DEPARTMENT OF TRANSPORTATION
Federal Highway Administration
23 CFR Parts 771, 1420, and 1430
Federal Transit Administration
23 CFR Parts 1420 and 1430
49 CFR Parts 622 and 623
[FHWA Docket No. FHWA-99-5989 ]
FHWA RIN 2125-AE64; FTA RIN 2132-AA43
NEPA and Related Procedures for Transportation Decisionmaking, Protection of Public Parks, Wildlife and Waterfowl Refuges, and Historic Sites

AGENCIES:

Federal Highway Administration (FHWA), Federal Transit Administration (FTA), DOT.

ACTION:

Notice of proposed rulemaking (NPRM); request for comments.

SUMMARY:

The FHWA and the FTA are issuing this notice of proposed rulemaking to update and revise their National Environmental Policy Act of 1969 (NEPA) implementing regulation for projects funded or approved by the FHWA and the FTA. The current regulation was issued in 1987 and experience since that time as well as changes in legislation, most recently by the Transportation Equity Act for the 21st Century (TEA-21), call for an updated approach to implementation of NEPA for FHWA and FTA projects and actions. Under this proposed rulemaking, the FHWA/FTA regulation for implementing NEPA would be redesignated and revised to further emphasize using the NEPA process to facilitate effective and timely decisionmaking.

This NPRM is being issued concurrently with another notice of proposed rulemaking on metropolitan and statewide transportation planning. This coordinated approach to rulemaking will further the goal of the FTA and the FHWA to better coordinate the results of the planning processes with project development activities and decisions associated with the NEPA process.

DATES:

Comments must be received on or before August 23, 2000. For dates of public information meetings see
Supplementary Information.

ADDRESSES:

Submit written, signed comments to the docket number appearing at the top of this document. You must submit your comments to the Docket Clerk, U.S. DOT Dockets, Room PL-401, 400 Seventh Street, SW., Washington, DC 20590-0001. All comments will be available for examination at the above address between 9 a.m. and 5 p.m., e.t., Monday through Friday, except Federal holidays. To receive notification of receipt of comments you must include a pre-addressed, stamped envelope or postcard. For addresses of public information meetings see
Supplementary Information.

FOR FURTHER INFORMATION CONTACT:

For the FHWA: Mr. Fred Skaer, (202) 366-2058, Office of Planning and Environment, HEPE, or Mr. L. Harold Aikens, (202) 366-0791, Office of the Chief Counsel, HCC-31. For the FTA: Mr. Joseph Ossi, (202) 366-0096, Office of Planning, TPL-22, or Mr. Scott Biehl, (202) 366-0952, Office of the Chief Counsel, TCC-30. Office hours are from 7:45 a.m. to 4:15 p.m., e.t., Monday through Friday, except Federal holidays.

SUPPLEMENTARY INFORMATION:

Electronic Access

Internet users may access all comments received by the U.S. DOT Dockets, Room PL401, by using the universal resource locator (URL):­
http://dms.dot.gov.
It is available 24 hours each day, 365 days each year. Please follow the instructions online for more information and help.

An electronic copy of this document may be downloaded by using a modem and suitable communications software from the Government Printing Office's Electronic Bulletin Board Service at (202) 512-1661. Internet users may reach the Office of the Federal Register's home page at:
http://www.nara.gov/fedreg
and the Government Printing Office's database at:
http://www.access.gpo.gov/nara.

Contents of Preamble

• Background on the NEPA Rule

• Overall Strategy for Regulatory Development

• Relationship to U.S. DOT's Statewide and Metropolitan Planning Regulation and other Rulemaking Efforts

• Section-by-Section Analysis of the Proposed Rule for NEPA and Related Procedures for Transportation Decisionmaking

• Section-by-Section Analysis of the Proposed Rule for Protection of Public Parks, Wildlife and Waterfowl Refuges, and Historic Sites.

Public Information Meetings

We will hold a series of seven public briefings within the comment period for the NPRM. The purposes of these briefings is to explain the content of the NPRM and encourage public input to the final rulemaking. The meetings will address this NPRM, the companion NPRM on the metropolitan and statewide planning process and the NPRM on Intelligent Transportation Systems Architecture consistency. The meetings will be scheduled from approximately 8 a.m. to 5 p.m. at the locations listed below. Changes in the information below will be made available after the publication of this NPRM through the FHWA and the FTA websites, other public announcement avenues and the newsletters and websites of major stakeholder groups. Individuals wishing information but without access to these sources may contact the individuals listed above.

The structure of the meetings will emphasize brief presentations by the DOT staff regarding the content of the NPRM. A period for clarifying questions will be provided. Under current statutory and regulatory provisions, the DOT staff will not be permitted to engage in a substantive dialog regarding what the content of the NPRMs and the final regulations should be. Attendees wishing to express ideas and thoughts regarding the final content of the rules should direct those comments to the docket. Briefing sites will include: Boston, MA, Auditorium, Volpe National Transportation Systems Center, 55 Broadway, June 9, 2000; Atlanta, GA, Westin Peachtree Plaza Hotel, 210 Peachtree Street, June 20, 2000; Washington, D.C., Marriott Metro Center, 775 12th Street, NW, June 23, 2000; Chicago, IL, Holiday Inn Mart Plaza, 350 North Orleans Street, June 27, 2000; Denver, CO, Marriott City Center, 1701 California Street, June 30 , 2000; Dallas, TX, Hyatt Regency Hotel Dallas, 300 Reunion Boulevard, July 11, 2000; and, San Francisco, CA, Radisson Miyako, 1625 Post Street, July 19, 2000.

As part of the outreach process planned for these proposed rules, the FHWA/FTA will be conducting a national teleconference on June 15, 2000 from 1 to 4 p.m., e.t., through the auspices of the Center for Transportation and the Environment at North Carolina State University. The teleconference will be accessible through numerous downlink locations nationwide and further information can be obtained from Ms. Katie McDermott at
kpm@unity.ncsu.edu
or (919) 515-8034. The purpose of the teleconference is to describe the proposed new statewide and metropolitan planning, NEPA implementation, and Intelligent Transportation Systems (ITS) rules.

An overview of each of the three notices of proposed rulemakings (NPRMs) will be presented and the audience (remote and local) will have opportunities to ask questions and seek clarification of FHWA/FTA proposals. By sponsoring this teleconference it is

hoped that interest in the NPRMs is generated, that stakeholders will be well informed about FHWA/FTA proposals, and that interested parties will participate in the rulemaking process by submitting written suggestions, comments and concerns to the docket.

Background

The FHWA and the FTA propose to update and revise the current regulation and guidance implementing the NEPA (42 U.S.C. 4321
et seq.
) for transportation projects using Federal funds or requiring Federal approval.

In this notice of proposed rulemaking, we are clearly communicating that our NEPA responsibilities include an affirmative duty to facilitate the development of transportation proposals which represent responsible stewardship of community and natural environmental resources. In the 13 years since the NEPA regulation was last issued, the nature of the highway and transit programs has evolved to reflect our country's changing transportation needs and the impact that the transportation network can have on a complex set of environmental, community, and economic considerations. What has not changed is the role of State and local officials and Federal land management agency decision makers to define transportation investment strategies, plan for a future transportation system that best reflects their community needs, and select and set priorities for transportation projects.

The NPRM was developed by an interagency Task Force of the FHWA and the FTA with input from other DOT modal agencies, the U.S. Environmental Protection Agency (EPA), other Federal agencies and the Office of the Secretary, U.S. DOT. The Task Force reviewed all input received from the outreach process which is described below and through other sources that communicate regularly with U.S. DOT. In addition, input was provided from the field staff of the FHWA and the FTA.

Over the past thirteen years we have developed an increased understanding of effective environmental analysis, a greater commitment to prevention of adverse environmental impacts, and a realization of the increased value of integrated agency and public coordination. Given these developments, our role to ensure that transportation projects are developed through a more effective and collaborative NEPA process at the State, local, and Federal levels becomes that much more pivotal. Our environmental rule reflects the understanding that NEPA is an important tool for helping make transportation decisions, rather than justifying decisions already made. In addition, we believe that a more coordinated approach to planning and project development (the NEPA process plus additional project level actions needed to prepare for project implementation) will contribute to more effective and environmentally sound decisions regarding investment choices and trade-offs.

By including the environmental streamlining provision in TEA-21, section 1309 of Public Law 105-178, 112 Stat. 108 at 232, the Congress intended that transportation planning and environmental considerations be better coordinated and that project delivery schedules be improved through a process that is efficient, comprehensive, and streamlined. Growing awareness of the need for a Federal role that would oversee development of a coordinated environmental review process is tempered with congressional intent that State and local decisions be respected. The most important Federal role in the transportation decisionmaking process is one where the FHWA and the FTA would facilitate other Federal agencies' early involvement and participation in NEPA activities so that redundant processes are identified and avoided. We will, in our role as lead agencies, highlight opportunities to use NEPA as a mechanism to address statutory responsibilities at Federal, State, and local levels of government. During the TEA-21 outreach process, there has been very strong support from our transportation and environmental partners for a better managed NEPA process which reflects these basic features: coordination, flexibility, and efficiency.

For these reasons, it is clear that a fundamentally new approach to NEPA is needed, one that emphasizes strong environmental policy, collaborative program solving approaches involving all levels of government and the public early in the process, and integrated and streamlined coordination and decisionmaking processes. Proposed approaches are included in this notice of proposed rulemaking. This NPRM fully supports “protection and enhancement of communities and the natural environment,” one of five U.S. DOT strategic goals. Translating this strategic direction into day-to-day operations requires that appropriate changes be made to regulations and nonregulatory operating guidance.

Overall Strategy for Regulatory Development

Our strategy for regulatory development has three principal elements: (1) Outreach and listening to stakeholders; (2) developing improvements that will allow the FHWA, the FTA, States and metropolitan areas to demonstrate measurable progress toward achieving congressional intent and objectives; and (3) seeking ways to improve coordination and performance, both internally and with our Federal partner agencies.

Input to Development of Notice of Proposed Rulemaking

We have used several venues to obtain feedback on how to improve the administration of NEPA. Of principal importance was the NEPA 25th Anniversary Workshop held in Chattanooga, Tennessee in 1995. Participants included a diverse group of governmental and nongovernmental individuals representing transportation and community interests, as well as those interested in protecting the natural environment. The blueprint document that resulted from the NEPA Workshop underscores the need for a fundamentally new approach to NEPA, one that focuses on decisionmaking rather than compliance.

The FHWA and the FTA, in concert with the Office of the Secretary and other modal administrations within the U.S. DOT, developed and implemented an extensive public outreach process on all elements of the TEA-21. The process began shortly after the legislation was enacted on June 9, 1998, and various types of outreach activities have been underway since that time. The initial six-month Departmentwide outreach process included twelve regional forums and over 50 focus groups and workshops (63 FR 40330, July 28, 1998). The U.S. DOT heard from over 3,000 people including members of Congress, Governors and Mayors, other elected officials, transportation practitioners at all levels, community activists and environmentalists, freight shippers and suppliers, and other interested individuals. The input received was valuable and has helped us shape implementation strategy, guidance, and regulations.

