbor obligation with respect to the 2008 ozone NAAQS. 83 FR 17123 (April 18, 2018). See Table I.A-1 for a list of states covered by this proposal.

Table I.A-1—States Covered by This Proposed Determination Regarding Good Neighbor Obligations for the 2008 Ozone NAAQS

State

Alabama.

Arkansas.

Illinois.

Indiana.

Iowa.

Kansas.

Louisiana.

Maryland.

Michigan.

Mississippi.

Missouri.

New Jersey.

New York.

Ohio.

Oklahoma.

Pennsylvania.

Texas.

Virginia.

West Virginia.

Wisconsin.

II. Background and Legal Authority

A.
Ground-Level Ozone Pollution and Public Health

Ground-level ozone causes a variety of negative effects on human health, vegetation, and ecosystems. In humans, acute and chronic exposure to ozone is associated with premature mortality and a number of morbidity effects, such as asthma exacerbation. In ecosystems, ozone exposure causes visible foliar injury in some plants, decreases growth in some plants, and affects ecosystem community composition.
1

1
For more information on the human health and welfare and ecosystem effects associated with ambient ozone exposure, see the EPA's October 2015 Regulatory Impact Analysis of the Final Revisions to the National Ambient Air Quality Standards for Ground-Level Ozone (EPA-452/R-15-007) in the docket for this rule and also found in the docket for the 2015 ozone NAAQS, Docket No. EPA-HQ-OAR-2013-0169-0057.

In this proposed action, consistent with previous rulemakings described in section II.B, the EPA relies on analysis that reflects the regional nature of transported ground-level ozone pollution. Ground-level ozone is not emitted directly into the air, but is a secondary air pollutant created by chemical reactions between nitrogen oxides (NO
X
), carbon monoxide (CO), methane (CH
4
), and non-methane volatile organic compounds (VOCs) in the presence of sunlight. Emissions from mobile sources, electric generating units (EGUs), industrial facilities, gasoline vapors, and chemical solvents are some of the major anthropogenic sources of ozone precursors. NO
X
emissions from the mobile source category lead all sectors and were more than double emissions from the second-highest emitting sector, and accounted from more than half of the national NO
X
emissions in 2014.
2

The potential for ground-level ozone formation increases during periods with warmer temperatures and stagnant air masses. Therefore, ozone levels are generally higher during the summer months.
3 4

Ground-level ozone concentrations and temperature are highly correlated in the eastern U.S., with observed ozone increases of 2-3 parts per billion (ppb) per degree Celsius reported.
5

2
EPA. 2014 National Emissions Inventory (NEI) v2. Released 2/2018 and available at
https://www.epa.gov/air-emissions-inventories
.

3
Rasmussen, D.J. et al. (2011). Ground-level ozone-temperature relationships in the eastern US: A monthly climatology for evaluating chemistry-climate models. Atmospheric Environment 47: 142-153.

4
High ozone concentrations have also been observed in cold months, where a few areas in the western U.S. have experienced high levels of local VOC and NO
X
emissions that have formed ozone when snow is on the ground and temperatures are near or below freezing.

5
Bloomer, B.J., J.W. Stehr, C.A. Piety, R.J. Salawitch, and R.R. Dickerson (2009). Observed relationships of ozone air pollution with temperature and emissions, Geophys. Res. Lett., 36, L09803.

Precursor emissions can be transported downwind directly or, after transformation in the atmosphere, as ozone. Studies have established that ozone formation, atmospheric residence, and transport occur on a regional scale (
i.e.,
hundreds of miles) over much of the eastern U.S. As a result of ozone transport, in any given location, ozone pollution levels are impacted by a combination of local emissions and emissions from upwind sources. Numerous observational studies have

demonstrated the transport of ozone and its precursors and the impact of upwind emissions on high concentrations of ozone pollution.
6

6
Bergin, M.S. et al. (2007). Regional air quality: local and interstate impacts of NO
X
and SO
2
emissions on ozone and fine particulate matter in the eastern United States. Environmental Sci & Tech. 41: 4677-4689.

The EPA concluded in several previous rulemakings (summarized in section II.B) that interstate ozone transport can be an important component of peak ozone concentrations during the summer ozone season and that NO
X
control strategies are effective for reducing regional-scale ozone transport. Model assessments have looked at impacts on peak ozone concentrations after potential emissions reduction scenarios for NO
X
and VOCs for NO
X
-limited and VOC-limited areas. For example, Jiang and Fast concluded that NO
X
emissions reduction strategies are effective in lowering ozone mixing ratios in urban areas and Liao et al. showed that NO
X
reductions result in lower peak ozone concentrations in non-attainment areas in the Mid-Atlantic.
7

Assessments of ozone conducted for the October 2015 Regulatory Impact Analysis of the Final Revisions to the National Ambient Air Quality Standards for Ground-Level Ozone (EPA-452/R-15-007) also show the importance of NO
X
emissions on ozone formation. This analysis is in the docket for this rule and also can be found in the docket for the 2015 ozone NAAQS regulatory impact analysis, Docket No. EPA-HQ-OAR-2013-0169 (document ID EPA-HQ-OAR-2013-0169-0057).

7
Jiang, G.; Fast, J.D. (2004). Modeling the effects of VOC and NO
X
emission sources on ozone formation in Houston during the TexAQS 2000 field campaign. Atmospheric Environment 38: 5071-5085.

Studies have found that NO
X
emissions reductions can be effective in reducing ozone pollution as quantified by the form of the 2008 ozone standard, 8-hour peak concentrations. Specifically, studies have found that NO
X
emissions reductions from EGUs, mobile sources, and other source categories can be effective in reducing the upper-end of the cumulative ozone distribution in the summer on a regional scale.
8

Analysis of air quality monitoring data trends shows reductions in summertime ozone concurrent with implementation of NO
X
reduction programs.
9

Gilliland et al. examined the NO
X
SIP Call and presented reductions in observed versus modeled ozone concentrations in the eastern U.S. downwind from major NO
X
sources.
10

The results showed significant reductions in ozone concentrations (10-25 percent) from observed measurements (CASTNET and AQS)
11

between 2002 and 2005, linking reductions in EGU NO
X
emissions from upwind states with ozone reductions downwind of the major source areas.
12

Additionally, Gégo et al. showed that ground-level ozone concentrations were significantly reduced after implementation of the NO
X
SIP Call.
13

8
Hidy, G.M. and Blanchard C.L. (2015). Precursor reductions and ground-level ozone in the Continental United States. J. of Air & Waste Management Assn. 65, 10.

9
Simon, H. et al. (2015). Ozone trends across the United States over a period of decreasing NO
X
and VOC emissions. Environmental Science & Technology 49, 186-195.

10
Gilliland, A.B. et al. (2008). Dynamic evaluation of regional air quality models: Assessing changes in O
3
stemming from changes in emissions and meteorology. Atmospheric Environment 42: 5110-5123.

11
CASTNET is the EPA's Clean Air Status and Trends Network. AQS is the EPA's Air Quality System.

12
Hou, Strickland & Liao. “Contributions of regional air pollutant emissions to ozone and fine particulate matter-related mortalities in eastern U.S. urban areas”. Environmental Research, Feb. 2015. Available at
https://ac.els-cdn.com/S0013935114004113/1-s2.0-S0013935114004113-main.pdf?_tid=78c88101-fa6e-4e75-a65c-f56746905e7d&acdnat=1525175812_0e62553b83c9ffa1105aa306a478e8bb

13
Gégo et al. (2007). Observation-based assessment of the impact of nitrogen oxides emissions reductions on O
3
air quality over the eastern United States. J. of Applied Meteorology and Climatology 46: 994-1008.

Mobile sources also account for a large share of the NO
X
emissions inventory (
i.e.,
about 7.3 million tons per year in the 2011 base year, which represented more than 50% of continental U.S. NO
X
emissions), and the EPA recognizes that emissions reductions achieved from this sector as well can reduce transported ozone pollution. The EPA has national programs that serve to reduce emissions from all contributors to the mobile source inventory (
i.e.,
projected NO
X
emissions reductions of about 4.7 million tons per year between the 2011 base year and the 2023 future analytical year). A detailed discussion of the EPA's mobile source emissions reduction programs can be found at
www.epa.gov/otaq.

In light of the regional nature of ozone transport discussed herein, and given that NO
X
emissions from mobile sources are being addressed in separate national rules, in the CSAPR Update (as in previous regional ozone transport actions) the EPA relied on regional analysis and required regional ozone-season NO
X
emissions reductions from EGUs to address interstate transport of ozone.

B.
The EPA's Statutory Authority for This Proposed Action

The statutory authority for this proposed action is provided by the CAA as amended (42 U.S.C. 7401
et seq.
). Specifically, sections 110 and 301 of the CAA provide the primary statutory underpinnings for this rule. The most relevant portions of section 110 are subsections 110(a)(1), 110(a)(2) (including 110(a)(2)(D)(i)(I)), and 110(c)(1).

Section 110(a)(1) provides that states must make SIP submissions “within 3 years (or such shorter period as the Administrator may prescribe) after the promulgation of a national primary ambient air quality standard (or any revision thereof),” and that these SIP submissions are to provide for the “implementation, maintenance, and enforcement” of such NAAQS.
14

The statute directly imposes on states the duty to make these SIP submissions, and the requirement to make the submissions is not conditioned upon the EPA taking any action other than promulgating a new or revised NAAQS.
15

14
42 U.S.C. 7410(a)(1).

15

See EPA
v.
EME Homer City Generation, L.P.,
134 S. Ct. 1584, 1601 (2014).

The EPA has historically referred to SIP submissions made for the purpose of satisfying the applicable requirements of CAA sections 110(a)(1) and 110(a)(2) as “infrastructure SIP” submissions. Section 110(a)(1) addresses the timing and general requirements for infrastructure SIP submissions, and section 110(a)(2) provides more details concerning the required content of these submissions. It includes a list of specific elements that “[e]ach such plan” submission must address.
16

All states, regardless of whether the state includes areas designated as nonattainment for the relevant NAAQS, must have SIPs that meet the applicable requirements of section 110(a)(2), including provisions of section 110(a)(2)(D)(i)(I) described later and that are the focus of this rule.

16
The EPA's general approach to infrastructure SIP submissions is explained in greater detail in individual notices acting or proposing to act on state infrastructure SIP submissions and in guidance.
See, e.g.,
Memorandum from Stephen D. Page on Guidance on Infrastructure State Implementation Plan (SIP) Elements under Clean Air Act Sections 110(a)(1) and 110(a)(2) (Sept. 13, 2013).

Section 110(c)(1) requires the Administrator to promulgate a FIP at any time within two years after the Administrator: (1) Finds that a state has failed to make a required SIP submission; (2) finds a SIP submission to be incomplete pursuant to CAA section 110(k)(1)(C); or (3) disapproves

a SIP submission, unless the state corrects the deficiency through a SIP revision that the Administrator approves before the FIP is promulgated.
17

17
42 U.S.C. 7410(c)(1).

Section 110(a)(2)(D)(i)(I), also known as the “good neighbor provision,” provides the primary basis for this action. It requires that each state SIP shall include provisions sufficient to “prohibit[ ] . . . any source or other type of emissions activity within the State from emitting any air pollutant in amounts which will—(I) contribute significantly to nonattainment in, or interfere with maintenance by, any other State with respect to any [NAAQS].”
18

18
42 U.S.C. 7410(a)(2)(D)(i)(I).

The EPA has previously issued four rules interpreting and clarifying the requirements of section 110(a)(2)(D)(i)(I) for states in the eastern United States. These rules, and the associated court decisions addressing these rules, summarized here, provide important guidance regarding the requirements of section 110(a)(2)(D)(i)(I).