With respect to the planning and environmental provisions of TEA-21, we learned a great deal through the twelve regional forums and focus group sessions and subsequently implemented a second, more focused phase of outreach which included issuing a discussion paper, “TEA-21 Planning and Environmental Provisions: Options for Discussion,” FHWA/FTA, February 1999. The content of the Options Paper reflected input received up to that time and built upon the existing statewide

and metropolitan planning regulations and our NEPA implementing regulation. We released the Options Paper on February 9, 1999, and received comments through April 30, 1999. More than 150 different sets of comments were received from State Departments of Transportation (DOTs), Metropolitan Planning Organizations (MPOs), counties, regional planning commissions, other Federal agencies, transit agencies, bicycle advocacy groups, engineering organizations, consultants, historical commissions, environmental groups, and customers— the American public. These comments were all reviewed and taken into consideration in the development of this NPRM. Another element of outreach has included meetings with our key stakeholder groups, other Federal agencies, and the regional and field staff within our agencies.

This proposed rule will be one part of a widespread agency effort to provide clear and consistent guidance on how the NEPA process can be most effectively used to help applicants make transportation decisions which reflect a concern for social, economic, and environmental well-being. It provides the framework upon which we, along with State DOTs, MPOs, transit agencies, and Federal land management agencies, can base our approach to transportation decisionmaking.

We recognize that a wide range of issues exist in the realm of transportation and the environment. Our outreach effort associated with TEA-21, as well as feedback to the Options Paper, have highlighted many areas of concern for which the FHWA and the FTA policy should be more clearly articulated. However, not all of these areas will be directly addressed as part of this rule. For many topics for which we feel regulatory treatment is unnecessary or inappropriate, we intend to issue a comprehensive package of materials to provide detailed, nonregulatory information on how to incorporate such considerations into the NEPA process. In addition, certain other topics will be the subject of individual, separate regulations or guidance.

The comprehensive package of informational materials is envisioned as a replacement both for the 1987 FHWA Technical Advisory 6640.8a on environmental documents and the FTA (formerly Urban Mass Transportation Administration) Circular 5620.1
1

on environmental assessments. The timing of its development is intended to be consistent with the development of the regulations that will result from this NPRM. We anticipate that the comments we receive on the NPRM will help guide the creation of the informational materials, as well as the regulations. Thus, a more complete picture of our approach will be presented.

1
The FHWA and the FTA internal directives are available for inspection and copying as prescribed at 49 CFR part 7.

Further, we have been working with Federal environmental agencies to implement the environmental streamlining provisions of TEA-21. The results of those activities are described in the section-by-section analysis discussion later in this preamble.

The TEA-21 outreach effort and comments on the Options Paper have all helped guide us in developing this notice of proposed rulemaking. Comments on this NPRM are welcomed and will be taken into account prior to the issuance of a final regulation containing updated NEPA implementation requirements.

Relationship to U.S. DOT's Statewide and Metropolitan Planning Regulation and Other Rulemaking Efforts

There are four additional rulemaking activities either underway or planned which relate closely to this notice of proposed rulemaking. These include: the joint FHWA/FTA rules on statewide and metropolitan planning and on section 4(f), and the FHWA rules on acquisition of right-of-way and decision-build contracting. The relationship with the statewide and metropolitan planning rulemaking is described below, and the TEA-21 provisions and input received through the Options Paper on the other three issue areas follows:

Statewide and Metropolitan Planning

Concurrent with the release of this notice of proposed rulemaking, the U.S. DOT is issuing a notice of proposed rulemaking to update and revise its statewide and metropolitan planning regulations (23 CFR part 450 and 49 CFR part 613). As proposed in these coordinated rulemaking actions, the statewide and metropolitan planning rule and the NEPA and transportation decisionmaking rules would both be moved to new parts: 1410 and 1420, respectively. This co-location is intended to underscore the integrated nature of transportation planning and the NEPA process.

We intend to ensure that the regulatory provisions governing statewide and metropolitan planning and NEPA work in a consistent and complementary fashion, and result in sound transportation decisions. We view the changes in TEA-21 as opportunities to improve and integrate planning and environmental processes to support more effective decisionmaking and it is in this context that both notices of proposed rulemaking were developed. It is our intent to establish consistency between the two regulations to allow our State and local transportation partners that choose to conduct social, economic, and environmental analysis at the planning stage to incorporate that analysis at the project development phase. This approach offers options for integrating project development efficiencies into the overall planning process, where States, MPOs, and transit agencies deem such action appropriate and desirable.

Section 4(f) (49 U.S.C. 303)

We propose to move the reference and citation for section 4(f)
2

in title 23 of the Code of Federal Regulations. This proposal removes the provisions on section 4(f) from the NEPA rule and establishes a separate regulation for section 4(f). Years of applying section 4(f) to new and unprecedented situations have led to a history of case experience which must be reflected in the regulation. As a result, the rules governing section 4(f) have grown to the point that they warrant their own part in the regulations. We can envision a separate effort to revise and update the section 4(f) rule; however, we are proposing minor changes at this time. Nevertheless, we invite comment on suggested changes to the Section 4(f) rule of a more substantive nature. A comprehensive package of informational materials that will be released concurrent with this final regulation will elaborate on the continued fully integrated relationship between the NEPA process and the section 4(f) evaluation process.

2
Section 4(f) of the Department of Transportation Act, which protected certain public lands and all historic sites, technically was repealed in 1983 when it was codified without substantive change, as 49 U.S.C. 303. This regulation continues to refer to section 4(f) because it would create needless confusion to do otherwise; the policies section 4(f) engendered are widely referred to as “section 4(f)” matters. A provision with the same meaning is found at 23 U.S.C. 138 and applies only to FHWA actions.

The information within the proposed section 4(f) regulation has not changed in concept. However, new information has been added to bring the administration of section 4(f) evaluations up-to-date with FHWA and FTA programs such as Transportation Enhancements, Transit Enhancements, the Symms National Trail Program, etc. There has been little substantive change in the requirements of the section 4(f) regulation; rather the format of the information presented has been changed

to reflect these program changes and proposed organizational changes.

The separation of the section 4(f) and NEPA procedures into separate regulations is not intended to fragment compliance with section 4(f) and NEPA. Our intent is to continue a fully integrated implementation under the unified and coordinated process provided by the NEPA procedures as an umbrella for addressing all relevant responsibilities, including section 4(f). Placing the two regulations in sequence within the Code of Federal Regulations, with cross references between them, is intended to communicate the continued integration of section 4(f) and the NEPA process.

Right-of-Way Acquisition

Section 1301 of the TEA-21 allows the value of land acquired by a State or local government without Federal assistance to be credited to the State share of a federally-assisted project which uses that land. However, the law stipulated that the land acquisition must not influence the environmental assessment of the project, including the need to construct the project, the consideration of alternatives, and the selection of a specific location.

The FHWA considered, under a separate rulemaking, covering “Right-of-Way Program Administration” published as a final rule in the December 21, 1999,
Federal Register
, an “early acquisition” policy to accommodate the acquisition of land or other property interests (including “at-risk” activities) by State or local agencies that may be deemed necessary while NEPA considerations are being concluded. These acquisitions would be considered “at-risk” in that the Federal reimbursement for a share of the acquisition costs would be forthcoming only if the acquired property is subsequently used in a federally-assisted project. Interested parties should refer to the December 21, 1999, final rulemaking (64 FR 71284-71297) in the
Federal Register
.

Advance right-of-way acquisition was the subject of considerable debate during the TEA-21 outreach efforts. Several commenters including the Capital Area MPO in Albany, NY, argued that the advance acquisition of right-of-way in rapidly growing areas is desirable, cost effective and good policy. These commenters view land acquisition as environmentally neutral, in that unused land can be disposed of, often at a profit. Others, including the National Coalition to Defend NEPA, noted the inherent conflict between allowing advance right-of-way acquisition and corridor preservation initiatives, and the selection of a preferred alternative as part of the NEPA process. The National Coalition to Defend NEPA argues that purchase of land represents a commitment to a particular project location and that it, therefore, would influence the assessment of the project under NEPA.

Design-Build Contracting

Section 1307 of the TEA-21 permits a State or local transportation agency to award a design-build contract during project development provided that final design shall not commence before the NEPA process has been completed.

We have been concerned about design-build contracts (also called “turnkey” contracts) for federally-assisted projects being let before the NEPA process has been completed. To do so could give the appearance that the State or local transportation agency is fully committed to a single course of action, and that the NEPA process is simply a clearance exercise and not a true decisionmaking process. There may, however, be some situations in which design-build procurement can be structured to allow for the design-builders to work on an alternative emerging from the NEPA process. Our agencies recognize that the emerging interest in design-build contracting may warrant specific regulatory language or guidance addressing the relationship between design-build procurement and NEPA.

During the TEA-21 outreach efforts, some commenters suggested that design-build contracting provisions could include clauses that would preclude work on construction or the “building” of projects until after the NEPA Record of Decision
3

is made. The American Road and Transportation Builders Association (ARTBA) suggested that any work done on projects using this type of procurement method would be “at-risk” until the NEPA Record of Decision is announced, meaning that the work may have to be discarded if the NEPA process ultimately results in selection of an alternative project. In these cases, the State or local agency would not be eligible to receive Federal reimbursement until that time, and only if the action was consistent with the Record of Decision. The Virginia DOT suggested that design-build procurement awards should not be made until after the NEPA process had been concluded, at which point the specifics of the location and design decisions would be known. This approach has been used by the FTA in its Turnkey Demonstration Program. The Orange County Transportation Corridors Agency suggested that having a design-build agency on board at the earliest possible time is actually environmentally beneficial, since it can contribute valuable input in a timely way, to arrive at implementable and cost effective recommendations.

3
NEPA Record of Decision is the documentation of final action by the FHWA and the FTA regarding their decision on a project action (final alternative chosen, impacts, mitigation and basis for decision, etc.) addressed in an Environmental Impact Statement.

For highway projects, the FHWA's Office of Infrastructure is responsible for developing regulations which implement this TEA-21 provision. It is currently engaged in fact-finding and consultation among transportation partners including the American Association of State Highway and Transportation Officials (AASHTO), and anticipates beginning the formal rulemaking process next year. Achieving a balance between realizing the fullest time-savings potential of design-build contracting and maintaining the integrity of the NEPA process will be the subject of considerable discussion during that rulemaking process.

Our agencies intend to adopt consistent policies on the NEPA-related aspects of the design-build issue for two reasons: (1) Transit projects should not have procedural disadvantages in comparison to highway projects, and (2) Federal transit law (49 U.S.C. 5304(e)) requires that the FTA and the FHWA conform their NEPA processes to each other's.

Section-by Section Analysis of the Proposed Rule on NEPA and Related Procedures for Transportation Decisionmaking

This section of the notice of proposed rulemaking includes a section-by-section analysis of the proposed rule on NEPA and incorporates summary information on comments received on the Options Paper. All comments on the Options Paper are contained in the docket. The comments are, of necessity, summarized in each of the relevant sections of the proposed rule and are intended to provide an overall perspective on the comments submitted to the FHWA and the FTA. Details on specific comments and input can be obtained by reviewing the materials in the docket.

The proposed regulations have been reordered as to content and organized into the following four subparts:

Subpart A—Purpose, Policy, and Mandate;

Subpart B—Program and Project Streamlining;

Subpart C—Process and Documentation Requirements; and

Subpart D—Definitions.

The following table highlights the reordering and organization for each proposed subpart:

Proposed Section
Current Section

Subpart A—Purpose, Policy, and Mandate
None.

1420.101 Purpose of this regulation
771.101 Purpose.

1420.103 Relationship of this regulation to the CEQ regulation and other guidance
771.103 [Reserved]

1420.105 Applicability of this regulation

771.109(a) Applicability and responsibilities and
771.111(f) Early coordination, public involvement, and project development.

1420.107 Goals of the NEPA process
None.

1420.109 The NEPA umbrella
771.105 Policy.

1420.111 Environmental justice
771.105 Policy.

1420.113 Avoidance, minimization, mitigation, and enhancement responsibilities
771.105 Policy.

Subpart B—Program and Project Streamlining
None.

1420.201 Relationship of planning and project development processes
None.

1420.203 Environmental streamlining
None.

1420.205 Programmatic approvals
None.

1420.207 Quality assurance process
771.125 Final environmental impact statements.

1420.209 Alternate procedures
None.

1420.211 Use of this part by other U.S. DOT agencies
None.

1420.213 Emergency action procedures
771.131 Emergency action procedures.

Subpart C—Process and Documentation Requirements
None.

1420.301 Responsibilities of the participating parties
771.109 Applicability and responsibilities.

1420.303 Interagency coordination
771.111 Early coordination, public involvement, and project development.

1420.305 Public involvement
771.111 Early coordination, public involvement, and project development.

1420.307 Project development and timing of activities
771.111 Early coordination, public involvement, and project development, and

None
771.113 Timing of administration activities.

1420.309 Classes of actions
771.115 Classes of actions.

1420.311 Categorical exclusions
771.117 Categorical exclusion.

1420.313 Environmental assessments
771.119 Environmental assessments.

1420.315 Findings of no significant impacts
771.121 Findings of no significant impacts.

1420.317 Draft environmental impact statements
771.123 Draft environmental impact statements.

1420.319 Final environmental impact statements
771.125 Final environmental impact statements.

1420.321 Record of decision
771.127 Record of decision.

1420.323 Re-evaluations
771.129 Re-evaluations.

1420.325 Supplemental environmental impact statements
771.130 Supplemental environmental impact statements.

Subpart D—Definitions
None.

1420.401 Terms defined elsewhere
None.

1420.403 Terms defined in this part
771.107 Definitions.

Subpart A—Purpose, Policy and Mandate

This proposed subpart sets out the framework for the FHWA/FTA NEPA process. It complements and supplements the United States Council on Environmental Quality (CEQ) provisions that serve a similar function for the entire Federal government.

Section 1420.101 Purpose of This Regulation

Current § 771.101 would be redesignated as § 1420.101 and revised to establish that the focus of the proposed regulation is to conduct a decisionmaking process for transportation projects that, under NEPA, integrates and streamlines compliance with all transportation and environmental laws applicable to decisionmaking during project development. Reference is made to the regulations for transportation planning as being a contributing factor to this decisionmaking process.

Section 1420.103 Relationship of This Regulation to the CEQ Regulation and Other Guidance

The proposed § 1420.103 does not appear in the current regulation. It clarifies that this regulation is to be read as a supplement to the CEQ's governmentwide regulations for implementing NEPA (40 CFR parts 1500-1508) and contains specific provisions for Federal surface transportation actions under our jurisdiction. Further, the proposed section acknowledges that, in addition to issuing revised NEPA regulations, we will conduct and fulfill our responsibilities under NEPA using any combination of approaches including, but not limited to, nonregulatory guidance, training, and technical assistance.

The CEQ regulations cover regulatory definition and general environmental procedural requirements (
e.g.,
acceptable development and evaluation of an acceptable range of alternatives). These are not repeated in this proposed rule because we want to avoid confusion by repeating or paraphrasing CEQ requirements. Reproducing requirements in the FHWA and the FTA environmental regulations that are identical to CEQ requirements could create potential conflicts and confusion as to the applicability of CEQ provisions not reproduced. Instead, the chosen approach makes a discernible connection between the different regulations, and provides the

opportunity for general practitioners to increase their familiarity with and understanding of the CEQ regulations, a familiarity of which is essential to their ability to comply fully with all of the environmental requirements applicable to transportation projects.

Section 1420.105 Applicability of This Regulation

The proposed section revises current §§ 771.109 and 771.111, Applicability and responsibilities and Early coordination, public involvement, and project development, respectively. The language appearing in paragraph (a) of the proposed section is a shortened version of paragraph (a) of current § 771.109. Paragraph (b) in the proposed section is essentially the existing criteria for allowable segmentation of projects, taken from paragraph (f) of § 771.111.

Section 1420.107 Goals of the NEPA Process

Proposed section § 1420.107 is to be read in close conjunction with the subsequent proposed § 1420.109. Section 1420.107 would establish the goals of the FHWA/FTA transportation decisionmaking process. The goals are drawn from a variety of statutory mandates, including NEPA itself, and provisions of the various transportation laws that authorize our programs. The NEPA process is a partnership among Federal, State, and local governments and, at times, private entities. Our intent in this section is to establish a common understanding within the partnership of the goals to be achieved through the NEPA process.

The FHWA and the FTA reaffirm their role as lead Federal agencies, and underscore their responsibility to manage the NEPA process with the objective of achieving these goals. This responsibility extends to ensuring that Federal NEPA decisions pay appropriate deference to State and local decisions made in good faith and not coerce a particular Federal point of view. State and local decisions made with full consideration of a broad range of social, economic, and environmental factors, and with the advice of appropriate Federal and other State resource agencies (i.e., the agencies responsible under law for the protection or management of natural and community resources) and with public involvement are those most likely to advance the NEPA goals.

Section 1420.109 The NEPA Umbrella

Proposed § 1420.109 would replace portions of current § 771.105, Policy. The proposed section sets forth our basic policy regarding how the decisionmaking process for surface transportation projects is to be conducted . The proposed section states the intent of our agencies to use the NEPA process as the overarching procedural construct under which the varied legal requirements, environmental issues, and public interests relevant to the transportation decision are brought to bear; hence the term “NEPA umbrella” is used to describe the concept. The consideration of a proposed action under NEPA concludes with a decision made in the best overall public interest: one that balances the need for safe and efficient transportation with the project's social, economic, environmental benefits and impacts, and the attainment of relevant environmental protection goals.

Experience in administering the NEPA process has shown that many practitioners do not fully understand or practice our approach of using the NEPA process as an umbrella for integrating their studies, reviews, or consultations and satisfying all relevant requirements in a single, integrated decisionmaking process. Instead, many have chosen to approach the various requirements as obstacles or hurdles to be addressed in a less than comprehensive fashion. Many delayed projects or failed processes can be traced back to a disintegrated and disconnected approach to meeting NEPA and other requirements. This section of the regulation is intended to clarify the preferred approach and explicitly demonstrate the multitude of factors that can influence Federal decisionmaking. Setting forth these expectations will contribute to a better, more efficient and timely NEPA process, one that is envisioned in the TEA-21 and highlighted in its section 1309 on environmental streamlining.

Section 1420.111 Environmental Justice

Subsequent to the previous regulatory revision in 1987, the 1994 Executive Order 12898 on Environmental Justice was issued to address disproportionately high and adverse human health and environmental effects of Federal government programs, policies, and activities on minority populations and low income populations. This section would be added to present regulatory language from our policy on environmental justice that is articulated in the DOT Order 5610.2 on Environmental Justice (62 FR 18377, April 15, 1997).

Section 1420.113 Avoidance, Minimization, Mitigation, and Enhancement Responsibilities

This section would present our policy regarding NEPA's mandate that Federal agencies, to the fullest extent possible, use all practicable means to restore and enhance, and avoid or minimize any possible adverse effects of their actions upon the quality of the human environment.

Our policy towards correcting adverse impacts is contained in the hierarchical but not necessarily sequential concepts of avoidance, minimization, and mitigation of impacts, and in the evaluation of environmental enhancements. The policy is consistent with the CEQ's approach to mitigation presented in 40 CFR 1500.2(f) and elsewhere, and would revise the language concerning mitigation of adverse impacts currently provided at § 771.105(d). The proposed language reflects also the broadened Federal funding eligibility for enhancement measures, such as transportation enhancement activities and transit enhancements, enacted with ISTEA and TEA-21. The section would address the eligibility for Federal funding (to the extent authorized by law), of measures to avoid, minimize, or mitigate impacts, or to provide or implement enhancements.

Our general responsibility for ensuring that mitigation is carried out would be presented in paragraph (d) of the proposed section, NEPA Commitments. These provisions would be redesignated from § 771.109(b) to streamline the subject matter of the new regulations; the original text would be revised to detail the responsibility for implementing mitigation measures and environmental enhancements that resulted from commitments made in the FHWA/FTA NEPA process.

Subpart B—Program and Project Streamlining

This subpart would group together a set of provisions aimed at improving the NEPA process, either on individual projects or on a programwide basis, so that transportation decisions can be made in a timely and environmentally sensitive manner. It would respond in part to the TEA-21 chapter on flexibility and streamlining, which addresses major investment study integration (section 1308) and contains the provisions on environmental streamlining (section 1309).

Section 1420.201 Relation of Planning and Project Development Processes

This section would clarify the relationship of the transportation

planning process and the project development process which is the subject of this NPRM. It reflects coordination with our concurrent proposed Metropolitan and Statewide Planning regulations; § 1420.318 of that proposed rule, and its preamble, provide further discussion of the relationship between the planning and project development processes. The section also stresses that the record of prior transportation planning activities, such as development of purpose and need and the systems-level evaluation of alternatives, shall be incorporated into the scoping or early coordination phases of an EIS or EA, respectively, in order to establish the alternatives to be advanced to the NEPA process.

Our agencies feel it is essential to clarify the nature of the linkage between planning and the NEPA process in this NPRM. The transportation planning process needs to be better coordinated with the project development/NEPA process so that transportation planning decisions can ultimately support the development of the individual projects which arise from transportation plans. During the TEA-21 outreach efforts, opinions varied over whether regulatory language or guidance should be used to integrate planning and programming activities, but most commenters agreed that the linkage between planning and project development needs to be cultivated. Many commenters, including the AASHTO and many State DOTs, opposed any regulatory language which would place requirements of NEPA into the planning process. Others, including the National Coalition to Defend NEPA, pointed to the need for the core values of the NEPA process to be incorporated into the planning process and suggested that regulatory language is in order.

The Options Paper discussed the notion that the establishment of purpose and need and the broad scale evaluation of alternatives can often be best accomplished during the planning process. How to frame the statement of purpose and need so that it is neither too narrow nor too broad is a continuing challenge. If too narrowly conceived, purpose and need can constrain the process with an unreasonably limited set of possible solutions; if too broadly constructed purpose and need may lead to an unmanageably large set of alternatives that unnecessarily bog down the process. Options to provide clearer direction regarding what constitutes an acceptable statement of purpose and need are being explored and we invite specific comments on this issue.

There was considerable support for allowing States and MPOs the option of addressing purpose and need in the planning process, and even to initiate the NEPA process at that time. This would allow stakeholders to conduct broad ranging planning and subregional studies, reach agreement on purpose and need during the planning process, and benefit from such analyses by using them directly in the NEPA process. There was also strong support for establishing a point during the NEPA process at which the participants would discuss and concur in a statement of purpose and need.

However, a considerable number of commenters, including many State DOTs and MPOs, objected to any mandate for the determination of purpose and need during planning and argued that it would burden the planning process and add considerable delay by seeking a determination of need at an inappropriate juncture.

The Surface Transportation Policy Project (STPP) recommended a two-stage NEPA process where the first phase would evaluate the range of social, fiscal, and environmental costs and benefits of various alternative visions for a corridor or community. Based on this evaluation, an initial statement of purpose and need would be articulated. This purpose and need statement would be very broad, an articulation of the goals for the area already arrived at through the planning process, for example. The STPP proposed that a wide field of inquiry would be maintained at this stage. Subsequent to this phase of evaluation, and once a detailed review of options is complete, an agency would have the information necessary to propose a revised, more specific statement of purpose and need. It would be this revised statement of purpose and need that would serve as the basis for a detailed review of alternatives under NEPA. Under both phases, the choice of a project purpose would be subject to public input.