The NO
X
SIP Call, promulgated in 1998, addressed the good neighbor provision for the 1979 1-hour ozone NAAQS.
19

The rule required 22 states and the District of Columbia to amend their SIPs to reduce NO
X
emissions that contribute to ozone nonattainment in downwind states. The EPA set an ozone season NO
X
budget for each covered state, essentially a cap on ozone season NO
X
emissions in the state. Covered states were given the option to participate in a regional cap-and-trade program, known as the NO
X
Budget Trading Program (NBP), to achieve a large portion of the reductions. The United States Court of Appeals for the District of Columbia Circuit (D.C. Circuit) largely upheld the NO
X
SIP Call in
Michigan
v.
EPA,
213 F.3d 663 (D.C. Cir. 2000),
cert. denied,
532 U.S. 904 (2001).

19
63 FR 57356 (Oct. 27, 1998). As originally promulgated, the NO
X
SIP Call also addressed good neighbor obligations under the 1997 8-hour ozone NAAQS, but the EPA subsequently stayed the rule's provisions with respect to that standard. 40 CFR 51.121(q).

The EPA's next rule addressing the good neighbor provision, Clean Air Interstate Rule (CAIR), was promulgated in 2005 and addressed both the 1997 PM
2.5
and 1997 ozone NAAQS.
20

CAIR required SIP revisions in 28 states and the District of Columbia to reduce emissions of sulfur dioxide (SO
2
) and/or NO
X
—important precursors of regionally transported PM
2.5
(SO
2
and NO
X
) and ozone (NO
X
). As in the NO
X
SIP Call, states were given the option to participate in regional cap-and-trade programs to achieve the reductions. When the EPA promulgated the final CAIR in May 2005, the EPA also issued a national rule, finding that states had failed to submit SIPs to address the requirements of CAA section 110(a)(2)(D)(i) with respect to the 1997 PM
2.5
and 1997 ozone NAAQS. Those states were required by the CAA to have submitted good neighbor SIPs for those standards by July 2000 (
i.e.,
three years after the standards were finalized).
21

These findings of failure to submit triggered a 2-year clock for the EPA to issue FIPs to address interstate transport,
22

and on March 15, 2006, the EPA promulgated FIPs to ensure that the emissions reductions required by CAIR would be achieved on schedule.
23

CAIR was remanded to the EPA by the D.C. Circuit in
North Carolina
v.
EPA,
531 F.3d 896 (D.C. Cir. 2008),
modified on reh'g,
550 F.3d 1176. For more information on the legal issues underlying CAIR and the D.C. Circuit's holding in
North Carolina,
refer to the preamble of the original CSAPR.
24

20
70 FR 25162 (May 12, 2005).

21
70 FR 21147 (May 12, 2005).
See
n.14 and main text,
supra.

22

See
n.17 and main text,
supra.

23
71 FR 25328 (April 28, 2006).

24
76 FR 48208, 48217 (Aug. 8, 2011).

In 2011, the EPA promulgated the original CSAPR to address the issues raised by the remand of CAIR. CSAPR addressed the two NAAQS at issue in CAIR and additionally addressed the good neighbor provision for the 2006 PM
2.5
NAAQS.
25

CSAPR required 28 states to reduce SO
2
emissions, annual NO
X
emissions, and/or ozone season NO
X
emissions that significantly contribute to other states' nonattainment or interfere with other states' abilities to maintain these air quality standards. To align implementation with the applicable attainment deadlines, the EPA promulgated FIPs for each of the 28 states covered by CSAPR. The FIPs implement regional cap-and-trade programs to achieve the necessary emissions reductions. Each state can submit a good neighbor SIP at any time that, if approved by the EPA, would replace the CSAPR FIP for that state.
26

CSAPR was the subject of an adverse decision by the D.C. Circuit in August 2012,
27

reversed in April 2014 by the Supreme Court,
28

which largely upheld the rule, including EPA's approach to addressing interstate transport in CSAPR, but remanded to the D.C. Circuit to consider other claims not addressed by the Court.
EPA
v.
EME Homer City Generation, L.P.,
134 S. Ct. 1584 (2014). On remand from the Supreme Court, in July 2015 the D.C. Circuit affirmed the EPA's interpretation of various statutory provisions and the EPA's technical decisions.
EME Homer City Generation, L.P.
v.
EPA,
795 F.3d 118 (2015) (
EME Homer City II
). However, the court also remanded the rule without vacatur for reconsideration of the EPA's emissions budgets for certain states, which the court found may over-control those states' emissions with respect to the downwind air quality problems to which the states were linked.
Id.
at 129-30, 138. For more information on the legal considerations of CSAPR and the court's decisions in the
EME Homer City
litigation, refer to the preamble of the CSAPR Update.
29

25
76 FR 48208.

26
EPA has already approved SIPs fully replacing the original CSAPR FIPs for Alabama, 81 FR 59869 (Aug. 31, 2016), Georgia, 82 FR 47930 (Oct. 13, 2017), and South Carolina, 82 FR 47936 (Oct. 13, 2017).

27
On August 21, 2012, the D.C. Circuit issued a decision in
EME Homer City Generation, L.P.
v.
EPA,
696 F.3d 7 (D.C. Cir. 2012) (
EME Homer I
), vacating CSAPR. The EPA sought review with the D.C. Circuit
en banc
and the D.C. Circuit declined to consider the EPA's appeal
en banc. EME Homer City Generation, L.P.
v.
EPA,
No. 11-1302 (D.C. Cir. January 24, 2013), ECF No. 1417012 (denying the EPA's motion for rehearing en banc).

28
On January 23, 2013, the Supreme Court granted the EPA's petition for certiorari.
EPA
v.
EME Homer City Generation, L.P.,
133 S. Ct. 2857 (2013) (granting the EPA's and other parties' petitions for certiorari). On April 29, 2014, the Supreme Court issued a decision reversing the D.C. Circuit's
EME Homer City
opinion.

29
81 FR 74511.

In 2016, the EPA promulgated the CSAPR Update to address interstate transport of ozone pollution with respect to the 2008 ozone NAAQS. The final rule generally updated the CSAPR ozone season NO
X
emissions budgets for 22 states to achieve cost-effective NO
X
emissions reductions from EGUs within those states.
30

The CSAPR Update implemented these budgets through FIPs requiring sources to participate in a revised CSAPR ozone season NO
X
allowance trading program. As under the original CSAPR, each state can submit a good neighbor SIP at any time that, if approved by the EPA, would replace the CSAPR Update FIP for that state.
31

The final CSAPR Update also addressed the remand by the D.C. Circuit of certain states' original CSAPR phase 2 ozone season NO
X
emissions budgets in
EME Homer City II.
The CSAPR Update is subject to pending

legal challenges in the D.C. Circuit.
Wisconsin
v.
EPA,
No. 16-1406 (D.C. Cir. filed Nov. 23, 2016). Further information about the CSAPR Update can be found in section II.D of this notice.

30
One state, Kansas, was made newly subject to a CSAPR ozone season NO
X
requirement by the CSAPR Update. All other CSAPR Update states were already subject to ozone season NO
X
requirements under the original CSAPR.

31
EPA has already approved a SIP fully replacing the CSAPR Update FIP for Alabama. 82 FR 46674 (Oct. 6, 2017).

Section 301(a)(1) of the CAA also gives the Administrator the general authority to prescribe such regulations as are necessary to carry out functions under the Act.
32

Pursuant to this section, the EPA has authority to clarify the applicability of CAA requirements. In this action, among other things, the EPA is clarifying the applicability of section 110(a)(2)(D)(i)(I) with respect to the 2008 ozone NAAQS. In particular, the EPA is using its authority under sections 110 and 301 to make a determination that no further enforceable reductions in emissions of NO
X
are required under this provision with respect to the 2008 ozone NAAQS for the states covered by this rule. The EPA is making minor revisions to the existing state-specific sections of the CSAPR Update regulations for all states covered by that action other than Kentucky and Tennessee.

32
42 U.S.C. 7601(a)(1).

C. Good Neighbor Obligations for the 2008 Ozone NAAQS

On March 12, 2008, the EPA promulgated a revision to the NAAQS, lowering both the primary and secondary standards to 75 ppb.
See
National Ambient Air Quality Standards for Ozone, Final Rule, 73 FR 16436 (March 27, 2008). Specifically, the standards require that an area may not exceed 75 ppb using the 3-year average of the fourth highest 24-hour maximum 8-hour rolling average ozone concentration. These revisions of the NAAQS, in turn, triggered a 3-year deadline for states to submit SIP revisions addressing infrastructure requirements under CAA sections 110(a)(1) and 110(a)(2), including the good neighbor provision. Several events affected application of the good neighbor provision for the 2008 ozone NAAQS, including reconsideration of the 2008 ozone NAAQS and legal developments pertaining to the EPA's original CSAPR, which created uncertainty surrounding the EPA's statutory interpretation and implementation of the good neighbor provision.
33

Notwithstanding these events, EPA ultimately affirmed that states' good neighbor SIPs were due on March 12, 2011.

33
These events are described in detail in section IV.A.2 of the CSAPR Update. 81 FR 74515.

The EPA subsequently took several actions that triggered the EPA's obligation under CAA section 110(c) to promulgate FIPs addressing the good neighbor provision for several states.
34

First, on July 13, 2015, the EPA published a rule finding that 24 states failed to make complete submissions that address the requirements of section 110(a)(2)(D)(i)(I) related to the interstate transport of pollution as to the 2008 ozone NAAQS.
See
80 FR 39961 (effective August 12, 2015). The finding action triggered a 2-year deadline for the EPA to issue FIPs to address the good neighbor provision for these states by August 12, 2017. The CSAPR Update finalized FIPs for 13 of these states (Alabama, Arkansas, Illinois, Iowa, Kansas, Michigan, Mississippi, Missouri, Oklahoma, Pennsylvania, Tennessee, Virginia, and West Virginia). The EPA also determined in the CSAPR Update that the Agency had fully satisfied its FIP obligation as to nine additional states identified in the finding of failure to submit (Florida, Georgia, Maine, Massachusetts, Minnesota, New Hampshire, North Carolina, South Carolina, and Vermont). The EPA determined that these states did not contribute significantly to nonattainment in, or interfere with maintenance by, any other state with respect to the 2008 ozone NAAQS. 81 FR 74506.
35

On June 15, 2016 and July 20, 2016, the EPA published additional rules finding that New Jersey and Maryland, respectively, also failed to submit transport SIPs for the 2008 ozone NAAQS.
See
81 FR 38963 (June 15, 2016) (effective July 15, 2016); 81 FR 47040 (July 20, 2016) (Maryland, effective August 19, 2016). The finding actions triggered 2-year deadlines for the EPA to issue FIPs to address the good neighbor provision for Maryland by August 19, 2018, and New Jersey by July 15, 2018. The CSAPR Update finalized FIPs for these two states.

34
This section of the preamble focuses on SIP and FIP actions for those states addressed in the CSAPR Update. The EPA has also acted on SIPs for other states not mentioned in this action. The memorandum,
Status of 110(a)(2)(D)(i)(I) SIPs for the 2008 Ozone NAAQS,
more fully describes the good neighbor SIP status for the 2008 ozone NAAQS and is available in the docket for this action.

35
The two remaining states addressed in the findings of failure to submit (California and New Mexico) were not part of the CSAPR Update analysis and are not addressed in this rulemaking.

In addition to the previously identified finding actions, the EPA also finalized disapproval or partial disapproval actions for SIPs submitted by Indiana, Kentucky, Louisiana, New York, Ohio, Texas, and Wisconsin.
36

These disapprovals triggered the EPA's obligation to promulgate FIPs to implement the requirements of the good neighbor provision for those states within 2 years of the effective date of each disapproval. The EPA promulgated CSAPR Update FIPs for Indiana, Kentucky, Louisiana, New York, Ohio, Texas, and Wisconsin.

36

See
the following actions: Indiana (81 FR 38957, June 15, 2016); Kentucky (78 FR 14681, March 7, 2013); Louisiana (81 FR 53308, August 12, 2016); New York (81 FR 58849, August 26, 2016); Ohio (81 FR 38957, June 15, 2016); Texas (81 FR 53284, August 12, 2016); and Wisconsin (81 FR 53309, August 12, 2016).

As discussed in more detail in the next section, in issuing the CSAPR Update, the EPA did not determine that it had entirely addressed the EPA's outstanding CAA obligations to implement the good neighbor provision with respect to the 2008 ozone NAAQS for 21 of 22 states covered by that rule. Accordingly, the CSAPR Update did not fully satisfy the EPA's obligation to address the good neighbor provision requirements for those states by approving SIPs, issuing FIPs, or some combination of those two actions. The EPA found that the CSAPR Update FIP fully addressed the good neighbor provision for the 2008 ozone NAAQS only with respect to Tennessee.

The EPA notes that it has also already separately proposed an action to fully address Kentucky's good neighbor obligation for the 2008 ozone NAAQS. 83 FR 17123 (Apr. 18, 2018). On May 23, 2017, the U.S. District Court for the Northern District of California issued an order requiring the EPA to take a final action fully addressing the good neighbor obligation for the 2008 ozone NAAQS for Kentucky by June 30, 2018.
See
Order,
Sierra Club
v.
Pruitt,
No. 3:15-cv-04328 (N.D. Cal. May 23, 2017). On February 28, 2018, Kentucky submitted to the EPA a draft SIP addressing the remaining good neighbor obligation. On May 10, 2018, Kentucky submitted their final SIP to EPA. The EPA proposed to approve the state's draft SIP, 83 FR 17123 (April 18, 2018), and intends to take an appropriate final action that would address this obligation for Kentucky consistent with the court-ordered deadline.

As noted previously, subsequent to the promulgation of the CSAPR Update, the EPA approved a SIP fully replacing the FIP for Alabama. 82 FR 46674 (October 6, 2017). In that SIP approval, the EPA found that the rule partially satisfies Alabama's good neighbor obligation for the 2008 ozone NAAQS. Thus, the EPA continues to have an obligation, stemming from the July 13, 2015 findings notice, to fully address the good neighbor provision requirements for the 2008 NAAQS with respect to Alabama. As previously

noted, other states have also submitted SIPs, some of which the EPA has approved and some of which still remain pending. However, these states are not the subject of this rulemaking and these actions are therefore not described in detail in this section.

Table II.C-1 summarizes the statutory deadline for the EPA to address its FIP obligation under CAA section 110(c) and the event that activated the EPA's obligation for each of the 20 remaining CSAPR Update states addressed in this proposed action. For more information regarding the actions triggering the EPA's FIP obligation and the EPA's action on SIPs addressing the good neighbor provision for the 2008 ozone NAAQS, see the memorandum,
Status of
110(a)(2)(D)(i)(I) SIPs
for the 2008 Ozone NAAQS,
in the docket for this action.

Table II.C-1—Events That Activated EPA's Obligation and Statutory FIP Deadlines

State

Type of action

(
Federal Register
citation, publication date)

Statutory FIP

deadline
37

Alabama
Finding of Failure to Submit (80 FR 39961, 7/13/2015)
8/12/2017

Arkansas
Finding of Failure to Submit (80 FR 39961, 7/13/2015)
8/12/2017

Illinois
Finding of Failure to Submit (80 FR 39961, 7/13/2015)
8/12/2017

Indiana
SIP disapproval (81 FR 38957, 6/15/2016)
7/15/2018

Iowa
Finding of Failure to Submit (80 FR 39961, 7/13/2015)
8/12/2017

Kansas
Finding of Failure to Submit (80 FR 39961, 7/13/2015)
8/12/2017

Louisiana
SIP disapproval (81 FR 53308, 8/12/2016)
9/12/2018

Maryland
Finding of Failure to Submit (81 FR 47040, 7/20/2016)
8/19/2018

Michigan
Finding of Failure to Submit (80 FR 39961, 7/13/2015)
8/12/2017

Mississippi
Finding of Failure to Submit (80 FR 39961, 7/13/2015)
8/12/2017

Missouri
Finding of Failure to Submit (80 FR 39961, 7/13/2015)
8/12/2017

New Jersey
Finding of Failure to Submit (81 FR 38963, 6/15/2016)
7/15/2018

New York
SIP disapproval (81 FR 58849, 8/12/2016)
9/26/2018

Ohio
SIP disapproval (81 FR 38957, 6/15/2016)
7/15/2018

Oklahoma
Finding of Failure to Submit (80 FR 39961, 7/13/2015)
8/12/2017

Pennsylvania
Finding of Failure to Submit (80 FR 39961, 7/13/2015)
8/12/2017

Texas
SIP disapproval (81 FR 53284, 8/12/2016)
9/12/2018

Virginia
Finding of Failure to Submit (80 FR 39961, 7/13/2015)
8/12/2017

West Virginia
Finding of Failure to Submit (80 FR 39961, 7/13/2015)
8/12/2017

Wisconsin
Partial SIP disapproval as to prong 2 (81 FR 53309, 8/12/2016)
9/12/2018

D. Summary

of the CSAPR Update

37
The FIP deadline is two years from the effective date of the SIP disapproval or Finding of Failure to Submit, which generally trails the publication date by 30 or 45 days.

On October 16, 2016, the EPA finalized the CSAPR Update. The purpose of the CSAPR Update was to protect public health and welfare by reducing interstate pollution transport that significantly contributes to nonattainment, or interferes with maintenance, of the 2008 ozone NAAQS in the eastern U.S. As discussed in section II.C, the EPA finalized a FIP for each of the 22 states subject to the rule,
38

either having previously found that those states failed to submit a complete good neighbor SIP (15 states) or having issued a final rule disapproving their good neighbor SIP submittals (7 states). For the 22 states covered by the CSAPR Update, the EPA promulgated EGU ozone season NO
X
emissions budgets, implemented through a regional allowance trading program, to reduce interstate ozone transport for the 2008 ozone NAAQS during the ozone season (May-September), beginning with the 2017 ozone season.

38
Alabama, Arkansas, Illinois, Indiana, Iowa, Kansas, Kentucky, Louisiana, Maryland, Michigan, Mississippi, Missouri, New Jersey, New York, Ohio, Oklahoma, Pennsylvania, Tennessee, Texas, Virginia, West Virginia, and Wisconsin.

The EPA aligned its analysis for the CSAPR Update (and implementation of the trading program) with relevant attainment dates for the 2008 ozone NAAQS, consistent with the D.C. Circuit's decision in
North Carolina
v.
EPA.
39

The EPA's final 2008 Ozone NAAQS SIP Requirements Rule established the attainment deadline of July 20, 2018 for ozone nonattainment areas classified as Moderate.
40

Because the attainment date falls during the 2018 ozone season, the 2017 ozone season was the last full season from which data could be used to determine attainment of the NAAQS by the July 20, 2018 attainment date. Therefore, consistent with the court's instruction in
North Carolina,
the EPA established and implemented emissions budgets starting with the 2017 ozone season. 81 FR 74507.

39
531 F.3d 896, 911-12 (D.C. Cir. 2008) (holding that the EPA must coordinate interstate transport compliance deadlines with downwind attainment deadlines).

40
80 FR 12264, 12268 (Mar. 6, 2015); 40 CFR 51.1103. Ozone nonattainment areas are classified as either Marginal, Moderate, Serious, Severe, or Extreme, based on the severity of the air quality problem in the area. Areas with more acute air quality problems are required to implement more stringent control requirements and are provided additional time to attain the NAAQS. See CAA sections 181 and 182, 42 U.S.C. 7511, 7511a.

To establish the CSAPR Update emissions budgets, the EPA followed a four-step analytic process that has been used in each of the Agency's regional interstate transport rulemakings. The four-step interstate transport framework is described in more detail in section III.A. To summarize, in step 1, the Agency identified downwind receptors that are expected to have problems attaining or maintaining the NAAQS. In step 2, the EPA examined which upwind states contribute to the nonattainment or maintenance receptors identified in step 1. In step 3, the EPA quantified the upwind emissions that significantly contribute to nonattainment or interfere with maintenance. The EPA quantified significantly contributing emissions from upwind states by evaluating levels of uniform NO
X
control stringency, represented by an estimated marginal cost per ton of NO
X
reduced. The EPA applied a multi-factor test to evaluate cost, available emissions reductions, and downwind air quality impacts to determine the appropriate level of uniform NO
X
control stringency that addressed the impacts of interstate transport on downwind nonattainment or maintenance receptors. The EPA used

this multi-factor assessment to gauge the extent to which emissions reductions should be implemented beginning in 2017 and to ensure those reductions do not represent over-control. In step 4, the EPA identified emissions budgets for significantly contributing states that reflected the absence of significant contribution and provided for implementation of the budgets through an allowance trading program.

The multi-factor test generated a “knee in the curve,”
i.e.,
a point at which the cost-effectiveness of the emissions reductions is maximized, so named for the discernable turning point observable in a cost curve.
See
81 FR 74550. In the CSAPR Update this was at the point where emissions budgets reflected a control stringency with an estimated marginal cost of $1,400 per ton of NO
X
reduced. This level of stringency in emissions budgets represented the level at which incremental EGU NO
X
reduction potential and corresponding downwind ozone air quality improvements were maximized—relative to other cost levels evaluated—with respect to marginal cost. That is, the ratio of emissions reductions to marginal cost and the ratio of ozone improvements to marginal cost were maximized relative to the other emissions budget levels evaluated. The EPA found that highly cost-effective EGU NO
X
reductions were available to make meaningful and timely improvements in downwind ozone air quality to address interstate ozone transport for the 2008 ozone NAAQS for the 2017 ozone season. 81 FR 74508. Further, the agency's evaluation showed that emissions budgets reflecting the $1,400 per ton cost threshold did not over-control upwind states' emissions relative to either the downwind air quality problems to which they were linked or the 1 percent contribution threshold in step 2 that triggered their further evaluation in step 3.
Id.
at 74551-52. As a result, the EPA finalized EGU ozone season NO
X
emissions budgets developed using uniform control stringency represented by $1,400 per ton.

To implement the CSAPR Update's emissions reductions, the EPA promulgated FIPs requiring power plants in covered states to participate in the CSAPR NO
X
Ozone Season Group 2 allowance trading program starting in 2017.
41

CSAPR's trading programs and the EPA's prior emissions trading programs (
e.g.,
CAIR and the NO
X
Budget Trading Program) provide a proven implementation framework for achieving emissions reductions. In addition to providing environmental certainty (
i.e.,
a cap on emissions), these programs also provide regulated sources with flexibility in choosing compliance strategies. By using the CSAPR allowance trading programs, the EPA applied an implementation framework that was shaped by notice and comment in previous rulemakings and reflected the evolution of these programs in response to court decisions and practical experience gained by states, industry, and the EPA.

41
The ozone season NO
X
allowance trading program created under the original CSAPR was renamed the CSAPR NO
X
Ozone Season Group 1 Trading Program and now applies only to sources in Georgia. In the CSAPR Update, the EPA found that Georgia did not contribute to interstate transport with respect to the 2008 ozone NAAQS, but the state has an ongoing ozone season NO
X
requirement under the original CSAPR.

Based on information available at the time of its promulgation, the EPA was unable to conclude that the CSAPR Update fully addressed most of the covered states' good neighbor obligations for the 2008 ozone NAAQS. 81 FR 74521. Information available at the time indicated that, even with CSAPR Update implementation, several downwind receptors were expected to continue having problems attaining and maintaining this NAAQS and that emissions from upwind states were expected to continue to contribute greater than or equal to 1 percent of the NAAQS to these areas during the 2017 ozone season.
Id.
at 74551-52. Further, the EPA could not conclude at that time whether additional EGU and non-EGU reductions implemented on a longer timeframe than 2017 would be feasible and cost-effective to address states' good neighbor obligations for this NAAQS.