The Environmental Law and Policy Center argued for the allowance of lower-cost and lesser impact project alternatives to be selected through the NEPA process even if they do not fully meet the stated purpose and need. Both the U.S. EPA and the U.S. Department of Interior argued for broadly defined purpose and need during planning to ensure that a full range of modal alternatives are considered.

The National Coalition to Defend NEPA expressed concern over the development of purpose and need during planning. It felt this could prematurely preclude options and alternatives and argued that, until the DEIS is completed, insufficient information is available with which to make such decisions. In short, it is concerned that defining purpose and need so early (in planning) could have the effect of “setting in stone” projects without adequate consideration of alternatives.

Commenters asked for examples, best practices and information on issues related to purpose and need determination, and there was general consensus that improvements in defining purpose and need are warranted. They felt that the difficulties articulated in the Options Paper relating to broad versus narrow statements of purpose and need are indeed real problems and that our agencies could provide useful guidance in this area.

We intend to provide continuity between the systems planning and project development processes so that the results of analysis performed during the planning stage, including project purpose and need, alternatives, public input, and environmental concerns are brought forward into project development. The proposed integration of the planning and project development process embodied in this regulation would enable a more broadly defined statement of purpose and need to be addressed at appropriate points in the integrated process.

There has also been much discussion of the standing given to planning decisions on alternatives to be advanced or dropped from consideration. The proposed regulation envisions an active discussion of this issue during scoping, with the involvement of the responsible planning agencies (
i.e.
, the MPO and/or the State DOT). Ultimately, the U.S. DOT agency, in cooperation with the applicant, must decide the range of alternatives to be evaluated in detail in the NEPA document. The proposed regulation allows these agencies to recognize planning decisions made with adequate supporting documentation. Though the form and content of this support will not be specified in the regulation, we expect to see some or all of the following offered in this context: technical studies as envisioned by proposed § 1420.318(b), documentation of public reviews and comments, formal policy board resolutions in the case of MPO actions, or other supporting materials. For proposed major transit investments, this review will also decide whether the documented planning activities constitute the Alternatives Analysis required by 49 U.S.C. 5309(e) or, alternatively, if the requirement must still be satisfied in the NEPA process.

We propose to provide more detailed treatment on the subjects of purpose and

need, and the development, analysis, and evaluation of alternatives in the comprehensive package of informational materials. This would include how to address alternatives which in the past have been rejected for not fully meeting traditional concepts of purpose and need. Further, we plan to showcase examples of successful practices which demonstrate how effective integration of planning and project development can protect communities and environmental resources and save time in providing needed transportation improvements.

Examples of issues that might be covered include: the further consideration of alternatives that may not fully meeting traditional concepts of purpose and need; more broadly defined purpose and need statements during the planning stage so that a full range of modal alternatives are considered; an alternative analysis that examines non-construction alternatives that use transportation demand strategies; and flexibility to encourage the consideration of alternatives which may have lower than originally desired levels of transportation service if there are cost, time, and impact savings that justify the lower levels of transportation service.

We are soliciting comments on a suggestion that specifically addressing the requirements of the major investment study in the planning process would enhance that process by forging a clearer link between the planning and the project-level NEPA processes, leading to greater streamlining at the project level.

Section 1420.203 Environmental Streamlining

This new section would be added to reflect the requirements of section 1309 of the TEA-21. The basic premise of section 1309 of the TEA-21 was to address concerns relating to delays, unnecessary duplication of efforts and costs associated with the development of highway and transit projects. Section 1309 also stipulates that nothing in section 1309 shall affect the applicability of NEPA or any other federal environmental statute or affect the responsibility of any federal offices to comply with or enforce such statutes. The rule responds to the TEA-21 environmental streamlining provisions by establishing a process intended to coordinate Federal agency involvement in major highway and transit projects with the goals of identifying decision points and potential conflicts as early as possible, integrating the NEPA process as early as possible, encouraging the full and early participation of all relevant agencies, and establishing coordinated time schedules for agencies to act on a project.

This proposed section of the regulation establishes the “coordinated environmental review process” which section 1309 of the TEA-21 directed the Secretary of Transportation to develop and implement. Paragraph (a) lays out the elements of this coordinated environmental review process, providing a substantive but flexible set of actions to be taken by the U.S. DOT in cooperation with the applicant to ensure that the goals of section 1309 are met. An important element of this coordinated environmental review process is reaching closure among the Federal agencies on the scoping process. This paragraph calls for agency concurrence at the end of scoping, which could take various forms depending upon the mutual understandings and agreements of the Federal agencies. In the event of nonconcurrence, this paragraph provides also for means to resolve interagency disagreements at the earliest possible time. Paragraph (b) describes the process for applying the coordinated environmental review process to State level environmental reviews. Paragraph (c) would implement the provisions of the statute which allow the Secretary to decide not to apply section 1309 to the preparation of an environmental assessment. Paragraph (d) would implement the CEQ NEPA regulation provisions on paperwork reduction and clarifies that the NEPA documentation need not explicitly contain a finding that a particular impact does not exist. For example, if the environmental inventory revealed that there were no wetlands in the project area, a specific finding indicating that the project would have no impacts on wetlands would not be required. This provision would help to focus NEPA documents on important issues in accordance with the CEQ NEPA regulations' provision on paperwork reduction.

One consistent theme that emerged through the outreach process pointed to the need for early and up-front involvement of Federal agencies in the NEPA process and for close coordination and cooperation among the Federal agencies throughout the process. The State DOTs, the MPOs, the National Association of County Engineers, the U.S. EPA, and the U.S. Department of Interior all felt that Federal agency involvement is critical to successful implementation of the environmental streamlining provisions. They also recommend that our field offices and the resource agencies' field offices throughout the country have the authority to participate in, review, and respond to issues associated with the NEPA process.

Inasmuch as stakeholder sentiments echoed a need for early collaboration and close coordination with all interested and affected parties, they also strongly reinforced the need for flexibility at the State and local levels for implementing the goals of streamlining. A “one-size-fits-all” regulatory approach was soundly rejected by an overwhelming majority of stakeholders, other Federal agencies, practitioners, project sponsors, and field offices.

We believe that successful implementation of environmental streamlining must be based upon a number of principles, and are pursuing a process that will ensure effective environmental decisionmaking in a timely manner. Both transportation and resource agencies must improve their environmental review processes. The U.S. DOT will provide national leadership on environmental streamlining, and is working with CEQ and headquarters offices of the EPA, the U.S. Army Corps of Engineers, the U.S. Fish and Wildlife Service, the U.S. National Park Service, the U.S. National Oceanic and Atmospheric Administration, the Advisory Council on Historic Preservation and others to obtain commitments to better decisionmaking. The framework for this commitment to the environment and to streamlining the environmental process is set forth in the national Memorandum of Understanding (MOU) which was entered into by the aforementioned agencies in July 1999.
4

We fully expect to track the commitments reflected in the national MOU. We recognize that tangible progress will evolve locally, and State by State, at different rates, based largely on good working relationships and trust established among the agencies at the field office level.

4
This Memorandum of Understanding is available electronically from FHWA's website at
http://www.fhwa.dot.gov/environment/strming.htm.

We are proposing to implement the environmental streamlining requirements largely outside of the regulatory process through the following means: (1) U.S. DOT memoranda of understanding with Federal or State agencies; (2) establishment of dispute resolution processes; (3) streamlining pilot efforts; (4) authorization of the U.S. DOT to approve State DOT or transit agency requests to reimburse Federal agencies for expenses associated with meeting expedited time frames; and (5) establishing performance measures to evaluate and measure success in both

environmental stewardship and environmental streamlining. We have established an environmental streamlining page on the FHWA website to keep the public up to date on our ongoing activities and resources (http://www.fhwa.dot.gov/environment/strming.htm). We are also providing a detailed description of our work to date on the following:

(1) National MOU

The central effort on the national MOU has been to craft an agreement among agencies which demonstrates a commitment to key principles and upon which further agreements can be executed at a local or regional level to address more specific issues. Establishing and maintaining clear and frank communication has been at the heart of the national MOU and would be the primary guide to further interagency agreements.

The process of developing the national MOU was aimed chiefly at responding to the concerns regarding early and up-front involvement of Federal agencies in the NEPA process and for close coordination and cooperation between Federal agencies throughout the process. We are working with representatives of other Federal agencies at the headquarters and field levels to develop a common understanding of the environmental streamlining provision and a coordinated implementation strategy. The development of the national MOU has followed the suggestion of AASHTO, Association of Metropolitan Planning Organizations (AMPO), and many State DOTs that the MOU include broad principles of agreement on how the NEPA process would be carried out but that project-specific or program-specific MOU's need to be developed at the State, regional, or local level, based upon these broad principles, and tailored to specific local circumstances or projects.

(2) Dispute Resolution Procedures

Procedures for resolving conflict at the national, regional, and State levels are under development. Mediation methods and systems for alternative dispute resolution are being developed and training programs in these methods will be established. This approach will enable parties to seek timely intervention over disputes during the project development process, as a way to circumvent and minimize the number of environmentally unacceptable projects that may otherwise be referred to CEQ for resolution, by either reestablishing consensus on the need for the project or reaching consensus to drop the project entirely. Alternative dispute resolution strategies will be defined so that they can be effectively applied to improve institutional relationships among parties or to resolve conflicts surrounding specific project issues.

On the matter of dispute resolution procedures, commenters made three key points. They felt that explicit time frames for document reviews are needed and should be agreed to, to the fullest extent possible, up-front in the process. Secondly, they supported an approach where the parties to the MOU agree, at an early stage, on the level of information and detail that is needed at various steps in the NEPA process. Resource agencies expressed frustration with the timing and level of detail of information that they are asked to consider and act upon, and State and local implementing agencies expressed frustration due to uncertainties over what specific information and level of detail would be required of them by the Federal resource, regulatory and permitting agencies. A third point made by many stakeholders was that procedures on coordination, documentation, and communications should be agreed to as early as possible. They felt that this would help to resolve differences that arise at various points in the process and which can contribute to delays.

(3) Pilot Efforts Are One Effective Mechanism for Testing and Evaluating Change

One specific topic suggested for pilot projects was from the North Carolina DOT and the American Road and Transportation Builders Association, which suggested the testing of alternative approaches to gaining interagency cooperation during the NEPA process. The Virginia DOT suggested that pilot project efforts should be directed at finding ways to resolve differences between Federal agencies. A third suggestion was that pilot projects should test approaches to providing States flexibility in carrying out the NEPA process.

Not all commenters supported the concept of pilot projects, however, and the National Coalition to Defend NEPA questions the legal authority of our agencies to conduct pilot projects and cautioned against using pilot projects to “back-door” the NEPA process. It was also concerned that pilot efforts not only involve partnership development between Federal and non-Federal partners and resource permitting agencies, but also include groups representing the public as well.

Based on the input received on the issue of pilot efforts, we are not proposing to establish a formal process for pilots at this time, through regulation or any other means. Instead, we will participate in pilot efforts on a case-by-case basis. These pilot efforts might be focused on a single project or on improving a particular process, but would not include the delegation of Federal NEPA responsibilities to States that was considered but not enacted in the TEA-21. We will continue to coordinate closely with the U.S. EPA, the AASHTO and others who are developing pilot efforts, and will actively assist in sharing information on efforts including lessons learned.