As noted, the EPA premised its conclusion that the CSAPR Update may not fully address states' good neighbor obligations in part on the Agency's assessment that air quality problems would persist at downwind receptors in 2017 even with CSAPR Update implementation. The EPA's assessment of CSAPR Update implementation using the Air Quality Assessment Tool (AQAT) indicated that certain eastern air quality monitors would continue to have problems attaining and maintaining the 2008 ozone NAAQS in 2017. 81 FR 74550-52. Specifically, projected nonattainment receptors remained in Connecticut, Texas, and Wisconsin, while projected maintenance-only receptors remained in Connecticut, Maryland, Michigan, New York, and Texas.
42

See Table II.C-1 for a list of remaining nonattainment receptors and Table II.C-2 for a list of remaining maintenance-only receptors. (The EPA's approach to defining nonattainment and maintenance-only receptors is explained in section III.C.1 below.)

42
Projected AQAT design values for the $1400/ton policy case are available in Tables D-6 and D-7 of the CSAPR Update “Ozone Transport Policy Analysis Final Rule TSD” (August 2016), Docket ID No. EPA-HQ-OAR-2015-0500-0555.

Table II.C-2—Remaining 2017 Projected Nonattainment Receptors in the Eastern U.S.

Monitor ID
State
County

090019003
Connecticut
Fairfield.

090099002
Connecticut
New Haven.

480391004
Texas
Brazoria.

484392003
Texas
Tarrant.

484393009
Texas
Tarrant.

551170006
Wisconsin
Sheboygan.

Table II.C-3—Remaining 2017 Projected Maintenance-Only Receptors in the Eastern U.S.

Monitor ID
State
County

090010017
Connecticut
Fairfield.

090013007
Connecticut
Fairfield.

240251001
Maryland
Harford.

260050003
Michigan
Allegan.

360850067
New York
Richmond.

361030002
New York
Suffolk.

481210034
Texas
Denton.

482010024
Texas
Harris.

482011034
Texas
Harris.

482011039
Texas
Harris.

The EPA's analysis also showed that 21 of the 22 CSAPR Update states would continue to contribute equal to or greater than 1 percent of the 2008 ozone NAAQS to at least one remaining nonattainment or maintenance receptor in 2017.
43

Thus, for those 21 states, the EPA could not, based on information available in the CSAPR Update rulemaking, make an air quality-based conclusion that the CSAPR Update would fully resolve states' good neighbor obligations with respect to the 2008 ozone NAAQS. (For one state, Tennessee, the EPA determined that the CSAPR Update fully resolved its good neighbor obligation.)

43

See
EPA's Air Quality Assessment Tool from the CSAPR Update in the docket for this rulemaking.

Further, it was not feasible for the EPA to complete an emissions control analysis that would otherwise be necessary to evaluate full elimination of each state's significant contribution to nonattainment or interference with maintenance and also ensure that emissions reductions would be achieved by 2017. 81 FR at 74522. Specifically, the EPA was unable to fully consider both non-EGU ozone season NO
X

reductions and further EGU reductions that may have been achievable after 2017.
Id.
at 74521. The EPA did not quantify non-EGU stationary source emissions reductions to address interstate ozone transport for the 2008 ozone NAAQS in the CSAPR Update for two reasons. First, the EPA explained that there was greater uncertainty in the EPA's assessment of non-EGU NO
X
mitigation potential, and that more time would be required for states and the EPA to improve non-EGU point source data and pollution control assumptions before we could develop emissions reduction obligations based on that data.
Id.
at 74542. Second, the EPA explained that we did not believe that significant, certain, and meaningful non-EGU NO
X
reductions were feasible for the 2017 ozone season.
Id.
Many commenters generally agreed with the EPA that non-EGU emissions reductions were not readily available for the 2017 ozone season but some advocated that such reductions should be included as appropriate in future mitigation actions.
Id.
at 74521-22. With respect to EGUs, the EPA concluded that additional control strategies, such as the implementation of new post-combustion controls, would take several years to implement, which was beyond the 2017 ozone season targeted in the CSAPR Update.
Id.
at 74541. Thus, the EPA could not make an emissions reduction-based conclusion that the CSAPR Update would fully resolve states' good neighbor obligations with respect to the 2008 ozone NAAQS because the reductions required by the CSAPR Update were EGU-only and because the EPA focused the policy analysis for the CSAPR Update on reductions available by the beginning of the 2017 ozone season.

Finally, in promulgating the CSAPR Update, the EPA stated its belief that it was beneficial to implement, without further delay, EGU NO
X
reductions that were achievable in the near term, particularly before the Moderate area attainment date of 2018. Notwithstanding that additional reductions may be required to fully address the states' interstate transport obligations, the EGU NO
X
emissions reductions implemented by the final rule were needed for upwind states to eliminate their significant contribution to nonattainment or interference with maintenance of the 2008 ozone NAAQS and to assist downwind states with ozone nonattainment areas that are required to attain the standard by July 20, 2018.

As a result of the remaining air quality problems and the limitations on the EPA's analysis, for all but one of the 21 states at issue, the EPA did not determine in the CSAPR Update that the CSAPR Update fully addressed those states' downwind air quality impacts under the good neighbor provision for the 2008 ozone NAAQS.
Id.
at 74521. For one state, Tennessee, the EPA determined in the final CSAPR Update that Tennessee's emissions budget fully eliminated the state's significant contribution to downwind nonattainment and interference with maintenance of the 2008 ozone NAAQS because the downwind air quality problems to which the state was linked were projected to be resolved with implementation of the CSAPR Update.
Id.
at 74552.

III. Proposed Determination Regarding Good Neighbor Obligations for the 2008 Ozone NAAQS

As described in section II.D, in the CSAPR Update the EPA promulgated FIPs intended to address the good neighbor provision for the 2008 ozone NAAQS, but could not at that time determine that those FIPs fully address 2008 ozone NAAQS good neighbor obligations for 21 of the 22 CSAPR Update states, based on information available when the rule was finalized. As a result, the CSAPR Update did not fully satisfy the EPA's obligation to issue FIPs or approve SIPs to address those states' good neighbor obligations for the 2008 ozone NAAQS. In this notice, the EPA proposes to determine that, based on additional information and analysis, the CSAPR Update fully addresses 20 of these states' good neighbor obligations for the 2008 ozone NAAQS. In particular, the EPA proposes to determine that there will be no remaining nonattainment or maintenance receptors in the eastern U.S. in 2023. Therefore, after the CSAPR Update is implemented, these states are not expected to contribute significantly to nonattainment in, or interfere with maintenance by, any other state with regard to the 2008 ozone NAAQS. The obligation as to the remaining state (Kentucky) is currently being addressed in a separate action.

A. Analytic Approach

The Agency is evaluating its determination regarding CSAPR Update states' remaining good neighbor obligations for the 2008 ozone NAAQS by applying the same approach used in previous federal actions addressing regional interstate transport of ozone pollution, including the CSAPR Update which addressed the same NAAQS at issue in this rulemaking. Each of these rulemakings followed the same four-step interstate transport framework to quantify and implement emissions reductions necessary to address the interstate transport requirements of the good neighbor provision.
44

These steps are summarized in the following four paragraphs.

44
With respect to the 2015 ozone NAAQS, the EPA recently provided information to states to inform their development of SIPs to address CAA section 110(a)(2)(D)(i)(I). In a memorandum dated March 27, 2018, the Agency noted that, in developing their own rules, states have flexibility to follow the familiar 4-step transport framework (using the EPA's analytical approach or somewhat different analytical approaches within these steps) or alternative frameworks, so long as their chosen approach has adequate technical justification and is consistent with the requirements of the CAA.

Step 1:

Identify downwind air quality problems
relative to the 2008 ozone NAAQS. The EPA has historically identified downwind receptors with air quality problems using air quality modeling projections and, where appropriate, considering monitored ozone data for a future compliance year. In the CSAPR Update, the agency relied on modeled and monitored data to identify not only those receptors expected to be in nonattainment with the ozone NAAQS, but also those receptors that may have difficulty maintaining the NAAQS, notwithstanding clean monitored data or projected attainment.

Step 2:

Determine which upwind states are “linked”
to these identified downwind air quality problems and thereby warrant further analysis to determine whether their emissions violate the good neighbor provision. In the CSAPR Update, the EPA identified such upwind states as those modeled to contribute to a downwind receptor at or above an air quality threshold equivalent to one percent of the 2008 ozone NAAQS.

Step 3:
For states linked to downwind air quality problems,
identify upwind emissions on a statewide basis that significantly contribute
to nonattainment or interfere with maintenance of a standard in any area. In all of the EPA's prior rulemakings addressing interstate ozone pollution transport, the Agency identified and apportioned emissions reduction responsibility among multiple upwind states linked to downwind air quality problems by considering feasible NO
X
control strategies and using cost-based and air quality-based criteria to evaluate regionally uniform NO
X
control strategies that were then used to quantify the amount of a linked upwind state's emissions, if any, that significantly contribute to nonattainment or interfere with maintenance in another state.

Step 4:
For upwind states that are found to have emissions that significantly contribute to nonattainment or interfere with maintenance of the NAAQS downwind,
implement the necessary emissions reductions
within the state. In the CSAPR Update, the EPA implemented the necessary emissions reductions from upwind states found to have good neighbor obligations by requiring EGUs in those states to participate in the CSAPR NO
X
Ozone Season Group 2 Trading Program, which is very similar to the allowance trading programs used to implement the emissions reductions quantified in the original CSAPR and other earlier rules.
45

45
Affected sources have participated in EPA-administered allowance trading programs under both SIPs and FIPs.

Because this action is evaluating outstanding obligations that remain with respect to the 2008 ozone NAAQS, the EPA believes it is reasonable to apply the same framework used in the CSAPR Update in this proposed action.

Within this four-step interstate transport framework, the EPA only proceeds to step four, in which it requires sources in upwind states to
implement
enforceable emissions limitations, if: (1) Downwind air quality
problems are identified
in at step 1; (2) an
upwind state is linked
to a downwind air quality problem at step 2;
and
(3) sources in the linked upwind state are
identified as having emissions
that significantly contribute to nonattainment and interfere with maintenance of the NAAQS considering cost- and air-quality-based factors. For the reasons described in the following paragraphs, the EPA believes this approach is a reasonable interpretation of the good neighbor provision.

The good neighbor provision instructs the EPA and states to apply its requirements “consistent with the provisions of” title I of the CAA. The EPA is therefore interpreting the requirements of the good neighbor provision, and the elements of its four-step interstate transport framework, to apply in a manner consistent with the designation and planning requirements in title I that apply in downwind states.
See North Carolina,
531 F.3d at 912 (holding that the good neighbor provision's reference to title I requires consideration of both procedural and substantive provisions in title I). The EPA notes that this consistency instruction follows the requirement that plans “contain adequate provisions prohibiting” certain emissions in the good neighbor provision. The following paragraphs will therefore explain how the EPA's interpretation of the circumstances under which the good neighbor provision requires that plans “prohibit” emissions through enforceable measures is consistent with the circumstances under which downwind states are required to implement emissions control measures in nonattainment areas.

For purposes of this analysis, the EPA notes specific aspects of the title I designations process and attainment planning requirements for the ozone NAAQS that provide particularly relevant context for evaluating the consistency of the EPA's approach to the good neighbor provision in upwind states. The EPA notes that this discussion is not intended to suggest that the specific requirements of designations and attainment planning apply to upwind states pursuant to the good neighbor provision, but rather to explain why the EPA's approach to interpreting the good neighbor approach is reasonable in light of relevant, comparable provisions found elsewhere in title I. In particular, these provisions demonstrate that the EPA's approach is consistent with other relevant provisions of title I with respect to what data is considered in the EPA's analysis and when states are required to implement enforceable measures.