(4) Use of Titles 23 and 49, U.S.C., Funds To Pay for Environmental Agency Work

The agency reimbursement language in the environmental streamlining provisions of the TEA-21 offers an opportunity to partially overcome an historic obstacle, that Federal agencies cannot involve themselves in the process early enough or regularly enough due to resource constraints within agencies. The TEA-21 includes specific conditions allowing States and transit agencies to use Federal transportation funds for reimbursement of expenses related to work done to meet the expedited time schedules required by section 1309 of the TEA-21. In addition, other statutory authorities exist for agency reimbursement, and we are exploring the full range of options for reimbursing agencies through any of the available authorities. Furthermore, approaches to developing collaborative efforts with other Federal agencies are being explored in order to develop model reimbursement agreements, and to facilitate the implementation of such agreements by Federal agency field staff.

Due to the need for flexibility and the different practices and needs of various State and resource agencies, it was determined that nonregulatory guidance would most appropriately address the use of Federal transportation funds for reimbursing costs associated with streamlining. Hence, we engaged participation by many other affected Federal agencies to develop a single guidance package that would be useful to transportation and environmental agencies, including State DOT's and transit agencies and Federal, State, and local resource agencies. The breadth of situations that might be addressed under this provision was such that the guidance does not try to anticipate them all. Rather, it reinforces the Federal government's belief in effective interagency coordination and

demonstrates a commitment from Headquarters offices to support field efforts in implementing this provision of the TEA-21.

There were a number of comments on this TEA-21 provision and a suggestion from the American Road and Transportation Builders Association that the principles to apply to reimbursement should include a provision that reimbursement for Federal agency activities to expedite NEPA reviews must be linked to a specific project, set of tasks, and person or position to be involved on behalf of the Federal agency. Others, including the Nevada and Missouri DOTs, felt that reimbursing an agency for working on one project over another is not a good approach. Reimbursing agencies for doing their jobs, it was argued, would introduce a bias into the NEPA process which would result in an expedited review or enhanced level of participation on some projects over others.

(5) Performance Measures

Our agencies have a joint effort underway to evaluate the timeliness and the effectiveness of the NEPA process at arriving at decisions that are in the best overall public interest. Further information on this effort can be obtained from the FHWA.

Section 1420.205 Programmatic Approvals

Section 1420.205 would be added to establish in regulation the FHWA/FTA practice of using programmatic environmental approvals as one way of addressing recurring situations in a streamlined manner.

This practice has been especially effective with categorical exclusions for meeting the NEPA requirements in uncomplicated and non-controversial situations. One example of this are programmatic categorical exclusion approvals in which FHWA and a State DOT established a set of environmental impact thresholds, which, if not exceeded, allow the State DOT to apply the categorical exclusion approval without a project specific review by FHWA. Periodically, the FHWA reviews a sample of projects after-the-fact to ensure that the approval was appropriately applied. Other examples of programmatic approvals include section 4(f) approvals for minor uses of parkland and approval to delegate certain USDOT responsibilities under the recently issued regulations implementing section 106 of the National Historic Preservation Act. The proposed section explicitly recognizes the appropriateness of programmatic approaches for compliance with NEPA and related statutes, but does not specify the types of actions for which programmatic approaches would be created. Programmatic approaches to meeting the NEPA requirements which would not directly involve project level Federal approvals would be subject to periodic process reviews to ensure that they are being properly applied. This would enable the Federal agencies to focus limited resources on more problematic project-level decisions and to maintain a quality assurance role for projects with beneficial or de minimis environmental impacts. There was general support for such an approach in comments on the Options Paper. We invite comments on public notice and interagency coordination processes appropriate for making programmatic approvals.

Section 1420.207 Quality Assurance Process

This new proposed section would establish an internal responsibility for our agencies to employ appropriate quality management methods to assure that the NEPA responsibilities are carried out in a competent and timely manner. Such a process is intended to streamline the process by institutionalizing lessons learned throughout the administration of our programs and NEPA so that mistakes are not repeated and innovative approaches are fully implemented.

The requirements in the current regulation for legal sufficiency review of Final Environmental Impact Statements (FEIS) and prior concurrence of the Headquarters on certain FEISs would be incorporated into this proposed section. These processes have proven helpful in assuring the quality of analysis, coordination, and documentation and can prevent costly and timely lawsuits and conflicts. As proposed, the nature of legal sufficiency review and the threshold for requiring prior concurrence at Headquarters would not be specified in regulation, but would be the subject of internal orders.

Section 1420.209 Alternate Procedures

This new section would be added to establish the procedures for processing and approving alternate procedures for complying with this regulation. This would give us the flexibility to partner with CEQ and State DOTs or transit agencies on NEPA reinvention efforts that achieve the goals of the NEPA process by using alternate methods or procedures that are more in tune with and supportive of non-Federal decisionmaking requirements.

Section 1420.211 Use of This Part by Other U.S. DOT Agencies

In 1993, the U.S. DOT National Performance Review effort recommended that the NEPA procedures of the various modes be blended into a single process. Efforts to accomplish this unified procedure were purposely delayed until after passage of the surface transportation reauthorization which became TEA-21. Recent discussions within the U.S. DOT are now pointing toward a dual effort, one element of which would cover the entire department, the other of which is this proposed regulation covering just the FHWA and the FTA. To advance the first element, U.S. DOT would revise the U.S. DOT Order on NEPA to update the departmentwide statement of environmental policy and to remove barriers to collaboration between the U.S. DOT modes on NEPA issues. It would provide authority for one U.S. DOT agency to use the NEPA procedures of another U.S. DOT agency or to act as the agent for another U.S. DOT agency when a situation warrants. This proposed section clarifies in regulation that the internal order is considered legally sufficient to provide these authorities. The further action at the departmental level to amend the U.S. DOT Order on NEPA is under development.

Most Options Paper commenters, including State DOTs, MPOs, associations, and authorities supported a coordinated approach to NEPA within the U.S. DOT and its modal administrations. There was strong support for the elimination of differences in how the FHWA and the FTA manage the NEPA process and for a consolidation of these approaches in the updated regulation. In addition, there was strong support from New York DOT, the American Road and Transportation Builders Association and others for the elimination of provisions duplicating the CEQ regulations, which many thought would lead to a streamlined regulation. Finally, many commenters supported the notion of the FHWA and the FTA having strong oversight over the NEPA process. Equally important, commenters noted, is that there be a true partnership between Federal agencies and State and local agencies.

Section 1420.213 Emergency Action Procedures

This proposed section would contain the provision currently found at 23 CFR 771.131.

Subpart C—Process and Documentation Requirements

This proposed subpart describes the requirements of carrying out the NEPA process, including establishing the roles of various governmental agencies and the public in the process, determining the appropriate level of environmental documentation under NEPA, and laying out the procedural requirements for processing NEPA documents. It complements and supplements the CEQ regulations that provide the general NEPA framework for the entire Federal government. In addition to the regulatory requirements described in this subpart, the FHWA's and FTA's comprehensive package of informational materials will provide detailed nonregulatory approaches to many of the subjects herein.

Section 1420.301 Responsibilities of the Participating Parties

This is a new section that addresses some of the items currently contained within § 771.109. Paragraph (a) of the proposed section utilizes the current CEQ regulations (40 CFR 1500-1508) to define terms and set forth concepts, such as: Lead and cooperating agencies; the relationship between Federal agencies, applicants, and contractors; and enhancing the efficiency of the NEPA process through cooperation between Federal, State, and local agencies.

Paragraph (b) would clarify in regulation current practice for administering the NEPA process for projects implemented directly by the Federal government on Federal lands. Namely, it is a shared responsibility of the U.S. DOT and the Federal land management agency. The precise nature of the responsibility is specified in agreements or standard operating procedures.

In the previous regulations, the provision in 23 CFR 771.109(c) on agency responsibilities is largely repetitive of what is also found in CEQ's regulations on NEPA. For this rulemaking effort, we are reluctant to propose regulatory language which simply restates existing sections of another regulation, and would streamline this section accordingly. Paragraph (c) of the proposed section addresses the use of contractors in the NEPA process for contracting for environmental and engineering services. The proposed rule allows a State to procure the services of a consultant, under a single contract, for environmental impact assessment and for subsequent post-NEPA engineering and design work in accordance with the provisions of 23 U.S.C. 112(g), as amended by the TEA-21.

Section 1205 of the TEA-21 allows a State to procure under a single contract, the services of a consultant to prepare environmental documents for a project, and to perform subsequent final engineering and design work on the project. This would only occur if the State conducted a review assessing the objectivity of the environmental documentation. Experience has shown that, although on many projects consultants do prepare the bulk of the detailed analyses and NEPA documentation, this process involves close oversight by the State or local public agency and by the lead Federal agency. It is the ongoing responsibility of our agencies to ensure that all consultant work reflected in the NEPA process and documentation meets appropriate standards of objectivity and professionalism.

The contracting provisions were included in the TEA-21 to clarify our agencies' positions on the use of contractors for environmental and engineering design work for Federal transportation projects, and were chiefly aimed at addressing concerns of potential conflict of interest on the part of the consultants.

The U.S. DOT believes that more detailed nonregulatory guidance will best address the specifics of disclosure statements, other requirements of 40 CFR 1505.5(c), and the requirement for a review of the objectivity of the environmental document.

Generally speaking, commenters on the Options Paper felt that current level of oversight and review is sufficient, and that additional documentation to ensure objectivity is unnecessary. The EPA suggested the need for the development of Federal procedures for monitoring, investigating, and resolving conflicts that might result from this TEA-21 provision.

Section 1420.303 Interagency Coordination

The proposed section would revise the current § 771.111 (a) through (e). The proposed section would simplify the current section by focusing on key terms and concepts that are the basis of an integrated decisionmaking process conducted under the NEPA umbrella. For example, the proposed section features the term “interagency coordination” to supplement the current “early coordination” in order to better express the collaborative intent of the FHWA/FTA NEPA process. The proposed section provides an explanation of the role and function of interagency coordination in the NEPA process. The term “interested agencies” would be added. The proposed section briefly outlines a procedure for notifying affected Federal, State, and local entities of the availability of approved documents for classes of action other than an EIS.

Scoping and early coordination can set the tone, positive or negative, for subsequent project development activities. Experience has shown that many of the conflicts which delay Federal approvals of highway and transit projects are somewhat predictable, and might be better anticipated and managed by using the scoping process as an early warning system. In addition, the development of interest-based negotiating and collaborative problem solving skills can help to craft implementable solutions. Two possible solutions emerged through the outreach process that could assist Federal agencies and applicants in performing more effective project scoping. One approach to the scoping of complex projects is that agencies agree on review schedules, but only after sufficient information on issues has emerged to allow them to gauge the required level of effort for their respective agencies. Another approach might make the scoping process, as part of an aggressive, high visibility project management role by our agencies as the lead Federal agenc(ies), a mechanism for identifying the issues, and agreeing on roles, time frames and methodologies associated with advancing the project, and possibly memorializing that agreement in a project MOU.

Both program reviews and feedback from stakeholders indicate that the FHWA and the FTA need to take a stronger leadership role in the NEPA process. Commenters including the National Coalition to Defend NEPA, the AASHTO, the American Road and Transportation Builders Association, and others reinforced this point in their comments on the Options Paper. These groups said that the FHWA and the FTA staff should attend meetings and serve as conflict resolution agents and mediators between other agencies. Also, they told us that we should provide information, such as, handbooks, best practices on scoping, and training for practitioners. As was the case in many areas, stakeholders including MPOs, State DOTs and others feel that much progress can be made in better integrating environmental and other considerations into the planning process through training, examples of where new approaches are working, handbooks and other useful materials.