First, areas are initially designated attainment or nonattainment for the ozone NAAQS based on actual measured ozone concentrations. CAA section 107(d) (noting that an area shall be designated attainment where it “meets” the NAAQS and nonattainment where it “does not meet” the NAAQS). Therefore, a designation of nonattainment does not in the first instance depend on what specific factors have influenced the measured ozone concentrations or whether such levels are due to enforceable emissions limits. If an area measures a violation of the relevant ozone NAAQS, then the area is designated nonattainment. In cases where the ozone nonattainment area is classified as Moderate or higher, the responsible state is required to develop an attainment plan, which generally includes the application of various enforceable control measures to sources of emissions located in the nonattainment area, consistent with the requirements in Part D of title I of the Act.
46

See generally
CAA section 182, 42 U.S.C. 7511a. If, however, an area measures compliance with the ozone NAAQS, the area is designated attainment, and sources in that area generally are not subject to any new enforceable control measures under Part D.
47

46
Areas classified as Marginal nonattainment areas are required to submit emissions inventories and implement a nonattainment new source review permitting program, but are not generally required to implement controls at existing sources.
See
CAA section 182(a), 42 U.S.C. 7511a(a).

47
Clean Air Act section 184 contains the exception to this general rule: states that are part of the Ozone Transport Region are required to provide SIPs that include specific enforceable control measures, similar to those for nonattainment areas, that apply to the whole state, even for areas designated attainment for the ozone NAAQS.
See generally
42 U.S.C. 7511c.

Similarly, in determining the boundaries of an ozone nonattainment area, the CAA requires the EPA to consider whether “nearby” areas “contribute” to ambient air quality in the area that does not meet the NAAQS. 42 U.S.C. 7407(d). For each monitor or group of monitors indicating a violation of the ozone NAAQS, the EPA assesses information related to five factors, including current emissions and emissions-related data from the areas near the monitor(s), for the purpose of establishing the appropriate geographic boundaries for the designated ozone nonattainment areas. A nearby area may be included within the boundary of the ozone nonattainment area only after assessing area-specific information, including an assessment of whether current emissions from that area contribute to the air quality problem identified at the violating monitor.
48

If such a determination is made, sources in the nearby area are also subject to the applicable Part D control requirements. However, if the EPA determines that the nearby area does not contribute to the measured nonattainment problem, then the nearby area is not part of the designated nonattainment area and sources in that area are not subject to such nonattainment control requirements.

48

See
Attachment 2 to
Area Designations for the 2008 Ozone National Ambient Air Quality Standards.
Memorandum from Robert J. Meyers, Principal Deputy Assistant Administrator, US EPA to Regional Administrators. December 4, 2008. Available at
https://archive.epa.gov/ozonedesignations/web/pdf/area_designations_for_the_2008_revised_ozone_naaqs.pdf.

The EPA's historical approach to addressing the good neighbor provision via the four-step interstate transport framework, and the approach the EPA proposes to continue to apply here, is consistent with these title I requirements. That is, in steps 1 and 2 of the framework, the EPA evaluates whether there is a downwind air quality problem (either nonattainment or maintenance), and whether an upwind state impacts the downwind area such that it contributes to and is therefore “linked” to the downwind area. The EPA's determination at step 1 of the good neighbor analysis that it has not

identified any downwind air quality problems to which an upwind state could contribute is analogous to the EPA's determination in the designation analysis that an area should be designated attainment. Similarly, EPA's determination at step 2 of the good neighbor analysis that, while it has at step 1 identified downwind air quality problems, an upwind state does not sufficiently impact the downwind area such that the state is “linked,” is analogous to the EPA's determination in the designation analysis that a nearby area does not contribute to a NAAQS violation in another area. Thus, under the good neighbor provision, the EPA determines at step 1 or 2, as appropriate, that the upwind state will not significantly contribute to nonattainment or interfere with maintenance in the downwind area.
See, e.g.,
81 FR 74506 (determining that emissions from 14 states do not significantly contribute to nonattainment or interfere with maintenance of the 2008 ozone NAAQS); 76 FR 48236 (finding that states whose contributions to downwind receptors are below the air quality threshold do not significantly contribute to nonattainment or interfere with maintenance of the relevant NAAQS). Under such circumstances, sources in the upwind state are not obligated to implement any control measures under the good neighbor provision, which is consistent with the fact that sources located in attainment areas generally are not required to implement the control measures found in Part D of the Act.
Cf. EME Homer City II,
795 F.3d at 130 (determining that CSAPR ozone-season NO
X
budgets for 10 states were invalid based on determination that modeling showed no future air quality problems); 81 FR 74523-24 (removing three states from CSAPR ozone season NO
X
program based on determination that states are not linked to any remaining air quality problems for the 1997 ozone NAAQS).

The EPA acknowledges one distinction between the good neighbor and designation analyses: The good neighbor analysis relies on
future-year
projections of emissions to calculate ozone concentrations and upwind state contributions, compared to the designation analysis's use of
current
measured data. As described in more detail later, this approach is a reasonable interpretation of the term “will” in the good neighbor provision,
see North Carolina,
531 F.3d at 913-14, and interpreting language specific to that provision does not create an impermissible inconsistency with other provisions of title I. Moreover, the EPA's use of future-year modeling in the good neighbor analysis to identify downwind air quality problems and linked states is consistent with its use of current measured data in the designations process. The EPA's future-year air quality projections consider a variety of factors, including current emissions data, anticipated future control measures, economic market influences, and meteorology. Many of these same factors,
e.g.,
current control measures, economic market influences, and meteorology, can affect the NO
X
emissions levels and consequent measured ozone concentrations that inform the designations process. Like the factors that affect measured ozone concentrations used in the designations process, not all of the factors influencing the EPA's modeling projections are or can be enforceable limitations on emissions or ozone concentrations. However, the EPA believes that consideration of these factors contributes to a reasonable estimate of anticipated future ozone concentrations.
See EME Homer City II,
795 F.3d at 135 (declining to invalidate EPA's modeling projections “solely because there might be discrepancies between those predictions and the real world”);
Chemical Manufacturers Association
v.
EPA,
28 F.3d 1259, 1264 (DC Cir. 1994) (“a model is meant to simplify reality in order to make it tractable”). Thus, the EPA believes that consideration of these factors in its future-year modeling projections used at steps 1 and 2 of the good neighbor analysis is reasonable and consistent with the use of measured data in the designation analysis.
49

49
The EPA also notes that the consideration of projected
actual
emissions in the future analytic year—as opposed to allowable levels—is also consistent with the statute's instruction that states (or EPA in the states' stead) prohibit emissions that “will” impermissibly impact downwind air quality. This term is reasonably interpreted to mean that the EPA should evaluate anticipated emissions (what sources
will
emit) rather than potential emissions (what sources
could
emit).

The EPA notes that there is a further distinction between the section 107(d) designations provision and the good neighbor provision in that the latter provision uses different terms to describe the threshold for determining whether emissions in an upwind state should be regulated (“contribute significantly”) as compared to the standard for evaluating the impact of nearby areas in the designations process (“contribute”). Thus, at step 3 of the good neighbor analysis the EPA evaluates additional factors, including cost and air-quality considerations, to determine whether emissions from a linked upwind state do or would violate the good neighbor provision. Only if the EPA at step 3 determines that the upwind state's emissions do or would violate the good neighbor provision will it proceed to step 4, at which point emissions in the upwind state must be controlled so as to address the identified violation, analogous to the trigger for the application of Part D requirements to sources located in designated nonattainment areas. The EPA interprets the good neighbor provision to not require it or the upwind state to proceed to step 4 and implement any enforceable measures to “prohibit” emissions unless it identifies a violation of the provision at step 3.
See, e.g.,
76 FR 48262 (finding at step 3 that the District of Columbia is not violating the good neighbor provision, and therefore will not at step 4 be subject to any control requirements in CSAPR, because no cost-effective emissions reductions were identified).

B. Selection of a Future Analytic Year

In this action, consistent with historical practice, the EPA focuses its analysis on a future year in light of the forward-looking nature of the good neighbor obligation in section 110(a)(2)(D)(i)(I). Specifically, the statute requires that states prohibit emissions that “will” significantly contribute to nonattainment or interfere with maintenance of the NAAQS in any other state. The EPA reasonably interprets this language as permitting states and the EPA in implementing the good neighbor provision to prospectively evaluate downwind air quality problems and the need for further upwind emissions reductions. In the EPA's prior regional transport rulemakings, the Agency generally evaluated whether upwind states “will” significantly contribute to nonattainment or interfere with maintenance based on projections of air quality in the future year in which any emissions reductions would be expected to go into effect. Thus, when the EPA finalized the NO
X
SIP Call in 1998, it used the anticipated 2007 full compliance year for its analysis, and when the EPA finalized CAIR in 2005, it used the years 2009 and 2010, anticipated compliance years for the 1997 ozone and 1997 PM
2.5
NAAQS, respectively. 63 FR 57377; 70 FR 25241. The D.C. Circuit affirmed the EPA's interpretation of “will” in CAIR, finding the EPA's consideration of future projected air quality (in addition to current measured data) to be a reasonable interpretation of an ambiguous term.
North Carolina,
531 F.3d at 913-14. The EPA applied the same approach in finalizing CSAPR in

2011 and the CSAPR Update in 2016 by evaluating air quality in 2012 and 2017, respectively. 76 FR 48211; 81 FR 74537. Thus, consistent with this precedent, a key decision that informs the application of the interstate transport framework is selecting a future analytic year. In determining the appropriate future analytic year for purposes of assessing remaining interstate transport obligations for the 2008 ozone NAAQS, the EPA considered two primary factors: (1) The applicable attainment dates; and (2) the timing to feasibly implement new NO
X
control strategies, which are discussed in the following two sections. The EPA proposes to determine that these factors collectively support the use of 2023 as the future analytic year for this proposed action.

1. Attainment Dates for the 2008 Ozone NAAQS

First, the EPA considers the downwind attainment dates for the 2008 ozone NAAQS. In
North Carolina,
the D.C. Circuit held that emissions reductions required by the good neighbor provision should be evaluated considering the relevant attainment dates of downwind nonattainment areas impacted by interstate transport. 531 F.3d at 911-12 (holding that the EPA must consider downwind attainment dates when establishing interstate transport compliance deadlines). Many areas currently have attainment dates of July 20, 2018 for areas classified as Moderate, but, as noted earlier, the 2017 ozone season was the last full season from which data could be used to determine attainment of the NAAQS by the July 20, 2018 attainment date. Given that the 2017 ozone season has now passed, it is not possible to achieve additional emissions reductions by the Moderate area attainment date. It is therefore necessary to consider what subsequent attainment dates should inform the EPA's analysis. The next attainment dates for the 2008 ozone NAAQS will be July 20, 2021, for nonattainment areas classified as Serious, and July 20, 2027, for nonattainment areas classified as Severe.
50

Because the various attainment deadlines are in July, which is in the middle of the ozone monitoring season for all states, data from the calendar year prior to the attainment date (
e.g.,
data from 2020 for the 2021 attainment date and from 2026 for the 2027 attainment date) are the last data that can be used to demonstrate attainment with the NAAQS by the relevant attainment date. Therefore, the EPA considers the control strategies that could be implemented by 2020 and 2026 in assessing the 2021 and 2027 attainment dates in its subsequent analysis. The EPA has also considered that, in all cases, the statute provides that areas should attain as expeditiously as practicable.
51

50
While there are no areas (outside of California) that are currently designated as Serious or Severe for the 2008 ozone NAAQS, the CAA requires that the EPA reclassify to Serious any Moderate nonattainment areas that fail to attain by their attainment date of July 20, 2018. Similarly, if any area fails to attain by the Serious area attainment date, the CAA requires that the EPA reclassify the area to Severe.

51

See
CAA section 181(a)(1), 42 U.S.C. 7511(a)(1).

2. Feasibility of Control Strategies To Reduce Ozone Season NO
X

Second, the EPA considers the timeframes that may be required to implement further emissions reductions as expeditiously as practicable. Generally, NO
X
emissions levels are expected to decline in the future through the combination of the implementation of existing local, state, and federal emissions reduction programs and changing market conditions for generation technologies and fuels.
52

This is an important consideration because the U.S. Supreme Court and the D.C. Circuit Court have both held that the EPA may not over-control: It may not require emissions reductions (at step 3 of the good neighbor framework) from a state that are greater than necessary to achieve attainment and maintenance of the NAAQS in all of the downwind areas to which that state is linked.
53

In particular, in
EME Homer City II,
the D.C. Circuit determined that the CSAPR phase 2 ozone-season NO
X
budgets for ten states were invalid because EPA's modeling showed that the downwind air quality problems to which these states were linked would be resolved by 2014, when the phase 2 budgets were scheduled to be implemented. 795 F.3d at 129-30. Therefore, because new controls cannot be implemented feasibly for several years, and at that later point in time air quality will likely be better due to continued phase-in of existing regulatory programs, changing market conditions, and fleet turnover, it is reasonable for the EPA to evaluate air quality (at step 1 of the good neighbor framework) in a future year that is aligned with feasible control installation timing in order to ensure that the upwind states continue (at step 2) to be linked to downwind air quality problems when any potential emissions reductions (identified at step 3) would be implemented (at step 4) and to ensure that such reductions do not over-control relative to the identified ozone problem.

52
Annual Energy Outlook 2018.
Electricity Supply, Disposition, Prices, and Emissions.
Reference Case. Department of Energy, Energy Information Administration. Available at
https://www.eia.gov/outlooks/aeo/data/browser/#/?id=8-AEO2018&cases=ref2018&sourcekey=0.

53

EPA
v.
EME Homer City Generation, L.P.,
134 S. Ct. at 1600-01;
EME Homer City II,
795 F.3d at 127.

The EPA's analysis of the feasibility of NO
X
control strategies reflects the time needed to plan for, install, test, and place into operation new EGU and non-EGU NO
X
reduction strategies regionally—
i.e.,
across multiple states. This regional analytic approach is consistent with the regional nature of interstate ozone pollution transport as described in section II.A. The Agency adopted this approach for this proposal based on previous interstate ozone transport analyses showing that where eastern downwind ozone problems are identified, multiple upwind states typically are linked to these problems.
54

Specifically of relevance to this action, as discussed in section II.C, the EPA's assessment of CSAPR Update implementation found that 21 states continued to contribute greater than or equal to 1% of the 2008 ozone NAAQS to identified downwind nonattainment or maintenance receptors in multiple downwind states in 2017. Thus, to reasonably address these ozone transport problems, the EPA must identify and apportion emissions reduction responsibility across multiple upwind states. In other words, the EPA's analysis should necessarily be regional, rather than focused on individual linkages. Where such an analysis is needed for multiple states, the inquiry into the availability and feasibility of control options is necessarily considerably more complicated than for a single state or sector.

54
81 FR 74538.

Further, the feasibility of new emissions controls should be considered with regard to multiple upwind source categories to ensure that the Agency properly evaluates NO
X
reduction potential and cost-effectiveness from all reasonable control measures (including those that are or may be available outside of the EGU sector). NO
X
emissions come from multiple anthropogenic source categories, such as mobile sources, electric utilities, resource extraction industries, and industrial and commercial facilities. As noted in section II.A, the EPA has historically addressed mobile source emissions through national rulemakings. Moreover, mobile source emissions are already decreasing

because of sector‐specific standards related to fuels, vehicle fuel economy, pollution controls, and repair and replacement of the existing fleet. Programs such as the Tier 3 vehicle emissions standards are already being phased in between now and 2023. That rule was finalized in 2014 with a phase-in schedule of 2017-2025 reflecting fleet turnover. Thus, another reason that in this proposed action the EPA has focused on stationary sources is that emissions reductions from those sources could likely be implemented more quickly than would result from any attempt to effect additional reductions from mobile sources beyond those described.

Among stationary sources, EGUs in the eastern U.S. have been the primary subject of regulation to address interstate ozone pollution transport and have made significant financial investments to achieve emissions reductions. While the EPA continues to evaluate control feasibility for EGUs in its analysis, the EPA's recent analyses indicate that non-EGU source categories, which the EPA has not made subject to new regulations to address interstate ozone transport since the NO
X
SIP Call, may also be well-positioned to cost-effectively reduce NO
X
relative to EGUs.
55

Accordingly, the EPA's assessment of control feasibility focuses on both EGU and non-EGU sources.

55
See Assessment of Non-EGU NO
X
Emission Controls, Cost of Controls, and Time for Compliance Final TSD from the CSAPR Update in the docket for this rulemaking.

a. EGUs

First, the EPA presents its feasibility assessment of NO
X
control strategies for EGUs. In establishing the CSAPR Update EGU ozone season NO
X
emissions budgets, the Agency quantified the emissions reductions achievable from all NO
X
control strategies that were feasible to implement in less than one year and cost-effective at a marginal cost of $1,400 per ton of NO
X
removed.
56

These EGU NO
X
control strategies were: optimizing NO
X
removal by existing, operational selective catalytic reduction (SCR) controls; turning on and optimizing existing idled SCR controls; installing state-of-the-art NO
X
combustion controls; and shifting generation to existing units with lower-NO
X
emissions rates within the same state. 81 FR 74541. The Agency believes that the resulting CSAPR Update emissions budgets are being appropriately implemented under the CSAPR NO
X
Ozone Season Group 2 allowance trading program. Preliminary data for the 2017 ozone season (the first CSAPR Update compliance period) indicate that power plant ozone season NO
X
emissions across the 22 state CSAPR Update region were reduced by 77,420 tons (or 21%) from 2016 to 2017.
57

As a result, total 2017 ozone season NO
X
emissions from covered EGUs across the 22 CSAPR Update states were approximately 294,478 tons,
58

well below the sum of states' emissions budgets established in the CSAPR Update of 316,464 tons. Accordingly, for the purposes of this proposed determination, the EPA considers the turning on and optimizing of existing SCR controls and the installation of combustion controls to be NO
X
control strategies that have already been appropriately evaluated and implemented in the final CSAPR Update.

56
The CSAPR Update was signed on September 7, 2016—approximately 8 months before the beginning of the 2017 ozone season on May 1.

57

https://ampd.epa.gov/ampd/
(Data current as of March 1, 2018).

58

Id.

In the CSAPR Update, the EPA also identified one EGU NO
X
control strategy that was considered feasible to implement within one year but was not cost-effective at a marginal cost of $1,400 per ton of NO
X
removed: specifically, turning on existing idled selective non-catalytic reduction (SNCR) controls. In the CSAPR Update, the EPA identified a marginal cost of $3,400 per ton as the level of uniform control stringency that represents turning on and fully operating idled SNCR controls.
59

However, the CSAPR Update finalized emissions budgets using $1,400 per ton control stringency, finding that this level of stringency represented the control level at which incremental EGU NO
X
reductions and corresponding downwind ozone air quality improvements were maximized with respect to marginal cost. In finding that use of the $1,400 control cost level was appropriate, the EPA established that the more stringent emissions budget level reflecting $3,400 per ton (representing turning on idled SNCR controls) yielded fewer additional emissions reductions and fewer air quality improvements relative to the increase in control costs. In other words, based on the CSAPR Update analysis, establishing emissions budgets at $3,400 per ton, and therefore developing budgets based on operation of idled SNCR controls, was not determined to be cost-effective for addressing good neighbor provision obligations for the 2008 ozone NAAQS. 81 FR 74550. The EPA believes that the strategy of turning on and fully operating idled SNCR controls was appropriately evaluated in the CSAPR Update with respect to addressing interstate ozone pollution transport for the 2008 ozone NAAQS. Accordingly, in this proposal the EPA is not further assessing this control strategy for purposes of identifying an appropriate future analytic year.

59

See
EGU NO
X
Mitigation Strategies Final Rule TSD (docket ID EPA-HQ-OAR-2015-0500-0554, available at
www.regulations.gov
and
https://www.epa.gov/sites/production/files/2017-05/documents/egu_nox_mitigation_strategies_final_rule_tsd.pdf
) (NO
X
Mitigation Strategies TSD).

As mentioned previously, the EPA evaluated shifting generation from EGUs with higher NO
X
-emissions rates to EGUs with lower NO
X
-emissions rates as a means of reducing emissions in the context of the CSAPR Update. Shifting generation is a NO
X
control strategy that occurs on a time- and cost-continuum, in contrast to the relatively discrete price-points and installation timeframes that can be identified for combustion and post-combustion controls. Therefore, in the CSAPR Update, the EPA identified the discrete cost thresholds used to evaluate upwind states' good neighbor obligations based on its evaluation of combustion and post-combustion controls, and secondarily examined the amount of generation shifting that would result at the same cost threshold associated with the particular control technology. Quantifying NO
X
reductions from shifting generation anticipated at the same cost thresholds relative to the control technologies being considered (
e.g.,
restarting idled SCR controls) helped ensure that the emissions reductions associated with the control strategies could be expected to occur. In other words, had the agency excluded consideration of generation shifting in calculating emissions budgets, generation shifting would have nonetheless occurred as a compliance strategy, but the consequence would have been a smaller amount of emissions reduction than what the agency knew to be achievable and cost‐effective at the selected cost threshold. Thus, although potential emissions reductions resulting from generation shifting were factored into the final budgets, this compliance strategy did not drive the EPA's identification of cost thresholds analyzed in the rule.

For the same reasons, the EPA does not find it appropriate to evaluate generation shifting, in isolation from viable combustion or post-combustion control assessments, for purposes of selecting a future analytic year. If the EPA were to choose an earlier analytic year based on the ability of upwind sources to implement some level of

generation shifting within that timeframe, before other specific control technologies could be implemented, this would have the consequence of limiting the EPA's analysis and the amount of emissions reductions that would be considered cost-effective and therefore subject to regulation under the good neighbor provision, relative to a more robust analysis that considers other emissions controls available within defined timeframes. Further, due to continued lower cost natural gas prices and price projections, significant shifting from higher emitting coal sources to lower emitting gas sources (relative to historical generation levels) is occurring and expected to continue to occur by 2023 due to market drivers. Thus, there may be limited opportunity for the sources to implement further emissions reductions through generation shifting over the next 5 years. Given the indeterminate implementation timeframes for generation shifting and the EPA's historical consideration of this strategy as a secondary factor in quantifying emissions budgets, the EPA believes the most reasonable approach for selecting a future analytic year is to focus on the timeframe in which specific control technologies other than generation shifting can be implemented.
60

60
Because the EPA is not in this proposal evaluating additional generation shifting possibilities, it does not at this time need to revisit the question whether it is within the EPA's authority or otherwise proper to consider generation shifting in implementing the good neighbor provision. The EPA is aware that this has been an issue of contention in the past, and stakeholders have raised serious concerns regarding this issue.
See, e.g.,
81 FR at 74545 (responding to comments); CSAPR Update Rule—Response to Comment, at 534-50 (EPA-HQ-OAR-2015-0500-0572) (summarizing and responding to comments). The EPA may revisit this question in addressing good neighbor requirements for other NAAQS but is not soliciting comment at this time on this issue with regard to the 2008 ozone NAAQS.