Many of the detailed considerations of the scoping process are outside the

scope of this proposed rule, and will be addressed separately. Effective project scoping and interagency coordination is a chief topic of our environmental streamlining efforts, and will be given more detailed treatment in the comprehensive package of informational materials to be issued in conjunction with the final rule. Scoping may also be the subject of further guidance on its own. We will make full use of input received through the outreach efforts, as well as through our ongoing coordination with transportation and environmental agencies, in the development of this additional guidance.

Section 1420.305 Public Involvement

Current § 771.111(h) would be redesignated as § 1420.305. It remains relatively unchanged for State DOTs except that the separate requirements specific to the FHWA and the FTA programs would be deleted; and new references specific to public involvement procedures, notification requirements, and accommodations for those with disabilities would be added. A requirement would be added to specifically ascertain if public involvement is warranted whenever a reevaluation is being conducted. Also a minimum 45-day public comment period would be established whenever public involvement procedures are initially adopted or revised.

The proposed rule also aims to consolidate requirements of our two agencies for public involvement so that the U.S. DOT can offer a more consistent approach on this subject. Based upon comments to the Options Paper, there was resounding support for a consistent approach to public involvement requirements between the FHWA and the FTA and this was cited by the National Coalition to Defend NEPA as one way to make the planning process more accessible and understandable to the public. This consolidation may mean that some transit agencies may have to formalize their public involvement procedures through board adoption, or revise their procedures to ensure their applicability to the NEPA process. The FTA does not expect to find many transit agencies without existing adopted procedures applicable to project development, but invites comment on this concern. We recognize the importance of public involvement to informed decisionmaking, and have issued a number of publications which provide nonregulatory guidance on how to increase the effectiveness of applicants' public involvement efforts.

The new § 1420.305(d) recognizes the need for public involvement on certain re-evaluations where the elapsed time may have altered public expectations.

Section 1420.307 Project Development and Timing of Activities

Current § 771.113 would be redesignated as § 1420.307 and revised. The proposed section would clarify the circumstances in which the FHWA/FTA would not approve initiation and funding for certain activities, such as, final design activities. The proposed section would encourage compliance with the requirements of all applicable environmental laws, regulations, executive orders, and other related requirements be demonstrated prior to approval of the final environmental documents or categorical exclusion (CE) designation. Conditions under which agencies responsible for metropolitan and statewide planning would be notified in order to satisfy the planning and programming requirements of proposed 23 CFR part 1410 would be identified.

However, under the NPRM the FHWA and the FTA would not prevent State and local governments and private entities from taking certain actions that are “at risk” of being rendered useless by the final NEPA decision. Such actions include final design or land acquisition prior to NEPA approval, but do not include those that would have an adverse impact, such as, demolition or construction. The FHWA and the FTA would view at risk activities that actually substantially harm environment as so subverting the NEPA process that we would inform applicants that the action would be ineligible for FHWA or FTA financial assistance. The FHWA and the FTA would not finance such “at risk” actions, and would not allow their decisions to be influenced by the actions taken by others. For projects that will be federally-funded, the present regulation prohibits final design and land acquisition (with certain limited exceptions) prior to the completion of the NEPA process. The enforcement of this prohibition has been confounded by the fact that specific funding sources, especially for smaller projects, are often not identified until late in project development. Hence, the applicability of the Federal requirements that attach only to Federal funding sources is not yet determined at the time the “at risk” activities are initiated.

We are considering issuing guidance on how to handle such situations, especially in terms of disclosure responsibilities.

We propose to clarify that full compliance with the transportation conformity rule (40 CFR parts 51 and 93) is required prior to the

approval of the final EIS, FONSI or CE
5

designation.

As a result, this proposal would allow preliminary engineering for project development activities to be done prior to final NEPA approval without having to meet conformity requirements. We request public comment on our proposed clarification.

5
Environmental Impact Statement (EIS), Finding of No Significant Impact (FONSI), categorical exclusion (CE).

We believe that this proposed change is allowed under current regulations. While the conformity rule requires that a project come from a conforming plan and transportation improvement program (TIP) before final NEPA approval, the rule does not explicitly specify that the project must be in a conforming plan and TIP in order to initiate the NEPA process. In fact, 40 CFR 93.126, table 2, identifies as exempt, “engineering to assess social, economic, and environmental effects of the proposed alternatives to that action.” We feel that this is an important distinction that may help to improve the quality of the NEPA process leading to more effective, efficient, and environmentally sound judgments, without compromising the planning process and air quality analysis.

We believe that the emissions impacts of the project should be considered as early as possible and continue to encourage the inclusion of projects in the plan and TIP conformity analysis as early as feasible prior to the completion of the NEPA process where it is feasible. Earlier inclusion of the project in the plan and TIP is beneficial for the overall development of the plan and TIP because regional analysis is used as a long term indicator of the area's emissions impacts and associated problems. Early analysis of projects in the plan and TIP allows a more comprehensive long term assessment of how emissions impacts can be minimized, whether through changes in the timing of projects or changes to the composition of the plan and TIP.

However, a major problem with this approach is that it is counterproductive to corridor planning, prejudges alternatives and can limit thorough exploration of all feasible alternatives throughout the project development process. It can be counterproductive to, rather than supportive of, good long term transportation systems planning in certain circumstances. The reason for this is that in order for a project to be included in the regional plan and TIP and regional analysis prior to

completion of NEPA, certain assumptions must be made about the project and related emissions impacts. It is difficult to define project design concept and scope that early in the planning process, especially for those projects requiring the highest level of environmental review and scrutiny. When taking complex projects through the project development process, it is very difficult to simply define two points of connection to the network, the number of lanes and facility type (that which is needed for regional analysis). Complex projects and corridor projects often examine multimodal options, some of which are not fully developed until later in the NEPA process. Under this scenario, the assumptions for regional analysis for conformity purposes may encourage an overly narrow alternatives analysis and constrain the environmental review process. We request comment on whether similar experiences have occurred in practice when accounting for preliminary engineering for project development in regional conformity analyses.

It is important to note that, under this proposal, preliminary development of new projects could proceed during a conformity lapse, since such activities would not need to meet conformity requirements. However, final NEPA documents on new projects could not be approved under this proposal until a new conforming plan and TIP are in place.

We believe the frequency requirements for conformity are sufficient to ensure that full emissions impacts of the projects are accounted for before projects move into the final design; therefore, long term risks are minimal and the projects must be included in the regional conformity emissions analysis prior to the completion of NEPA. The regional emissions analysis and conformity determinations can be made as frequently as once a year, but at a minimum at least every three years; therefore, it is reasonable to allow environmental reviews and the NEPA process to be initiated without the project being included in the conformity analysis.

Section 1420.309 Classes of Actions

Current § 771.115 would be redesignated as § 1420.309 and the text would remain the same, except for the addition of certain intercity railroad and intermodal actions.

Section 1420.311 Categorical Exclusions

The proposed § 1430.311 would make several changes from the list of CEs in the current § 771.117 to reflect changes in the FHWA and the FTA programs since 1987. Modal limitations would be eliminated wherever possible. In addition, the CEs would be reordered and regrouped so that similar actions are listed together. The CEs would continue to be organized into two major groupings: those in paragraph (c) that require no further U.S. DOT agency approval, and those in paragraph (d) that require a written demonstration that the CE is appropriate. Paragraph (c) would clarify the need for NEPA approval by the U.S. DOT agency for listed CEs to which other environmental laws (
e.g.
, section 106 of the National Historic Preservation Act) apply.

The proposed changes in CEs in paragraph (c) would be as follows:

Paragraph (c)(1) (non-construction activities) would incorporate the text of current § 771.117(c)(1), (c)(20), and part of (c)(16) without substantive change. It would add designations to the National Highway System to the list.

Paragraph (c)(2) (resurfacing) would move part of the text of current § 771.117(d)(1) to paragraph (c). Experience has shown that simple resurfacing of an existing pavement does not require additional written information for a CE determination.

Paragraph (c)(3) (routine maintenance) is not explicitly covered in the current § 771.117, but it is an important program activity, especially for transit with the re-definition of preventive maintenance as a capital expense.

Paragraph (c)(4) (ITS elements) is not explicitly covered in the text of current § 771.117. Installation of isolated ITS elements is proposed for paragraph (c), but an areawide coordination of multiple ITS elements that would have greater impact on the transportation system is proposed for paragraph (d)(2).

Paragraph (c)(5) (safety programs) would incorporate the text of current § 771.117(c)(4) and would add a current CE of the Federal Railroad Administration related to safety.

Paragraph (c)(6) (support facility improvements) would incorporate the current § 771.117(c)(12), but would extend it to cover toll facilities, control centers, and vehicle test centers, facilities that are similar in size and activity to those in the current CE.

Paragraph (c)(7) (carpool programs) uses a defined term to incorporate the text of current § 771.117(c)(13) except that carpool activities requiring land acquisition and construction (such as new parking lots) would be excluded and covered in paragraph (d)(6).

Paragraph (c)(8) (emergency repairs) would incorporate the text of current § 771.117(c)(9), but extends it to cover modes other than highways.

Paragraph (c)(9) (operating assistance) would incorporate the second part of the text of current § 771.117(c)(16) without substantive change.

Paragraph (c)(10) (vehicle acquisition) would incorporate the text of current § 771.117(c)(17) without substantive change.

Paragraph (c)(11) (purchase and lease of equipment) would incorporate the text of current § 771.117(c)(19), but would extend it to cover leases and the capital cost of contracting for transit services.

Paragraph (c)(12) (vehicle rehabilitation) would incorporate the current § 771.117(c)(14), but would extend it to cover conversions to alternative fuels.

Paragraph (c)(13) (track maintenance) would incorporate the text of current § 771.117(c)(18), but would extend it to cover wayside systems in addition to tracks and railbeds.

Paragraph (c)(14) (bicycle-pedestrian facilities) would incorporate the text of current § 771.117(c)(3) except that bicycle and pedestrian projects requiring land acquisition and construction (such as bike paths on new right-of-way) would be excluded and covered in paragraph (d)(19).

Paragraph (c)(15) (ADA accessibility) would incorporate the text of current § 771.117(c)(15) without substantive change.

Paragraph (c)(16) (signing, etc.) would incorporate the text of current § 771.117(c)(8) without substantive change.

Paragraph (c)(17) (property management) would incorporate the text of current § 771.117(c)(2), (5), and (11), and similar property management activities under the transit program. In addition, disposal of excess property would be moved from § 771.117(d)(6) because experience has shown that the sale or transfer of property does not have significant impact in and of itself, and the U.S. DOT agency does not have the statutory authority to control the subsequent use of property after it has been sold by the applicant.

Paragraph (c)(18) (transportation enhancements) would incorporate the text of current § 771.117(c)(7) and (10), and would add other transportation enhancement activities and transit enhancements to the list.

Paragraph (c)(19) (noise walls) would incorporate the current § 771.117(c)(6) without substantive change.

Paragraph (c)(20) (mitigation banking) would be added due to the transportation enhancement provisions and changes in the mitigation policies of Federal resource agencies that allow or encourage this form of mitigation.

The proposed changes in CEs in paragraph (d) would be as follows:

Paragraph (d)(1) (highway rehabilitation) would incorporate the text of current § 771.117(d)(1) except that simple resurfacing is now proposed to be moved to paragraph (c) and would not require a written CE demonstration.

Paragraph (d)(2) (operational improvements) would incorporate part of the text of current § 771.117(d)(2), with clarification through examples of the ITS systems that would be covered.