For these reasons, for purposes of identifying an appropriate future analytic year, the EPA is focusing its assessment of EGUs in this action on controls that were deemed to be infeasible to install for the 2017 ozone season rather than reassessing controls previously analyzed for cost-effective emissions reductions in the CSAPR Update. In establishing the CSAPR Update emissions budgets, the EPA identified but did not analyze the following two EGU NO
X
control strategies in establishing the CSAPR Update emissions budgets because implementation by 2017 was not considered feasible: (1) Installing new SCR controls; and (2) installing new SNCR controls. In the CSAPR Update, EPA observed that EGU SCR post-combustion controls can achieve up to 90 percent reduction in EGU NO
X
emissions. In 2017, these controls were in widespread use by EGUs in the east. EPA also observed that SNCR controls can be effective at reducing NO
X
emissions and can achieve up to a 25 percent emissions reduction from EGUs (with sufficient reagent). In 2017, these controls were also used across the power sector. In the 22-state CSAPR Update region, approximately 62 percent of coal-fired EGU capacity is equipped with SCR controls and 12 percent is equipped with SNCR controls.
61

61
National Electric Energy Data System v6 (NEEDS). EPA. Available at
https://www.epa.gov/airmarkets/national-electric-energy-data-system-needs-v6.

Installing new SCR or SNCR controls for EGUs generally involves the following steps: conducting an engineering review of the facility; advertising and awarding a procurement contract; obtaining a construction permit; installing the control technology; testing the control technology; and obtaining or modifying an operating permit.
62

Because installing these post-combustion controls—SCR or SNCR—involve the same steps and many of the same considerations, the timing of their feasible regional development is described together in the following paragraphs. However, the EPA notes differences between these control technologies with respect to the potential viability of achieving cost-effective regional NO
X
reductions from EGUs. As described above, SCR controls generally achieve greater EGU NO
X
reduction efficiency (up to 90%) than SNCR controls (up to 25%). Resulting in part from this disparity in NO
X
reduction efficiency, when considering both control costs and NO
X
reduction potential in developing cost per ton analysis for the CSAPR Update, the EPA found new SCR controls to be more cost-effective at removing NO
X
. Specifically, the EPA found that new SCR controls could generally reduce EGU emissions for $5,000 per ton of NO
X
removed whereas new SNCR controls could generally reduce EGU emissions at a higher cost of $6,400 per ton of NO
X
removed.
63

In other words, the greater NO
X
reduction efficiency for SCR controls translates into greater cost-effectiveness relative to SNCR controls. The general cost-effectiveness advantage is consistent with observed installation patterns where SCR controls (62% of coal-fired capacity) are more prevalent across the east relative to SNCR (12% of coal-fired capacity).

62
Final Report: Engineering and Economic Factors Affecting the Installation of Control Technologies for Multipollutant Strategies, EPA-600/R-02/073 (Oct. 2002),
available at https://nepis.epa.gov/Adobe/PDF/P1001G0O.pdf.

63
NO
X
Mitigation Strategies TSD.

For SCR, the total time associated with navigating necessary steps is estimated to be up to 39 months for an individual power plant installing SCR on more than one boiler.
64

However, more time is needed when considering installation timing for new SCR controls across the Eastern EGU fleet addressed in this action. As described in the subsequent paragraphs, EPA determined that a minimum of 48 months is a reasonable time period to allow for the coordination of outages, shepherding of labor and material supply, and identification of retrofit projects. This timeframe would facilitate multiple power plants with multiple boilers to conduct all stages of post-combustion and combustion control project planning, installation, and operation.

64
Engineering and Economic Factors Affecting the Installation of Control Technologies for Multipollutant Strategies. EPA Final Report. Table 3-1. Available at
https://archive.epa.gov/clearskies/web/pdf/multi102902.pdf.

Scheduled curtailment, or planned outage, for pollution control installation would be necessary to complete either SCR or SNCR projects. Given that peak demand and rule compliance would both fall in the ozone season, sources would likely try to schedule installation projects for the “shoulder” seasons (
i.e.,
the spring and/or fall seasons), when electricity demand is lower than in the summer, reserves are higher, and ozone season compliance requirements are not in effect. If multiple units were under the same timeline to complete the retrofit projects as soon as feasible from an engineering perspective, this could lead to bottlenecks of scheduled outages as each unit attempts to start and finish its installation in roughly the same compressed time period. Thus, any compliance timeframe that would assume installation of new SCR or SNCR controls should encompass multiple shoulder seasons to accommodate scheduling of curtailment for control installation purposes and better accommodate the regional nature of the program.

In addition to the coordination of scheduled curtailment, an appropriate compliance timeframe should accommodate the additional coordination of labor and material supply necessary for any fleet-wide mitigation efforts. The total construction labor for a SCR system associated with a 500-megawatt (MW) EGU is in the range of 300,000 to 500,000 man-hours, with boilermakers accounting for

approximately half of this time.
65

SNCR installations, while generally having shorter individual project timeframes of 10 to 13 months from bid solicitation to startup, share similar labor and material resources and the timing of SNCR installation planning is therefore linked to the timing of SCR installation planning. In recent industry surveys, one of the largest shortages of union craft workers was for boilermakers. This shortage of skilled boilermakers is expected to rise due to an anticipated nine percent increase in boilermaker labor demand growth by 2026, coupled with expected retirements and comparatively low numbers of apprentices joining the workforce.
66

The shortage of and demand for skilled labor, including other craft workers critical to pollution control installation, is pronounced in the manufacturing industry. The Association of Union Constructors conducted a survey of identified labor shortages and found that boilermakers were the second-most frequently reported skilled labor market with a labor shortage.
67

Moreover, recovery efforts from the natural disasters of Hurricanes Harvey and Irma and wildfires in 2017 are expected to further tighten the labor supply market in manufacturing in the near term.
68

The EPA determined that these tight labor market conditions within the relevant manufacturing sectors, combined with fleet-level mitigation initiatives, would likely lead to some sequencing and staging of labor pool usage, rather than simultaneous construction across all efforts. This sector-wide trend supports SCR and SNCR installation timeframes for a fleet-wide program that exceeds the demonstrated single-unit installation timeframe.

65

Id.

66
Occupational Outlook Handbook. Bureau of Labor Statistics. Available at
https://www.bls.gov/ooh/construction-and-extraction/boilermakers.htm.

67
Union Craft Labor Supply Survey. The Association of Union Constructors. Exhibit 4-2 at page 29. Available at
https://www.tauc.org/files/2017_TAUC_UNION_CRAFT_LABOR_SUPPLY_REVISEDBC_FINAL.pdf.

68
Skilled Wage Growth Less Robust, Worker Shortage Still an Issue. Industry Week. October 23, 2017. Available at
http://www.industryweek.com/talent/skilled-wage-growth-less-robust-worker-shortage-still-issue.

In addition to labor supply, NO
X
post-combustion control projects also require materials and equipment such as steel and cranes. Sheet metal workers, necessary for steel production, are also reported as having well above an average supply-side shortage of labor.
69

This, coupled with growth in steel demand estimated at three percent in 2018 suggests that there may be a constricted supply of steel needed for installation of new post-combustion controls.
70

Similarly, cranes are critical for installation of SCRs, components of which must be lifted hundreds of feet in the air during construction. Cranes are also facing higher demand during this period of economic growth, with companies reporting a shortage in both equipment and manpower.
71 72

The tightening markets in relevant skilled labor, materials, and equipment, combined with the large number of installations that could be required fleet-wide under a regional air pollution transport program, necessitates longer installation time-tables relative to what has been historically demonstrated at the unit-level.

69
Union Craft Labor Supply Survey. The Association of Union Constructors. Exhibit 4-2 at page 29. Available at
https://www.tauc.org/files/2017_TAUC_UNION_CRAFT_LABOR_SUPPLY_REVISEDBC_FINAL.pdf.

70
Worldsteel Short Range Outlook. October 16, 2017. Available at
https://www.worldsteel.org/media-centre/press-releases/2017/worldsteel-Short-Range-Outlook-2017-2018.html.

71

See, e.g.,
Seattle Has Most Cranes in the Country for 2nd Year in a Row—and Lead is Growing. Seattle Times. July 11, 2017. Available at
https://www.seattletimes.com/business/real-estate/seattle-has-most-cranes-in-the-country-for-2nd-year-in-a-row-and-lead-is-growing/.

72
See RLB Crane Index, January 2018 in the docket for this action.

The time lag observed between the planning phase and in-service date of SCR operations in certain cases also illustrates that site-specific conditions sometimes lead to installation times of four years or longer. For instance, SCR projects for units at the Ottumwa power plant (Iowa), Columbia power plant (Wisconsin), and Oakley power plant (California) were all in the planning phase in 2014. By 2016, these projects were under construction with estimated in-service dates of 2018.
73

Similarly, individual SNCR projects can exceed their estimated 10 through 13-month construction time frame. For example, projects such as SNCR installation at the Jeffrey power plant (Kansas) were in the planning phase in 2013, but not in service until 2015.
74

Completed projects, when large in scale, also illustrate how timelines can extend beyond the bare minimum necessary for a single unit when the project is part of a larger air quality initiative involving more than one unit at a plant. For instance, the Big Bend Power Station in Florida completed a multi-faceted project that involved adding SCRs to all four units as well as converting furnaces, over-fire air changes, and making windbox modifications. The time from the initial planning stages to completion was a decade.
75

73
2014 EIA Form 860. Schedule 6. Environmental Control Equipment.

74
2013 EIA Form 860, Schedule 6, Environmental Control Equipment.

75

Big Bend's Multi-Unit SCR Retrofit.
Power Magazine. March 1, 2010. Available at
http://www.powermag.com/big-bends-multi-unit-scr-retrofit/.

While individual unit-level SCR and SNCR projects can average 39 and 10 months, respectively, from bid to startup, a comprehensive and regional emissions reduction effort also requires more time to accommodate the labor, materials, and outage coordination for these two types of control strategies. Because these post-combustion control strategies share similar resource inputs and are part of regional emissions reduction programs rather than unit-specific technology mandates, the timeframes for one type are inherently linked to the other type. This means that SNCR projects cannot be put on an early schedule in light of their reduced construction timing without impacting the availability of resources for the manufacture and installation of SCRs and thus the potential start dates of those projects.

In short, given the market and regulatory circumstances in which EPA evaluated this effort, our analysis shows that four years would be an expeditious timeframe to coordinate the planning and completion of any mitigation efforts necessary in this instance.

b. Non-EGU Control Technologies

The EPA is also evaluating the feasibility of implementing NO
X
control technologies for non-EGUs in its assessment of an appropriate future analytic year. While the EPA did not regulate non-EGUs in the CSAPR Update, the rule did evaluate the feasibility of NO
X
controls on non-EGUs in the eastern United States to assess whether any such controls could be implemented in time for the 2017 ozone season. The EPA noted that there was greater uncertainty in the assessment of non-EGU point-source NO
X
mitigation potential as compared to EGUs, and therefore explained that more time was required for states and the EPA to improve non-EGU point source data, including data on existing control efficiencies, additional applicable pollution control technologies, and installation times for those control technologies. 81 FR 74542. A significant factor influencing uncertainty was that the EPA lacked sufficient information on the capacity and experience of suppliers and major engineering firms' supply chains to determine if they would be able to install the required pollution controls for non-EGU sources

in time for the 2017 ozone season. Further, using the best information available to the EPA at that time, the EPA found that there were more non-EGU point sources than EGU sources and that these sources on average emit less NO
X
than EGUs. The implication was that there were more individual sources that could be controlled, but relatively fewer emissions reductions available from each source when compared to the number of EGUs and emissions reductions available from EGUs. Considering these factors, the EPA found that it was substantially uncertain whether significant aggregate NO
X
mitigation would be achievable from non-EGU point sources to address the 2008 ozone NAAQS by the 2017 ozone season.
Id.

Although the EPA determined that there were limited achievable emissions reductions available from non-EGUs by the 2017 ozone season, the EPA acknowledged that it may be appropriate to evaluate potential non-EGU emissions reductions achievable on a timeframe after the 2017 ozone season to assess upwind states' full good neighbor obligation for the 2008 ozone NAAQS. 81 FR 74522. In particular, the EPA's preliminary assessment indicated that there may be emissions reductions achievable from non-EGUs at marginal costs lower than the costs of remaining NO
X
control strategies available for EGUs. Accordingly, in assessing an appropriate future analytic year, the EPA is also considering the potential implementation timeframes for NO
X
emissions reductions available for non-EGUs. In evaluating potential non-EGU emissions reductions in the CSAPR Update, the EPA included preliminary estimates of installation times for some non-EGU NO
X
control technologies in a technical support document entitled Assessment of Non-EGU NO
X
Emission Controls, Cost of Controls, and Time for Compliance Final Technical Support Document (henceforth, “Final Non-EGU TSD”). These preliminary estimates were based on research from a variety of information sources, including:

•
Typical Installation Timelines for NO
X

Emissions Control Technologies on Industrial Sources, Institute of Clean Air Companies,
December 2006 (all sources except cement kilns and reciprocating internal combustion engines (RICE));
76

76
Institute of Clean Air Companies. Typical Installation Timelines for NO
X
Emissions Control Technologies on Industrial Sources, December 2006. Available at
https://c.ymcdn.com/sites/icac.site-ym.com/resource/resmgr/ICAC_NOx_Control_Installatio.pdf.

•
Cement Kilns Technical Support Document for the NO
X

FIP
, US EPA, January 2001;
77

and

77
US EPA. Cement Kilns Technical Support Document for the NO
X
FIP. January 2001. Available at
https://www.regulations.gov/document?D=EPA-HQ-OAR-2015-0500-0094
.

•
Availability and Limitations of NO
X

Emission Control Resources for Natural Gas-Fired Reciprocating Engine Prime Movers Used in the Interstate Natural Gas Transmission Industry,
Innovative Environmental Solutions Inc., July 2014 (prepared for the INGAA Foundation).
78

78
INGAA Foundation. Availability and Limitations of NO
X
Emission Control Resources for Natural Gas-Fired Reciprocating Engine Prime Movers Used in the Interstate Natural Gas Transmission Industry, Innovative Environmental Solutions Inc., July 2014. Available at
http://www.ingaa.org/Foundation/Foundation-Reports/NO
X
.aspx
.

The EPA's analysis in the Final Non-EGU TSD focused on potential control technologies within the range of costs considered in the final CSAPR Update for EGUs, or those controls available at a marginal cost of $3,400 per ton (2011 dollars) of NO
X
reduced or less. The EPA's analysis did not evaluate implementation timeframes or potential emissions reductions available from controls at higher cost thresholds.
See
Final Non-EGU TSD at 18. This focus excluded some emissions source groups with emissions reduction potential at a marginal cost greater than $3,400 per ton, including: industrial/commercial/institutional boilers using SCR and low-NO
X
burners (LNB); and catalytic cracking units, process heaters, and coke ovens using LNB and flue gas recirculation. However, while emissions reduction potential from these source groups is uncertain, the timeframe for these control technologies would be subject to similar considerations and limitations discussed in the following paragraphs.

Among the control technologies that were evaluated in the Final Non-EGU TSD, the EPA identified six categories of common control technologies available for different non-EGU emissions source categories.
Id.
at 19. For four of the technology categories (SNCR, SCR, LNB, and mid-kiln firing), the EPA preliminarily estimated that such controls for non-EGUs could be installed in approximately 1 year or less in some unit-specific cases. Installation time estimates presented in the Final Non-EGU TSD begin with control technology bid evaluation (bids from vendors) and end with the startup of the control technology.
79

See
Final Non-EGU TSD at 20. For the other two technology categories (biosolid injection technology (BSI) and OXY-firing), as well as one emissions source category (RICE), the EPA had no installation time estimates or uncertain installation time estimates. For example, the EPA found that the use of BSI is not widespread, and therefore the EPA does not have reliable information regarding the time required to install the technology on cement kilns. The installation timing for OXY-firing is similarly uncertain because the control technology is installed only at the time of a furnace rebuild, and such rebuilds occur at infrequent intervals of a decade or more.

79
In this document, we present different installation time estimates for SCRs for EGUs and non-EGUs. These installation times are not inconsistent because: (i) The EGU time estimate of 39 months mentioned above is based on multi-boiler installation and factors in a pre-vendor bid engineering study consideration; and (ii) the non-EGU SCR installation time estimates are based on single-unit installation and do not factor in pre-vendor bid evaluation.

For those categories for which preliminary estimates were available, as noted in the Final Non-EGU TSD, the single-unit installation time estimates provided do not account for additional important considerations in assessing the full amount of time needed for installation of NO
X
control measures at non-EGUs; those considerations include time, labor, and materials needed for programmatic adoption of measures and time required for installing controls on multiple sources in a few to several non-EGU sectors across the region.

The preliminary estimates of installation time shown in the Final Non-EGU TSD are for installation at a single source and do not account for the time required for installing controls to achieve sector-wide compliance. When considering installation of control measures on sources regionally and across non-EGU sectors, the time for full sector-wide compliance is uncertain, but it is likely longer than the installation times shown for control measures as mentioned above for individual sources in the Final Non-EGU TSD. As discussed earlier with respect to EGUs, regional, sector-wide compliance could be slowed down by limited vendor capacity, limited available skilled labor for manufacturers such as boilermakers (who produce steel fabrications, including those for pollution control equipment), availability of raw materials and equipment (
e.g.,
cranes) for control technology construction, and bottlenecks in delivery and installation of control technologies. Some of the difficulties with control technology installation as part of regional, sector-wide compliance at non-EGUs, such as availability of skilled labor and materials, could also have an impact on monitor installation at such sources.

EPA currently has insufficient information on vendor capacity and limited experience with suppliers of control technologies and major engineering firms, which results in uncertainty in the installation time estimates for non-EGU sectors. In summary, there is significant uncertainty regarding the implementation timeframes for various NO
X
control technologies for non-EGUs. While the EPA has developed preliminary estimates for some potential control technologies, these estimates do not account for additional considerations such as the impacts of sector- and region-wide compliance. For purposes of this analysis, the EPA believes that it is reasonable to assume that it is likely that an expeditious timeframe for installing sector- or region-wide controls on non-EGU sources may collectively require four years or more.

3. Focusing on 2023 for Analysis

As discussed in section III.B, the EPA weighed several factors to identify an appropriate future analytic year for evaluating interstate transport obligations for the 2008 ozone NAAQS. First, the EPA identified the relevant attainment dates to guide the EPA's consideration as 2021 and 2027, respectively the Serious and Severe area attainment dates for the 2008 ozone NAAQS.

Second, the EPA identified and analyzed the feasibility and timing needed for installing additional NO
X
emissions controls. As discussed in section III.B.2, the EPA believes it is appropriate to assume that planning for, installing, and commencing operation of new controls, regionally, for EGUs and non-EGUs would take up to 48 months, and possibly more in some cases, following promulgation of a final rule requiring appropriate emissions reductions. This period of time reflects, among other considerations, the time needed to regionally develop new post-combustion SCR projects—systems that continue to represent the engineering gold-standard in terms of reducing NO
X
from the U.S. power sector.

To determine how this feasibility assessment should influence potential compliance timeframes, the EPA believes it is appropriate to consider the anticipated date of promulgation of a rule that would set any appropriate emissions reduction requirements, since regulated entities cannot be expected or required to take action to comply with a rule prior to its promulgation. The EPA, therefore, considered the timeframe in which a future rulemaking that might require such emissions reductions would likely be finalized.

The EPA is subject to several statutory and court-ordered deadlines to issue FIPs (or, alternatively, to fully approve a SIP) to address the requirements of the good neighbor provision for the 2008 ozone NAAQS for several states. An August 12, 2017 statutory deadline has passed for the EPA to act with respect to 13 states.
80

The EPA also has several upcoming statutory deadlines in 2018 and 2019 to address these requirements for eight other CSAPR Update states.
81

The timeframe for the EPA's action to resolve the obligation as to five of those states is the subject of litigation in the United States District Court for the Southern District of New York. The EPA is subject to court-ordered deadlines to sign and disseminate a proposed action fully addressing the good neighbor obligations under the 2008 ozone NAAQS for those five states by no later than June 29, 2018, and to promulgate a final action addressing these requirements by December 6, 2018.
82

As noted earlier, the EPA is also subject to a court-ordered deadline of June 30, 2018, for the EPA to address these requirements for Kentucky,
83

which the EPA intends to address in a separate rulemaking. Considering the EPA's conclusion that four years is an expeditious timeframe for implementation of any of the control strategies considered herein, compliance is likely not feasible until the 2023 ozone season. In other words, 48 months from a final rule promulgated in December 2018 would be December 2022, after which the next ozone season begins in May 2023. Considering the time necessary to implement the controls calculated from a realistic timeframe in which EPA expects to promulgate a final rule requiring such controls, the EPA believes that such reductions on a variety of sources across the region are unlikely to be implemented for a full ozone season until 2023.

80
80 FR 39961 (finding that states failed to make complete submissions that address the requirements of section 110(a)(2)(D)(i)(I) related to the interstate transport of pollution as to the 2008 ozone NAAQS).

81
The EPA has deadlines to promulgate FIPs for Indiana (81 FR 38957), Ohio (81 FR 38957) and New Jersey (81 FR 38963) by July 15, 2018; for Maryland (81 FR 47040) by August 19, 2018; for Louisiana (81 FR 53308), Texas (81 FR 53284) and Wisconsin (81 FR 53309) by September 12, 2018; and for New York (81 FR 58849) by September 26, 2018.

82
Order,
New York
v.
Pruitt,
No. 1:18-cv-00406-JGK (S.D.N.Y. June 12, 2018).

83
Order,
Sierra Club
v.
Pruitt,
No. 3:15-cv-04328 (N.D. Cal. May 23, 2017).

Finally, consistent with the court's holding in
North Carolina,
the Agency considers this timing in light of upcoming attainment dates for the 2008 ozone NAAQS. While 2023 is later than the next attainment date for nonattainment areas classified as Serious (
i.e.,
July 20, 2021), for the reasons discussed above the EPA does not believe it is realistically possible that substantial emissions control requirements could be promulgated and implemented by that Serious area attainment date. Rather, the most expeditious timeframe in which additional control strategies could be implemented at both EGUs and non-EGUs is four years after promulgation of a final rule requiring appropriate emissions reductions. At the same time, the EPA does not believe that it should generally take longer than 2023 to install emissions controls on a regional basis, based on the analysis above. Therefore, there is no basis to postpone all emissions reductions to the next attainment date after 2023, which is for nonattainment areas classified as Severe (
i.e.,
July 20, 2027). Accordingly, the EPA believes implementation of additional emissions reductions by 2023 is the earliest feasible timeframe that could be reasonably required of EGU and non-EGU sources that would be potentially subject to control requirements. Although this year does not precisely align with a particular attainment date, it reflects the year that is as expeditious as practicable for region-wide implementation, while also taking into account the relevant attainment dates.

Given the current stage of the 2008 ozone implementation cycle, the EPA's feasibility analysis set forth above, the relevant attainment dates, and the courts' holdings in
North Carolina
and
EME Homer City II,
the EPA believes that 2023 is the most appropriate year for all states covered in this action, to assess downwind air quality and to evaluate any remaining requirements under the good neighbor provision for the 2008 ozone NAAQS. The EPA is requesting comment on the use of 2023 as a reasonable year for this assessment.

C. Air Qualit