Paragraph (d)(3) (safety improvements) would incorporate parts of the text of current § 771.117(d)(2) and (3) without substantive change. It would add safety-related programs of recent importance including seismic retrofit and mitigation of wildlife hazards.

Paragraph (d)(4) (bridge rehabilitation) would incorporate part of the text of current § 771.117(d)(3) with the clarification that the approaches to the bridge or tunnel would also be included in the project and that historic bridges and bridges providing access to ecologically sensitive areas are excluded.

Paragraph (d)(5) (bridge replacement) would incorporate the remaining part of the text of current § 771.117(d)(3). If applicable, “section 106” (National Historic Preservation Act (16 U.S.C. 470
et seq.
)), “4(f)” (49 U.S.C. 303), “section 404” (Federal Water Pollution Control Act, as amended (33 U.S.C. 1251 to 1376)) and coastal zone management issues must be addressed in the CE documentation and coordinated with the other agencies in accordance with those statutes.

Paragraph (d)(6) (parking facilities) would incorporate activities from the current § 771.117(c)(13) and (d)(4), but would apply to all parking facilities, not just those on transportation fringes, if the CE conditions are met.

Paragraph (d)(7) (new operations centers) would be added as a CE primarily covering the construction of buildings to house the control centers from which ITS systems are operated and managed.

Paragraph (d)(8) (support facility construction) would incorporate the text of current § 771.117(d)(5) with the addition of other similarly sized support facilities.

Paragraph (d)(9) (access control) would incorporate the text of current § 771.117(d)(7) without substantive change.

Paragraph (d)(10) (track improvements) would incorporate the text of current § 771.117(c)(18) in situations where land acquisition is needed.

Paragraph (d)(11) (storage yards and shops) would incorporate the text of current § 771.117(d)(8) and (11) without substantive change.

Paragraph (d)(12) (building renovation) would incorporate the text of current § 771.117(d)(9) without substantive change.

Paragraph (d)(13) (transfer facilities) would incorporate the text of current § 771.117(d)(10) without substantive change.

Paragraph (d)(14) (ferry facilities) would be added as an explicit statement that work on existing ferry facilities may be a CE, but concern for water-related impacts necessitates its inclusion in paragraph (d) so that a written CE demonstration must be provided.

Paragraph (d)(15) (rail service demonstrations) would be added as a CE, based on our experience with previous similar cases. If the service demonstration were to lead to proposal for permanent service involving Federal financial support, that permanent project would be separately evaluated for its impacts.

Paragraph (d)(16) (advance land acquisition) would have three parts to it as follows:

(1) Paragraph (d)(16)(i) would allow the acquisition primarily of underutilized private railroad rights-of-way (ROW). It reflects current FTA practice where present or recent rail operations on the ROW ensure that adjacent land uses remain generally compatible with the continued transportation use of the ROW;

(2) Paragraph (d)(16)(ii) would respond to the provisions of the TEA-21 section 1301 without attempting to elaborate on those provisions. Such elaboration would be covered in separate guidance on the issue of advance land acquisition; and,

(3) Paragraph (d)(16)(iii) would incorporate the text of current § 771.117(d)(12) covering hardship and protective acquisitions, without substantive change.

Paragraph (d)(17) (joint development) would incorporate part of the text of current § 771.117(d)(6) without substantive change.

Paragraph (d)(18) (bicycle facilities) would incorporate activities covered in the text of current § 771.117(c)(3). With this change, bicycle projects involving land acquisition and construction would require a written CE demonstration.

Paragraph (d)(19) (storm water management) would add a new CE that covers a transportation enhancement activity that may involve land acquisition and construction of storm water detention or retention ponds. It is, therefore, proposed to be included in the list where a CE demonstration is required.

Paragraph (d)(20) (historic transportation facilities) would add a new CE that covers a transportation enhancement activity that will have section 106 (historic preservation) implications. It is, therefore, proposed to be included in the list where a CE demonstration is required.

Paragraph (d)(21) (other transportation enhancements) would add a new CE that covers the other transportation enhancement activities and transit enhancements that are not explicitly listed.

We propose additional, nonregulatory guidance on situations where a group of different, but related, categorically excluded actions may need to be evaluated as a whole if they have a net effect that warrants further environmental analysis (e.g., ITS projects throughout a corridor).

Some commenters including the Michigan DOT, the AASHTO and others requested that advance right-of-way acquisition be added to the categorical exclusion list. The U.S. EPA was concerned about coordinating any expansions of the list with other Federal agencies and was particularly concerned about wetlands mitigation needs. The Ohio DOT suggested that rather than expand the list of categorical exclusions, our agencies develop “thresholds of significance” whereby projects within those thresholds would be those considered for categorical exclusions. Finally, a number of commenters, including the Ventura County Transportation Commission, the ARTBA, and the Oregon DOT supported the categorical exclusion of transportation enhancement activities and suggested categorically excluding congestion mitigation and air quality program (CMAQ) eligible projects. We have considered these comments in devising the proposed list. Nevertheless, we invite comment on these suggestions and on the appropriateness of the activities proposed to be categorically excluded, including whether or not specific activities should be included in the list under paragraph (c) or the list under paragraph (d). We encourage commenters to provide examples or information drawn from their

experience bearing on the appropriateness of the proposed categorical exclusions. We also invite comments on the practice, begun with the 1987 regulation, of using an open-ended list of examples of activities that can be categorically excluded only after appropriate documentation has been prepared and approved on a case-by-case basis by the USDOT agency.

Section 1420.313 Environmental Assessments

Current § 771.119 would be redesignated as § 1420.313 with some minor editing changes.

Section 1420.315 Findings of No Significant Impact

Current § 771.121 would be redesignated as § 1420.121 with minor editing changes.

Section 1420.317 Draft Environmental Impact Statements

The proposed section would revise the current § 771.123 by expanding the description of both public involvement procedures and the information products developed in accordance to the proposed 23 CFR part 1410. Paragraph (b) would specifically indicate that the scoping process must consider the results of the planning process including public involvement and interagency coordination. Items related to mitigation would be expanded to include environmental enhancements. Paragraph (b) would now emphasize public involvement and interagency coordination. Paragraph (c) would add language to our goals and policies in terms of implementing NEPA. The discussion on the use of consultants in the development of the draft EIS would be removed to avoid repetition with proposed § 1420.301.

Section 1420.319 Final Environmental Impact Statements

Current § 771.125 would be redesignated as § 1420.319. Information would be added in paragraph (a)(1) to require any additional environmental studies, public involvement, and/or coordination to consider refinements of alternatives and mitigation to be presented in the FEIS.

Section 1420.321 Record of Decision

Current § 771.127 would be redesignated as § 1420.321. In paragraph (a), the information about preparation of the notice of availability would be expanded to indicate where and to whom the notice should be provided. In paragraph (c), wording would be added to emphasize that mitigation and enhancement features associated with the selected alternative become enforceable conditions of any U.S. DOT actions.

Section 1420.323 Re-evaluations

Current § 771.129 would be redesignated as § 1420.323. Paragraphs (a) through (c) are essentially unchanged from the current regulation. Paragraph (d) has been added to ensure public involvement and interagency coordination when the situation warrants. Guidance will be provided on this subject. We invite comment on how effective the proposed reevaluation provision would be in addressing projects which are implemented over an extended period of time, with construction occurring under multiple contracts. We also invite comment on the appropriate role of public involvement in reevaluations.

Section 1420.325 Supplemental Environmental Impact Statements

Current § 771.130 would be redesignated as § 1420.325. It is essentially unchanged from the current regulation except that supplementation now includes consideration of public involvement and interagency coordination.

Section-by-Section Analysis of the Proposed Rule on Protection of Public Parks, Wildlife and Waterfowl Refuges, and Historic Sites

For ease of reference, a distribution table is provided for the current sections and proposed sections as follows:

Current Section
Proposed Section

None
1430.101 Purpose.

771.109(a)(1) and(2) and part of 771.135(b)
1430.105 Applicability.

771.135(a)
1430.103 Mandate.

771.135(c) and (e)
1430.109 Significance.

771.135(p)(1),(2),(4), and (7)
1430.107 Use of land.

771.135(d),(f),(g),(h), and (p)(5)
1430.111 Exceptions.

771.135(a)(2), part of (b), part of (i), (j),(k),(l),(p)(3), and (p)(6)
1430.113 Evaluations under NEPA.

771.135(m) and (o)
1430.115 Separate evaluations.

771.135(i)[last sentence]
1430.117 Programmatic evaluations.

771.135(o)
1430.119 Linkage to planning.

None
1430.121 Definitions.

Section 1430.101 Purpose

This new section would be added to state that this regulation implements 49 U.S.C. 303 and 23 U.S.C. 138 (section 4(f)).

Section 1430.103 Mandate

Current § 771.135(a)(1) would be redesignated as § 1430.103 without substantive change in text.

Section 1430.105 Applicability

Current §§ 771.109(a)(1) and (2) provide the basis for this proposed section. Also, part of § 771.135(b) would be incorporated to make clear that the U.S. DOT agency decides the applicability of section 4(f).

Section 1430.107 Use of Land

Current § 771.135(p)(1), (2), (4), and (7) would be redesignated as § 1430.107 without substantive change.

Section 1430.109 Significance of the Section 4(f) Resource

Current § 135(c) and (e) would be redesignated as § 1430.109 without substantive change.

Section 1430.111 Exceptions

Current § 771.135(d), (g), (h), and (p)(5) would be redesignated as § 1430.111 without substantive change. The proposed section also incorporates the current § 771.135(f), except that the consultation requirement has been modified to be consistent with the new 36 CFR part 800 recently published by the Advisory Council on Historic Preservation. As proposed, the provision is silent with respect to the relationship between “adverse effects” under 36 CFR part 800 and “constructive use” under this regulation. We invite comment as to whether or not a specific relationship should be established in this regulation. We also invite comment as to other measures that we might take to better

coordinate the section 4(f) process with the process established under 36 CFR 800. The proposed section also has three new provisions in paragraphs (a), (b), and (c), stating that section 4(f) would not apply to park roads, parkways, trails, transportation enhancement activities, and transit enhancements where the purpose of the U.S. DOT agency approval of transportation funding is to improve the section 4(f) resource.

Section 1430.113 Section 4(f) Evaluations and Determinations Under the NEPA Umbrella

Current § 771.135(a)(2), (j), (k), (l), (p)(3), (p)(6), most of (i), and part of (b) would be redesignated as § 1430.113 without substantive change. The proposed section also would include a new provision in proposed paragraph (b) allowing consideration of the products of the planning process in the section 4(f) evaluation. Both the current and proposed regulation continue to codify in regulation language of the Supreme Court decision in Overton Park (401 U.S. 402 (1971)) that an avoidance alternative must be preferred unless the evaluation demonstrates that there are “unique problems or unusual features associated with it, or that the cost, the social, economical, or environmental impacts, or the community disruption resulting from such alternatives reach extraordinary magnitudes.” We invite comment on whether or not this standard deserves further definition in regulation or in guidance in light of changes to the highway program in the years since the court's decision. In particular, we would appreciate views on whether or not the qualitative importance or value of the section 4(f) resource should be explicitly taken into account in determining whether or not an avoidance alternative is “feasible and prudent,” especially when balancing the impacts of the various alternatives.

Section 1430.115 Separate Section 4(f) Evaluations

Current § 771.135(m) and (n) would be redesignated as § 1430.115 without substantive change.

Section 1430.117 Programmatic Section 4(f) Evaluations

The last sentence of current § 771.135(i) would be redesignated as § 1430.117, including a new explanatory introductory sentence. The proposed provision would provide a clear regulatory basis for programmatic section 4(f) evaluations and approvals, a practice which the Department of Transportation has used from time to time. For example, programmatic section 4(f) evaluations have been prepared for the following situations: Bikeways, historic bridges, projects involving minimal use of property for historic properties and projects involving minimal use of parkland. We invite suggestions of additional situations that would be appropriate subjects of future programmatic section 4(f) evaluations.

Section 1430.119 Linkage with Transportation Planning

Current § 771.135(o) would be redesignated as § 1430.119 and would remain substantively unchanged except that the concept of a preliminary section 4(f) evaluation has been extended to the planning process in exactly the same way it previously applied to first-tier EISs.

Section 1430.121 Definitions

A new § 1430.121 would be added to provide a consistent set of definitions of terms used in the planning regulations (23 CFR part 1410), the NEPA regulation (23 CFR part 1420), and this regulation (23 CFR part 1430).

Rulemaking Analyses and Notices

All comments received before the close of business on the comment closing date indicated above will be considered and will be available for examination using the docket number appearing at the top of this document in the docket room at the above address or via the electronic addresses provided above. The FHWA and the FTA will file comments received after the comment closing date in the docket and will consider late comments to the extent practicable. The FHWA and the FTA may, however, issue a final rule at any time after the close of the comment period. In addition to late comments, the FHWA and the FTA will also continue to file in the docket relevant information becoming available after the comment closing date, and interested persons should continue to examine the docket for new material.

Executive Order 12866 (Regulatory Planning and Review) and DOT Regulatory Policies and Procedures

We have determined that this proposed action is a significant regulatory action within the meaning of Executive Order 12866, and under the Department of Transportation regulatory policies and procedures because of substantial State, local government, congressional, and public interest. These interests involve receipt of Federal financial support for transportation investments, appropriate compliance with statutory requirements, and balancing of transportation mobility and environmental goals. We anticipate that the economic impact of this rulemaking will be minimal. Most costs associated with these rules are attributable to the provisions of the TEA-21, the ISTEA, the Clean Air Act (as amended), and other statutes including earlier highway acts.

We consider this proposal to be a means to simplify, clarify, and reorganize existing regulatory requirements. There have been no changes to NEPA or CEQ regulations. These rules would merely revise existing NEPA regulations of the FHWA and the FTA and conform those regulations to the environmental streamlining requirements of TEA-21. In response to congressional direction in TEA-21, the U.S. DOT is proposing to implement improved coordinated environmental review processes for highway and transit projects. States have been carrying out statewide transportation planning activities with title 23, U.S.C., and FTA planning and research funds for many years. Neither the individual nor the cumulative impact of this action would be significant because this action would not alter the funding levels available to the States for Federal or federally-assisted programs covered by the TEA-21.

The amendments impose no additional requirements. The environmental streamlining process under section 1309 of TEA-21 establishes coordinated environmental review processes by which U.S. DOT would work with other Federal agencies to assure that major highway and transit projects are advanced according to cooperatively determined time frames. Such processes have been incorporated into a memorandum of understanding between U.S. DOT and other Federal agencies.

Regulatory Flexibility Act

In compliance with the Regulatory Flexibility Act (5 U.S.C. 601-602), we have evaluated the effects of this rule on small entities, such as local governments and businesses. The TEA-21 provides the flexibility for these agencies to provide the resources necessary to meet any time limits established under environmental streamlining. Additionally, the FHWA has issued guidance concerning transportation funding for Federal agency coordination using a full range of options for reimbursement under appropriate authorities. Accordingly, the FHWA and the FTA certify that this action would not have a significant economic impact on a substantial

number of small entities. This proposed action would merely update and clarify existing procedures. We specifically invite comments on the projected economic impact of this proposal, and will actively consider such information before completing our Regulatory Flexibility Act analysis when adopting final rules.

Environmental Impacts

We have also analyzed this proposed action for the purpose of the National Environmental Policy Act (42 U.S.C. 4321
et seq.
), and preliminarily conclude that this action would not have any effect on the quality of the human and natural environment and is therefore categorically excluded under 23 CFR 771.117(c)(20). The TEA-21 directs the implementation of a coordinated environmental review process for highway construction projects, yet, also ensures that such concurrent review shall not result in a significant adverse impact to the environment or substantively alter the operation of Federal law. Time periods for review shall be consistent with time periods established by the Council on Environmental Quality under 40 CFR 1501.8 and 1506.10. As stated in the TEA-21, nothing in section 1309 (the environmental streamlining section) shall affect the applicability of NEPA or any other Federal environmental statute or affect the responsibility of any Federal officer to comply with or enforce any such statute.

Executive Order 13132 (Federalism Assessment)

This proposed action has been analyzed in accordance with the principles and criteria contained in Executive Order 13132, dated August 4, 1999, and it has been determined that this action does not have a substantial direct effect or sufficient Federalism implications on States and local governments that would limit the policymaking discretion of the States. Nothing in this document directly preempts any State law or regulation. The TEA-21 directs the DOT to establish an integrated NEPA review and permitting process and to encourage approvals as early as possible in the scoping and planning process, yet also to maintain an emphasis on a strong environmental policy. Throughout the proposed regulation there is an effort to keep administrative burdens to a minimum.

Executive Order 12372 (Intergovernmental Review)

Catalog of Federal Domestic Assistance Program Number 20.205, Highway planning and construction (or 20.217, Motor Carrier Safety). The regulations implementing Executive Order 12372 regarding intergovernmental consultation on Federal programs and activities apply to this program.

Unfunded Mandates Reform Act of 1995

This rule does not impose a Federal mandate resulting in the expenditure by State, local, tribal governments, in the aggregate, or by the private sector, of $100 million or more in any one year. (2 U.S.C. 1531
et seq.
).

Paperwork Reduction Act

This proposal contains no new collection of information requirements for purposes of the Paperwork Reduction Act of 1995, 44 U.S.C. 3501-3520. This notice of proposed rulemaking would encourage the coordination of approvals by Federal agencies involved in the NEPA process and could reduce the level of recordkeeping.

The information prepared by non-Federal parties pursuant to this proposed regulation is exempt from the requirements of the Paperwork Reduction Act. First, the collection of information does not entail reporting of information in response to identical questions. NEPA documents do not involve answering specific questions; they address issues relating to the requirements of multiple Federal environmental statutes. There are too many variables relating to the proposed action, the location in which the action is to be taken, and the statutes that are implicated (and to what extent) to permit a standardized format or content. The issues to be addressed in NEPA documents are therefore determined on a case by case basis. Each is a one of a kind document.

Second, the information is not requested of non-Federal entities but of Federal agencies. The State and local transportation departments and transit agencies compiling information are voluntarily serving as consultants to FHWA and FTA for their own convenience. As the proposers of the actions subject to NEPA, and the owners, operators, and maintainers of the resulting facility, and key decisionmakers regarding the choices involved in project development, it is easier for them to prepare the NEPA documents. Information is not requested of outside entities except within the PRA exception relating to “facts or opinions submitted in response from general solicitations of comments for the general public (5 CFR 1320.3(h)(4).”

Third, State and local departments of transportation and transit agencies develop this information reported to FHWA/FTA as a normal part of doing business. NEPA documents contain engineering and environmental information that is integral to developing projects in a way that conforms to State and local laws. The development of engineering and environmental information is an unavoidable step in project development whether or not the Federal government is involved. We invite comments on this analysis.

Executive Order 12630 (Taking of Private Property)

This rule will not effect a taking of private property or otherwise have taking implications under Executive Order 12630, Governmental Actions and Interference with Constitutionally Protected Property Rights.

Executive Order 12988 (Civil Justice Reform)

This action meets applicable standards in sections 3(a) and 3(b)(2) of Executive Order 12988, Civil Justice Reform, to minimize litigation, eliminate ambiguity, and reduce burden.

Executive Order 13045 (Protection of Children)

We have analyzed this action under Executive Order 13045, Protection of Children from Environmental Health Risks and Safety Risks. This rule is not an economically significant rule and does not concern an environmental risk to healthy or safety that may disproportionately affect children.

Regulation Identification Number

A regulation identification number (RIN) is assigned to each regulatory action listed in the Unified Agenda of Federal Regulations. The Regulatory Information Service Center publishes the Unified Agenda in April and October of each year. The RIN contained in the heading of this document can be used to cross reference this action with the Unified Agenda.

List of Subjects

23 CFR Part 771
Environmental protection, Grant programs—transportation, Highways and roads, Historic preservation, Public lands, Recreation areas, Reporting and recordkeeping requirements.

23 CFR Part 1420

Environmental impact statements, Grant programs—transportation, Highways and roads, Mass

transportation, Reporting and recordkeeping requirements.

23 CFR Part 1430
Environmental protection, Grant programs—transportation, Highways and roads, Historic preservation, Mass transportation, Public lands, Recreation areas, Reporting and recordkeeping requirements, Wildlife refuges.

49 CFR Part 622
Environmental impact statements, Grant programs—transportation, Mass transportation, Reporting and recordkeeping requirements.

49 CFR Part 623
Environmental protection, Grant programs—transportation, Mass Transportation, Public lands, Recreation areas, Reporting and recordkeeping requirements, Wildlife refuges.

Federal Highway Administration

23 CFR Chapter I
For reasons set forth in the preamble, and under the authority of 23 U.S.C. 109, 128, 134, 138, and 315, the Federal Highway Administration proposes to amend Chapter I of title 23, Code of Federal Regulations, as follows:

PART 771—[REMOVED]

1. Remove part 771.

23 CFR Chapter IV

For reasons set forth in the preamble, the Federal Highway Administration and the Federal Transit Administration propose to amend proposed Chapter IV in title 23, Code of Federal Regulations (published elsewhere in this
Federal Register
), as set forth below:

2. Add parts 1420 and 1430 to read as follows:

PART 1420—NEPA AND RELATED PROCEDURES FOR TRANSPORTATION DECISIONMAKING

Subpart A—Purpose, Policy, and Mandate

Sec.
1420.101
Purpose.
1420.103
Relationship of this regulation to the CEQ regulation and other guidance.
1420.105
Applicability of this part.
1420.107
Goals of the NEPA process.
1420.109
The NEPA umbrella.
1420.111
Environmental justice.
1420.113
Avoidance, minimization, mitigation, and enhancement responsibilities.

Subpart B—Program and Project Streamlining

1420.201
Relation of planning and project development processes.
1420.203
Environmental streamlining.
1420.205
Programmatic approvals.
1420.207
Quality assurance process.
1420.209
Alternate procedures.
1420.211
Use of this part by other U.S. DOT agencies.
1420.213
Emergency action procedures.

Subpart C—Process and Documentation Requirements

1420.301
Responsibilities of the participating parties.
1420.303
Interagency coordination.
1420.305
Public involvement.
1420.307
Project development and timing of activities.
1420.309
Classes of actions.
1420.311
Categorical exclusions.
1420.313
Environmental assessments.
1420.315
Findings of no significant impact.
1420.317
Draft environmental impact statements.
1420.319
Final environmental impact statements.
1420.321
Record of decision.
1420.323
Re-evaluations.
1420.325
Supplemental environmental impact statements.

Subpart D—Definitions

1420.401
Terms defined elsewhere.
1420.403
Terms defined in this part.

Authority:

23 U.S.C.

[Text truncated at 120,000 characters. The full text is on the page linked above.]

---

Source: Frix Law Library, https://www.frixlaw.com/law-library/documents/fr%3A00-13022. Public record. Not legal advice.